This document provides details for a federal construction contract opportunity to renovate and expand operating rooms at the Charles George VA Medical Center in Asheville, North Carolina. The project scope includes renovating approximately 5,000 square feet of existing operating room space and constructing approximately 8,000 square feet of new space. Key responsibilities for the contractor include permitting, demolition, construction, construction management, submittals, fixtures and equipment installation, scheduling, inspection and testing, environmental protection, alterations to existing structures, mechanical, electrical and plumbing work, fire protection, hazardous material removal, utility system expansion, and commissioning. The pre-proposal site visit is scheduled for January 23, 2020, with responses due February 27, 2020. The estimated value is between $10-20 million. The solicitation will be issued as 100% set aside for Service-Disabled Veteran Owned Small Businesses. The North American Industry Classification System code is 236220 with a size standard of $39.5 million.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Charles George VA Medical Center VA Project No. 637-315
Asheville, North Carolina
Expand/Renovate Operating Rooms Bid Documents: 03/22/19
Revision 1: 05/29/20
00 01 10-1
DEPARTMENT OF VETERANS AFFAIRS
VHA MASTER SPECIFICATIONS
TABLE OF CONTENTS
Section 00 01 10
DIVISION 00 - SPECIAL SECTIONS DATE
00 01 15 List of Drawing Sheets 09-11
DIVISION 01 - GENERAL REQUIREMENTS
01 00 00 General Requirements 10-14
01 32 16.15 Project Schedules 02-15
01 33 23 Shop Drawings, Product Data, and Samples 03-12
01 35 26 Safety Requirements 10-14
01 42 19 Reference Standards 09-11
01 45 00 Quality Control for Minor Construction --
01 45 29 Testing Laboratory Services 07-13
01 57 19 Temporary Environmental Controls 01-11
01 58 16 Temporary Interior Signage 08-11
01 74 19 Construction Waste Management 09-13
01 91 00 General Commissioning Requirements 06-13
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Demolition 04-13
02 82 11 Traditional Asbestos Abatement 07-11
02 82 13.19 Asbestos Floor Tile and Mastic Abatement 04-15
02 82 13.21 Asbestos Roofing Abatement 04-15
DIVISION 03 – CONCRETE
03 30 53 (Short-Form) Cast-in-Place Concrete 10-12
DIVISION 04 – MASONRY
04 05 13 Masonry Mortaring 09-11
04 05 31 Masonry Tuck Pointing 10-08
04 20 00 Unit Masonry 05-12
DIVISION 05 – METALS
05 12 00 Structural Steel Framing 11-12
05 21 00 Steel Joist Framing 03-10
05 31 00 Steel Decking 10-12
05 50 00 Metal Fabrications 07-14
DIVISION 06 – WOOD,PLASTICS AND COMPOSITES
00 01 10-2
06 10 00 Rough Carpentry 09-11
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 13 Thermal Insulation 06-12
07 22 00 Roof and Deck Insulation 10-10
07 24 00 Exterior Insulation and Finish Systems 10-11
07 42 13 Metal Wall Panels --
07 54 23 Thermoplastic Polyolefin Roofing --
07 60 00 Flashing and Sheet Metal 07-14
07 81 00 Applied Fireproofing 11-11
07 84 00 Firestopping 10-11
07 92 00 Joint Sealants 12-11
07 95 13 Expansion Joint Cover Assemblies 07-14
DIVISION 08 – OPENINGS
08 11 13 Hollow Metal Doors and Frames 01-13
08 14 00 Interior Wood Doors 10-12
08 31 13 Access Doors and Frames 10-11
08 41 13 Aluminum-Framed Entrances and Storefronts 10-11
08 71 00 Door Hardware 11-14
08 71 13 Automatic Door Operators 06-12
08 80 00 Glazing 05-14
08 90 00 Louvers and Vents 10-11
DIVISION 09 – FINISHES
09 06 00 Schedule for Finishes 10-11
09 22 16 Non-Structural Metal Framing 10-14
09 29 00 Gypsum Board 11-14
09 51 00 Acoustical Ceilings 12-13
09 65 13 Resilient Base and Accessories 10-11
09 65 16 Resilient Sheet Flooring 07-13
09 67 23.30 Resinous (Epoxy Resin Composition)Mortar Flooring (RES-
3)
07-14
09 91 00 Painting 07-13
09 96 59 Resinous Specialty Glazed Coating Systems for Walls and
Walboard (RES-W2)
DIVISION 10 – SPECIALTIES
10 26 00 Wall and Door Protection 01-11
10 44 13 Fire Extinguisher Cabinets 08-14
DIVISION 12 – FURNISHINGS
12 31 00 Manufactured Metal Casework 04-11
12 32 00 Manufactured Wood Casework 11-11
12 36 00 Countertops 06-13
00 01 10-3
DIVISION 13 – SPECIAL CONSTRUCTION
13 05 41 Seismic Restraint Requirements for Non Structural
Components
01-14
13 49 00 Radiation Protection 07-11
DIVISION 21- FIRE SUPPRESSION
21 05 11 Common Work Results for Fire Suppression 06-13
21 13 13 Wet-Pipe Sprinkler Systems 05-08
DIVISION 22 – PLUMBING
22 05 11 Common Work Results for Plumbing 07-14
22 05 23 General-Duty Valves for Plumbing Piping 07-14
22 07 11 Plumbing Insulation 05-11
22 11 00 Facility Water Distribution 01-14
22 13 00 Facility Sanitary and Vent Piping 07-14
22 14 00 Facility Storm Drainage 12-09
22 40 00 Plumbing Fixtures 01-14
22 62 00 Vacuum Systems for Laboratory and Healthcare Facilities 08-12
22 63 00 Gas Systems for Laboratory and Healthcare Facilities 12-10
DIVISION 23 – HEATING, VENTILATING, AND AIR
CONDITIONING (HVAC)
23 05 11 Common Work Results for HVAC 11-10
23 05 12 General Motor Requirements for HVAC and Steam
Generation Equipment
11-10
23 05 41 Noise and Vibration Control for HVAC Piping and
Equipment
11-10
23 05 93 Testing, Adjusting, and Balancing for HVAC 05-11
23 07 11 HVAC and Boiler Plant Insulation 05-11
23 08 00 Commissioning of HVAC Systems 06-13
23 09 23 Direct-Digital Control System for HVAC 09-11
23 21 13 Hydronic Piping 09-12
23 21 23 Hydronic Pumps 02-10
23 22 13 Steam and Condensate Heating Piping 03-10
23 22 23 Steam Condensate Pumps 02-10
23 25 00 HVAC Water Treatment 02-10
23 31 00 HVAC Ducts and Casings 03-13
23 34 00 HVAC Fans 11-09
23 36 00 Air Terminal Units 03-10
23 37 00 Air Outlets and Inlets 11-09
23 40 00 HVAC Air Cleaning Devices 02-12
23 64 00 Packaged Water Chillers 04-11
23 74 43 Custom, Outdoor, Air Handling Unit
23 82 16 Air Coils 04-11
DIVISION 26 – ELECTRICAL
00 01 10-4
26 05 11 Requirements for Electrical Installations 12-12
26 05 19 Low-Voltage Electrical Power Conductors and Cables 07-13
26 05 26 Grounding and Bonding for Electrical Systems 12-12
26 05 33 Raceway and Boxes for Electrical Systems 05-14
26 09 23 Lighting Controls 05-14
26 20 11 Isolated Power Systems 12-12
26 24 16 Panelboards 05-14
26 27 26 Wiring Devices 08-14
26 29 11 Motor Controllers 08-14
26 29 21 Enclosed Switches and Circuit Breakers 12-12
26 41 00 Facility Lightning Protection 12-12
26 51 00 Interior Lighting 08-14
DIVISION 27 – COMMUNICATIONS
27 05 11 Requirements for Communications Installations 11-09
27 05 26 Grounding and Bonding for Communications Systems 10-06
27 05 33 Raceways and Boxes for Communications Systems 12-05
27 10 00 Structured Cabling 12-05
27 15 00 Communications Horizontal Cabling 06-13
27 51 16 Public Address and Mass Notification Systems 06-13
27 52 23 Nurse Call and Code Blue Systems 06-13
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY
28 05 00 Common Work Results for Electronic Safety and Security 09-11
28 05 13 Conductors and Cables for Electronic Safety and
Security
09-11
28 05 26 Grounding and Bonding for Electronic Safety and
Security
09-11
28 05 28.33 Conduits and Backboxes for Electronic Safety and
Security
09-11
28 31 00 Fire Detection and Alarm 10-11
DIVISION 31 – EARTHWORK
31 32 23 Pressure Grouting Soil Stabilization 10-12
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 31 13 Chain Link Fences and Gates 05-13