Bronx Windows Phase 1 FINAL-Set1.pdf
PDF 9 MB Posted
- Attached to
- Y1DZ--Project Number 526-18-103 Replace Exterior Windows, Phase 1 Federal contract opportunity
- Solicitation number
- 36C24221B0069
About this file
This notice provides details for a solicitation seeking construction services to replace exterior windows at the James J. Peters VA Medical Center in Bronx, New York. The solicitation number is 36C24221B0069 with a project number of 526-18-103, and has an estimated cost between $5-10 million. The opportunity is set aside for Service-Disabled Veteran Owned Small Businesses, with a response due date to be specified in the solicitation releasing on or around December 31, 2021. Scope of work includes removal and replacement of exterior windows, fall protection, and relocation or reinstallation of any medical equipment impacted. The contract duration is 726 calendar days from notice to proceed. Interested parties must be registered in SAM, D&B, and VIP databases and verified as an SDVOSB. This notice provides advance information and instructs interested SDVOSBs to submit capability statements by the presolicitation due date.
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
JAMES J. PETERS VA MEDICAL CENTER
BRONX, NEW YORK
PROJECT NO. 526-18-103
INDEX OF DRAWINGS
DRAWING NO. DRAWING TITLE
GENERAL
GI001 COVER SHEET
DETAIL MAP
GI002 LEGENDS, SYMBOLS AND ABBREVIATIONS
REPLACE EXTERIOR WINDOWS
PHASE 1
INDEX OF DRAWINGS
DRAWING TITLE
AS011
ARCHITECTURAL
AS012
AS013
FIRST FLOOR OVERALL PLAN
AS021
AS022
AS023
AS031
AS042
AS041
AS033
AS043
AS051
AS032
AS052
AS053
AS061
AS062
AS073
AS072
AS071
GI003 PHASING PLAN
SECOND FLOOR OVERALL PLAN
THIRD FLOOR OVERALL PLAN
FOURTH FLOOR OVERALL PLAN
FIFTH FLOOR OVERALL PLAN
SIXTH FLOOR OVERALL PLAN
SEVENTH FLOOR OVERALL PLAN
PARTIAL FIRST FLOOR PLAN EAST SIDE - SOUTH END
AS091
AS092
AS301
AS201
AS101
AS401
AS093
NINTH FLOOR OVERALL PLAN
PARTIAL EXTERIOR ELEVATIONS - EAST
WINDOW SCHEDULE & DETAILS
BUILDING DETAILS EXISTING CONDITIONS
AS102 PARTIAL EXTERIOR ELEVATIONS - EAST
AS103 PARTIAL EXTERIOR ELEVATIONS - EAST
AS104
AS105
EXTERIOR ELEVATION - NORTH END
GI004 PHASING PLAN
GI005 CONSTRUCTION SAFETY PLAN
ARCHITECTURAL (CONTINUED)
SHEET NO.
SHEET NO.
HAZMAT
HA001 ASBESTOS ABATEMENT GENERAL NOTES & EXISTING CONDITIONS
AS081
AS082
AS083
EIGHTH FLOOR OVERALL PLAN
AS202
AS203
AS204
VICINITY MAP
GI006
GI007
GI008 SHEDDING DETAILS
HA002
AS402 PSYCHIATRIC WINDOW DETAILS
SITE
SITE
BUILDING SECTIONS
AS403 WINDOW ELEVATION & DETAILS
EXTERIOR ELEVATION - SOUTH END
CONSTRUCTION SAFETY PLAN
CONSTRUCTION SAFETY PLAN
AS404 WINDOW DETAILS
9GI009 ROOF PLAN - SUSPENDED SCAFFOLDING PHASING
BUILDING SECTIONS
BUILDING SECTIONS
BUILDING SECTIONS
INFECTION CONTROL DETAILS
AS405 WINDOW DETAILS54
AS406 WINDOW DETAILS55
AS407 WINDOW DETAILS56
AS408 WINDOW DETAILS
DRAWING NO.
10GI010 GROUND FLOOR PLAN - SCAFFOLDING PHASING
PARTIAL FIRST FLOOR PLAN EAST SIDE - NORTH END
PARTIAL SECOND FLOOR PLAN EAST SIDE - SOUTH END
PARTIAL SECOND FLOOR PLAN EAST SIDE - NORTH END
PARTIAL THIRD FLOOR PLAN EAST SIDE - SOUTH END
PARTIAL THIRD FLOOR PLAN EAST SIDE - NORTH END
PARTIAL FOURTH FLOOR PLAN EAST SIDE - SOUTH END
PARTIAL FOURTH FLOOR PLAN EAST SIDE - NORTH END
PARTIAL FIFTH FLOOR PLAN EAST SIDE - SOUTH END
PARTIAL FIFTH FLOOR PLAN EAST SIDE - NORTH END
PARTIAL SIXTH FLOOR PLAN EAST SIDE - NORTH END
PARTIAL SEVENTH FLOOR PLAN EAST SIDE - SOUTH END
PARTIAL SEVENTH FLOOR PLAN EAST SIDE - NORTH END
PARTIAL EIGHTH FLOOR PLAN EAST SIDE - SOUTH END
PARTIAL EIGHTH FLOOR PLAN EAST SIDE - NORTH END
PARTIAL NINTH FLOOR PLAN EAST SIDE - SOUTH END
PARTIAL NINTH FLOOR PLAN EAST SIDE - NORTH END
PARTIAL SIXTH FLOOR PLAN EAST SIDE - SOUTH END
AS063
AS409 58
AS410 59
AS411 60
AS412 61
NOT TO SCALE
NOT TO SCALE
AS413 62 NON-IMPACT RATED WINDOW HARDWARE DETAILS
IMPACT RATED WINDOW HARDWARE DETAILS
IMPACT RATED WINDOW HARDWARE DETAILS
IMPACT RATED WINDOW HARDWARE DETAILS
IMPACT RATED WINDOW HARDWARE DETAILS
HOLIHAN ASSOCIATES LLC
FINAL SUBMISSION
Bronx, New York
NOVEMBER 2020
Office of
Facility
Management
Service
REPLACE EXTERIOR WINDOWS PHASE 1
JAMES J. PETERS MEDICAL CENTER
BRONX, NEW YORK
526-18-103
Drawing TitleMedical Center Director Approval
Associate Director Approval
PCC Director Approval
Chief Engineer Approval
Safety Manager Approval
Chief Nurse Executive / Chief of Staff Approval Location
Drawing Number
Building Number
Project Title
Of
DrawnCheckedDate
Project Number
Dwg.
DESIGN CHANGE APPROVED
DESCRIPTION DATE
CONSULTANT FIRM ARCHITECTURAL ENGINEERING FIRM
311 FELS AVE. FAIRHOPE, AL 36532
COVER SHEET
GI001
JLLSD
KEY PLAN
N
NTS
F
D E
A
G
BC
BID ALTERNATES
ALTERNATE 1 - DELETE W10 WINDOWS.
ALTERNATE 2 - DELETE W8 WINDOWS.
ALTERNATE 3 - DELETE W6 & W7 WINDOWS, EAST SIDE OF WING G.
ALTERNATE 4 - DELETE W1 & W2 WINDOWS, EAST SIDE OF WING F.
ALTERNATE 5 - DELETE W4 & W12 WINDOWS, SOUTH END OF WING F
AND NORTH END OF WING G.
130 W. KINGSBRIDGE RD.,
BRONX, NY 10468
BUILDING CODES AND STANDARDS
SYMBOLS LEGEND
STANDARD ABBREVIATIONS
A
A.C. AIR CONDITIONED
AFF ABOVE FINISHED FLOOR
A.H.U. AIR HANDLING UNIT
ALT. ALTERNATIVE
ALUM. ALUMINUM
A.O. ACCESS OPENING
APPROX. APPROXIMATELY
ARCH. ARCHITECTURAL
ACMU ARCHITECTURAL CONC. MASONRY UNIT
ACT ACOUSTIC CEILING TILE
AV AUDIO VISUAL
AFF ABOVE FINISHED FLOOR
B
BD. BOARD
BLDG. BUILDING
BM. BEAM
BOT. BOTTOM
BRG. BEARING
BOC BOTTOM OF CURB (ELEVATION)
C
CABT. CABINET
CAP. CAPACITY
CCTV CLOSED CIRCUIT TV
C.D. CEILING DIFFUSER
CEM. CEMENT
CIRC. CIRCULATING
C.J. CONTROL JOINT
CLG CEILING
CMU CONCRETE MASONRY UNIT
C.O. CLEAN OUT
COL. COLUMN
CONC. CONCRETE
CONN. CONNECTION
CONST. CONSTRUCTION
CONT. CONTINUOUS
COR CONTRACTING OFFICER'S REPRESENTATIVE
C.T. CERAMIC TILE
C.T.B. CERAMIC TILE BASE
C.F.C.I. CONTRACTOR FURNISHED/CONTRACTOR
INSTALLED
D
DET. DETAIL
DEST. DESTINATION
DIA. DIAMETER
DIFF. DIFFUSER
DIM. DIMENSION
DN DOWN
DR. DRAIN
DS DOWN SPOUT
DWGs DRAWING(S)
E
EA. EACH
E.F. EXHAUST FAN
ELEV. ELEVATION
ELEC. ELECTRICAL
E.P. ELECTRICAL PANEL
EQUIP. EQUIPMENT
EWC ELECTRIC WATER COOLER
EXH. EXHAUST
EXP. JT. EXPANSION JOINT
EXT. EXTERIOR
EXIST. EXISTING
F
F.A. FIRE ALARM
F.D. FLOOR DRAIN
F.E. FIRE EXTINGUISHER
F.E.C. FIRE EXTINGUISHER CABINET
FIN. FINISH
FL. FLOOR
F.O. FACE OF
FR. FRAME
FT. FOOT, FEET
FTG. FOOTING
G
GA. GAGE
GAL. GALLON
GALV. GALVANIZED
GFCI GOVERNMENT FURNISHED,
CONTRACTOR INSTALLED
GFGI GOVERNMENT FURNISHED,
GOVERNMENT INSTALLED
GL. GLASS
GND. GROUND
GOV'T GOVERNMENT
G.P.H. GALLONS/HOUR
G.P.M. GALLONS/MINUTE
GR. GRILLE
G.B. GYPSUM BOARD
H
HB HOSE BIB
H.C. HOLLOW CORE
HEWC HANDICAPPED ELECTRICAL
WATER COOLER
HT. HEIGHT
H.M. HOLLOW METAL
HR. HOUR
HTG. HEATING
HTR. HEATER
HW HOT WATER
I
IGU INSULATED GLASS UNIT
IN. INCHES
INSUL. INSULATION
INT. INTERIOR
J
J.B. JUNCTION BOX
JCT. JUNCTION
JT. JOINT
L
LB., # POUND
L.P. LIGHTING PANEL
LTG. LIGHTING
M
MAINT. MAINTENANCE
MAX. MAXIMUM
MECH. MECHANICAL
MTL. METAL
MIN. MINIMUM
MISC. MISCELLANEOUS
M.O. MASONRY OPENING
M.T. METAL THRESHOLD
MTD. MOUNTED
MTG. MOUNTING
N
N.A. NOT APPLICABLE
N.I.C. NOT IN CONTACT
NO. NUMBER
NOM. NOMINAL
NTS NOT TO SCALE
O
O.C. ON CENTER
O.D. OUTSIDE DIAMETER
O.F..I. OWNER FURNISH CONTRACTOR INSTALL
O.F.O.I. OWNER FURNISH OWNER INSTALL
OH. OVERHEAD
OPNG. OPENING
P
PART. PARTITION
PEMB PRE-ENGINEERED MANUFACTURED BUILDING
PH PHASE
P.I. PROJECT IN
PL. PLATE
PLBG. PLUMBING
PLW'D PLYWOOD
PNL. PANEL
P.O. PROJECT OUT
PRES PRESSURE
PSF POUNDS/SQUARE FOOT
PSI POUNDS/SQUARE INCH
PT PRESSURE TREATED
Q
QTR. QUARTER
R
R.A. RETURN AIR
RAD. RADIUS
RCP REFLECTED CEILING PLAN
RD. ROUND
RE RESIDENT ENGINEER
REC'D RECESSED
RECP. RECEPTACLE
REINF. REINFORCING
REQ. REQUIRED
RM. ROOM
S
SAB SOUND ATTENUATION BLANKET
S.A. SUPPLY AIR
SCH. SCHEDULE
S.D. SOAP DISPENSER
SECT. SECTION
SHT. SHEET
S.J. SLIP JOINT
SPEC. SPECIFICATIONS
SQ. FT. SQUARE FEET
STL. STEEL
STOR. STORAGE
SS SANITARY SEWER
STRUCT. STRUCTURAL
SUSP. SUSPENDED
T
T THERMOSTAT
TELE. TELEPHONE
THD. THRESHOLD
TOIL. TOILET
TYP. TYPICAL
TOC TOP OF CURB (ELEVATION)
U
UNK. UNKNOWN
UNO UNLESS NOTED OTHERWISE
UNK DEST UNKNOWN DESTINATION
V
V.T. VINYL TILE
VCT VINYL COMPOSITION TILE
VENT. VENTILATION
VERT. VERTICAL
VIF VERIFY IN FIELD
W
W/ WITH
WD. WOOD
INTERIOR FINISH
INTERIOR FINISH INDICATOR
EQUIPMENT INDICATOR
EQUIPMENT NUMBER
WINDOW INDICATOR
ROOM NAME
ROOM NUMBER
ROOM NAME
SHEET NUMBER
DETAIL NUMBER
INTERIOR ELEVATIONS
COLUMN NUMBER
COLUMN INDICATOR
DETAIL NUMBER
SHEET NUMBER
SECTION INDICATOR
SHEET NUMBER
DETAIL NUMBER
EXTERIOR ELEVATION
ALTERNATE INDICATOR
ALTERNATE NUMBER
NOT ALL SYMBOLS ARE USED IN THIS DRAWING SET
DEMOLITION NOTES
1. VA DESIGN MANUAL (PG-18-0)
2. VA DESIGN, QUALITY, AND STANDARD ALERTS
3. VA DESIGN GUIDES (PG-18-12)
4. VA DESIGN AND CONSTRUCTION PROCEDURES (PG-18-3)
5. PHYSICAL SECURITY DESIGN MANUAL FOR VA FACILITIES
6. VA FIRE PROTECTION DESIGN MANUAL
7. VA BARRIER FREE DESIGN GUIDE (PG-18-3)
8. NFPA 101: LIFE SAFETY CODE, VERSION 2018
9. NFPA 13: STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS,
VERSION 2019
10. NFPA 70: NATIONAL ELECTRICAL CODE, VERSION 2017
11. ASHRAE 62.1-2019: VENTILATION FOR ACCEPTABLE INDOOR AIR QUALITY
12. ASHRAE 90.1-2019: ENERGY STANDARD FOR BUILDINGS EXCEPT LOW RISE
RESIDENTIAL BUILDINGS
13. NATIONAL FIRE PROTECTION ASSOCIATION (NFPA) CODES AND STANDARDS
(EXCEPT NFPA 900 AND NFPA 5000) - CURRENT EDITION ACCEPTED BY LOCAL
AUTHORITY HAVING JURISDICTION.
14. VA SEISMIC DESIGN REQUIREMENTS, H-18-8, NOVEMBER 1, 2019, REVISED MAY
1, 2020
15. OSHA STANDARDS
16. EPA 2005
17. VA MASTER SPECIFICATIONS
18. VA SUSTAINABLE DESIGN MANUAL, MAY 2014
19. VA MENTAL HEALTH FACILITIES DESIGN GUIDE, DEC. 2010
SUSTAINABLE DESIGN
PHOTO DETAIL
KEY NOTE TAG
DEMOLITION NOTE TAG
ROOM
NAME
WINDOW
DESIGNATION
MATERIAL KEYNOTE
SEALED CONCRETE
METAL TRIM W/ GYPSUM
RADIATOR
GYPSUM BOARD
METAL TRIM
RECESSED METAL TRIM
CERAMIC TILE 4X4
ACT 2X2
ACT 2X4
GYPSUM BOARD
CERAMIC TILE 2X2
VINYL PLANK
LINOLEUM TILE
QUARRY TILE
TERRAZZO
CONCRETE
LAMINATE FLOORING
CARPET
VINYL COMPOSITION TILE
WINDOW SILLSIDE WALLSCEILINGS
FLOORS
INTERIOR FINISH LEGEND
GYPSUM BOARD W/ 4X4
CERAMIC TILE UP 42" AFF
GYPSUM BOARD W/1X2
WOOD TRIM AT 4'-0" AFF
METAL TRIM W/4X4 CERAMIC
TILE BELOW
SOLID SURFACE
W/GYP.BOARD BELOW
GENERAL SUMMARY
DUE TO THE NATURE OF THIS RENOVATION PROJECT NOT ALL SUSTAINABLE DESIGN CONCEPTS AND
GOALS CAN BE COMPLETED FOR THIS PROJECT. HOWEVER, THERE ARE A NUMBER OF SUSTAINABLE
DESIGN STRATEGIES THAT HAVE BEEN IMPLEMENTED IN THE DESIGN AND CONSTRUCTION.
ENERGY AND ATMOSPHERE (EA)
WINDOW REPLACEMENT WITHIN THE FACILITY IS BEING COMPLETED TO IMPROVE THE OVERALL ENERGY
EFFICIENCY OF THE FACILITY. THE EXISTING WINDOWS DO NOT PROMOTE ENERGY CONSERVATION AS
MANY OF THE SEALS ARE DAMAGED OR MISSING ALLOWING FOR AIR INFILTRATION THROUGH THE
SYSTEM. THE NEW WINDOWS HAVE BEEN DESIGNED TO PROVIDE MAXIMUM ENERGY EFFICIENCY WITH
INSULATED GLASS UNITS, THERMALLY BROKEN ALUMINUM FRAMES, AND HIGH QUALITY GLASS UNITS.
THERMAL IMPROVEMENTS ARE ALSO BEING IMPLEMENTED BETWEEN THE WINDOWS WITH THE
INSTALLATION OF THERMAL BATT INSULATION WITHIN THE CAVITY OF THE WINDOW MULLIONS.
MATERIALS AND RESOURCES (MR)
THE USE OF RECYCLED MATERIALS AND WASTE REDUCTION MANAGEMENT IS A SUSTAINABLE DESIGN
PRACTICE THAT WILL BE IMPLEMENTED DURING THE CONSTRUCTION PHASE. NEW MATERIALS SHALL BE
PROVIDED WITH THE USE OF RECYCLED CONTENT WITHIN THE PRODUCT. CONSTRUCTION WASTE SHALL
BE SALVAGED OR RECYCLED TO THE EXTENT POSSIBLE WITH A GOAL OF 50% OF NON-HAZARDOUS
CONSTRUCTION MATERIALS BEING DIVERTED FROM LANDFILLS. THE CONTRACTOR SHALL MAINTAIN
RECORDS OF ALL WASTE THAT IS DELIVERED TO A LANDFILL AS WELL AS ALL WASTE THAT IS RECYCLED
DURING CONSTRUCTION. A COPY OF THESE REPORTS SHALL BE SUBMITTED TO THE COR/RE AS PART OF
THE CONSTRUCTION CLOSE-OUT DOCUMENTS.
BOARD BELOW
INDOOR ENVIRONMENTAL QUALITY (IEQ)
THE NEW WINDOWS NOT ONLY PROVIDE FOR INCREASED ENERGY CONSERVATION OF THE FACILITY BUT THEY
WILL ALSO IMPROVE INDOOR ENVIRONMENTAL QUALITY. OCCUPANT COMFORT WITHIN A SPACE HAS BEEN
PROVEN TO IMPROVE PERSONAL ATTITUDES AND INCREASE PRODUCTIVITY. THERMAL COMFORT WILL BE
ACHIEVED WITH THE NEW WINDOW UNITS DUE TO THE IMPROVED GLASS AND WINDOW FRAMES. THE
OPERABLE WINDOWS WILL PROVIDE POTENTIAL FOR VENTILATION WITHIN THE ROOMS. ANOTHER ASPECT OF
OCCUPANT COMFORT IS DAYLIGHTING, THE NEW WINDOWS HAVE BEEN DESIGNED WITH GLASS THAT HAS A
HIGH LEVEL OF OPTICAL PERFORMANCE TO PROMOTE DAYLIGHTING AND VIEWS.
DURING CONSTRUCTION THE CONTRACTOR SHALL PROTECT INDOOR AIR QUALITY THROUGHOUT THE COURSE
OF THE CONSTRUCTION, INCLUDING MINIMIZED EXPOSURE TO CONTAMINANTS AND MAINTAINING INDOOR AIR
TEMPERATURE AND RELATIVE HUMIDITY. NEW MATERIALS AND PRODUCTS INSTALLED SHALL BE LOW-EMITTING
MATERIALS.
ACT 2X2 VINYL FACED
GYPSUM BOARD
DEFINITIONS:
CUTTING: REMOVAL OF IN-PLACE CONSTRUCTION NECESSARY TO PERMIT INSTALLATION OR PERFORMANCE OF OTHER WORK.
PATCHING: FITTING AND REPAIR WORK REQUIRED TO RESTORE SURFACES TO ORIGINAL CONDITIONS AFTER INSTALLATION OF NEW
WORK.
REMOVE: DETACH ITEMS FROM EXISTING CONSTRUCTION AND LEGALLY DISPOSE OF THEM OFF-SITE, UNLESS INDICATED TO BE
SALVAGED OR REMOVED AND REINSTALLED.
SALVAGE: DETACH ITEMS FROM EXISTING CONSTRUCTION AND DELIVER THEM TO OWNER READY FOR REUSE.
REMOVE AND REINSTALL: DETACH ITEMS FROM EXISTING CONSTRUCTION, PREPARE THEM FOR REUSE, AND REINSTALL THEM
WHERE INDICATED.
EXISTING TO REMAIN: EXISTING ITEMS OF CONSTRUCTION THAT ARE NOT TO BE REMOVED AND THAT ARE NOT OTHERWISE
INDICATED TO BE REMOVED, REMOVED AND SALVAGED, OR REMOVED AND REINSTALLED.
GENERAL NOTES:
1. DEPICTION OF EXISTING CONDITIONS IS BASED ON THE ORIGINAL CONSTRUCTION DOCUMENTS AND LIMITED FIELD
OBSERVATIONS. EXISTING ELEMENTS AND CONDITIONS CONCEALED BY IN-PLACE EQUIPMENT AND FINISHES WERE NOT
OBSERVED OR INVESTIGATED. ONCE CUTTING AND SELECTIVE DEMOLITION WORK IS COMPLETE, REPORT ANY CONFLICTS TO
COR/RE/AE.
2. PROTECT ALL EXISTING FINISHES AND ELEMENTS TO REMAIN. REPAIR OR REPLACE DAMAGED SURFACES TO MATCH ADJACENT
FINISHES EXACTLY.
3. INTERIOR DEMOLITION WORK SHALL BE CONDUCTED TO MINIMIZE DAMAGE TO EXISTING INTERIOR FINISHES ADJACENT TO THE
WORK. DAMAGED MATERIALS SHALL BE REPAIRED/RESTORED TO THEIR ORIGINAL CONDITION PRIOR TO FINAL ACCEPTANCE BY
THE COR/RE/AE.
4. EXISTING CEILINGS, EQUIPMENT, FIXTURES, AND FURNISHINGS SHALL REMAIN WITHIN THE AREAS OF WORK DURING
CONSTRUCTION. THE CONTRACTOR SHALL BE RESPONSIBLE TO PROTECT AND/OR TEMPORARILY RELOCATE THESE ITEMS
DURING THE WORK. ALL ITEMS SHALL BE RETURNED TO THEIR ORIGINAL LOCATIONS AND WORKING CONDITIONS PRIOR TO FINAL
ACCEPTANCE BY THE COR/RE.
5. REMOVAL OF ALL EXISTING WINDOWS MUST BE PERFORMED FROM THE EXTERIOR TO AVOID CONTAMINATION OF INTERIOR
SPACES. THE CONTRACTOR SHALL SUBMIT ALL SCAFFOLD PLANS FOR APPROVAL.
6. CONTRACTOR TO PERFORM THE COMPLETE SCOPE OF WORK WITHIN THE TIME FRAME OF APRIL 1, 2021 TO NOVEMBER 1, 2021. NO
MOBILIZATION COST WILL BE PAID AS PART OF THIS CONTRACT.
7. WORK SHALL COMMENCE ON THE NINTH FLOOR OF BUILDING 100 OF THE FACILITY, IN THE 9B AREA.
8. DO NOT CONSIDER DEMOLITION AND ALTERATION NOTES TO BE ALL-INCLUSIVE. IT IS THE CONTRACTOR'S RESPONSIBILITY TO
INSPECT AND ASSESS EACH SPACE AND TO FULFILL THE INTENT OF THE WORK INDICATED BY THE CONTRACT DOCUMENTS.
VERIFY EXTENT OF ALL DEMOLITION WITHIN THE CONTRACT LIMITS. BRING DEVIATIONS FROM THE CONTRACT DOCUMENTS
NECESSITATED BY FIELD CONDITIONS TO THE ATTENTION OF THE COR/RE/AE.
9. CONTRACTOR IS TO COORDINATE ALL INDICATED DEMOLITION WITH NEW CONSTRUCTION TO INSURE PROPER LOCATION AND
DIMENSION OF DEMOLISHED AREAS. INFORM COR/RE/AE OF ANY DISCREPANCIES.
10. EXISTING WALL FINISHES TO REMAIN INTACT, EXCEPT AS OTHERWISE NOTED. WHERE DAMAGE IS INCURRED, OR PATCHING IS
REQUIRED DUE TO DEMOLITION, PROVIDE NEW FINISH TO MATCH EXISTING SURFACE, FLUSH WITH EXISTING.
11. LOCATION OF EXISTING ITEMS AND ALL CONCEALED WORKS, ETC. ARE APPROXIMATE. IT IS REQUIRED THAT THE CONTRACTOR EXAMINE
THE SITE AFTER DEMOLITION HAS EXPOSED "AS-BUILT" CONDITIONS TO VERIFY EXISTING CONDITIONS. THE CONTRACTOR SHALL MAKE
ADJUSTMENTS AND/OR ALTERATIONS AS NECESSARY TO INSTALL COMPLETE AND OPERABLE SYSTEMS IN ACCORDANCE WITH THE CODES
HAVING JURISDICTION AT NO ADDITIONAL COST TO THE GOVERNMENT
12. ALL OPENINGS AND SURFACES MADE BARE BY DEMOLITION AND/OR REMOVAL OF MATERIALS SHALL BE REPAIRED AND/OR PATCHED TO
MATCH ADJACENT FINISH. PREPARE SURFACES TO RECEIVE NEW FINISH, SEE ARCHITECTURAL DRAWINGS FOR NEW FINISH SCHEDULE.
ALL REPAIRS AND NEW FINISH SHALL BE BY TRADES SKILLED IN FINISH WORK.
13. DURING THE LIFE OF THE CONTRACT (DEMOLITION AND CONSTRUCTION TO POINT OF BENEFICIAL OCCUPANCY BY OWNER). THE
CONTRACTOR SHALL PROTECT MATERIALS TO REMAIN FOR REUSE FROM DAMAGE.
14. ALL HAZMAT WILL BE REMOVED FROM THE BUILDING THROUGH OUTSIDE, DO NOT PLAN TO USE THE INSIDE OF THE BUILDING FOR THE
REMOVAL OF MATERIALS.
ROLL VINYL
GENERAL NOTES
1. VA WORK HOURS ARE FROM 0800 TO 1630 MONDAY THRU FRIDAY.
2. CONTRACTOR ALLOWED TO MOVE ITEMS THROUGH THE MEDICAL CENTER ONLY BEFORE 0800
HOURS AND AFTER 1700 HOURS.
3. CONTRACTOR MUST STOP WORK WHEN SUSTAINED WIND SPEEDS EXCEED 25 MILES PER HOUR.
CAREFUL CONSIDERATION SHOULD BE GIVEN WHEN SUSTAINED WINDS ARE AT OR ABOVE 15 MPH.
4. FIRE EXITS AT GRADE LEVEL WILL NOT BE BLOCKED DURING CONSTRUCTION.
5. CONTRACTOR SHALL FURNISH THE COR A TWO WEEK LOOK-AHEAD WITH THE PROPOSED PHASING
DATES.
6. CONTRACTOR SHALL COORDINATE THE PHASING PLAN WITH THE COR.
7. CONTRACTOR SHALL PROVIDE SHOP DRAWINGS WITH ACCURATE WINDOW COUNTS PER THE SHOP
DRAWING REQUIREMENT IN THE SPECIFICATIONS.
8. CONTRACTOR SHALL LIMIT THE NUMBER OF WINDOWS STORED ON SITE TO THOSE REQUIRED FOR
THE NEXT FIVE PHASES.
9. WHEN CODE PERMITS, THE CONTRACTOR SHALL TAKE DOWN THE SIDEWALK SCAFFOLDING NO
LONGER NEEDED DURING NON-WORKING PERIODS.
10. CONTRACTOR SHALL ATTEND A BI-WEEKLY JOB PROGRESS MEETING HELD AT THE TIME AND
LOCATION DETERMINED BY COR. AGENDA ITEMS TO INCLUDE:
· PROVIDE AN UPDATED CONSTRUCTION SCHEDULE.
· REPORT ON PROGRESS SINCE LAST MEETING AND PROJECTED ACTIVITY FOR THE NEXT TWO
WEEKS.
· ITEMS TO BE COORDINATED AND SCHEDULED WITH COR.
11. THE CONTRACTOR SHALL VERIFY ALL WINDOW SIZES AND COUNTS PRIOR TO CONSTRUCTION.
1. ERECT AND TEST A PERFORMANCE MOCK-UP IN COORDINATION WITH APPROVED SCOPE AND MOCKUP DRAWINGS, AT THE PROJECT
SITE. THE TESTING SHALL INCORPORATE A PORTION OF THE WINDOW SYSTEM. SCOPE WILL INCLUDE ALL LABOR AND MATERIAL TO
DEMOLISH AND INSTALL ONE SECTION OF THE WINDOW SYSTEM. SECTION WILL BE ONE FLOOR HIGH AND ONE COLUMN-TO-COLUMN
SPACING WIDE. SCOPE WIDTH WILL START AND STOP AT BUILDING EXPANSION JOINTS. THIS IS ROUGHLY 22'6" X 6'4". TOTAL COSTS OF
SUCH TESTING AND REQUIRED TEST MATERIALS SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR.
2. PERFORMANCE MOCKUP SHOP DRAWINGS: SUBMISSION OF ON -SITE PERFORMANCE MOCK-UPS SHOP DRAWINGS ARE REQUIRED.
PROVIDE DETAILED SHOP DRAWINGS DESCRIBING THE FABRICATED OF SPECIFIED TESTING MOCK-UP. SUBMISSION SHOULD ALSO
INCLUDE:
a. PROPOSED TEST PROCEDURES BY 3RD PARTY TESTING AGENCY.
b. MATERIAL AND SAMPLE SUBMITTALS
c. STAMPED STRUCTURAL CALCULATIONS
3. BUILD MOCKUPS TO COMPLY WITH THE FOLLOWING REQUIREMENTS, USING MATERIALS INDICATED FOR WORK:
a. OBTAIN A/E/BRONX VA APPROVAL OF MOCKUPS BEFORE START OF WORK.
b. NOTIFY ARCHITECT 7 DAYS IN ADVANCE OF THE DATES AND TIMES WHEN MOCKUPS WILL BE CONSTRUCTED.
c. DEMONSTRATE THE PROPOSED RANGE OF AESTHETIC EFFECTS AND WORKMANSHIP.
d. THE TEST PROCEDURE SHALL INCLUDE, BUT NOT BE LIMITED TO:
i. OPEN, CLOSE AND LOCK ALL OPERABLE UNITS A MINIMUM OF 5 TIMES.
ii. STATIC AIR INFILTRATION AND EXFILTRATION - ASTM E783: AT 6.24 PSF AIR INFILTRATION ALLOWANCE FOR OPERABLE WINDOWS TO
BE 0.30 CFM.
iii. STATIC WATER INFILTRATION- ASTM E 1105: WHEN STATIC PRESSURE OF 10 PSF (2/3 FIELD REDUCTION) HAS BEEN STABILIZED, FIVE
GALLONS OF WATER PER SQUARE FOOT SHALL BE APPLIED FOR A PERIOD OF 15 MINUTES. NO UNCONTROLLED WATER/LEAKAGE
AT INTERIOR FACE OF THE WINDOW IS ALLOWED.
iv. IMMEDIATELY AFTER SATISFACTORY COMPLETION OF LABORATORY TESTING, PREPARE "AS-BUILT" MOCK-UP DRAWINGS SHOWING
ANY MODIFICATIONS OR ADDITIONS MADE DURING TESTING TO MEET THE SYSTEM PERFORMANCE REQUIREMENTS. SUBMIT WITHIN
15 DAYS AFTER COMPLETING MOCK-UP TESTING.
v. RE-TESTING: WHERE MANUFACTURING OR INSTALLATION METHODS REQUIRE MODIFICATION IN ORDER TO MEET SPECIFIED
PERFORMANCE REQUIREMENTS, THE CONTRACTOR WHOSE WORK FAILS TO MEET THE SPECIFIED REQUIREMENTS SHALL, AT NO
ADDITIONAL COST TO THE GOVERNMENT , MODIFY, REBUILD, AND RETEST MOCK-UPS UNTIL THE SPECIFIED PERFORMANCE
REQUIREMENTS ARE MET. SHOW THE REQUIRED MODIFICATIONS ON THE PROJECT SHOP DRAWINGS AND RESUBMIT SHOP
DRAWINGS AS REQUIRED.
vi. MOCK-UP MATERIALS AND ASSEMBLIES, AS TESTED AND APPROVED, GOVERN THE MATERIALS AND ASSEMBLIES FURNISHED FOR
FINAL ERECTION.
4. THE CONTRACTOR WILL NOT BE GIVEN THE GO AHEAD TO PROCEED TO PRODUCTION UNTIL THE DESIGN A/E AND BRONX VA ARE
SATISFIED THAT THE WINDOWS PROPOSED AND THE INSTALLATION PROCEDURE AND MATERIAL MEET THE DESIGN REQUIREMENTS.
ON SITE PERFORMANCE MOCK-UP
SPECIAL NOTES/PHASING/DEMOLITION
1. THE CONTRACTOR SHALL BE RESPONSIBLE TO TEMPORARILY RELOCATE, STORE AND PROTECT
EXISTING FURNISHINGS AND EQUIPMENT WITHIN EACH ROOM DURING DEMOLITION AND CONSTRUCTION.
THE CONTRACTOR SHALL RELOCATE THESE ITEMS BACK TO THEIR ORIGINAL LOCATION PRIOR TO
COMPLETION OF EACH PHASE. IF REQUIRED, THE CONTRACTOR SHALL REMOVE ALL EXISTING SPECIAL
EQUIPMENT IN THE VICINITY OF THE WINDOWS BEING REPLACED THAT IMPACTS/AFFECTS THE
CONTRACT PERFORMANCE. THE CONTRACTOR SHALL REMOVE, STORE AND REINSTALL, BY CERTIFIED
TECHNICIANS/INSTALLERS, ALL EXISTING SPECIALIZED EQUIPMENT, SUCH AS, BUT NOT LIMITED TO;
MEDICAL GAS TOWERS, DIALYSIS EQUIPMENT, PATIENT LIFTS, PARTITIONS AND SOFFITS. ALL
EQUIPMENT, TO INCLUDE SPECIALIZED EQUIPMENT THAT IS REMOVED, SHALL BE REINSTALLED AND
CERTIFIED BY CERTIFIED INSTALLERS. THIS WILL BE AT NO COST TO THE GOVERNMENT.
HOLIHAN ASSOCIATES LLC
FINAL SUBMISSION
Bronx, New York
NOVEMBER 2020
Office of
Facility
Management
Service
REPLACE EXTERIOR WINDOWS PHASE 1
JAMES J. PETERS MEDICAL CENTER
BRONX, NEW YORK
526-18-103
Drawing TitleMedical Center Director Approval
Associate Director Approval
PCC Director Approval
Chief Engineer Approval
Safety Manager Approval
Chief Nurse Executive / Chief of Staff Approval Location
Drawing Number
Building Number
Project Title
Of
DrawnCheckedDate
Project Number
Dwg.
DESIGN CHANGE APPROVED
DESCRIPTION DATE
CONSULTANT FIRM ARCHITECTURAL ENGINEERING FIRM
311 FELS AVE. FAIRHOPE, AL 36532
LEGENDS, SYMBOLS
AND ABBREVIATIONS
GI002
JLLSD
AutoCAD SHX Text
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text A
AutoCAD SHX Text A100
AutoCAD SHX Text A
AutoCAD SHX Text A100
AutoCAD SHX Text
ALT.16
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AE100
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text F10
AutoCAD SHX Text J6
AutoCAD SHX Text J5
AutoCAD SHX Text S1
AutoCAD SHX Text S2
AutoCAD SHX Text S3
AutoCAD SHX Text S4
AutoCAD SHX Text J1
AutoCAD SHX Text J2
AutoCAD SHX Text J3
AutoCAD SHX Text J4
AutoCAD SHX Text C1
AutoCAD SHX Text C2
AutoCAD SHX Text C3
AutoCAD SHX Text C4
AutoCAD SHX Text F9
AutoCAD SHX Text F8
AutoCAD SHX Text F7
AutoCAD SHX Text F6
AutoCAD SHX Text F5
AutoCAD SHX Text F4
AutoCAD SHX Text F3
AutoCAD SHX Text F2
AutoCAD SHX Text F1
AutoCAD SHX Text F11
AutoCAD SHX Text one-eighth inch = one foot
AutoCAD SHX Text one-quarter inch = one foot
AutoCAD SHX Text three-eights inch = one foot
AutoCAD SHX Text one-half inch = one foot
AutoCAD SHX Text three-quarter inch = one foot
AutoCAD SHX Text one inch = one foot
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
FULL SIZE, USE GRAPHIC SCALES
AutoCAD SHX Text IF THIS SHEET IS NOT 30" x 42"
AutoCAD SHX Text
INCORPORATED
| GI002-GIO02X.pdf |
| Sheets and Views |
| GIO02 |
File details come from the government source that posted it. Updated .