36C24718B0635 0002 VA Birmingham Switchgear -Structural.pdf
View the file
Other files for this federal contract opportunity
Show all 30
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
3380 Trickum Road
Woodstock, GA. 30188 770-517-5507 voice 770-517-5508 fax
Bldg. 500, Ste. 100 www.ieiusa.com
INCORPORATED
INNOVATIVE
ENGINEERING
Department of
Veterans Affairs
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
Date:
Drawing Title:
Approved Project Director
Project Title:
1 2 3 4 5 6 7 8 9
100% SUBMITTAL
590 MEANS ST NW N/A
Phase Project Number
Building Number
Drawing NumberLocation
Issue Date CheckedFULLY SPRINKLERED
STAMP
STE. 200
ATLANTA, GA 30318
ARCHITECT/ENGINEER OF RECORDCONSULTANT
F ile
P a th
A
B
C
D
E
F
U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
Drawn
STRUCTURAL NOTES REPLACE/UPGRADE
ELECTRICAL SWITCHGEAR
PHASE 3
BIRMINGHAM, AL
S001
521-16-103
SLW SLM10-02-2017
UP
VTS
W
X
W8X10
W18X35
W8X10
W18X35
W16X31
W
X
W16X31
REF
30' - 0"
REF.
30' - 0"
4'
1"
2'
/4
2'
S501
S501
TYP
FACE OF BRICK FACADE
S501
W16X26
S501
S501
RAILING,
SEE 6/S501
TYP
S501
L3x3x1/4
HORIZONTAL
BRACING TYP
FACE OF BUILDING BELOW
FACE OF
BUILDING
BELOW
2'
3/ 4"
5'
NEW BACK UP GENERATOR
4'
W 8X
W 8X
W 8X
W
X
W8X10
W8X10
W
X
W8X10
W8X10 W8X10
W8X10
4' - 0"
4'
3' - 0"
FACE OF BUILDING BELOW
W8X10
W8X10
8'
17.9
L4x4x1/4 VERTICAL
KNEE BRACEING TYP.
S501
S501
S501
PLAN
NORTH
TRUE
NORTH
PLATFORM FRAMING PLAN NOTES
1. T/GRATING = +4'-1" ABOVE EXISTING CONCRETE FILL.
2. REF. DENOTES FOR REFERENCE ONLY FIELD VERIFY
3. FIELD VERIFY EXISTING CONDITIONS PRIOR TO FABRICATION.
4. GRATING SHALL BE W19-4 (1" x 1/8") GALVANIZED STEEL GRATING U.N.O.
5. ANCHORAGE OF EQUIPMENT TO PLATFORM BY EQUIPMENT SUPPLIER
EXISTING ROOF FRAMING PLAN NOTES
1. REF. DENOTES FOR REFERENCE ONLY FIELD VERIFY
2. FIELD VERIFY EXISTING CONDITIONS PRIOR TO FABRICATION.
DENOTES GRATING SPAN DIRECTION
DENOTES EXTENTS OF GRATING
DENOTES VERTICAL BRACING
DENOTES HORIZONTAL BRACING
DENOTES EXISTING WIDE FLANGE BEAM
DENOTES NEW WIDE FLANGE BEAM
PLATFORM FRAMING PLAN LEGEND
WXxXX
WXxXX
KEY PLAN
PROJECT
AREA
VTS
REF
30' - 0"
REF.
30' - 0"
W18X46 W14X30
W
X
W
X
W14X30
W14X30
W16X26
W18X46
W18X46
W18X46 W14X30
W
X
W16X26
HSS4X4X1/2
HSS14X14X1/2 HSS14X14X1/2
W14X43
W14X43
W14X74 W14X48R
E F
4'
W
X
REF.
4' - 5 7/8"
EDGE OF ROOF DECK
EXISTING BEAM
REINFORCING
S501
S501
S501
2'
2'
EXISTING 3" COMP DECK WITH
3.25" CONCRETE FILL
S501
TYP
HSS4X4X1/2
HSS4X4X1/2
HSS4X4X1/2
17.9
S501
S501
2'
2'
EXISTING BEAM
REINFORCING
S501
S501
R E
F
3380 Trickum Road
Woodstock, GA. 30188 770-517-5507 voice 770-517-5508 fax
Bldg. 500, Ste. 100 www.ieiusa.com
INCORPORATED
INNOVATIVE
ENGINEERING
Department of
Veterans Affairs
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
Date:
Drawing Title:
Approved Project Director
Project Title:
1 2 3 4 5 6 7 8 9
100% SUBMITTAL
590 MEANS ST NW N/A
Phase Project Number
Building Number
Drawing NumberLocation
Issue Date CheckedFULLY SPRINKLERED
STAMP
STE. 200
ATLANTA, GA 30318
ARCHITECT/ENGINEER OF RECORDCONSULTANT
F ile
P a th
A
B
C
D
E
F
U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
Drawn
ROOF AND PLATFORM FRAMING
PLANS
REPLACE/UPGRADE
ELECTRICAL SWITCHGEAR
PHASE 3
BIRMINGHAM, AL
S101
521-16-103
SLW SLM06-26-17
1/4" = 1'-0"S101
2 GENERATOR PLATFORM FRAMING PLAN
1/4" = 1'-0"S101
1 ROOF FRAMING PLAN
BEAM-SEE PLAN
STEEL COLUMN,
SEE PLAN
BEAM
WORK POINT
3/8" GUSSET PLATE TYP.
T/ STL
SEE PLAN
CL
WORK POINT
WORK POINT
2 1 /2"
3"
2"
1/2
3/4" Ø BOLTS
L 4X4X1/4
3/16
TYP
1/4
+1-0" ABOVE EXISTING
ROOF SLAB
HORIZTONAL BRACE -
SEE PLAN
3/8" STIFFENER
PLATE EA. SIDE
3/16
BEAM-SEE PLAN
STEEL COLUMN,
SEE PLAN
BEAM
WORK POINT
T/ STL
SEE PLAN
CL
WORK POINT
WORK POINT
3/8" PLATE
2 1 /2"
3"
2"
1/2
3/4" Ø BOLTS
L 4X4X1/4
1/4
TYP
CL
1/8
1/4" PLATE
+1-0" ABOVE EXISTING
ROOF SLAB
HORIZTONAL
BRACE -SEE
PLAN
3"
3"
STEEL COLUMN,
SEE PLAN
5/16
3/4" THICK BASE PLATE, U.N.O.
CL
CL
0'-10"
0' -1
0"
STEEL BEAM,
SEE PLAN
DOUBLE ANGLES (5/16"
THICKNESS MIN.)
NOTE:
QTY OF FASTENERS TO BE
BASED ON THE BEAM SIZE.
C BEAML
BEAM SIZE
W8
W10
W12
W16
# OF 3/4" A325
BOLTS
W14
3" MAX.
3" S
P A
C E
S
3" M
A X
W18 5
4'-0" MAX. E
Q
E Q
3' -6
T
Y P
1 1/2" XS
PIPE-TYP.
BEAM, SEE PLAN
TOE PLATEGRATING - SEE PLAN
WT3x4.5xWEB HEIGHT AT W18x35 WT2.5x9.5xWEB HEIGHT AT W16x31
S501
1/4" CLOSURE PLATE
1/4"x4"XCONT.
TOE PLATE
(1/8")
1/ 4"
BEAM SEE PLAN
WT3x4.5xWEB HEIGHT AT W18x35 WT2.5x9.5xWEB HEIGHT AT W16x31
CHAMFER AS REQUIRED
CHAMFER AS REQUIRED
GUARDRAIL
1/8
3/16
T/ ROOFING
T/ CONCRETE FILL ON METAL DECK
3" DIAMETER STD PIPE POST AT EACH
STRINGER WITH 1/2"x0'-5"x0'-5" PLATE
TOP AND BOTTOM. ANCHOR TO SLAB
WITH (2) 1/2"x2 3/4" EMBED
EXPANSION ANCHORS
4'
3'
3'
E Q
E Q
M A
X
7"
F
IE
LD
V
E R
IF
Y
1 1/2" XS PIPE TYP
1 1/2" XS PIPE TYP
S P
A C
IN
G
4" T
O 7"
E Q
MIN
11"
M
IN
1'
SEE TYPICAL WIDE
FLANGE CONNECTION
DETAILS
BEAM, SEE
PLAN
C12X20.7
CHANNEL
STRINGER TYP
L2x2x3/8
TYP
GRATING SEE
PLAN. NOTCH
AROUND RAIL
POST AS REQD
3/16
TYP
1"
GRATING
SEE PLAN
3/16
TYP
EXISTING BEAM ,
SEE PLAN
WT8x25
3/16 2@12
STAGGER WELD
POST SEE PLAN
EXISTING DECK, SEE PLAN.
DEMO ONLY AS REQUIRED
TO INSTALL NEW POST AND
BASE PLATE.
EXISTING BEAM, SEE PLAN.
DEMO (1) HEADED STUD
MAX TO INSTALL NEW BASE
PLATE
BEAM REINFORCING SEE
PLAN AND TYPICAL
DETAIL
BASE PLATE, SEE
TYPICAL BASE PLATE
DETAIL
1/4
TYP
POST SEE PLAN
EXISTING DECK, SEE PLAN.
DEMO ONLY AS REQUIRED
TO INSTALL NEW POST AND
BASE PLATE.
EXISTING BEAM, SEE PLAN.
DEMO (1) HEADED STUD
MAX TO INSTALL NEW BASE
PLATE
BASE PLATE, SEE
TYPICAL BASE PLATE
DETAIL
1/4
TYP
EXIST. COLUMN,
SEE PLAN
BEAM-SEE PLAN
STEEL COLUMN,
SEE PLAN
BEAM
WORK POINT
T/ STL
SEE PLAN
CL
WORK POINT
WORK POINT
3/8" PLATE
2 1 /2"
3"
2"
1/2
3/4" Ø BOLTS
L 4X4X1/4
1/4
TYP
CL
1/8
1/4" PLATE
+1-0" ABOVE EXISTING
ROOF SLAB
HORIZTONAL
BRACE -SEE
PLAN
3380 Trickum Road
Woodstock, GA. 30188 770-517-5507 voice 770-517-5508 fax
Bldg. 500, Ste. 100 www.ieiusa.com
INCORPORATED
INNOVATIVE
ENGINEERING
Department of
Veterans Affairs
VA FORM 08-6231
1 2 3 4 5 6 7 8 9
Date:
Drawing Title:
Approved Project Director
Project Title:
1 2 3 4 5 6 7 8 9
100% SUBMITTAL
590 MEANS ST NW N/A
Phase Project Number
Building Number
Drawing NumberLocation
Issue Date CheckedFULLY SPRINKLERED
STAMP
STE. 200
ATLANTA, GA 30318
ARCHITECT/ENGINEER OF RECORDCONSULTANT
F ile
P a th
A
B
C
D
E
F
U.S. Department of Veterans Affairs
Office of Construction and Facilities Management
Drawn
STEEL DETAILS REPLACE/UPGRADE
ELECTRICAL SWITCHGEAR
PHASE 3
BIRMINGHAM, AL
S501
521-16-103
Checker Author
1 1/2" = 1'-0"S501
SINGLE BRACE CONNECTION DETAIL TO
COLUMN - BEAM OVER COLUMN
1 1/2" = 1'-0"S501
2 SINGLE BRACE CONNECTION DETAIL TO COLUMN
1 1/2" = 1'-0"S501
3 TYPICAL BASE PLATE
3/4" = 1'-0"S501
4 TYPICAL BEAM TO BEAM CONNECTION
3/4" = 1'-0"S501
5 TYPICAL RAILING DETAIL
3/4" = 1'-0"S501
6 TYPICAL RAILING CONNECTION DETAIL
3/4" = 1'-0"S501
9 TYPICAL STAIR SECTION
1 1/2" = 1'-0"S501
7 TYPICAL BEAM REINFORCING DETAIL
3/4" = 1'-0"S501
8 SECTION AT NEW POST TO EXISTING BEAM
3/4" = 1'-0"S501
11 NEW POST TO EXISTING COLUMN DETAIL
1 1/2" = 1'-0"S501
10 SINGLE BRACE CONNECTION DETAIL TO BEAM
File details come from the government source that posted it.