TIL SPEC 312319_DeWatering.pdf

PDF 79 KB Posted

Attached to
F109--AMENDMENT POSTING ANSWER TO RFIS, UPDATED SOW, NEW SUB CLINS 36C24525Q0343 0002
Solicitation number
36C24525Q0343
Issued by

About this file

This document is a technical specification section (31 23 19) for Dewatering requirements in construction projects. The specification outlines comprehensive requirements for controlling groundwater and surface water during excavation and construction activities. Key requirements include:

The contractor must design and implement a dewatering system that lowers the groundwater table at least 1 foot below the excavation surface, maintains dry working conditions, prevents soil instability, and controls erosion and runoff. The system must operate continuously 24/7 until construction and backfilling are complete, with standby equipment available to ensure uninterrupted operation. Contractors must submit detailed dewatering plans 30 days prior to excavation, including equipment specifications, pump capacities, drainage methods, and compliance with all relevant permits. The specification emphasizes the contractor's responsibility for protecting the work area, preventing water-related damage, and immediately repairing any damages caused by dewatering operations.

View the file

Other files

File Type Posted
TIL SPEC 312011_Earthwork Compaction Backfilling.pdf PDF
TIL SPEC MATERIALS TESTING 014529.pdf PDF
TIL SPEC 013526 Safety.pdf PDF
36C24525Q0343 0003_1.docx DOCX document
Oil Ops Permit Extended PP VA MDE 03132024.pdf PDF
ICP_Loch Raven VAMC FinalAugust2020_v6r1eSigsreducedAD sign - SIGNED.pdf PDF
Tank Bldg D344_1977_1.pdf PDF
MDE AST_Closure_Fact_Sheet_6.9.23_6pgs.pdf PDF
ICP_1st half_Perry Point VAMC FINAL Oct 2021 SIGNED.pdf PDF
36C24525Q0343 0002 AMENDMENT.pdf PDF
Oil Ops Permit_PP MAR 2019 Update pg2.pdf PDF
VAMHCS SOW_AST SUPPORT 2025 Final R1 03202025.pdf PDF
SOP_Liquid Fuel Systems.pdf PDF
Oil Ops Permit_PP MAR 2019.pdf PDF
POLICY_VAMHCS AST UST 2022.pdf PDF
DWGS_Tank D315_1978 150KGal.pdf PDF
Tank Bldg D344_1977_3.pdf PDF
VAMHCS AST UST MCP 2022.pdf PDF
RFI Question and Answers.docx DOCX document
ICP 2nd half_Perry Point VAMCFINAL Oct 2021 SIGNED.pdf PDF
36C24525Q0343 0002_1.docx DOCX document
Tank Bldg D344_1977_2.pdf PDF
Tank D315_1978 150KGal_Dwgs.pdf PDF
ICP_Baltimore FINAL-August 2020_SIGNED.pdf PDF
36C24525Q0343 0001.pdf PDF
36C24525Q0343 0001_1.docx DOCX document
WAGE DETERMINATION 2015-4265_BT.pdf PDF
WAGE DETERMINATION 2015-4215_PP.pdf PDF
AST_Closure_Fact_Sheet_6.9.23_6pgs.pdf PDF
Loch Raven VAMC ICP Site Plan.pdf PDF
Perry Point VA Medical Center Visitor Guide.pdf PDF
Perry Point VAMC ICP Site Plan.pdf PDF
36C24525Q0343_RFQ-.pdf PDF
36C24525Q0343_1.docx DOCX document
Baltimore VAMC ICP Site Plan.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

10-01-12

31 23 19 - 1

SECTION 31 23 19

DEWATERING

PART 1 - GENERAL

1.1 DESCRIPTION:

This section specifies performance of dewatering required to lower and control ground water table levels and hydrostatic pressures to permit excavation, backfill, and construction to be performed in the dry.

Control of surface water shall be considered as part of the work under this specification.

1.2 SUMMARY:

A. The work to be completed by the Contractor includes, but is not necessarily limited to the following:

1. Implementation of the Erosion and Sedimentation Control Plan.

2. Dewater excavations, including seepage and precipitation.

B. The Contractor shall be responsible for providing all materials, equipment, labor, and services necessary for care of water and erosion control. Excavation work shall not begin before the Erosion and

Sedimentation Control Plan is in place.

1.3 REQUIREMENT:

A. Dewatering system shall be of sufficient size and capacity necessary to lower and maintain ground water table to an elevation to allow material to be excavated in a reasonably dry condition. Materials to be removed shall be sufficiently dry to permit excavation to grades shown and to stabilize excavation slopes where sheeting is not required. Operate dewatering system continuously until backfill work has been completed.

B. Reduce hydrostatic head below any excavation to the extent that water level in the construction area is a minimum of 300 mm (1 foot) below prevailing excavation surface.

C. Prevent loss of fines, seepage, boils, quick conditions or softening of foundation strata.

D. Maintain stability of sides and bottom of excavation.

E. Construction operations are performed in the dry.

F. Control of surface and subsurface water is part of dewatering requirements. Maintain adequate control so that:

1. The stability of excavated and constructed slopes are not adversely affected by saturated soil, including water entering prepared subbase and subgrades where underlying materials are not free draining or are subject to swelling or freeze-thaw action.

31 23 19 - 2

2. Erosion is controlled.

3. Flooding of excavations or damage to structures does not occur.

4. Surface water drains away from excavations.

5. Excavations are protected from becoming wet from surface water, or insure excavations are dry before additional work is undertaken.

G. Permitting Requirements: The contractor shall comply with and obtain the required State and County permits where the work is performed. For tank closures, must comply with required state and county permits already obtained by the Construction projects for which they are associated.

1.4 RELATED WORK:

A. Materials testing and inspection during construction: Section 01 45 29, TESTING LABORATORY SERVICES.

B. Safety Requirements: Section 01 35 26

C. Protection of existing utilities, fire protection services, existing equipment, roads, and pavements: Section 01 00 00, GENERAL

REQUIREMENTS.

E. Subsurface Investigation: Section 01 00 00, GENERAL REQUIREMENTS, Article 1.11, PHYSICAL DATA.

F. Excavation, backfilling, site grade and utilities: Section 31 20 11, EARTH MOVING.

1.5 SUBMITTALS:

A. Data:

1. Submit the method to be employed in dewatering excavated areas 30 days before commencement of excavation.

2. Material shall include: location, depth and size of wellpoints, headers, sumps, ditches, size and location of discharge lines, capacities of pumps and standby units, and detailed description of dewatering methods to be employed to convey the water from site to adequate disposal.

3. Provide control procedures to be adopted if dewatering problem arises.

4. Capacities of pumps, prime movers, and standby equipment.

5. The dewatering system shall be designed using accepted and professional methods of design and engineering consistent with the best modern practice. The dewatering system shall include the deep

31 23 19 - 3 wells, wellpoints, and other equipment, appurtenances, and related earthwork necessary to perform the function.

6. Detailed description of dewatering procedure and maintenance method.

7. Materials submitted shall be in a format acceptable for inclusion in required permit applications to any and all regulatory agencies for which existing permits for discharge water from the dewatering system are required due to the discharge reaching regulated bodies of water.

C. All required existing permits.

PART 2 - EXECUTION

2.1 INSTALLATION:

A. Install a dewatering system to lower and control ground surface water in order to permit excavation, construction of structure, and placement of backfill materials to be performed under dry conditions. Make the dewatering system adequate to pre-drain the water-bearing strata above and below the bottom of structure foundations, utilities and other excavations.

B. In addition, reduce hydrostatic pressure head in water-bearing strata below structure foundations, utility lines, and other excavations, to extent that water levels in construction area are below prevailing excavation surface at all times.

2.2 OPERATION:

A. Prior to any excavation below the ground water table, place system into operation to lower water table as required and operate it continuously

24 hours a day, 7 days a week until utilities and structures have been satisfactorily constructed, which includes the placement of backfill materials and dewatering is no longer required.

B. Place an adequate weight of backfill material to prevent buoyancy prior to discontinuing operation of the system.

2.3 WATER DISPOSAL:

A. Dispose of water removed from the excavations in such a manner as:

1. Will not endanger portions of work under construction or completed.

2. Will cause no inconvenience to Government or to others working near site.

3. Will comply with the stipulations of required permits for disposal of water.

4. Will Control Runoff: The Contractor shall be responsible for control of runoff in all work areas including but not limited to:

31 23 19 - 4 excavations, access roads, parking areas, laydown, and staging areas. The Contractor shall provide, operate, and maintain all ditches, basins, sumps, culverts, site grading, and pumping facilities to divert, collect, and remove all water from the work areas. All water shall be removed from the immediate work areas and shall be disposed of in accordance with applicable permits.

B. Excavation Dewatering:

1. The Contractor shall be responsible for providing all facilities required to divert, collect, control, and remove water from all construction work areas and excavations.

2. Drainage features shall have sufficient capacity to avoid flooding of work areas.

3. Drainage features shall be so arranged and altered as required to avoid degradation of the final excavated surface(s).

4. The Contractor shall utilize all necessary erosion and sediment control measures as described herein to avoid construction related degradation of the natural water quality.

C. Dewatering equipment shall be provided to remove and dispose of all surface and ground water entering excavations, trenches, or other parts of the work during construction. Each excavation shall be kept dry during subgrade preparation and continually thereafter until the structure to be built, or the pipe to be installed therein, is completed to the extent that no damage from hydrostatic pressure, flotation, or other cause will result.

2.4 STANDBY EQUIPMENT:

Provide complete standby equipment, installed and available for immediate operation, as may be required to adequately maintain de-watering on a continuous basis and in the event that all or any part of the system may become inadequate or fail.

2.5 CORRECTIVE ACTION:

If dewatering requirements are not satisfied due to inadequacy or failure of the dewatering system (loosening of the foundation strata, or instability of slopes, or damage to foundations or structures), perform work necessary for reinstatement of foundation soil and damaged structure or damages to work in place resulting from such inadequacy or failure by Contractor, at no additional cost to Government.

31 23 19 - 5

2.6 DAMAGES:

Immediately repair damages to adjacent facilities caused by dewatering operations.

2.7 REMOVAL:

Insure compliance with all conditions of regulating permits and provide such information to the Resident Engineer. Obtain written approval from

COR before discontinuing operation of dewatering system.

----- E N D -----