36C24718B0635-0002001.pdf

PDF 10 MB Posted

Attached to
Replace/Upgrade Electrical Switchgear Phase 3 Federal contract opportunity
Solicitation number
36C24718B0635
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 7

About this file

36C24718B0635 0002 Replace Elec Switchgear-MEP.pdf

View the file

Other files for this federal contract opportunity

Other files attached to Replace/Upgrade Electrical Switchgear Phase 3, newest first.
File Type Posted
36C24718B0635-0011001.pdf PDF
36C24718B0635-0011000.docx DOCX document
36C24718B0635-0010006.docx DOCX document
36C24718B0635-0010009.pdf PDF
36C24718B0635-0010008.pdf PDF
36C24718B0635-0010007.pdf PDF
36C24718B0635-0009000.docx DOCX document
36C24718B0635-0009001.pdf PDF
36C24718B0635-0009002.pdf PDF
36C24718B0635-0008000.docx DOCX document
36C24718B0635-0007000.docx DOCX document
36C24718B0635-0007001.pdf PDF
36C24718B0635-0007002.pdf PDF
36C24718B0635-0007003.pdf PDF
36C24718B0635-0006001.pdf PDF
36C24718B0635-0006000.docx DOCX document
36C24718B0635-0006002.pdf PDF
36C24718B0635-0005000.docx DOCX document
36C24718B0635-0005001.pdf PDF
36C24718B0635-0004002.pdf PDF
36C24718B0635-0004001.pdf PDF
36C24718B0635-0004000.docx DOCX document
36C24718B0635-0002000.docx DOCX document
36C24718B0635-0002002.pdf PDF
36C24718B0635-0002003.pdf PDF
36C24718B0635-0001007.pdf PDF
36C24718B0635-0001008.pdf PDF
36C24718B0635-0001006.docx DOCX document
36C24718B0635-001.docx DOCX document
36C24718B0635-000.docx DOCX document
Show all 30

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

LEGEND AND GENERAL NOTES

PM001

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

PARTIAL FIRST AND SECOND

FLOOR PLUMBING AND

MECHANICAL PLANS

PM101

EXIT

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

FUEL OIL PIPING FOR

NEW GENERATOR

F101

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

LEGEND, SCHEDULES,

AND DETAILS

E101

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

MEDIUM VOLTAGE SYSETM

ONE-LINE DIAR=GRAM

DEMOLITION AND NEW WORK

E102

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

MCC NSBD

WORK PLAN

E201

CHILLER

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

MCC NSBD2

E202

VARIOUS PUMPS

AND EQUIPMENT

AREA

CHILLER

CHILLER

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

MCC NSBDA

E203

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

MCC N5D

E204

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

MCC Q5D

E205

VARIOUS PUMPS

AND EQUIPMENT

AREA

CHILLER

CHILLER

Project Number

Building Number

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

F

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

MCC QSBD

E206

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

T-1A & T-1N

TRANSFORMER WORK PLAN

E207

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

T-4A & T-4N

E208

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

T-3A, T-3N, T-5A & T-5N

E209

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

T-2A & T-2N

E210

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

EMERGENCY SYSTEM

E211

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

NEW GENERATOR

WORK PLAN - 2ND FLOOR

E212

Drawing Number

Project Title

Location

Issue Date Checked Drawn

Drawing Title

Approved:

A

100% SUBMITTAL

FULLY SPRINKLERED

Office of Construction and Facilities Management

U.S. Department of Veterans Affairs

B

C

D

E

A

B

C

D

E

F

21 4 5 6 7 8 9 10

Phase

ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT

321 4 5 6 7 8 9 10

REPLACE / UPGRADE

ELECTRICAL SWITCHGEAR

PHASE 3

BIRMINGHAM, AL

521-16-103

N/A

Project Director

10-02-17 RBP EGLRevisions: Date:

440 Martin Luther King Jr. Blvd

Macon, GA 31201

478.743.8415 Fax: 478.743.8239

www.clarknexsen.com

MEDIUM VOLTAGE CABLE

ROUTING COMPOSITE PLAN

E213

6948 PM001 LEGEND AND GENERAL NOTES
Layout(1)
Insert from: "6948 E213 MV CABLE ROUTING PLAN.pdf"
6948 E213 MV CABLE ROUTING PLAN
Layout
Insert from: "6948 E212 NEW GENERATOR WORK PLAN.pdf"
6948 E212 NEW GENERATOR WORK PLAN
Layout
Insert from: "6948 E211 EXISTING GENERATOR AND SWB WORK PLAN.pdf"
6948 E211 EXISTING GENERATOR AND SWB WORK PLAN
Layout
Insert from: "6948 E210 T-2A & T-2N TRANSFORMER WORK PLAN.pdf"
6948 E210 T-2A & T-2N TRANSFORMER WORK PLAN
Layout
Insert from: "6948 E209 T-3A, T-3N, T-5A & T-5N TRANSFORMER WORK PLAN.pdf"
6948 E209 T-3A, T-3N, T-5A & T-5N TRANSFORMER WORK PLAN
Layout
Insert from: "6948 E208 T-4A & T-4N TRANSFORMER WORK PLAN.pdf"
6948 E208 T-4A & T-4N TRANSFORMER WORK PLAN
Layout
Insert from: "6948 E207 T-1A & T-1N TRANSFORMER WORK PLAN.pdf"
6948 E207 T-1A & T-1N TRANSFORMER WORK PLAN
Layout
Insert from: "6948 E206 MCC-QSBD WORK PLAN.pdf"
6948 E206 MCC-QSBD WORK PLAN
Layout
Insert from: "6948 E205 MCC-Q5D WORK PLAN.pdf"
6948 E205 MCC-Q5D WORK PLAN
Layout
Insert from: "6948 E204 MCC-N5D WORK PLAN.pdf"
6948 E204 MCC-N5D WORK PLAN
Layout
Insert from: "6948 E203 MCC-NSBDA WORK PLAN.pdf"
6948 E203 MCC-NSBDA WORK PLAN
Layout
Insert from: "6948 E202 MCC-NSDB2 WORK PLAN.pdf"
6948 E202 MCC-NSDB2 WORK PLAN
Layout
Insert from: "6948 E201 MCC-NSBD WORK PLAN.pdf"
6948 E201 MCC-NSBD WORK PLAN
Layout
Insert from: "6948 E102 MEDIUM VOLTAGE SYSTEM ONE-LINE DIAGRAM - DEMOLITION AND NEW WORK.pdf"
6948 E102 MEDIUM VOLTAGE SYSTEM ONE-LINE DIAGRAM - DEMOLITION AND NEW WORK
Layout
Insert from: "6948 E101 LEGEND, SCHEDULES, AND DETAILS.pdf"
6948 E101 LEGEND, SCHEDULES, AND DETAILS
Layout
Insert from: "6948 F101FUEL OIL PIPING.pdf"
6948 F101FUEL OIL PIPING
Layout
Insert from: "6948 PM101 MECHANICAL 1ST FLOOR.pdf"
6948 PM101 MECHANICAL 1ST FLOOR
Layout

File details come from the government source that posted it.