1352.011 Section 01 22 13 Unit Prices and Allowances - Add 2.pdf
PDF 120 KB Posted
- Attached to
- Replace Repair Roofs for Buildings 4, 15, 90, 93
- Solicitation number
- 36C24725R0018
About this file
This document is an Addendum 2 to Section 01 22 13 for Unit Prices and Allowances related to a roof replacement project. The document outlines specific unit pricing and allowances for various repair and replacement activities during roof renovation, including wood blocking replacement, supplemental wood deck fastening, damaged wood plank deck repairs, and lightweight concrete fill repairs. The contract includes predefined allowances for each unit price category, such as 1,000 board feet of wood blocking replacement, 250 side lap screws, 500 board feet of tongue-and-groove wood plank deck replacement, and 15,000 square feet of potential asbestos abatement.
The unit prices cover scenarios like replacing damaged wood blocking, adding supplemental fasteners to tongue-and-groove wood planks, repairing or replacing deteriorated deck planks, and addressing lightweight concrete fill damage in areas of varying sizes. The document specifies detailed technical requirements for each repair type, including fastening methods, extent of replacement, and submission of technical data. The contractor is required to include these allowances in the base bid, with the option for the owner to exercise unit prices beyond the initial allowance, which will include overhead and profit.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
05-25-23
01 22 13 Addenda 2 - 1
SECTION 01 22 13
UNIT PRICES AND ALLOWANCES – ADDENDA 2
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes: Replacement of damaged and deteriorated materials uncovered during roof replacement.
1.2 RELATED WORK
A. Section 06 10 00 ROUGH CARPENTRY:
B. Section 07 01 50.19, PREPARATION FOR RE-ROOFING:
1.3 PROCEDURES
A. Unit prices will be exercised at the option of the Owner.
B. Modify and coordinate related activities as required to complete the work if, and when, acceptance is designated by the Owner in the standard form of agreement.
C. In the event unit prices are exercised, applicable sections of this
Specification shall govern. Other sections may be modified as required to address the unit price.
D. Cost associated with any anomalies identified on plans, on the roof, and/or in the Specification shall be included in the Base Bid.
E. Cost associated with any necessary removals at roof drains to install new roof drains and/or drain sumps shall be included in the Base Bid.
F. Cost associated with the repair of decking at removed abandoned penetrations identified on plans and/or marked on the roof shall be included in the Base Bid.
G. Bidders shall provide a unit price for the items listed on the Bid
Form. Bidder shall include a cash allowance in the Base Bid for each unit price in the quantity list below and on the bid form. Payment will be made for unit price work in excess of the cash allowance, which includes all overhead and profit. In the event it is necessary to replace fewer than quantity associated with the cash allowance, the
Owner will take a credit at the unit price rate. The Designer shall be responsible for verifying the actual quantity and extent of the unit price work.
01 22 13 Addenda 2 - 2
PART 2 - PRODUCTS
2.1 SEE APPLICABLE SPECIFICATION SECTIONS.
PART 3 - EXECUTION
3.1 DAMAGED OR DETERIORATED WOOD BLOCKING
A. (Unit Price No. 1) Where wood blocking or curbs are damaged or deteriorated, remove existing wood blocking to a point 6 inches beyond the damage and/or deterioration, and repair and/or replace with new wood blocking to match existing. Secure new blocking to the substrate using specified screws at spacings not to exceed 12 inches on-center, staggered. Pattern.
1. (Allowance No.1) Contract shall include 1,000 board feet of wood blocking replacement in the Base Bid.
3.2 TOUNGUE-AND-GROOVE WOOD PLANK DECK, SUPPLEMENTAL FASTENING
A. (Unit Price No. 2) At those locations where the existing tongue and groove wood plank deck is not fastened to each framing member with two fasteners, furnish and install new #12 wood screws as specified in section 07 01 50.19 at missing fastener locations. Contractor shall submit technical data on the proposed screws before the start of this phase of the work.
1. (Allowance No. 2) Contract shall include the installation of 250 side laps screws in the base bid.
3.3 TOUNGUE-AND-GROOVE WOOD PLANK DECK, DAMAGED OR DETERIORATE PLANKS
A. (Unit Price No. 3) At locations where existing tongue and groove wood planks are damaged or deteriorated, cut and replace damaged section of deck board. All deck boards shall be required to be supported by a minimum of 3 framing members. If cutting the damaged plank would result in the remainder of the plank be supported by less than 3 framing members, the entire plank shall be replaced. Fasten new board to each framing member with 2 screws. Tongue of the new plank may be cut to facilitate installation between two existing planks. Contractor shall submit technical data on the proposed screws and tongue and groove boards before the start of this phase of the work.
1. (Allowance No. 3) Contractor shall include the replacement of 500 board feet of tongue-and-groove wood plank deck in the base bid.
3.4 LIGHTWEIGHT CONCRETE, DETERIORATED OR DAMAGED
A. (Unit Price No. 4) Where lightweight concrete fill is damaged or deteriorated at small areas less than 12 inches on the largest side, furnish and install over the damaged area a 20 ga. galvanized steel
01 22 13 Addenda 2 - 3 plate secured to the existing deck with ½” diameter toggle bolts, located 1 inch from the perimeter of the plate, and at 6 inches on center. Extend the new steel plate a minimum of 6 inches onto the surface of the existing lightweight insulating concrete fill beyond the damaged area.
1. (Allowance No. 4) Contractor shall include the installation of 50 SF of 20-ga. galvanized steel in the base bid.
B. (Unit Price No. 5) Where lightweight concrete fill is damaged or deteriorated at areas larger than 12 inches on the largest side but the forming substrate is structurally sound, remove the damaged or deteriorated existing lightweight concrete fill to the forming substrate and to an area of sound lightweight insulating concrete fill.
Furnish and install new lightweight concrete fill over the substrate in accordance with section 07 01 50.19 Preparation for Re-Roofing.
1. (Allowance No. 5) Contractor shall include 50 SF of lightweight concrete fill replacement in the base bid.
C. (Unit Price No. 6) Where the lightweight concrete fill is damaged and/or deteriorated at areas that are larger than 12 inches on any side where the steel centering is damaged or deteriorated. The lightweight concrete fill shall be removed so that the existing steel centering can be removed and replaced. Furnish and install new lightweight concrete fill and steel centering in accordance with section 07 01 50.19
Preparation for Re-Roofing. The lightweight concrete fill shall be removed so that the new steel centering can be nested over three structural supports and the existing steel centering a minimum of 12 inches in all directions.
1. (Allowance No. 6) Contractor shall include 315 SF of lightweight concrete and form replacement in the base bid.
3.5 ASBESTOS ABATEMENT
A. (Unit Price No. 7) Where asbestos containing materials are discovered by the contractor’s retained certified industrial hygienist, contractor shall perform asbestos abatement activities as specified in specification section 02 82 13.21 ASBESTOS ROOING ABATEMENT.
1. (Allowance No. 7) Contractor shall include 15,000 SF of asbestos abatement of roofing materials in their base bid.
- - E N D - -