Pre-Bid RFIs Log -613-124 POD C 1-06-2022 SENT.xlsx
XLSX spreadsheet 276 KB Posted
- Solicitation number
- 36C24521B0011
About this file
This is a solicitation for a construction project to renovate and expand a 47-bed domiciliary pod at a Department of Veterans Affairs medical center. The scope of work includes a complete renovation of an existing 17,600 square foot single-story building that is 30 years old, replacement of the HVAC system, addition of 5,000 square feet of new construction, abatement of asbestos floor tile and duct mastic, and exterior transite panels. Competition is restricted to Service Disabled Veteran Owned Small Businesses. The estimated construction cost range is $5 million to $10 million. Responses are due on October 13, 2021. Interested parties must register on the Vendor Information Pages and SAM websites to be eligible. A pre-bid site visit will be held, and all questions must be submitted in writing. The award will be made to the responsive and responsible bidder with the lowest price.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
3.1 PTSD
| CONSTRUCTION RFI LOG | |||||||||||||
| Project | PTSD RRTP | RFIs allow 10 business days for review | |||||||||||
| VA PN: | 554-318 | ||||||||||||
| VEG PN: | 3.01 | ||||||||||||
| ID | Date | Request for Information | Responsible Firm | Decision Maker | Date Forwarded | Request for Information Response | DATE DUE | Date Completed | Date on Sub CV | Date on Faith CV | Faith Deadline | ||
| Unique ID | Date | ||||||||||||
| Added | Describe request for information. | Ex: VA or VEG or Corps of ENG | Person who will | ||||||||||
| provide a response. | Provide response to request for information. | Date information is |
needed by.
*green: complete *beige: due >7days *yellow: due < 7 days
| *red: past due | Date this item was completed. | |||||||||||
| 1 | 11/20/20 | Rcvd. 11/23/2020 Due 10/27/2020 (Civil/Structural Dept. Lead) Rick Keeler Arch. Lead Need misc steel details required by steel fabricator in order to prepare steel shop drawings. Due to long lead dleivery for joists these shop drawings are critical to our schedule So.02, S1.11, S1.12, S1.14, S1.15, A1.11 | VEG | Reid Dumas | See markings on RFI response | 11/30/20 | 11/25/20 | 11/20/20 | 11/20/20 | 11/20/20 | ||
| 2 | 11/20/20 | Rcvd 10/23/2020 Due 10/27/2020 (Civil/Structural Dept.) | ||||||||||
| Details need to be consistent and cover all situations Recommend CMU not be set below grade SHEETS: S3.41, A3.21, A3.42, A3.51 - | VEG | Reid Dumas & Rick Keeler | Wall Section D10 on Sheet A3.22 should be revised to match Wall Section H6 on Sheet A3.22. The lug for the concrete block should be deleted and the slab poured continuous to the outside face of the foundation wall. This also applies to Wall Section D4 on Sheet A3.21. Refer to attached revised structural Detail D8. |
| Well Section H8 on Sheet A3.22 should also delete the concrete block shown on the foundation wall. The floor slab and foundation wall should be poured out to the face of the concrete block wall above. The intent of this Wall Section is to show the finish applied to the foundation wall at this location. The basis of design for the retaining wall is the Versa-Lok System. When the retaining wall returns to the building foundation, a portion of the foundation wall is exposed concrete. See Elevation B9 on Sheet A2.11. The textured face of a Versa-Lok unit can be split off to form a 2”+/- unit which will be mortared to the face of the foundation wall. This will provide a finish on the foundation wall that will match the Versa-Lok Retaining Wall System. This design has been coordinated with a local representative | 11/30/20 | 11/25/20 | 11/23/20 | 11/23/20 | 11/23/20 | |||||||
| 3 | 11/23/20 | Rcvd 11/23/2020 (Civil/Structural Dept. Lead) Rick Keeler Arch. In accordance with paragraph 1.29 please provide details for the site project sign. In accordance with paragraph 1.30 request Standard Detail Drawing Number SD10000-02 (found on VA TIL) of safety sign showing required legend and otehr characteristics of sign. Spec oi 0000-24 1.29 & 1.30 | VEG | Reid Dumas & Rick Keeler | Safety sign drawing submitted by Moses Jacobs | 12/3/20 | 11/30/20 | None | 11/23/20 | 11/23/20 | ||
| 4 | 11/25/20 | Rcvd 11/25/20 Foundation details S1.11 | VEG | Will | 1. U/S of baseplate confirmed at 99’-5 ½” resting on pilaster. The |
round objects are aluminum column covers and do not affect the u/s of base plate elevation (See note on DWG A1.11).
2. Top of footing shall be changed to 1’-0” to be consistent with adjacent footings.
3. Those are not structural columns. They are architectural features and must remain. 4. U/S of baseplate confirmed at 99’-5 ½” resting on pilaster as shown on DWG’S S3.21 and S3.22. It is not on continuous concrete ledge.
5. Sizes on footing details are typical and pilaster sizes shown are acceptable to accommodate base plates and anchor rod clear cover.
Baseplate types 1 and 3 max length is 16” and is attached to 20”
| pilaster. Type 2 baseplate is 20” length attached to 24” pilaster. | 12/5/20 | 12/1/20 | 11/24/20 | 11/24/20 | 11/24/20 | ||
| 5 | 11/24/20 | Please see the attached RFI and advise on items 1 thru 3 for clarification at the door jamb steel. | VEG | Will | 1. Type shall read Q-125 and Q-126. |
2. Anchors shall be post applied. Anchors shall be expoxy type concrete anchors at the diameter and embed as specified on the drawings. Hilti HY-200 or Simpson Set-XP or approved equivalent is acceptable.
3. Proposed connection is acceptable if the strength of the proposed
| connection is equal to or exceeds strength of original weld design | 12/1/20 | 12/1/20 | 11/24/20 | 11/24/20 | 11/24/20 | |||||||
| 6 | 11/24/20 | Please see the attached and proivde verification of items 1 thru 3 at the entrance roof area. See S1.13 | VEG/ Sans Structural | Will | 12/1/20 | 12/11/20 | 11/24/20 | 11/24/20 | 11/24/20 | |||
| 7 | 11/24/20 | See Subcontractor input S1.13 and S1.14 | VEG/ Sans Structural | 12/1/20 | 12/11/20 | 11/24/20 | 11/24/20 | 11/24/20 | ||||
| 8 | 11/24/20 | See subcontractor input S1.13-S1.15, S2.22, S2.42-43 | VEG/ Sans Structural | 12/1/20 | 12/14/20 | 11/24/20 | 11/24/20 | 11/24/20 | ||||
| 9 | 11/25/20 | CD101 require relocation of existing irrigation control valve that is near East property Line. Can not find any indication of where this valve is to be relocated to. Also will removing this valve deactivate irrigation system for our project site? | VEG/ Sans Structural | Adam | On CD101 change “EXISTING IRRIGATION VALVE TO BE |
RELOCATED” to “EXISTING IRRIGATION VALVE TO BE
REMOVED”.
The existing irrigation valve will not be used in irrigation for the project
| site. See L-400 for site irrigation point of connection in building. | 12/1/20 | 12/1/20 | None | 11/25/20 | 11/25/20 | ||||||||
| 10 | 11/30/20 | Floor loading confirmation | VEG/ Sans Structural | Reid | See markings on RFI response | 12/5/20 | 12/14/20 | 11/30/20 | 11/30/20 | 11/30/20 | |||
| 11 | 12/3/20 | Potential impact to method excavation and backfill | VEG/ Sans Structural | Reid | Provided new grade drawings - Will and John provided first response, then Reid and Dustin completed second revision | 12/16/20 | 12/18/20 | 12/3/20 | 3-Dec | 12/3/20 | |||
| 12 | 12/11/20 | REMOVED | Architectural | Rick K. | REMOVED | 12/24/20 | NA | ||||||
| 13 | 12/15/20 | Proposed alternate connection - clip angles on both sides of HSS members | Structural | Reid | Subcontractors alternative approved | 12/28/20 | 12/27/20 | 12/11/20 | 12/15/20 | 12/15/20 | |||
| 14 | 12/15/20 | Drawing and detail sketches | Structural | Reid | John at San and Reid completed response including several new details | 12/30/20 | 12/30/20 | 12/11/20 | 12/15/20 | 12/15/20 | |||
| 15 | 12/15/20 | Building footing subgrade soil compaction | Structural | Reid | 95% required - 100% not necessary - Kumar report used for reference on soil type only | 12/28/20 | 12/17/20 | None | 12/15/20 | 12/17/20 | |||
| 16 | 12/18/20 | Deck openings requiring support frames below | Structural | Dan Nyugen | Dan Nyugen replied - coordinate with sheet M202 and mech contractor for consolidated layout drawing for all new systems - refer to spec 23 05 11 1.4.F for requirements | 12/23/20 | 12/23/20 | 12/18/20 | 12/18/20 | 12/18/20 | |||
| 17 | 12/18/20 | Deck clarifications | Structural | Reid | Yes, Vulcrafts suggestions were accepted | 12/23/20 | 12/22/20 | 12/17/20 | 12/18/20 | 12/18/20 | |||
| 18 | 12/18/20 | Spray on fireproofing requirements | Architectural | Rick K. | No spray on fireproofing required - LS101 and key note 9.29A are called out by Rick First response provided 12/29/20 | 12/23/20 | 12/31/20 | 12/18/20 | 12/18/20 | 12/23/20 | |||
| 19 | 12/18/20 | Grid layout dimensions and verifcation | Structural | Reid | Reid provided dimensions | 1/1/21 | 12/23/20 | 11/20/20 | 12/18/20 | 12/18/20 | |||
| 20 | 12/21/20 | Deck sidelap connection | Structural | Will | Will provided: See S1.12 for plan notes | 1/1/21 | 12/22/20 | 12/18/20 | 12/21/20 | 12/21/20 | |||
| 21 | 12/18/20 | Joist seat depths from Vulcraft | Structural | Reid | Approved | 12/24/20 | 12/29/20 | 12/18/20 | 12/21/20 | 12/21/20 | |||
| 22 | 12/22/20 | Strip stone v panels | Architectural | Rick K. | Yes they match | 1/1/21 | 12/24/20 | 12/22/20 | 12/22/20 | 12/22/20 | |||
| 23 | 12/29/20 | Aluminium framed siding | Architectural | Paul | Paul provided guidance on siding - spec 08 41 13 | 1/10/21 | 12/31/20 | 12/11/20 | 12/29/20 | 12/29/20 | |||
| 24 | 12/31/20 | Transformers | Electrical | Trent | Dry type transformer is specd however, EPA requires oil containment type pad | 1/12/21 | 1/12/21 | 11/13/20 | 12/30/20 | 12/30/20 | |||
| 25 | 1/4/21 | Connection clarifications | Structural | Reid/John | John at San and Reid completed response including several new details | 1/15/21 | 1/14/21 | 12/31/20 | 1/1/21 | 1/7/21 | |||
| 26 | 1/4/21 | Edge of deck | Structural | Reid/John | 1/15/21 | 1/15/21 | 12/31/20 | 1/1/21 | 1/7/21 | ||||
| 27 | 1/8/21 | Step footing | Structural | Reid/Dustin | VEG provided step footing details for elevation | 1/8/21 | 1/8/21 | None | 1/8/21 | 1/8/21 | |||
| 28 | 1/8/21 | Screenwall anchor and steel | Structural | Reid/ Paul | Proceed with profile size shown | 1/22/21 | 1/15/21 | 1/5/21 | 1/8/21 | 1/8/21 | |||
| 29 | 1/8/21 | HSS Connection verification | Structural | Reid/Dustin/ John | 1/19/21 | 1.1/4” plate stiffener is acceptable at this moment connection. | |||||||
| 2.HSS connection is acceptable adjacent to moment connection. | 1/22/21 | 1/22/21 | 1/5/21 | 1/8/21 | 1/8/21 | ||||||||
| 30 | 1/8/21 | Overhang clarification | Structural | Reid/Dustin | 1/19/21 | 1'-10" overhang. | 1/22/21 | 1/20/21 | 1/5/21 | 1/8/21 | 1/8/21 | ||
| 31 | 1/13/21 | Back flow preventers (P301) | Plumbing | Mark/ Bud | 1/19/21 | See specification section 22 05 23 Paragraph 2.7 for reduced pressure backflow preventer requirements. | 1/26/21 | 1/19/21 | None | 1/12/21 | 1/12/21 | ||
| 32 | 1/14/21 | cabinet width clarification | Architectural | Rick K. | 1/19/21 | Original design intent was that glass shelving would be supported by KV shelf brackets, one at each edge and one at the midpoint. No single glass span is greater than 2'-0". Color to match clear anodized aluminum or stainless steel per | |||||||
| manufacturer's recommendations. | 1/27/21 | 1/27/21 | 1/14/21 | ||||||||||
| 33 | 1/14/21 | Moment Weld clarifications | Structural | Reid/Dustin | 1/19/21 | 1.Proposed moment connection at sloped connection is acceptable. |
2.Plates can be reduced to 5” wide at top and 7” wide at bottom to work with W18x40 flange width.
3.L5x5x3/8 angle is acceptable where column terminates at roof level.
4.Use ¼” fillet welds at these connections.
5.Use ¼” fillet welds at these connections.
| 6.The proposed moment connection is acceptable. | 1/27/21 | 1/22/21 | 1/14/21 | ||||||||
| 34 | 1/18/21 | Drainage | Civil | NA | NA | Abandoned pipe - RFI removed | NA | NA | 1/18/21 | ||
| 35 | 1/18/21 | Storm drain from Fisher | Civil | Dustin | 1/20/21 | See completed design from Ron and Dustin - design was redone due to missing pipe information on sewer pipe | 1/29/21 | 2/1/21 | 1/18/21 | ||
| 36 | 1/19/21 | ES102 COM Box | Electrical | Ron | 1/20/21 | Faith decided to remove com box, and build new | 1/31/21 | 1/21/21 | 1/19/21 | ||
| 37 | 1/19/21 | ES102 Transformer Pad | Civil | Reid | 1/19/21 | Reid provided dimensions | 2/1/21 | 1/19/21 | 1/19/21 | ||
| 38 | 1/19/21 | Shower Slabs | Architectural | Paul | 1/20/21 | All showers shall have depressed slabs to coordinate with E7/A9.31 | 2/1/21 | 1/22/21 | 1/19/21 | ||
| 39 | 1/20/21 | Stair materials | Architectural | Paul | 1/22/21 | Construction documents show 9 risers on the bottom string, 14 on the top, with approximately 4’-6” clear at bottom of stairs on first floor. Please clarify the detail where the topmost riser and stringer meet the penthouse deck. Construction documents show the edge of deck on gridline B1. The intent was to cope the stringer to achieve this. Shop drawings show the edge of deck projecting +/- 9” into the stairwell. | 2/1/21 | 1/28/21 | 1/20/21 | ||
| 40 | 1/27/21 | Conductors | Electrical | Trent | 1/27/21 | Please disregard wire sizes in Key Notes 2 & 3 and refer to feeder 700 on |
sheet E-601 which shows the conductors being extended from the 15kV Normal Power Paralleling Switchgear in the main building through Vault EN3A as well as from the 15kV Paralleling Generator Switchgear through
| Vault EN3B to the new transformers TN-1 and TE-1 serving the building. | 2/9/21 | 1/28/21 | 1/25/21 | ||||||
| 41 | 1/28/21 | CD 102 VA signs | Electrical | Trent | 1/28/21 | REDO DESIGN FOR LIGHTED SIGNS | 2/10/21 | ||
| 42 | 1/28/21 | RFI 27 Footing | Structural | Reid/Dustin/ John | 1/29/21 | 2/10/21 | |||
| 43 | 1/28/21 | P202 sewer/footing interface | Plumbing | Mark/ Bud | 2/2/21 | 2/10/21 | |||
| 44 | 1/28/21 | Light pole bases and coordination | Lighting | Jill | 1/28/21 | 2/10/21 | |||
| 45 | 2/1/21 | Retainage wall elevation | Reid/Dustin | 2/1/21 | 2/12/21 | ||||
| 46 | 2/3/21 | Stair layout - RFI 39 clarification | Paul | 2/3/21 | 2/16/21 | ||||
| 47 | |||||||||
| 48 | |||||||||
| 49 | |||||||||
| 50 | |||||||||
| 51 | |||||||||
| 52 |
&D Page &P of &N &G
3.06
4.08
4.17
4.26
18.10
19.26
| Construction Request For Information (RFI) Log | ||||||||
| Project | Renovate 47-Bed Domiciliary Pod C and Replace AHUs | |||||||
| VA PN: | 613-124 | |||||||
| VEG PN: | 19.26 | DATE: 1/19/2022 | ||||||
| ID | Date Rec'd | Design Comment | Response | Client/ Source | Assignee(s) | Priority | Date Needed | Date Completed |
| Unique ID | Date |
Added (Incoming) Describe request for information (RFI). Response to the RFI Ex: VA, CFM, VEG or Corps of ENG Assignee Relative priority:
1-High 2-Medium 3-Low Date information is needed by.
*green: complete *beige: due >7days *yellow: due < 7 days *red: past due Date this item was completed.
(Outbound)
| 1 | 12/15/21 | What are the permit requirements for this project? | VERIFY PERMIT REQUIREMENTS WITH SITE SAFETY OFFICER AND SAM POWELL, VA COR | VA CO | Moses Jacobs, Project Architect | 1 | 12/22/21 | 12/27/21 | ||
| 2 | 12/15/21 | Is it possible to provide as-built drawings of POD C for all trades? | CD was burned with all drawings provided by VA at beginning of project and shipped Wednesday with arrival at noon Thrusday, Dec 30, 2021 | VA CO | Moses Jacobs, Project Architect | 1 | 12/22/21 | 12/30/21 | ||
| 3 | 12/15/21 | Please provide a copy of the HazMat survey referenced on Drawing Page HA101 Volume II Part 1 | Copy of Hazmat/ ACM survey sent via email 12/29/2021 | VA CO | Moses Jacobs, Project Architect | 1 | 12/22/21 | 12/29/21 | ||
| 4 | 12/15/21 | Details on A-620 and A-621 do not show sufficient anchorage to support blast rated aluminum storefront. Steel angle embeds will need to be provided by others in order for blast rated system to meet design criteria. Can you please provide steel angle details and sizing? | SPECIFIC ANCHORAGE TO THE BUILDING STRUCTURE (INCLUDING BUT NOT LIMITED TO EMBEDS, TRANSFER BRACKETS AND ANCHORS) MUST BE DESIGNED AND PROVIDED BY THE STOREFRONT SUPPLIER/CONTRACTOR AND COORDINATED WITH OTHER TRADES. REFER TO Q5 RESPONSE. | VA CO | Moses Jacobs/ Carrie Davis | 1 | 12/22/21 | 12/27/21 | ||
| 5 | 12/15/21 | Due to the Mission Critical with GP2 loading and 50’ standoff requirements, all exterior frames and glazing will need to be blast resistant. This includes frames 1 and 2/A-620. All exterior aluminum frames will require connection to head and sill substrate. Slab embed plates will be required to which the custom mullion anchored. The head condition will need to have structural steel framing for custom mullion anchor connections. The current drawing details show only wood blocking. Can you please provide steel embed details and sizing? | REFER TO STRUCTURAL DRAWINGS AND RESPONSE TO Q4 | VA CO | Moses Jacobs/ Carrie Davis | 1 | 12/22/21 | 12/27/21 | ||
| 6 | 12/15/21 | Can you confirm that the only details to be included in the proposal are: | ||||||||
| a. | Signed/Completed SF-1442 | |||||||||
| b. | Pricing Sheets | |||||||||
| c. | Bid Bond | |||||||||
| d. | Safety & Environmental Record | |||||||||
| e. | EMR | |||||||||
| f. | Reps & Certs | |||||||||
| g. | Acknowledgement of Immigration & Nationality Act of 1952 | These are the required documents. Please ensure that a full review is completed of the package requirements so all items are received complete. | VA CO | Kathryn Kaiser | 1 | 12/22/21 | 1/27/22 | |||
| 7 | 12/15/21 | In addition to the original, how many copies of the proposal should be submitted? | One copy should be provided, as referenced on the SF1442. | VA CO | Kathryn Kaiser | 1 | 12/22/21 | 1/27/22 | ||
| 8 | 12/15/21 | Is hand delivery the only acceptable proposal delivery method? | Proposals may be hand delivered or mailed to: |
Department of Veterans Affairs Attn: Kathryn Kaiser 510 Butler Avenue, Bldg. 306A
| Martinsburg, WV 25405 | VA CO | Kathryn Kaiser | 1 | 12/22/21 | 1/27/22 | |||||
| 9 | 12/15/21 | Will Pod C be occupied during construction? | The C Pod will not be occupied during construction. | VA CO | Kathryn Kaiser | 1 | 12/22/21 | 1/27/22 | ||
| 10 | 12/20/21 | According to spec 09 06 00 – Schedule for Finishes, Wardrobes & Bedroom Desks, Desktop is noted to be Quartz “Stellar Snow” and vertical surfaces are noted to be PLAM #1 – Formica “9479-NG Wide Plank Walnut”. Elevations 4 & 5/A-224 indicates the desktop as PLAM #2 and the vertical surfaces of the wardrobe as PLAM #3. Which is correct? If Plam #3 is correct – can you provide the plastic laminate color selection? | FINISH CALLOUTS INDICATED ON ELEVATIONS 4 & 5/A-224 ARE SUPERSEDED BY THE SPECIFICATION. COMPLY WITH FINISHES INDICATED IN SPECIFICATION SECTION 09 06 00, SCHEDULE FOR FINISHES, 2.6 DIVISION 06 WOOD, PLASTICS, AND COMPOSITES, A. SECTION 06 20 00, FINISH CARPENTRY, 7. WARDROBES & BEDROOM DESKS. | VA CO | Moses Jacobs, Project Architect | 1 | 12/27/21 | 12/27/21 | ||
| 11 | 12/20/21 | On plan A-113, there may be casework/cabinetry in the Laundry Rm 502C-149. There is no enlarged plan or elevations provided. Please clarify casework / countertop requirements for this room | COMPLY WITH FINISHES INDICATED IN SPECIFICATION SECTION 09 06 00, SCHEDULE FOR FINISHES, 2.6 DIVISION 06 WOOD, PLASTICS, AND COMPOSITES, A. SECTION 06 20 00, FINISH CARPENTRY, 6. KITCHEN CABINETS. | VA CO | Moses Jacobs, Project Architect | 1 | 12/27/21 | 12/27/21 | ||
| 12 | 1/3/22 | Reference: |
•Dwg E001 communications general notes (D) states all data to be Cat 6A, but on the same drawing under communication cabling requirements (1.A) states Cat 6 cabling •Dwg E001 communications general notes (F) states cameras to be Cat 6, but on dwg ET110 keynotes (3 & 7) states Cat 6A for cameras.
•Dwg E001 communication cabling requirements (14.A) states Cat 6 for WAP’s, but dwg ET110 keynote (1) states Cat 6A for WAP’s.
| Need clarification on the structured cabling required (Cat 6 or Cat 6A): | Cat 6A is now a VA requirement. | VA CO | Trent Lindsley | |
| Electrical Engineering | 1 | 1/10/22 | 1/9/22 | |
| 13 | 1/3/22 | Flooring |
• The finish plans show "WSF" or welded sheet flooring throughout except in the bathrooms. However, the finish schedule lists two products they call SV#1 & SV#2, both of which are plank tiles, not sheet vinyl.
| • We are including wall tile for the shower enclosures. “Wall Tile & Schluter Dilex Trim inside shower enclosures receives wall panels.” Will these be installed by (others) or should we plan to install wall board and Schlueter with the tile? | 1- Provide and install per plans and specs dated 12/11/2020. Refer to Q22 Response (item 22). 2- Refer to plan pg A-413 / General note E and plan pg A-220 detail 17 for further clarification. | VA CO | Moses Jacobs, Project Architect | 1 | 1/10/22 | 1/12/22 | ||||
| 14 | 1/3/22 | Can we be provided a link for the plans and specifications for this project? The information on Sam.Gov does not seem complete/full size, can Architectural drawings showing building elevations, window/storefront details, door schedule be provided? They seem to be missing | The drawing and specifications for this project were provided with the solicitation package on SAMS.gov. Missing or updated information has been resolved with this amendment. Exterior Building Elevations are indicated on sheets A-210 to A-212. Window and Storefront Details are indicated on sheet A-621. The Door Schedule is shown on sheet A-620. | VA CO | VA - Kathryn Kaiser | 1 | 1/10/22 | 1/27/22 | ||
| 15 | 1/3/22 | For the blast windows and storefront I would require the intended standoff distance, charge size and blast level. (blast levels are: 1, 2 , 3a, 3b or 4) can this information be provided? From what I see the intention is to use level 2. | ||||||||
| Glazing 08 80 00 section 2.1 D call for low iron glass while in several other places I see sample requirements for tinted glass. The whole idea of low iron is to remove the excess iron from standard glass that removes the greenish tint present. Low Iron with tint defeats the purpose of Low Iron? | Design standoff distance = 25-feet. Provide blast rated (hardened) window and storefront frames with 1-in AN IGU* glazing. Window/Storefront framing system must be connected to the primary building structure as indicated on the drawings. *1-in AN IGU = 1/4-in annealed outer lite x 1/2-in air gap x 1/4-in AN laminated inner lite with 0.030-in PVB interlayer. | VA CO | Moses Jacobs, Project Architect | 1 | 1/10/22 | 1/10/22 | ||||
| 18 | 1/3/22 | Ref Dwgs: EL113,EL114,EL115, and E504 | ||||||||
| EL114 calls for (1) 24 channel LV Panel. EL113 and EL115 has 16 channel LV panels Total (2). E 504 has description of 4 channel LV panels, which there is a total of 57. There is nothing in the specs nor any detail drawings show manufacturer or design. Requesting info on panel used in design or manufacturer. | Refer to attached manufacturers information arp.PDF | VA CO | Moses Jacobs, Project Architect |
Trent Lindsley
| Electrical Engineering | 1 | 1/10/22 | 1/10/22 | ||||
| 19 | 1/3/22 | E505 calls for a Graphic Wall Pod. There is nothing in the specs nor any detail drawings show manufacturer or design. Requesting info on panel used in design or manufacturer. | Refer to attached manufacturers information npod_gfx-form.PDF | VA CO | Moses Jacobs, Project Architect |
Trent Lindsley
| Electrical Engineering | 1 | 1/10/22 | 1/10/22 | ||||
| 20 | 1/3/22 | E505 calls for a 8 Port Network Bridge.. There is nothing in the specs nor any detail drawings show manufacturer or design. Requesting info on panel used in design or manufacturer. | Refer to attached manufacturers information nbrg-8.PDF | VA CO | Trent Lindsley | ||
| Electrical Engineering | 1 | 1/10/22 | 1/10/22 | ||||
| 21 | 1/3/22 | E601 show 1-line description of MDP and MDPE. Specs Section 26-24-13 details requirements including electrical ratings, breaker sizes, interrupting ratings, etc. Can we assume that using existing Switchboard dimensions is all we need above this, to furnish vendors for pricing. | ES-103 shows locations. Contractor should field verify space available. | VA CO | Trent Lindsley | ||
| Electrical Engineering | 1 | 1/10/22 | 1/10/22 | ||||
| 22 | 1/3/22 | Vinyl Sheet Flooring WSF (SV#1 and SV#2) specs given in the spec book does not verify as sheet but as plank. (Provided Option for both sheet and Plank separately, please confirm) |
R: SV#1: Patcraft, Style TBD, 00250 Beachscape, Resilient 1600V Click Refresh, https://www.patcraft.com/product/detail/I600V/00250?installation-method=stagger&room-scene=1162#specs-sustainability
R: SV#2: Karndean, Style TBD, Neutral Oak LLP 307, Loose Lay Longboard
| https://www.karndean.com/en/commercial-flooring/products/neutral-oak-llp307 | Provide and install WSF per A-640 - Room Finish Schedule (sheet dated 12/11/2020). Specification Section 09 06 00 (D. Section 09 65 16, Vinyl Sheet Flooring, Heat Welded Seams (WSF): should be corrected to read as follows: Finish Code = SV#1, Pattern Name = Enrich, Collection name = Eco System, Manufacturer = Patcraft, Mfg. Color Name/No. = Meditate/ 00105. NOTE: Omit SV#2. | VA CO | Moses Jacobs, Project Architect | 1 | 1/10/22 | 1/12/22 |
| 23 | 1/3/22 | Two Resilient Sheet finishes are given that is SV#1 and SV#2 but room finish schedule as well as Finish plan only shows WSF therefore Separate sheet or planks are estimated for Corridors, Offices, Bedrooms, Bariatric Rooms and Lounges and separate for BOH Room respectively as per General Note D on sheet A-641. (Please confirm) | ||||
| All flooring will be WSF except bathrooms as shown on plans and in specs. Refer to Q22 Response (item 22). | VA CO | Moses Jacobs, Project Architect | 1 | 1/10/22 | 1/12/22 | |
| 24 | 1/3/22 | Option for Resilient Plank is provided as per the General Note C on Sheet A-642 (Please confirm) |
| General Note C: Install Laminate Flooring at all corridors, Offices, Bedrooms, Bariatric Rooms, and Lounges | Disregard "general note C". All flooring will be WSF as shown, other than bathrooms. Refer to Q22 Response (item 22). | VA CO | Moses Jacobs, Project Architect | 1 | 1/10/22 | 1/12/22 | ||||
| 25 | 1/3/22 | Shower Surrounds are composite shower panels therefore they are not estimated. (Please confirm) | Include in bid as indicated on plans and in specs dated 12/11/2020. | VA CO | Moses Jacobs, Project Architect | 1 | 1/10/22 | 1/12/22 | ||
| 26 | 1/4/22 | Is there any documentation of the invert of the 4” sanitary mains that run through the corridors? | Project # 613-012B, record drawings 9/27/1982, sheet W-4R indicates an invert of 502.60' same drawings indicate a finished floor elevation of 508' | VA CO | Moses Jacobs - Arch | |||||
| Mitch Bible - Mech Eng. | 1 | 1/11/22 | 1/11/22 | |||||||
| 27 | 1/4/22 | Will a temporary hose bibb need to be provided during construction? | Refer to Specification Section 01 00 00, Paragraph 1.21, subparagraph F. | VA CO | Moses Jacobs - Arch | |||||
| Mitch Bible - Mech Eng. | 1 | 1/11/22 | 1/11/22 | |||||||
| 28 | 1/4/22 | The specifications and Fixture Schedule on drawing P701 are for Shower Bath Faucet only, not the shower stall itself. During the site visit I noticed in the recently completed units the shower was a roll in one piece fiberglass unit that was recessed into the floor. What brand, size, and seat requirement are needed? | Line 6 of the "Plumbing Fixture Schedule" identifies mark P-704 as "Shower with antiscald valve, head and hand held". Plan pg A-224 detail 1 shows fold down seat which is called out on pg A-413 detail 1, mark 12 and 13 under "Toilet Accessories Legend", also see pg A-414. Spec section 10 21 16 identifies the prefabricated shower enclosure product. | VA CO | Moses Jacobs - Arch | |||||
| Mitch Bible - Mech Eng. | 1 | 1/11/22 | 1/12/22 | |||||||
| 29 | 1/4/22 | We were informed that Johnson Controls Inc are the proprietary controls contractor for the facilities. Can we get the hospital's contact for JCI? | Contact Abbad Malik - abbad.m.malik@jci.com | VA CO | VA - Sam Powell/ COR | 1 | 1/11/22 | 1/27/22 | ||
| 30 | 1/4/22 | On the site walk, we were taken to a similar space that was just completed. We noticed that components were not the same manufacturer as indicated in these prints schedule. As long as we meet "equivalent", are there any issues with submitting substitute manufacturers? | Equivalents are not acceptable, provide and install per plans and specs dated 12/11/2020. | VA CO | Moses Jacobs - Arch | |||||
| Mitch Bible - Mech Eng. | 1 | 1/11/22 | 1/12/22 | |||||||
| 31 | 1/4/22 | What will the regular working hours be on this project? | Normal business hours, as listed in the solicitation, are Monday - Friday from 8:00am - 4:30pm. There are flexibilities to these hours that can be discussed after award. | VA CO | VA - Kathryn Kaiser | 1 | 1/11/22 | 1/27/22 | ||
| 32 | 1/4/22 | Will all work be performed during regular hours? | Not necessarily, refer to the General Requirements specification included with the package. Electrical, mech, data, etc shutdowns that affect other parts of the hospital will have to be performed off hrs. and as approved by the COR. | VA CO | VA - Kathryn Kaiser | 1 | 1/11/22 | 1/27/22 | ||
| 33 | 1/5/22 | Is there a generator included in this project or is there some type of tie-in to a pre-existing generator? | There is no new generator. Drawing E-602 shows connection to emergency power. | VA CO | Moses Jacobs-Arch Trent Lindsley-EE | 1 | 1/11/22 | 1/11/22 | ||
| 34 | 1/6/22 | Will the contractor be responsible for removing/storing and re-installing furniture? | No. The VA will remove moveable furniture. Built-in items are the contractor's responsibility. Equipment and other items to be re-installed are the responsibility of the contractor to remove, protect and re-install. | GC | VA - Sam Powell/ COR | 1 | 1/13/22 | 1/13/22 | ||
| 35 | 1/6/22 | Will the contractor be responsible for disposing of any furniture? | No. The VA will remove moveable furniture. Built-in items are the contractor's responsibility. Equipment and other items to be re-installed are the responsibility of the contractor to remove, protect and re-install. | GC | VA - Sam Powell/ COR | 1 | 1/13/22 | 1/13/22 | ||
| 36 | 1/6/22 | Will the contractor be responsible for supplying any new furniture? | No. The VA is responsible for furnishing and installing moveable items. The contractor is responsible for furnishing and installing built-in items, like millwork. | GC | VA - Sam Powell/ COR | 1 | 1/13/22 | 1/13/22 | ||
| 37 | 1/6/22 | Can other lighting controls be used instead of the nLight controls in the drawings? | Systems by other manufacturers are allowed to bid as nLight was used as a basis of design. Final approval and acceptance of the proposed lighting control system will be determined by the design engineer during product submittal review for meeting design intent and specification requirements. | GC | Robert / Jill | 1 | 1/13/22 | 1/12/22 | ||
| 38 | 1/6/22 | We are getting feedback from numerous subcontractors in different trades and experiencing the same issue with both sets of plans that were released on Amd #2. Once they are uploaded to Planswift or any takeoff software, the drawings seem to pixalate and the scales are not working. It almost seems like they are screenshots. Vol 1 and 3 work perfectly, is there a way to export volume 2A and 2B the same way? | The drawing issues were corrected through Amendment #2. If there are still difficulties contact the CO at kathryn.kaiser@va.gov | VA CO | Kathryn Kaiser | 1 | 1/13/22 | 1/27/22 | ||
| 39 | 1/6/22 | Storefront frames type 1 and 2 call for a 1” solid panel (B.O.D. mapes). These frames are blast rated with a criteria that Mapes cannot match. The best they can offer is their MapeShield panel that is teste to DoD standards in 2005. One item we could offer is use the 1-5/16” blast rated glazing in these areas with a spandrel layer to give the desired aesthetics. Please let us know your thoughts. | Provide opaque insulated panels in accordance with storefront manufacturer's requirements to maintain storefront system blast rating. | GC | Moses/Dee | 1 | 1/13/22 | 1/13/22 | ||
| 40 | 1/6/22 | Bid item 5 or Alternate #6 listed in the specifications is not listed on the solicitation’s description of work. Please confirm if this alternate will apply. If so, can the VA add that extra line item in Block 17 of the SF1442. | The solicitation states, in Block 17 of the SF1442, that remaining bid items #2-5 are listed on pg. 9. The CO noticed during review, however, that there is a Bid Item #6 listed in the General Requirements that was not listed on pg. 1 of the 1442, listed in the Bid Item tabulation on pg. 2 of the 1442 or provided in the additional Bid Item's starting on pg. 9. A revised, complete 1442 document has been attached to this Amendment for response usage. | GC | Kathryn Kaiser | 1 | 1/13/22 | 1/13/22 | ||
| 41 | 1/6/22 | Please confirm if Contractor will include dumpsters and/or storage units for any furniture to be removed or relocated currently inside bldg. | See answers 34 and 35 | GC | VA - Sam Powell/ COR | 1 | 1/13/22 | 1/27/22 | ||
| 42 | 1/6/22 | Window Basis of design? | Wojan Window and Door Corp, M950 Blast | GC | Moses/Dee | 1 | 1/13/22 | 1/27/22 | ||
| 43 | 1/6/22 | When is the project intended to get awarded, NTP? | This project is planned to be awarded well within the bid acceptance period. | GC | VA - Sam Powell/ COR | 1 | 1/13/22 | 1/27/22 | ||
| 44 | 1/6/22 | Are funds available this year? | This solicitation is subject to the availability of funds but, award is anticipated this fiscal year | GC | VA - Sam Powell/ COR | 1 | 1/13/22 | 1/27/22 | ||
| 45 | 1/6/22 | Please confirm that the qualified Superintendent cannot double hat the SSHO. | See spec section 01 35 26 | GC | VA - Sam Powell/ COR | 1 | 1/13/22 | 1/27/22 | ||
| 46 | 1/6/22 | Is this project sales tax exempt? | No | GC | VA - Sam Powell/ COR | 1 | 1/13/22 | 1/27/22 | ||
| 47 | 1/7/22 | Is MC cable acceptable for branch power and/or feeders? | MC in not acceptable. See VA Specs. | GC | Robert | 1 | 1/14/22 | 1/14/22 | ||
| 48 | 1/7/22 | Is aluminum wire acceptable for feeders? | See VA specs. Must be copper. | GC | Robert | 1 | 1/14/22 | 1/14/22 | ||
| 49 | 1/7/22 | Does the lighting control wiring (Cat 5) need to be in a raceway, or can it be installed without raceways? | Cable tray is to be used for the installation and routing of the CAT5 lighting control network cable inside the bldg. If cable tray is not available in the area where the lighting control cable is installed, then provide hangers or j-hooks to avoid the cable resting upon the ceiling, piping or ductwork. | GC | Jill / Robert | 1 | 1/14/22 | 1/10/22 | ||
| 50 | 1/7/22 | Please provide the preferred fire alarm vendor. | COR has no access to vendor right now. | GC | VA - Sam Powell/ COR | 1 | 1/14/22 | 1/7/22 | ||
| 51 | 1/7/22 | Is there a schedule for this project? | Schedules are developed by contractor. | GC | VA - Sam Powell/ COR | 1 | 1/14/22 | 1/7/22 | ||
| 52 | 1/7/22 | Will any of the electrical portion of the work need to be completed on off hrs? | Yes | GC | VA - Sam Powell/ COR | 1 | 1/14/22 | 1/7/22 | ||
| 53 | 1/7/22 | E-001 and appendix to Div 27(Communication Cable Requirement-1) states "2 data and 2 voice". E-501 #12 states "1 voice and 2 data", which is correct? | The specs say (3) cables. 2-data and 1-voice. Use specifications for this item. | GC | Robert / John Cazer | 1 | 1/15/22 | 1/11/22 | ||
| 54 | 1/24/22 | What is the hardware group for doors 123, 132, 136 and 141 | For Doors 123, 132, and 141 CHANGE SPECIFICATION – | |||||||
| A. | 08 71 00 DOOR HARDWARE, Paragraph 3.5 Hardware Sets, : ADD Hardware Set as follows: |
HW-10C
| Hinges | QUANTITIY & TYPE AS NEEDED | ||||
| 2 | Wall Stop | L02121 CONVEX | |||
| 1 | Set Auto Flush Bolts | Type 25 | |||
| 1 | Dust Proof Strike (L04021) | 570 | |||
| 1 | Storeroom Lock | F07 | Interchangeable Core | ||
| 1 | Coordinator (Type 21A) | 2600 Series | |||
| 2 | Closer | C02011/C02021 | |||
| 2 Kick Plate | J102 | ||||
| 2 | Silencer | L03011 | |||
| 1 | set frame seals | R0Y164 |
OPERATION DESCRIPTION:
1. The doors are normally closed and secure.
2. Egress from the unsecured side is always available by turning the lever on the lockset.
| 3. Key on secured side will retract latch to allow entry. For Door 136: CHANGE Sheet A-620, Door Schedule (for Door No. 136) HDW SET from 10C to SH-5A. | GC | Moses/Dee | 1 | 1/24/22 | 1/25/22 | |||||
| 55 | 1/24/22 | What is the minimum gauge of cold formed metal framing? | Specification Section 054000 and Section 092216 supesede drawing requirements. Cold Formed Metal Framing must be 20 guage, minimum. | VEG | Moses | 1 | 1/24/22 | 1/26/22 | ||
| 56 | 1/24/22 | On Sheet A-113 there are several unreferenced Section call-outs. Where are these unreferenced Section call-outs shown on the drawings? | The unreferenced Section call-outs on Sheet A-113 are unintended and should be ignored. | VEG | Moses | 1 | 1/24/22 | 1/26/22 |
18.12
18.13
18.14
| CONSTRUCTION RFI LOG | ||||||||||||
| Project | Replace Boiler #1 | |||||||||||
| VA PN: | 660-17-100 | |||||||||||
| VEG PN: | 18.14 | |||||||||||
| ID | Date | Request for Information | Client/ Source | Decision Maker | Priority | Valhalla Response | Date Needed | Date Completed | Action for Bulletin | Date Completed | ||
| Unique ID | Date | |||||||||||
| Added | Describe request for information. | Ex: VA, CFM, VEG or Corps of ENG | Assignee | Relative priority: |
1-High 2-Medium 3-Low Provide response to Client Comment/ Request Date information is needed by.
*green: complete *beige: due >7days *yellow: due < 7 days *red: past due Date this answer was provided. Date this item as completed.
| 1 | 4/27/20 | Composition Analysis Natural Gas | ***Answered directly by the VA*** | 5/7/20 | 5/7/20 | ||
| 2 | 6/3/20 | Boiler Tie-In Location | 6/13/20 | 6/18/20 | |||
| 3 | 6/3/20 | Coal Bin Demolition | 6/13/20 | 6/10/20 | |||
| 4 | 6/17/20 | Wall Location and Expansion | 6/27/20 | 6/26/20 | |||
| 5 | 6/17/20 | Access Panels for CMU | 6/27/20 | 6/25/20 | |||
| 6 | 8/3/20 | Rebar Splicing Requirements | 8/13/20 | 8/3/20 | |||
| 7 | 8/20/20 | Electrical Relocation | Forwarded to electrical on 08/21/2020 | 8/30/20 | 8/24/20 | ||
| 8 | 8/20/20 | Footing and Foundation Steps | 8/30/20 | 8/25/20 | |||
| 9 | 8/24/20 | Foundation and Footing Clarifications | 9/3/20 | 8/25/20 | |||
| 10 | 8/24/20 | Steel Joist Measurements | Canyons contacted the steel fabricator directly to answer their questions since this RFI was really a shop drawing that need some clarifications. No official RFI response was issued. | ||||
| UPDATE: Steel joist design information was submitted in the resubmitted structutral steel shop drawings which were reviewed and returned. | 9/3/20 | - | |||||
| 11 | 9/8/20 | Steam Vault Issues | RHI was delayed in getting the GPR test results to the design team for structural evalulation of the vault lid. After analysis, the vault lid does not have sufficient capacity to carry the boiler load during installation so a 1" thick steel construction plate is being proposed to distribute the load. | 9/18/20 | 10/21/20 | ||
| 12 | 9/15/20 | Foundation Wall Thickness | 9/25/20 | 9/18/20 | |||
| 13 | 10/22/20 | Footing and Foundation Continuous Pour | 11/1/20 | 10/22/20 | |||
| 14 | 10/26/20 | Brick Veneer at Existing Electrical Shop Wall | Pour new foundation stem wall to carry the new brick veneer | 11/5/20 | 11/3/20 | ||
| 15 | 11/17/20 | Expansion joint above damper on flue exhaust stack | Reviewed with no Exceptions…. as shown on drawings | 11/27/20 | 1/29/21 | ||
| 16 | |||||||
| 17 | |||||||
| 18 | |||||||
| 19 | |||||||
| 20 | |||||||
| 21 | |||||||
| 22 | |||||||
| 23 | |||||||
| 24 | |||||||
| 25 | |||||||
| 26 | |||||||
| 27 | |||||||
| 28 | |||||||
| 29 | |||||||
| 30 | |||||||
| 31 | |||||||
| 32 | |||||||
| 33 | |||||||
| 34 | |||||||
| 35 | |||||||
| 36 | |||||||
| 37 | |||||||
| 38 | |||||||
| 39 | |||||||
| 40 | |||||||
| 41 | |||||||
| 42 | |||||||
| 43 | |||||||
| 44 | |||||||
| 45 | |||||||
| 46 | |||||||
| 47 | |||||||
| 48 | |||||||
| 49 | |||||||
| 50 | |||||||
| 51 | |||||||
| 52 | |||||||
| 53 | |||||||
| 54 | |||||||
| 55 | |||||||
| 56 | |||||||
| 57 | |||||||
| 58 | |||||||
| 59 | |||||||
| 60 |