This document contains details regarding a Multiple Award Task Order Contract (MATOC) solicitation for construction projects at VA medical centers in Pittsburgh, Erie, and Butler, Pennsylvania. The scope of work includes furnishing labor and materials for construction projects valued between $2,000 and $20,000,000, to be performed at VA facilities in those locations. Eligible projects include new hospital construction, renovations, and general maintenance and expansion of hospital campuses. The solicitation is a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses. The VA intends to award between 5 and 10 MATOC contracts, with an initial task order for renovating prosthetics at the Heinz campus in Pittsburgh to be awarded to one contractor on a lowest price basis, valued between $1,000,000 and $2,000,000. The period of performance for the seed project is 365 days from notice to proceed. The solicitation is expected to be posted on August 30, 2019. Offerors must register in SAM and be verified as eligible in VIP by the proposal due date.
36C24419R0037 EXHIBIT D - CALCULATION OF SELF-PERFORMED WORK.pdf
View the file
Other files
Show all 33
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT D - CALCULATION OF SELF-PERFORMED WORK
SUBMITTED IN RESPONSE TO RFP 36C24419R0037
Use a format similar to the following to identify and calculate cost of the work to be self-performed. Refer to the definitions pertaining to “Self-performance of work”, “On the Site” and “Total amount of work to be performed under the contract”.
(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)
Clearly describe the work to be self-performed:
Show Calculation of Self-Performed work: $
B.1 Total Offer Price: $
B.2 Subtract Specialty Trades If applying as a General Contractor (unless being self-performed): $
B.3 Subtract G&A, home office overhead, prime contractor’s markups for profit, bond, state use tax, etc.: $
B.4 Remainder (“Total amount of work to be performed under the Contract”: $
B.5 Work to be self-performed: $
Amount shown on this line should match the amount shown for “Show Calculation of Self-Performed work”?
(Includes mobilization and utilization of owned or rented plant and equipment to be operated by the prime contractor’s own employees; only those materials which will be both purchased and installed by the prime’s own forces; labor associated with those aforementioned materials or equipment; only those supplies to directly support work performed by the contractor’s own employees; and the contractor’s own job overhead costs.)
B.6 15 % Self-performed Work = Line B.5 / B.4 X 100% = %