078400-Rev 2.pdf

PDF 65 KB Posted

Attached to
VISN 7 CONSTRUCTION MATOC 36C24726R0026 - SOLICITATION
Solicitation number
36C24726R0026
Issued by

About this file

This is a specification section for firestopping work as part of the Ralph H. Johnson VAMC Renovate project (Restrooms, Stairwells, and Doors), Project No. 534-23-910, effective December 8, 2025, Revision 2.

The specification requires the contractor to provide UL or equivalent approved firestopping systems for closures of openings in walls, floors, and roof decks to prevent penetration of flame, heat, smoke, and gases in fire-resistant rated construction, as well as smoke stopping systems for smoke partitions. Through-penetration firestop systems and devices must be tested in accordance with ASTM E814 or UL 1479 using "F" or "T" ratings; "T" ratings are waived for penetrations smaller than or equal to 101 mm (4 inches) nominal pipe or 0.01 square meter (16 square inches) in cross-sectional area. Firestop sealants must contain no flammable or toxic solvents, be water-resistant after curing, and achieve maximum flame spread of 25 and smoke development of 50 per ASTM E84 or UL 723. Materials must be nontoxic, noncarcinogenic, and free from ethylene glycol, PCB, MEK, and asbestos. The contractor must engage installers approved by FM Global per FM Global 4991 or evaluated by UL under its Qualified Firestop Contractor Program, and must employ a qualified independent inspector meeting ASTM E699 criteria with minimum two years' experience in firestopping inspections. Submittals must include installer and inspector qualifications, manufacturer literature, FM/UL/WH classification numbers, certified laboratory test reports for non-listed systems, and manufacturer compliance certificates. All work must be inspected and documented per ASTM E2393 and ASTM E2174 prior to concealment, with written reports identifying penetration locations, types, and corresponding UL-listed firestopping system numbers.

View the file

Other files

File Type Posted
36C24726R0026 0013.pdf PDF
Seed 2_Project 557-20-101_27 10 00_Update Structured Cabling.pdf PDF
RFI LOG AMENDMENT 0012_ SEED 3.pdf PDF
36C24726R0026 0012.pdf PDF
SEED 1_PROJECT 534-23-910 INFECTION CONTROL DETAILS.pdf PDF
SEED 1_PROJECT 534-23-910 INFECTION CONTROL RISK ASSESSMENT.pdf PDF
ATTACHMENT 18 - SEED 3 WAGE DETERMINATION TUSKEGEE AL20260078 5 18 2026.pdf PDF
RFI LOG AMENDMENT 0006_SEED 2 - Revised.pdf PDF
ATTACHMENT 11 - SEED 1_WAGE DETERMINATION SC20260023 05 18 2026.pdf PDF
Seed 2_557-20-101 - Project Bldg 5 As-Builts.pdf PDF
Seed 1_534-23-910 SOW Rev1 - Final.pdf PDF
Seed 3_619A4-25-102 Wage Rates AL20260078 01 02 2026.pdf PDF
Seed 2_557-20-101 - Photos_RFI 262 263.docx DOCX document
36C24726R0026 0006.pdf PDF
RFI LOG AMENDMENT 0006_SEED 2-557-20-101.pdf PDF
Seed 2_557-20-101 -GEHC-SP_REVAPEX_6-120F.pdf PDF
Seed 2_557-20-101 - Persona RF PREMIUM Brochure Fuji.pdf PDF
Seed 2_557-20-101 -Cardiac_D-Spect Specs.pdf PDF
Seed 2_557.20-101 - REVIT and CAD Screenshot.docx DOCX document
RFI LOG AMENDMENT 0006_MATOC RFP.pdf PDF
Seed 2_557-20-101 - VA Radiology - CD100 Final Bid Documents - Combined Set - SIGNED.pdf PDF
Seed 2_557-20-101 - Med Gas Master Alarm Panel.jpg JPG image
Seed 2_557-20-101 -Probe Cabinet specs.pdf PDF
RFI LOG AMENDMENT 0005_Seed 1.pdf PDF
534-23-910 VA Charleston Stairwells Restrooms and Doors - Revision 2.pdf PDF
534-23-910 VA Charleston Stairwells Restrooms and Doors - Revision 1- A101-A601.pdf PDF
534-23-910 VA Charleston Stairwells Restrooms and Doors - Revision 1-Demolition pages.pdf PDF
534-23-910 - Environmental Survey Report.pdf PDF
36C24726R0026 0003.pdf PDF
534-23-910 VA Charleston Stairwells Restrooms and Doors - Revision 1- General pages.pdf PDF
Seed 1 - 534-23-910 Site Visit Attendance Roster_4 21 26.pdf PDF
Seed 2 - 557-20-101 Site Visit Attendance Roster_4 22 26.pdf PDF
36C24726R0026 0002.pdf PDF
NCS-VISN 7-MATOC-SEED 2-RFI 1 - 2 A600.pdf PDF
Seed 3 - 619A4-25-102 Site Visit Attendance Roster_4 23 26.pdf PDF
ATTACHMENT 8R - SEED 1_PROJECT 534-23-910_SPECIFICATIONS REV 4.pdf PDF
ATTACHMENT 10 - SEED 1_ PROJECT 534-23-910_ FINAL CONSTRUCTION DOCUMENTS VOL II.pdf PDF
ATTACHMENT 13 - SEED 2_PROJECT 557-20-101 DRAWINGS.pdf PDF
ATTACHMENT 14 - SEED 2_WAGE DETERMINATION GA20260095 01 23 26.pdf PDF
ATTACHMENT 18 - SEED 3_ WAGE DETERMINATION AL20260098 01 02 26.pdf PDF
ATTACHMENT 1 - CONTRACTOR EXPERIENCE FORM.docx DOCX document
ATTACHMENT 2 - CONTRACTOR SURETY LIMITATION.docx DOCX document
ATTACHMENT 7 - ITEMIZED COST BREAKDOWN.xlsx XLSX spreadsheet
ATTACHMENT 19 - VAAR 852.219-75 VA Notice of Limitations on Subcontracting Jan 2023 Deviation.pdf PDF
36C24726R0026_VISN 7 CONSTRUCTION MATOC.pdf PDF
ATTACHMENT 4 - SUBCONTRACTOR CONSENT FOR PAST PERFORMANCE.docx DOCX document
ATTACHMENT 5 - EXPERIENCE MODIFICATION RATE FORM.docx DOCX document
ATTACHMENT 11 - SEED 1_WAGE DETERMINATION SC20260023 01 02 26.pdf PDF
ATTACHMENT 15 - SEED 3_PROJECT 619A4-25-102_SPECS 100 FINAL rev1.pdf PDF
ATTACHMENT 17 - SEED 3_PROJECT 619A4-25-102_PIC BOOK 100 FINAL.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01-01-21 RALPH H. JOHNSON VAMC – RENOVATE Final Construction Documents

RESTROOMS, STAIRWELLS, AND DOORS

PROJECT NO. 534-23-910 8 December 2025 Rev 2- 5.7.2026

07 84 00 - 1

SECTION 07 84 00

FIRESTOPPING

PART 1 - GENERAL

1.1 DESCRIPTION

A. Provide UL or equivalent approved firestopping system for the closures of openings in walls, floors, and roof decks against penetration of flame, heat, and smoke or gases in fire resistant rated construction.

B. Provide UL or equivalent approved firestopping system for the closure of openings in walls against penetration of gases or smoke in smoke partitions.

1.2 RELATED WORK

A. Section 07 92 00, JOINT SEALANTS: Sealants and application.

B. Section 23 31 00, HVAC DUCTS AND CASINGS: Fire and smoke damper assemblies in ductwork.

C. Section 23 37 00, AIR OUTLETS AND INLETS: Fire and smoke damper assemblies in ductwork.

1.3 SUBMITTALS

A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT

DATA, AND SAMPLES.

B. Installer qualifications.

C. Inspector qualifications.

D. Manufacturers literature, data, and installation instructions for types of firestopping and smoke stopping used.

E. List of FM, UL, or WH classification number of systems installed.

F. Certified laboratory test reports for ASTM E814 tests for systems not listed by FM, UL, or WH proposed for use.

G. Submit certificates from manufacturer attesting that firestopping materials comply with the specified requirements.

1.4 DELIVERY AND STORAGE

A. Deliver materials in their original unopened containers with manufacturer’s name and product identification.

B. Store in a location providing protection from damage and exposure to the elements.

1.5 QUALITY ASSURANCE

A. FM, UL, or WH or other approved laboratory tested products will be acceptable.

RESTROOMS, STAIRWELLS, AND DOORS

PROJECT NO. 534-23-910 8 December 2025 Rev 2- 5.7.2026

07 84 00 - 2

B. Installer Qualifications: A firm that has been approved by FM Global according to FM Global 4991 or been evaluated by UL and found to comply with UL’s “Qualified Firestop Contractor Program Requirements.” Submit qualification data.

C. Inspector Qualifications: Contractor to engage a qualified inspector to perform inspections and final reports. The inspector to meet the criteria contained in ASTM E699 for agencies involved in quality assurance and to have a minimum of two years’ experience in construction field inspections of firestopping systems, products, and assemblies. The inspector to be completely independent of, and divested from, the Contractor, the installer, the manufacturer, and the supplier of material or item being inspected. Submit inspector qualifications.

1.6 APPLICABLE PUBLICATIONS

A. Publications listed below form a part of this specification to the extent referenced. Publications are referenced in the text by the basic designation only.

B. ASTM International (ASTM):

E84-20 .................Surface Burning Characteristics of Building

Materials

E699-16 ................Standard Specification for Agencies Involved in

Testing, Quality Assurance, and Evaluating of

Manufactured Building Components

E814-13a(2017) .........Fire Tests of Penetration Firestop Systems

E2174-20a ..............Standard Practice for On-Site Inspection of

Installed Firestop Systems

E2393-20 ...............Standard Practice for On-Site Inspection of

Installed Fire Resistive Joint Systems and

Perimeter Fire Barriers

C. FM Global (FM):

Annual Issue Approval Guide Building Materials

4991-13 ................Approval of Firestop Contractors

D. Underwriters Laboratories, Inc. (UL):

Annual Issue Building Materials Directory

E. Annual Issue Fire Resistance Directory

723-Edition 11(2018) ...Standard for Test for Surface Burning

Characteristics of Building Materials

1479-04(2015) ..........Fire Tests of Penetration Firestops

RESTROOMS, STAIRWELLS, AND DOORS

PROJECT NO. 534-23-910 8 December 2025 Rev 2- 5.7.2026

07 84 00 - 3

F. Intertek Testing Services - Warnock Hersey (ITS-WH):

Annual Issue Certification Listings

G. Environmental Protection Agency (EPA):

40 CFR 59(2014) ........National Volatile Organic Compound Emission

Standards for Consumer and Commercial Products

PART 2 - PRODUCTS

2.1 FIRESTOP SYSTEMS

A. Provide either factory built (Firestop Devices) or field erected

(through-Penetration Firestop Systems) to form a specific building system maintaining required integrity of the fire barrier and stop the passage of gases or smoke. Firestop systems to accommodate building movements without impairing their integrity.

B. Through-penetration firestop systems and firestop devices tested in accordance with ASTM E814 or UL 1479 using the "F" or "T" rating to maintain the same rating and integrity as the fire barrier being sealed. "T" ratings are not required for penetrations smaller than or equal to 101 mm (4 inches) nominal pipe or 0.01 square meter (16 square inches) in overall cross sectional area.

C. Firestop sealants used for firestopping or smoke sealing to have the following properties:

1. Contain no flammable or toxic solvents.

2. Release no dangerous or flammable out gassing during the drying or curing of products.

3. Water-resistant after drying or curing and unaffected by high humidity, condensation or transient water exposure.

4. When installed in exposed areas, capable of being sanded and finished with similar surface treatments as used on the surrounding wall or floor surface.

D. Firestopping system or devices used for penetrations by glass pipe, plastic pipe or conduits, unenclosed cables, or other non-metallic materials to have following properties:

1. Classified for use with the particular type of penetrating material used.

2. Penetrations containing loose electrical cables, computer data cables, and communications cables protected using firestopping systems that allow unrestricted cable changes without damage to the seal.

RESTROOMS, STAIRWELLS, AND DOORS

PROJECT NO. 534-23-910 8 December 2025 Rev 2- 5.7.2026

07 84 00 - 4

E. Maximum flame spread of 25 and smoke development of 50 when tested in accordance with ASTM E84 or UL 723. Material to be an approved firestopping material as listed in UL Fire Resistance Directory or by a nationally recognized testing laboratory.

F. FM, UL, or WH rated or tested by an approved laboratory in accordance with ASTM E814.

G. Materials to be nontoxic and noncarcinogen at all stages of application or during fire conditions and to not contain hazardous chemicals.

Provide firestop material that is free from Ethylene Glycol, PCB, MEK, and asbestos.

H. For firestopping exposed to view, traffic, moisture, and physical damage, provide products that do not deteriorate when exposed to these conditions.

1. For piping penetrations for plumbing and wet-pipe sprinkler systems, provide moisture-resistant through-penetration firestop systems.

2. For floor penetrations with annular spaces exceeding 101 mm

(4 inches) or more in width and exposed to possible loading and traffic, provide firestop systems capable of supporting the floor loads involved either by installing floor plates or by other means acceptable to the firestop manufacturer.

3. For penetrations involving insulated piping, provide through-penetration firestop systems not requiring removal of insulation.

2.2 SMOKE STOPPING IN SMOKE PARTITIONS

A. Provide silicone sealant in smoke partitions as specified in Section

07 92 00, JOINT SEALANTS.

B. Provide mineral fiber filler and bond breaker behind sealant.

C. Sealants to have a maximum flame spread of 25 and smoke developed of 50 when tested in accordance with ASTM E84.

D. When used in exposed areas capable of being sanded and finished with similar surface treatments as used on the surrounding wall or floor surface.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Submit product data and installation instructions, as required by article, submittals, after an on-site examination of areas to receive firestopping.

RESTROOMS, STAIRWELLS, AND DOORS

PROJECT NO. 534-23-910 8 December 2025 Rev 2- 5.7.2026

07 84 00 - 5

B. Examine substrates and conditions with installer present for compliance with requirements for opening configuration, penetrating items, substrates, and other conditions affecting performance of firestopping.

Do not proceed with installation until unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Remove dirt, grease, oil, laitance and form-release agents from concrete, loose materials, or other substances that prevent adherence and bonding or application of the firestopping or smoke stopping materials.

B. Remove insulation on insulated pipe for a distance of 150 mm (6 inches) on each side of the fire rated assembly prior to applying the firestopping materials unless the firestopping materials are tested and approved for use on insulated pipes.

C. Prime substrates where required by joint firestopping system manufacturer using that manufacturer’s recommended products and methods. Confine primers to areas of bond; do not allow spillage and migration onto exposed surfaces.

D. Masking Tape: Apply masking tape to prevent firestopping from contacting adjoining surfaces that will remain exposed upon completion of work and that would otherwise be permanently stained or damaged by such contact or by cleaning methods used to remove smears from firestopping materials. Remove tape as soon as it is possible to do so without disturbing seal of firestopping with substrates.

3.3 INSTALLATION

A. Do not begin firestopping work until the specified material data and installation instructions of the proposed firestopping systems have been submitted and approved.

B. Install firestopping systems with smoke stopping in accordance with FM, UL, WH, or other approved system details and installation instructions.

C. Install smoke stopping seals in smoke partitions.

3.4 CLEAN-UP

A. As work on each floor is completed, remove materials, litter, and debris.

B. Clean up spills of liquid type materials.

C. Clean off excess fill materials and sealants adjacent to openings and joints as work progresses by methods and with cleaning materials

RESTROOMS, STAIRWELLS, AND DOORS

PROJECT NO. 534-23-910 8 December 2025 Rev 2- 5.7.2026

07 84 00 - 6 approved by manufacturers of firestopping products and of products in which opening and joints occur.

D. Protect firestopping during and after curing period from contact with contaminating substances or from damage resulting from construction operations or other causes so that they are without deterioration or damage at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out and remove damaged or deteriorated firestopping immediately and install new materials to provide firestopping complying with specified requirements.

3.5 INSPECTIONS AND ACCEPTANCE OF WORK

A. Do not conceal or enclose firestop assemblies until inspection is complete and approved by the Contracting Officer Representative (COR).

B. Furnish service of approved inspector to inspect firestopping in accordance with ASTM E2393 and ASTM E2174 for firestop inspection, and document inspection results. Submit written reports indicating locations of and types of penetrations and type of firestopping used at each location; type is to be recorded by UL listed printed numbers.

- - - E N D - - -

SECTION 07 84 00 FIRESTOPPING
PART 1 - GENERAL
1.1 DESCRIPTION
1.2 RELATED WORK
1.3 SUBMITTALS
1.4 DELIVERY AND STORAGE
1.5 QUALITY ASSURANCE
1.6 APPLICABLE PUBLICATIONS
PART 2 - PRODUCTS
2.1 FIRESTOP SYSTEMS
2.2 SMOKE STOPPING IN SMOKE PARTITIONS
PART 3 - EXECUTION
3.1 EXAMINATION
3.2 PREPARATION
3.3 INSTALLATION
3.4 CLEAN-UP
3.5 INSPECTIONS AND ACCEPTANCE OF WORK