This solicitation is for a construction project to replace exterior windows at the James J. Peters VA Medical Center in Bronx, New York. The project has a cost estimate between $5-10 million and is classified under NAICS code 236220 with a size standard of $39.5 million. It will be set aside for Service-Disabled Veteran Owned Small Businesses. The scope of work involves replacing windows to create an energy efficient and environmentally-friendly facility in compliance with green building standards. The construction contractor will be responsible for fall protection, removing and reinstalling any equipment impacted by the window replacements, and completing the project within 726 calendar days of receiving the notice to proceed. Interested SDVOSBs should submit capability statements by the presolicitation response due date. The full solicitation with additional details will be posted on SAM.gov around December 31, 2021.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HOLIHAN ASSOCIATES LLC
FINAL SUBMISSION
Bronx, New York
NOVEMBER 2020
Office of
Facility
Management
Service
REPLACE EXTERIOR WINDOWS PHASE 1
JAMES J. PETERS MEDICAL CENTER
BRONX, NEW YORK
526-18-103
Drawing TitleMedical Center Director Approval
Associate Director Approval
PCC Director Approval
Chief Engineer Approval
Safety Manager Approval
Chief Nurse Executive / Chief of Staff Approval
Location Drawing Number
Building Number
Project Title
Of
DrawnChecked Date
Project Number
Dwg.
DESIGN CHANGE APPROVED
DESCRIPTION DATE
CONSULTANT FIRM ARCHITECTURAL ENGINEERING FIRM
311 FELS AVE. FAIRHOPE, AL 36532
KEY PLAN
NINTH FLOOR
OVERALL PLAN
AS091
JMA
SD
NINTH FLOOR
OVERALL PLAN
SCALE: 1/16" = 1'-0"
AS091
F
D E
A
G
BC
GENERAL NOTES
1. OVERALL FLOOR PLAN HAS BEEN PROVIDED FOR REFERENCE USE TO DETERMINE INTERIOR AND
EXTERIOR ACCESS IN AND AROUND THE FACILITY.
2. REFER TO ENLARGED FLOOR PLANS AS REFERENCED FOR ADDITIONAL INFORMATION RELATED TO
DEMOLITION AND NEW WORK PLANS.
3. SUBMIT CONSTRUCTION ACCESS ROUTES, LAY DOWN AND STAGING AREA PLANS TO CO/COR FOR
APPROVAL PRIOR TO START OF WORK.
4. CONSTRUCTION ACTIVITIES IN SOME PHASES MAY AFFECT MEANS OF EGRESS FROM PORTIONS OF THE
FACILITY. CONTRACTOR SHALL COORDINATE ANY TEMPORARY BLOCKAGE OR REROUTING OF
EMERGENCY EGRESS DURING CONSTRUCTION WITH THE FACILITY SAFETY OFFICER PRIOR TO ANY DISRUPTION. CONTRACTOR SHALL SUBMIT A SAFETY PLAN TO THE CO/COR FOR APPROVAL PRIOR TO START OF WORK. CONTRACTOR SHALL OBTAIN WRITTEN APPROVAL OF SAFETY PLAN FROM CO/COR A
MINIMUM OF 72 HOURS PRIOR TO START OF WORK.
W2
W2
W3
W3
W5
W4
W4
W4
W5
W5
W3
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W1
W1
W1
W1
W1
W1
W1
W1
W1
W1
W1
W1
W1
W1
HOLIHAN ASSOCIATES LLC
FINAL SUBMISSION
Bronx, New York
NOVEMBER 2020
Office of
Facility
Management
Service
REPLACE EXTERIOR WINDOWS PHASE 1
JAMES J. PETERS MEDICAL CENTER
BRONX, NEW YORK
526-18-103
Drawing TitleMedical Center Director Approval
Associate Director Approval
PCC Director Approval
Chief Engineer Approval
Safety Manager Approval
Chief Nurse Executive / Chief of Staff Approval
Location Drawing Number
Building Number
Project Title
Of
DrawnChecked Date
Project Number
Dwg.
DESIGN CHANGE APPROVED
DESCRIPTION DATE
CONSULTANT FIRM ARCHITECTURAL ENGINEERING FIRM
311 FELS AVE. FAIRHOPE, AL 36532
KEY PLAN
PARTIAL NINTH FLOOR PLAN
EAST SIDE - SOUTH END
AS092
JMA
SD
AS092
SCALE: 1/8" = 1'-0"
PARTIAL NINTH FLOOR PLAN -
EAST SIDE - SOUTH END
LEGEND
WINDOW TAG (SEE SHEET AS401
FOR ADDITIONAL INFORMATION)
INTERIOR FINISH TAG (SEE SHEET GI002 FOR
ADDITIONAL INFORMATION)
KEY NOTE TAG
F
D E
A
G
BC
GENERAL NOTES
1. ALL DEMOLITION WORK AND NEW WORK REQUIRED FOR THIS PROJECT SHALL BE COMPLETED IN PHASES. EACH PHASE SHALL BE COMPLETED AND ACCEPTED BY THE OWNER BEFORE MOVING TO THE
NEXT PHASE. REFER TO DRAWINGS GI003 & GI004 FOR ADDITIONAL INFORMATION.
2. ALL EXISTING WINDOWS INDICATED WITH A WINDOW TAG SHALL BE DEMOLISHED COMPLETELY.
RECYCLE ALL DEMOLISHED MATERIALS TO THE GREATEST EXTENT POSSIBLE. PROVIDE NEW WINDOWS
IN EXISTING OPENINGS AS INDICATED ON WINDOW SCHEDULE SHEET AS401.
3. CONTRACTOR SHALL PROVIDE ALL TEMPORARY BARRICADES, ENVIRONMENTAL CONTROLS AND
INFECTIOUS CONTROL MEASURES WITHIN EACH ROOM PRIOR TO START OF DEMOLITION WORK IN ROOM.
4. INTERIOR FINISHES ARE INDICATED IN ROOMS INCLUDED IN THE SCOPE OF WORK. PROTECT EXISTING INTERIOR FINISHES FROM DAMAGE DURING THE WORK. REFER TO SHEET GI002 FOR INTERIOR FINISH SCHEDULE. ANY DAMAGE TO THE EXISTING FINISHES BY THE CONTRACTOR SHALL BE REPAIRED TO
MATCH THE EXISTING ADJACENT FINISHES TO THE SATISFACTION OF THE OWNER.
5. CONTRACTOR SHALL COORDINATE SCHEDULES AND SEQUENCE OF WORK WITH CONTRACTING OFFICER PRIOR TO BEGINNING WORK. CONDUCT ALL WORK TO MINIMIZE IMPACT ON THE DAILY OPERATIONS OF
THE FACILITY. DO NOT BLOCK EXISTING MEANS OF EGRESS.
6. DO NOT CONSIDER DEMOLITION AND ALTERATION NOTES TO BE ALL-INCLUSIVE. IT IS THE CONTRACTOR'S RESPONSIBILITY TO INSPECT, MEASURE AND ASSESS EACH SPACE AND TO FULFILL THE INTENT OF THE WORK INDICATED BY THE CONTRACT DOCUMENTS. VERIFY EXTENT OF ALL DEMOLITION WITHIN THE CONTRACT LIMITS. BRING DEVIATIONS FROM THE CONTRACT DOCUMENTS NECESSITATED
BY FIELD CONDITIONS TO THE ATTENTION OF THE VA.
7. ALL OPENINGS AND SURFACES MADE BARE BY DEMOLITION AND/OR REMOVAL OF MATERIALS SHALL BE REPAIRED AND/OR PATCHED TO MATCH ADJACENT FINISH. ALL REPAIRS AND NEW FINISHES SHALL BE BY
TRADES SKILLED IN FINISH WORK.
8. DURING THE LIFE OF THE CONTRACT (DEMOLITION AND CONSTRUCTION TO THE POINT OF BENEFICIAL OCCUPANCY BY OWNER), THE CONTRACTOR SHALL PROTECT ALL MATERIALS TO REMAIN FOR REUSE
FROM DAMAGE.
9. FIRE EXITS AT GRADE LEVEL SHALL NOT BE BLOCKED DURING CONSTRUCTION.
W2W3
W1
W5
W4
W5
W5
W4
W4
W3
W3
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W2
W1
W1
W1
W1
W1
W1
W1
W1
W1
W1
W1
W1
W1
HOLIHAN ASSOCIATES LLC
FINAL SUBMISSION
Bronx, New York
NOVEMBER 2020
Office of
Facility
Management
Service
REPLACE EXTERIOR WINDOWS PHASE 1
JAMES J. PETERS MEDICAL CENTER
BRONX, NEW YORK
526-18-103
Drawing TitleMedical Center Director Approval
Associate Director Approval
PCC Director Approval
Chief Engineer Approval
Safety Manager Approval
Chief Nurse Executive / Chief of Staff Approval
Location Drawing Number
Building Number
Project Title
Of
DrawnChecked Date
Project Number
Dwg.
DESIGN CHANGE APPROVED
DESCRIPTION DATE
CONSULTANT FIRM ARCHITECTURAL ENGINEERING FIRM
311 FELS AVE. FAIRHOPE, AL 36532
KEY PLAN
PARTIAL NINTH FLOOR PLAN
EAST SIDE - NORTH END
AS093
JMA
SD
AS093
SCALE: 1/8" = 1'-0"
PARTIAL NINTH FLOOR PLAN -
EAST SIDE - NORTH END
LEGEND
WINDOW TAG (SEE SHEET AS401
FOR ADDITIONAL INFORMATION)
INTERIOR FINISH TAG (SEE SHEET GI002 FOR
ADDITIONAL INFORMATION)
KEY NOTE TAG
F
D E
A
G
BC
GENERAL NOTES
1. ALL DEMOLITION WORK AND NEW WORK REQUIRED FOR THIS PROJECT SHALL BE COMPLETED IN PHASES. EACH PHASE SHALL BE COMPLETED AND ACCEPTED BY THE OWNER BEFORE MOVING TO THE
NEXT PHASE. REFER TO DRAWINGS GI003 & GI004 FOR ADDITIONAL INFORMATION.
2. ALL EXISTING WINDOWS INDICATED WITH A WINDOW TAG SHALL BE DEMOLISHED COMPLETELY.
RECYCLE ALL DEMOLISHED MATERIALS TO THE GREATEST EXTENT POSSIBLE. PROVIDE NEW WINDOWS
IN EXISTING OPENINGS AS INDICATED ON WINDOW SCHEDULE SHEET AS401.
3. CONTRACTOR SHALL PROVIDE ALL TEMPORARY BARRICADES, ENVIRONMENTAL CONTROLS AND
INFECTIOUS CONTROL MEASURES WITHIN EACH ROOM PRIOR TO START OF DEMOLITION WORK IN ROOM.
4. INTERIOR FINISHES ARE INDICATED IN ROOMS INCLUDED IN THE SCOPE OF WORK. PROTECT EXISTING INTERIOR FINISHES FROM DAMAGE DURING THE WORK. REFER TO SHEET GI002 FOR INTERIOR FINISH SCHEDULE. ANY DAMAGE TO THE EXISTING FINISHES BY THE CONTRACTOR SHALL BE REPAIRED TO
MATCH THE EXISTING ADJACENT FINISHES TO THE SATISFACTION OF THE OWNER.
5. CONTRACTOR SHALL COORDINATE SCHEDULES AND SEQUENCE OF WORK WITH CONTRACTING OFFICER PRIOR TO BEGINNING WORK. CONDUCT ALL WORK TO MINIMIZE IMPACT ON THE DAILY OPERATIONS OF
THE FACILITY. DO NOT BLOCK EXISTING MEANS OF EGRESS.
6. DO NOT CONSIDER DEMOLITION AND ALTERATION NOTES TO BE ALL-INCLUSIVE. IT IS THE CONTRACTOR'S RESPONSIBILITY TO INSPECT, MEASURE AND ASSESS EACH SPACE AND TO FULFILL THE INTENT OF THE WORK INDICATED BY THE CONTRACT DOCUMENTS. VERIFY EXTENT OF ALL DEMOLITION WITHIN THE CONTRACT LIMITS. BRING DEVIATIONS FROM THE CONTRACT DOCUMENTS NECESSITATED
BY FIELD CONDITIONS TO THE ATTENTION OF THE VA.
7. ALL OPENINGS AND SURFACES MADE BARE BY DEMOLITION AND/OR REMOVAL OF MATERIALS SHALL BE REPAIRED AND/OR PATCHED TO MATCH ADJACENT FINISH. ALL REPAIRS AND NEW FINISHES SHALL BE BY
TRADES SKILLED IN FINISH WORK.
8. DURING THE LIFE OF THE CONTRACT (DEMOLITION AND CONSTRUCTION TO THE POINT OF BENEFICIAL OCCUPANCY BY OWNER), THE CONTRACTOR SHALL PROTECT ALL MATERIALS TO REMAIN FOR REUSE
FROM DAMAGE.
9. FIRE EXITS AT GRADE LEVEL SHALL NOT BE BLOCKED DURING CONSTRUCTION.