This document is an Amendment to Solicitation for a renovation project at the Durham VA Medical Center. The solicitation (36C24624B0005) is a 100% set-aside for a Service-Disabled Veteran Owned Small Business, with a construction project magnitude between $2-5 million under NAICS code 236220. The amendment extends the bid submission deadline to May 6, 2025, at 11 AM EDT and includes responses to contractor questions about specific project details such as tile specifications, lead paint abatement, ceiling work, and traffic flow during renovation.

The amendment also implements changes related to Executive Orders 14173 and 14168, removing several standard labor and equal opportunity contract clauses. Contractors are required to submit hard copy bids by mail to the Department of Veterans Affairs Network Contracting Office in Hampton, VA, with specific attention to Vangie Miller. The project involves renovating halls, walls, and ceilings at the Durham VA Medical Center, with specific technical considerations including asbestos abatement, lead paint management, and potential hallway traffic management during construction phases.

View the file

Other files

File Type Posted
S07 Bid Abstract - 36C24624B0005.pdf PDF
36C24624B0005 0021.docx DOCX document
36C24624B0005 0020.docx DOCX document
36C24624B0005 0019.docx DOCX document
36C24624B0005 0017 04032025.pdf PDF
36C24624B0005 0016.docx DOCX document
36C24624B0005 0015.docx DOCX document
028333.14 ACM and LP Report.pdf PDF
36C24624B0005 0014.docx DOCX document
36C24624B0005 0013.docx DOCX document
36C24624B0005 0012.docx DOCX document
36C24624B0005 0011.docx DOCX document
36C24624B0005 0010.docx DOCX document
36C24624B0005 0009.docx DOCX document
36C24624B0005 0008.docx DOCX document
36C24624B0005 Amendment 0007 RFI regarding dates.pdf PDF
36C24624B0005 0007.docx DOCX document
RFI 10282024.pdf PDF
36C24624B0005 Amendment 0007 RFI regarding dates.pdf PDF
36C24624B0005 Amendment 0003 RFI regarding taxes (1).pdf PDF
36C24624B0005 0004 Solicitation Amendment Answer Questions.pdf PDF
36C24624B0005 0006.docx DOCX document
36C24624B0005 Solicitation Amendment 9.27.24.pdf PDF
36C24624B0005 0002.docx DOCX document
01 Drawings.pdf PDF
36C24624B0005_1.docx DOCX document
Project Specs.pdf PDF
Show all 27

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE

7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER

3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO.

1. CONTRACT ID CODE

FACILITY CODE

CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office.

is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER

16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30

PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243 (Type or print) (Type or print) (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code) (If other than Item 6) (Specify type of modification and authority) (such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

TBD

04-0 -2025 558-18-260 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Building 27 Hampton VA 23667 Department of Veterans Affairs Network Contracting Office 6 100 Emancipation Drive Hampton VA 23667 To all Offerors/Bidders

36C24624B0005 02-27-2024

X X X ** HOUR & DATE for Receipt of Offers is EXTENDED to: 05-06-2025 11 AM EDT x The purpose of this amendment is to update the solicitation and revise solicitation per Executive Orders.

See attachment for answers to questions received. Hour and date extended as in Box 11.

Bids must be hard copy and mailed IAW FAR 52.214-5 to the address in Box 6.

Send attention: Vangie Miller. Do not send electronic submissions.

Bid time is being extended to allow VA to answer questions shown on next page.

The question period is not being re-opened. Sign and return a copy of all amendments to the solicitation with bids.

Would you please confirm the precise Armstrong Ultima Tile reference # for this project?

Ultima Health Zone High NRC #1445 w/ Prelude XL 15/16" Exposed Tee grid?

Ultima Health Zone AirAssure #1950 w/ Prelude XL 15/16" Exposed Tee grid?

Ultima Health Zone #1935 w/ Prelude XL 15/16" Exposed Tee grid?

Ultima Health Zone #1935 w/ Prelude XL 15/16" Exposed Tee grid

Can you confirm if there will be (or not) any work be done on F Wing Reflected Ceiling?
See sheet A-113
Is all Lead paint located within the 6 phases, which is outlined within the specs, to be abated completely or just encapsulated/RRP?
The lead testing and lead specs were included so that if the asbestos abatement affects any surfaces with lead-containing paint, the contractor is aware of it to protect their employees properly, following RRP guidelines for cleanup, safety, etc. otherwise encapsulating with paint
At the walk through there was mention of doing the abatement in hallways “half and half.” meaning that there will always be a walkway during the abatement process. This will not only increase the cost but also increase the time it takes to abate each phase. Also, during demolition of the ceilings and wall-mounted items/accessories how will things be adjusted to accommodate for traffic flow? It may be in the best interest to lock down the phases for the duration of demolition/abatement so it can be done quicker with no disturbances
VA to answer by 4/16/25.
In wing E, will there be a new grid ceiling required? If so, will the entire Sprinkler system be required to be drained or can that hall be drained separately.
According to Drawing 3 on Sheet A-112, there will be dry fog spray exposed deck above in the corridors. There will not be new grid ceiling required.
Regarding abatement, It was stated that the hall can abated ½ at a time to allow traffic. If the work is done after hours can the entire hall be abated at once and an alternate traffic be found to accomplish this.
Recommend abating 1/2 at a time to allow traffic.
Regarding new material, will there be an area inside the building to acclimate the new flooring material?
VA to answer by 4/16/25.
Regarding expansion joints in the hallways. It was mentioned in the plans but there are no quantities in the plans.
Refer to Sheets A-001, A-101, A-102, A-103, A-201, A-202, and A-203 for the locations ( & quantities in graphical representation) of expansion joints and cover plates.

Implement the following changes pursuant to the Class Deviation from the Federal Acquisition Regulation, (FAR) regarding Executive Orders 14173 and 14168.

The following FAR clauses are hereby removed:

•52.222-9, Apprentices and Trainees
•52.222-21, Prohibition of Segregated Facilities
•52.222-22, Previous Contracts and Compliance Reports
•52.222-23, Notice of Requirement for Affirmative Action To Ensure Equal Employment Opportunity for Construction
•52.222-24, Preaward On-Site Equal Opportunity Compliance Evaluation
•52.222-25, Affirmative Action Compliance
•52.222-26, Equal Opportunity
•52.222-27, Affirmative Action Compliance Requirements for Construction

System updates may lag policy updates. The System for Award Management (SAM) may continue to require entities to complete representations based on provisions that are not included in agency solicitations. Examples include 52.222-25, Affirmative Action Compliance, and paragraph (d) of 52.212-3, Offeror Representations and Certifications—Commercial Products and Commercial Services. Contracting officers will not consider these representations when making award decisions or enforce requirements. Entities are not required to, nor are they able to, update their entity registration to remove these representations in SAM.

The following changes are made to reflect compliance with (DEVIATION FEB 2025) Executive Order 14173, “Ending Illegal Discrimination and Restoring Merit-Based Opportunity,” of January 21, 2025, revoking Executive Order 11246, “Equal Employment Opportunity”

· Replace 52.204-8 ANNUAL REPRESENTATIONS AND CERTIFICATIONS (MAR 2023) with 52.204-8, Annual Representations and Certifications (JAN 2025) (DEVIATION FEB 2025).

· Replace 52.222-6 CONSTRUCTION WAGE RATE REQUIREMETNS (AUG 2018) with 52.222-6 Construction Wage Rate Requirements (AUG 2018) (DEVIATION FEB 2025)

· Replace 52.222-11 SUBCONTRACTS (LABOR STANDARDS) (MAY 2014) with 52.222-11 Subcontracts (Labor Standards) (MAY 2014) (DEVIATION FEB 2025)

· Replace 52.222-12 CONTRACT TERMINATION—DEBARMENT (MAY 2014) with 52.222-12 Contract Termination—Debarment (MAY 2014) (DEVIATION FEB 2025)

· Replace 52.244-6 SUBCONTRACTS FOR COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (DEC 2023) WITH 52.244-6, Subcontracts for Commercial Products and Commercial Services (JAN 2025) (DEVIATION FEB 2025)