This solicitation is for renovations to patient ward 4W at the Manhattan VA Medical Center in New York. The scope of work includes renovations to the step-down unit, including architectural, mechanical, electrical, and infrastructure upgrades. Specific requirements include renovating patient rooms, nurse stations, bathrooms, and common areas; replacing windows; upgrading mechanical, electrical, and plumbing systems; and installing new finishes. The solicitation includes construction drawings and specifications outlining the renovation work. The estimated award date is listed as February 2022.
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
360 Madison Avenue, New York, New York 10017 212.972.9800 o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
Revisions:
Date o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t
Building Number
Approved:
Drawing Title Project Title
Date
Office of Construction &
Facilities Management
F
E
D o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e in c h e s o n e fo o t
1 2 3 4 5 6 7 8 9
C
B
A
Location
Checked Drawn
Drawing Number
Project Number
CONSULTANTS: ARCHITECT/ENGINEERS:
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
KEY PLAN:
VA FORM 08-6231
Contractor to Provide Seismic Bracing for All Utilities Building is Fully Sprinklered
ASBESTOS ABATEMENT CONSULTANT:
14 HIGH STREET
MAHWAH, NEW JERSEY 07430
Tel: (914) 320-7924
Egan Environmental Consulting, Inc. 423 EAST 23RD STREET
NEW YORK, NY 10010
VA NY HARBOR HEALTHCARE SYSTEM
MANHATTAN VAMC -
BUILDING 1 WARD RENOVATIONS
Sheet Number 113of
1-G001
DRAWING INDEX - 4TH FLOOR WEST
& CENTRAL
AH GV
630-18-101
February 12, 2021 2
DRAWING INDEX - 4TH FLOOR WEST
SHEET NUMBER SHEET NAME 0
/0
/2
S c h e m a ti c D e s ig n S u b m is s io n
/2
/2
C o n s tr u c ti o n
D o c u m e n t S u b m is s io n
/1
/2
C o n s tr u c ti o n
D o c u m e n t S u b m is s io n
/1
/2
A D
D E
N D
U M
1-Q104W EQUIPMENT PLAN AND INDEX - 4TH FLOOR - WEST & CENTRAL • •
MECHANICAL DEMOLITION
1-MD001 MECHANICAL DEMOLITION GENERAL NOTES, SYMBOLS, & ABBREVIATIONS • •
1-MD104W MECHANICAL DEMOLITION PLAN 4TH FLOOR - WEST & CENTRAL • • •
1-MD105W MECHANICAL DEMOLITION PLAN 5TH FLOOR WEST MER • •
MECHANICAL
1-M001 GENERAL NOTES, SYMBOLS & ABBREVIATIONS • • •
1-M002 MECHANICAL AHU ZONING PLAN • • • •
1-M104W DUCTWORK PLAN 4TH FLOOR - WEST & CENTRAL • • •
1-M204W MECHANICAL PIPING PLAN 4TH FLOOR - WEST & CENTRAL • • •
1-M301 ENLARGED PLANS AND SECTIONS • • •
1-M302 ENLARGED PLANS AND SECTIONS • •
1-M401 ENLARGED MECHANICAL PLANS - TYPICAL ROOMS • • •
1-M501 MECHANICAL DETAILS • • •
1-M502 MECHANICAL DETAILS • •
1-M503 MECHANICAL DETAILS • •
1-M504 MECHANICAL DETAILS • •
1-M505 MECHANICAL DETAILS •
1-M601 MECHANICAL SCHEDULES • •
1-M701 MECHANICAL DUCT RISER DIAGRAM • •
1-M801 MECHANICAL FLOW AND CONTROL DIAGRAMS • •
1-M802 MECHANICAL FLOW AND CONTROL DIAGRAMS •
1-M803 MECHANICAL FLOW AND CONTROL DIAGRAMS • •
FIRE ALARM
1-FA001 FIRE ALARM SYMBOLS, NOTES, ABBREVIATIONS AND SMOKE ZONE
DIAGRAMS
1-FA104W FIRE ALARM PLAN - 4TH FLOOR - WEST AND CENTRAL • • •
1-FA601 PARTIAL FIRE ALARM RISER DIAGRAM • • •
ELECTRICAL DEMOLITION
1-ED103W ELECTRICAL DEMOLITION PLAN - 3RD FLOOR - WEST AND CENTRAL - 5TH
FLOOR - CENTRAL
1-ED104W ELECTRICAL DEMOLITION PLAN - 4TH FLOOR - WEST AND CENTRAL • • •
1-ED601 EXISTING PARTIAL ONE-LINE DIAGRAM - ELECTRICAL DEMOLITION • • •
ELECTRICAL
1-E0001 ELECTRICAL SYMBOLS, NOTES AND ABBREVIATIONS • • •
1-EL104W ELECTRICAL LIGHTING PLAN - 4TH FLOOR - WEST AND CENTRAL • • • •
1-EL601 LUMINAIRE SCHEDULE AND DETAILS • • • •
1-EP104W ELECTRICAL POWER PLAN - 4TH FLOOR - WEST AND CENTRAL • • •
1-EP401 ELECTRICAL ENLARGED PLANS - ELECTRICAL POWER PLAN - 5TH FLOOR • • •
1-EP501 ELECTRICAL DETAILS • •
1-EP502 ELECTRICAL PATIENT SERVICE WALL DETAILS • •
1-EP601 NEW PARTIAL ONE-LINE DIAGRAM • • • •
1-EP602 ELECTRICAL SCHEDULES - 4 WEST NORMAL • •
1-EP603 ELECTRICAL SCHEDULES - 4 WEST EMERGENCY • •
TELECOMMUNICATION
1-T001 TELECOMMUNICATIONS LEGENDS, SYMBOLS & ABBREVIATIONS • • •
1-T101 TELECOMMUNICATIONS PLAN - 2ND FLOOR - WEST • • •
1-T102 TELECOMMUNICATIONS PLAN - 4TH FLOOR - WEST AND CENTRAL • • • •
1-T201 AUDIO VISUAL PLAN - 4TH FLOOR - WEST AND CENTRAL • • •
1-T301 NURSE CALL PLAN - 4TH FLOOR - WEST AND CENTRAL • • •
1-T401 SECURITY PLAN - 4TH FLOOR - WEST AND CENTRAL • • •
1-T611 OPTICAL FIBER BACKBONE DISTRIBUTION RISER • • •
1-T612 COPPER BACKBONE DISTRIBUTION RISER • • •
1-T711 TELECOMMUNICATIONS DETAILS • •
1-T712 TELECOMMUNICATIONS DETAILS • •
1-T721 AUDIO VISUAL DETAILS • •
1-T731 NURSE CALL DETAILS • • •
1-T741 SECURITY DETAILS • •
1-T742 SECURITY DETAILS • •
PLUMBING DEMOLITION
1-PD103W PLUMBING DEMOLITION PLAN 3RD FLOOR - WEST AND CENTRAL • • •
1-PD104W PLUMBING DEMOLITION PLAN 4TH FLOOR - WEST AND CENTRAL • • •
PLUMBING
1-P001 PLUMBING - ABBREVIATIONS AND SYMBOLS • • •
1-P103W PLUMBING SANITARY PLAN 3RD FLOOR - WEST AND CENTRAL • • •
1-P104W PLUMBING SANITARY PLAN 4TH FLOOR - WEST AND CENTRAL • • •
1-P203W PLUMBING SUPPLY PLAN 3RD FLOOR - WEST AND CENTRAL • • •
1-P204W PLUMBING SUPPLY PLAN 4TH FLOOR - WEST AND CENTRAL • • •
1-P304W PLUMBING MEDICAL GAS PLAN 4TH FLOOR - WEST AND CENTRAL • • •
1-P601 SANITARY RISER DIAGRAMS - 4TH FLOOR • • •
1-P602 SANITARY RISER DIAGRAMS - 4TH FLOOR • • •
1-P603 SANITARY RISER DIAGRAMS - 4TH FLOOR • • •
1-P604 WATER RISER DIAGRAMS - 4TH FLOOR • • •
1-P605 WATER RISER DIAGRAMS - 4TH FLOOR • • •
1-P606 WATER RISER DIAGRAMS - 4TH FLOOR • • •
1-P607 MEDICAL GAS RISER DIAGRAMS •
FIRE PROTECTION - DEMOLITION
1-FD104W FIRE PROTECTION DEMOLITION PLAN 4TH FLOOR - WEST AND CENTRAL • • •
FIRE PROTECTION
1-F001 FIRE PROTECTION GENERAL NOTES, ABBREVIATIONS AND SYMBOLS • • •
1-F104W FIRE PROTECTION PLAN 4TH FLOOR - WEST AND CENTRAL • • •
DRAWING INDEX - 4TH FLOOR WEST
SHEET NUMBER SHEET NAME 0
/0
/2
S c h e m a ti c D e s ig n S u b m is s io n
/2
/2
C o n s tr u c ti o n
D o c u m e n t S u b m is s io n
/1
/2
C o n s tr u c ti o n
D o c u m e n t S u b m is s io n
/1
/2
A D
D E
N D
U M
GENERAL PROJECT
1-G000 COVER SHEET - 4TH FLOOR WEST & CENTRAL • • •
1-G001 DRAWING INDEX - 4TH FLOOR WEST & CENTRAL • • • •
LIFE SAFETY
1-G104 LIFE SAFETY PLAN 4TH FLOOR - OVERALL • • •
1-G104W LIFE SAFETY PLAN 4TH FLOOR - WEST & CENTRAL • • •
1-G204W ICRA & PHASING - 3RD & 4TH FLOOR - WEST & CENTRAL • •
ARCHITECTURAL DEMOLITION
1-AD103W DEMOLITION PLANS 3RD FLOOR - WEST & CENTRAL • • •
1-AD104W DEMOLITION PLANS 4TH FLOOR - WEST & CENTRAL • • •
HAZARDOUS MATERIALS
1-H001 ASBESTOS ABATEMENT NOTES AND ACM QUANTITY TABLE • • •
1-H104W ASBESTOS ABATEMENT PLAN 4TH FLOOR - WEST & CENTRAL • • •
STRUCTURAL
1-S001 STRUCTURAL DETAILS AND GENERAL NOTES • • • •
ARCHITECTURAL
1-A001 SYMBOLS & ABBREVIATIONS • • •
1-A002 TYPICAL MOUNTING HEIGHTS • • • •
1-A104W ARCHITECTURAL PLAN 4TH FLOOR - WEST & CENTRAL • • • •
1-A451 EXTERIOR SECTION DETAILS • • •
1-A452 EXTERIOR SECTION DETAILS • •
1-A453 EXTERIOR WINDOW DETAILS • •
1-A601 PATIENT BED SERVICE WALL ELEVATIONS 4TH FLOOR - WEST • • •
1-A602 ENLARGED PLANS & INTERIOR ELEVATIONS 4TH FLOOR - WEST • •
1-A603 ENLARGED PLANS & INTERIOR ELEVATIONS 4TH FLOOR - WEST • • •
1-A604 ENLARGED PLANS & INTERIOR ELEVATIONS 4TH FLOOR - WEST • •
1-A605 ENLARGED PLANS & INTERIOR ELEVATIONS 4TH FLOOR - WEST • •
1-A606 ENLARGED PLANS & INTERIOR ELEVATIONS 4TH FLOOR - WEST • •
1-A607 INTERIOR ELEVATIONS 4TH FLOOR - WEST • •
1-A704W REFLECTED CEILING PLAN 4TH FLOOR - WEST & CENTRAL • • •
1-A711 CEILING DETAILS • • •
1-A801 INTERIOR DETAILS • • •
1-A802 INTERIOR DETAILS • • •
1-A901 MILLWORK DETAILS • • •
1-A902 MILLWORK DETAILS • • •
1-A903 MILLWORK DETAILS •
1-A1001 PARTITION SCHEDULE AND DETAILS • • •
1-A1002 PARTITION DETAILS • • •
1-A1005 DOOR SCHEDULE, WINDOW SCHEDULE, FRAME ELEVATIONS AND DETAILS
4TH FLOOR - WEST
1-A1006 DOOR FRAMES, ELEVATIONS AND DETAILS • •
1-A1201 FINISH LEGEND • • • •
1-A1202 FINISH SCHEDULE 4TH FLOOR - WEST & CENTRAL • • •
1-A1204W FINISH PLAN 4TH FLOOR - WEST & CENTRAL • • •
1-A1251 ENLARGED FINISH PLAN VIEWS 4TH FLOOR - WEST & CENTRAL • •
1-A1301 SIGNAGE ABBREVIATIONS SYMBOLS AND GENERAL NOTES • •
1-A1302 MESSAGE SCHEDULE 4TH FLOOR - WEST • •
1-A1304W WAYFINDING PLAN 4TH FLOOR - WEST & CENTRAL • •
1-A1311 INTERIOR SIGNAGE ELEVATIONS AND DETAILS • •
1-A1312 INTERIOR SIGNAGE ELEVATIONS AND DETAILS • •
1-A1313 INTERIOR SIGNAGE ELEVATIONS AND DETAILS • •
1-A1404W FURNITURE PLAN 4TH FLOOR - WEST & CENTRAL • •
EQUIPMENT
ADDENDUM 01 1 02/12/2021
1 1
DN
UP
UP
UP
UP
DN
UP
DN
UP
17 19 21
20 2212.8 15.2
18.716.8
17.1
16.9
16.2
A
B
C
D
E
G
F
J.2
H
J
L
N
O
Q
R
S S.1
T
U.6
15.3
E.9
U.1
W.1
F.5
12.1 13 15.1 16
V
X.1
RESIDENT
SURG. SERV.
4184N
RESIDENTS
4137AN
STAFF LOUNGE
4135N
STAFF
LOCKERS
4136N
LOUNGE
4088S
EQUIP. STOR.
4127aC
SOIL. EQUIP.
4086AC
STOR.
4086C
STAFF LOUNGE
4085S
DISTRIBUTION
4127C
SERV. LOBBY
4128C
2 BEDROOM
4084S
TOILET
4054C
HAC
4053C
HAC
4052C
IT
4051C
DR. OFFICE
4046C
2 BED ROOM
4044W
TOILET
4043W
2 BED ROOM
4042W
PHYS. OFFICE
4041W
MEDS
4040W
NURSE
STATION
4039W
2 BED ROOM
4037W
ISOLATION
ROOM
4034W
2 BED ROOM
4032W
2 BED ROOM
4030W
4 BEDROOM
4028W
TOILET
4029W
TOILET
4031W
TOILET
4035W
ANTE
4033W
TOILET
4038W
HAC
4002W
TOILET
4003W
2 BED ROOM
4004W
DAY ROOM
4005W
STORAGE
4006W
TOILET
4006AW
SOIL. UTL.
4007W
TOILET
4008W
KITCHEN
4010W
FAMILY
COORD.
4011W
EXAM
4012W
STORAGE
4013W
CORRIDOR
4019W
2 BED ROOM
4014W
2 BED ROOM
4016W
TOILET
4015W
STOR.
4019aW
CLEAN LINEN
4018W
SUPPLY
4017W
ELEC. CLOS.
4013W
TOILET
4020W
TOILET
4021W
ANTE
4023W
ISOLATION
ROOM
4022W
4 STAIR W
4STW
HOSE
CLOSET
4015W
2 BED ROOM
4024W
2 BED ROOM
4027W
TOILET
4026W
VERNACARE
4024aW
ELEC.
4049C
FEC
4053C
ELEC. CLOS.
4025aW
ELEC. CLOS.
4025bW
STORAGE
4001aW
STORAGE
4001bW
4 STAIR C
4STC
CONNECTION TO OR'S
(BUILDING 6)
OPEN TO
BELOW
STAFF
LOCKERS
4138N
STAFF TOILET
4137N
WAITING
4132N
TOILET
4130N
TOILET
4131N
CORRIDOR
4180N
11 14
17 19 21
20 2212.8 15.2
18.716.8
17.1
16.9
16.2
A
B
C
D
E
G
F
J.2
H
J
L
N
O
Q
R
S S.1
T
U.6
15.3
E.9
U.1
W.1
F.5
12.1 13 15.1 16
V
X.1
HOSPITAL
DIRECTOR
3022W
ADMIN
ASSISTANT
3029W
EXEC. CHIEF
OF STAFF
3021W
ASS. DIRECTOR
PATIENT SERV.
3020W
PERF. IMPROV
MGR
3019WSTAFF
ASSISTANT
3024W
HEALTH SYS.
SPEC. COS
3032W
STAFF
ASSISTANT
3033W
DATA
MANAGER
3034W
BUSINESS
OFFICER
3035W
CONFERENCE
A
3036W
ASSOCIATE
DIRECTOR
3023W
F.A.C.
3015W
EL. CLOS.
3011W
T. STAFF MALE
3009W
T. STAFF
FEMALE
3010W
CORRIDOR
3010AW
CONFERENCE
PM.
3011EW
WAITING
3011W
STORAGE
3011DW
ACNS OPC.
COORDINATOR
3011CW
INFO. MGR.
3011AW
ADMIN.
RESIDENT
3010W
LOCKERS-FAX-COPY
3008A-W
FILES
3008B-W
OFFICE
(F.FRASER)
3008W
PROGRAM
MNG. OFFICE
3007W
M.V.P.
CO-COORDINATOR
3005W
CLOSET
3006W
HOUSEKEEPING
3003C
CONFERENCE
B
3036BW
EEO
SPECIALIST
3036C
PATIENT REP.
PROG.
3037C
PATIENT REP.
PROG.
3038C
ELEC. CLOSET
3001C
3 STAIR C
3STC
ELEVATOR
LOBBY
3000C
CORRIDOR
3039C
F.E.C.
3045C
CORRIDOR
3040C
FILE STORAGE
3061AE
DISTR.
3077C
EQUIP. STOR
3078C
SERVICE
LOBBY
3076C
PAT. SERVICES
SUPERVISOR
3038C
SECRETARY
MEDICAL
3043S
DEPUTY PL
MANAGER
3043S
CORRIDOR
3041S
MED CARE LINE
MANAGEMENT
3075S
NURSE
EDUCATOR
3075AS
CONFERENCE
ROOM
3076S
DIET.
VOLUNTEER
3081E
SALAD PREP
3080C
CORRIDOR
3102E
J.C.
3103C
L.C.
3102C
STORAGE
ROOM
3101C
UTILITY
3100E
DISH WASHERS
3105C
KITCH. & DISH
WASHING
3107N
CORRIDOR
3109N
SEC. TO CHIEF
3123N
CHIEF
DIETETIC
SERVICE
3123N
PROGRAM
CLERK
3123BN
DIETECIAN
3123N
TOILET
3123EN
TOILET
3123EN
MECHANICAL
ROOM
3122N
3078C
3 STAIR W
3STW
NATIONAL
ETHICS CTR.
3011BW
ICRA & PHASING LEGEND
ICRA & PHASING KEYED NOTEX
PHASING IMPACT AREA - STAGE 1
PHASING IMPACT AREA - STAGE 2
GENERAL ICRA & PHASING NOTES
PHASING IMPACT AREA - STAGE 3
SPECIFIC ICRA & PHASING NOTES
TEMPORARY FULL HEIGHT ICRA BARRIER SEALED AIR-
TIGHT, REFER TO PARTITION TYPE 11b
A. TYPE OF CONSTRUCTION PROJECT ACTIVITY:
TYPE D - MAJOR DEMOLITION AND CONSTRUCTION
PROJECTS. INCLUDES, BUT IS NOT LIMITED TO ACTIVITIES
WHICH REQUIRE CONSECUTIVE WORK SHIFTS; REQUIRES
HEAVY DEMOLITION OR REMOVAL OF A COMPLETE
CABLING SYSTEM; NEW CONSTRUCTION; ASBESTOS
ABATEMENT WORK.
B. PATIENT RISK GROUPS THAT WILL BE AFFECTED:
HIGH RISK: CCU, EMERGENCY ROOM, LABORATORIES
(SPECIMEN), OUTPATIENT SURGERY, PHARMACY, POST
ANESTHESIA CARE UNIT, SURGICAL UNITS
C. DESCRIPTION OF REQUIRED INFECTION CONTROL
PRECAUTIONS BY CLASS (IV):
DURING CONSTRUCTION OF PROJECT:
1. ISOLATE HVAC SYSTEM IN AREA WHERE WORK IS BEING
DONE TO PREVENT CONTAMINATION OF DUCT SYSTEM.
2. COMPLETE ALL CRITICAL BARRIERS I.E. SHEETROCK,
PLYWOOD, PLASTIC, TO SEAL AREA FROM NON-WORK
AREA OR IMPLEMENT CONTROL CUBE METHOD (CART WITH
PLASTIC COVERING AND SEALED CONNECTION TO WORK
SITE WITH HEPA VACUUM FOR VACUUMING PRIOR TO EXIT)
BEFORE CONSTRUCTION BEGINS.
3. MAINTAIN NEGATIVE AIR PRESSURE WITHIN WORK SITE
UTILIZING HEPA EQUIPPED AIR FILTRATION UNITS.
4. SEAL HOLES, PIPES, CONDUITS, AND PUNCTURES
APPROPRIATELY.
5. CONSTRUCT ANTEROOM AND REQUIRE ALL PERSONNEL
TO PASS THROUGH THIS ROOM SO THEY CAN BE
VACUUMED USING A HEPA VACUUM CLEANER BEFORE
LEAVING WORK SITE OR THEY CAN WEAR CLOTH OR PAPER
COVERALLS THAT ARE REMOVED EACH TIME THEY LEAVE
THE WORK SITE.
6. ALL PERSONNEL ENTERING WORK SITE ARE REQUIRED
TO WEAR SHOE COVERS. SHOE COVERS MUST BE
CHANGED EACH TIME THE WORKER EXITS THE WORK
AREA.
7. DO NOT REMOVE BARRIERS FROM WORK AREA UNTIL
COMPLETED PROJECT IS INSPECTED BY THE OWNER’S
SAFETY DEPARTMENT AND INFECTION CONTROL
DEPARTMENT AND THOROUGHLY CLEANED BY THE
OWNER’S ENVIRONMENTAL
SERVICES DEPARTMENT.
8. NOTE: ALL ASBESTOS ABATEMENT WORK SHALL BE
PERFORMED AS CLASS IV WORK, AND IS FURTHER
SUBJECT TO ADDITIONAL PROVISIONS OF THE NY STATE
ASBESTOS REGULATIONS (NY DEPARTMENT OF LABOR
INDUSTRIAL CODE RULE 56).
UPON COMPLETION OF PROJECT:
1. REMOVE BARRIER MATERIAL CAREFULLY TO MINIMIZE
SPREADING OF DIRT AND DEBRIS ASSOCIATED WITH
CONSTRUCTION.
2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT
IN TIGHTLY COVERED CONTAINERS.
3. COVER TRANSPORT RECEPTACLES OR CARTS. TAPE
COVERING UNLESS SOLID LID.
4. VACUUM WORK AREA WITH HEPA FILTERED VACUUMS.
5. WET MOP AREA WITH DISINFECTANT.
6. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE
WORK IS BEING PERFORMED.
7. FOR ASBESTOS ABATEMENT WORK, CONFIRM THAT THE
LICENSED PROJECT MONITOR HAS PERFORMED A FINAL
VISUAL INSPECTION AND CONDUCTED CLEARANCE AIR
SAMPLING AS REQUIRED UNDER NY STATE ASBESTOS
REGULATIONS (NY DEPARTMENT OF LABOR INDUSTRIAL
CODE RULE 56).
D. CONSTRUCTION BARRIER MUST BE APPROVED BY COR &
SAFETY MANAGER PRIOR TO START OF CONSTRUCTION WORK.
E. SWING SPACE WILL BE REQUIRED TO FACILITATE NEW WORK.
EXACT LOCATION TBD PRIOR TO NOTICE TO PROCEED FOR
CONSTRUCTION. COORDINATE SCOPE AND LOCATION WITH VA
PROJECT MANAGER.
F. PROVIDE STICKY WALK-OFF MATS ON BOTH SIDES OF ALL ICRA
DOORS AND ACCESS POINTS.
G. CONTRACTOR TO COORDINATE TEMP PARTITION LOCATIONS
WITH THE OPERATIONAL AND SECURITY REQUIREMENTS OF THE
VETERANS ASSOCIATION (VA). TEMP BARRIER TO BE PARTITION
TYPE 11b. CONTRACTOR TO PROVIDE 45 MINUTE DOOR TYPE F (3'-0" X 7'-0") WITH HOLLOW METAL FRAME TYPE a. DOOR TO
INCLUDE HARDWARE TYPE HW-5 WHICH INCLUDES AN EXIT
DEVICE, CLOSER AND STORAGE ROOM LOCKSET WITH 6 SETS OF
KEYS CREATED FOR USE BY CONTRACTOR & VA.
H. CONSTRUCTION BARRIER MUST BE INSTALLED AND APPROVED
BY COR & SAFETY MANAGER PRIOR TO START OF ANY
CONSTRUCTION WORK.
I. GC SHALL PROVIDE ALL ICRA ELEMENTS FOR ALL AREAS OF
WORK. COORDINATE WITH WORK SHOWN BY ALL DISCIPLINES,
ESPECIALLY WITH EXISTING OCCUPIED SPACES.
J. COORDINATE ICRA PLAN WITH CONSTRUCTION PHASES. NOT ALL
ICRA PARTITIONS ARE SHOWN ON THESE PLANS. ALL PHASES
MUST BE COORDINATED WITH THE OWNER PRIOR TO ANY WORK.
K. COORDINATE ALL SHUT-DOWNS WITH OWNER AND
COSNTRUCTION MANAGER AS PART OF ICRA REQUIREMENTS.
L. PROTECTIVE COVERALLS AND SHOE COVERS ARE REQUIRED
FOR ALL WORK TO BE DONE IN EXISTING BUILDING.
M. FOR PHASE 3, DESCRIPTION OF REQUIRED INFECTION CONTROL
PRECAUTIONS BY CLASS (II):
DURING CONSTRUCTION OF PROJECT:
1. PROVIDE AVTICE MEANS TO PREVENT AIRBORNE DUST
FROM DISPERSING INTO ATMOSPHERE.
2. WATER MIST WORK SURFACES TO CONTROL DUST
WHILE CUTTING.
3. SEAL UNUSED DOORS WITH DUCT TAPE.
4. BLOCK OFF AND SEAL AIR VENTS.
5. PLACE DUCT MAT AT ENTRANCE AND EXIT OF WORK
AREA.
6. REMOVE OR ISOLATE HVAC SYSTEM IN AREAS WHERE
WORK IS BEING PERFORMED.
UPON COMPLETION OF PROJECT:
1. WIPE WORK SURFACES WITH DISINFECTANT.
2. CONTAIN CONSTRUCTION WASTE BEFORE TRANSPORT
IN TIGHTLY COVERED CONTAINERS.
3. WET MOP AND/OR VACUUM WITH HEPA FILTERED
VACUUM BEFORE LEAVING WORK AREA.
4. REMOVE ISOLATION OF HVAC SYSTEM IN AREAS WHERE
WORK IS BEING PERFORMED.
PROJECT IMPACT AREA
EXISTING FULL HEIGHT PARTITION AS BARRIER
STAFF/PATIENT TRAFFIC FLOW
SECURE STAIR DURING CONSTRUCITON. PROVIDE
TEMPORARY LOCK TO RESTRICT RE-ENTRY INTO THE
UNIT, BUT PROVIDE FREE EGRESS INTO THE STAIRWELL,
COORDINATE WITH VA TO PROVIDE KEYS FOR SECURITY
AND FACILITIES..
PROVIDE TEMPORARY BARRIER, HM DOOR WITH CARD
READER ACCESS TO RESTRICT ACCESS INTO BUILDING 6
DURING CONSTRUCTION, COORDINATE WITH VA TO
PROVIDE KEYS FOR SECURITY AND FACILITIES..
CONTRACTOR TO COORDINATE SCHEDULED WORK NEAR
THE ENTRANCES TO 4N AND 4S WITH THE VA TO
FACILITATE NEW SCOPE OF 4 CENTRAL. CONCEPT
SHOWN IS TO SHUTDOWN ONLY ONE ENTRANCE AT A
TIME SO THAT TRAFFIC AND EGRESS FROM CENTRAL
ZONE IS ACCESSIBLE IN AT LEAST ONE DIRECTION. ICRA
PRECAUTIONS IN THIS ZONE IS LIMITED TO CLASS II (TYPE
C, LOW RISK).
4N AND 4S ONLY HAVE 1 MEANS OF EGRESS AVAILABLE IF
ENTRANCE IS SHUTDOWN. PROVIDE ABILITY TO EXIT
THROUGH AREA OF WORK IN CASE OF EMERGENCY.
PROVIDE TEMPORARY BARRIER, HM DOOR WITH CARD
READER ACCESS TO RESTRICT ACCESS INTO THE
CONSTRUCTION ZONE, COORDINATE WITH VA TO
PROVIDE KEYS FOR SECURITY AND FACILITIES.
EGRESS PATH
HEPA EXHAUST UNIT TO EXTERIOR
NEGATIVE AIR MONITOR (BALL-IN-WALL OR EQUAL)
UTILIZE EXISTING DOOR AS CONSTRUCTION ENTRANCE.
PROVIDE TEMPORARY HARDWARE TO ALLOW FOR
LOCKING, COORDINATE WITH VA TO PROVIDE KEYS FOR
SECURITY AND FACILITIES.
TEMPORARILY REMOVE RESTRICTED ACCESS
CAPABILITIES TO ALLOW ACCESS FROM ELEVATORS TO
4N, 4S AND 4 CENTRAL.
SECOND MEANS OF EGRESS FROM 4S, 4N AND 4CENTRAL
IS AVAILABLE IN BOTH 4S AND 4N WINGS.
TWO MEANS OF EGRESS IS AVAILABLE FROM
CONSTRUCTION PHASE 1 IN THE 4W WING WITHOUT
BEING REQUIRED TO EXIT THE ZONE.
MAINTAIN OPERATIONS OF 4 ELEVATOR BAYS DURING
CONSTRUCTION PHASE 1 AND 2. COORDINATE
SHUTDOWN AND ACCESS CONTROL OF ELEVATORS WITH
OWNER.
TEMPORARY ICRA POLY BARRIER WITH ZIPPER ACCESS
DOOR.
14 2012.8 15.2
18.716.8
17.1
16.9
16.2
O
Q
R
S S.1
T
U.6
15.3
U.1
W.1
12.1 13 15.1 16
V
X.1
STAFF
LOCKERS
4136N
LOUNGE
4088S
EQUIP. STOR.
4127aC
SOIL. EQUIP.
4086AC
STOR.
4086C
STAFF LOUNGE
4085S
DISTRIBUTION
4127C
SERV. LOBBY
4128C
TOILET
4054C
HAC
4053C
HAC
4052C
IT
4051C
DR. OFFICE
4046C
2 BED ROOM
4044W
HAC
4002W
ELEC.
4049C
FEC
4053C
4 STAIR C
4STC
STAFF
LOCKERS
4138N
WAITING
4132N
CORRIDOR
4180N
5 7
14 2012.8 15.2
18.716.8
17.1
16.9
16.2
O
Q
R
S S.1
T
U.6
15.3
U.1
W.1
12.1 13 15.1 16
V
X.1
STAFF
LOCKERS
4136N
LOUNGE
4088S
EQUIP. STOR.
4127aC
SOIL. EQUIP.
4086AC
STOR.
4086C
STAFF LOUNGE
4085S
DISTRIBUTION
4127C
SERV. LOBBY
4128C
TOILET
4054C
HAC
4053C
HAC
4052C
IT
4051C
DR. OFFICE
4046C
2 BED ROOM
4044W
HAC
4002W
ELEC.
4049C
FEC
4053C
4 STAIR C
4STC
STAFF
LOCKERS
4138N
WAITING
4132N
CORRIDOR
4180N
1412.8 15.2
18.716.8
17.1
16.9
16.2
T
U.6
15.3
U.1
W.1
12.1 13 15.1 16
V
STOR.
4086C
SERV. LOBBY
4128C
HAC
4053C
FEC
4053C
CORRIDOR
4180N
4 3
WEST
SOUTH NORTH
360 Madison Avenue, New York, New York 10017 212.972.9800 o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
Revisions:
Date o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t
Building Number
Approved:
Drawing Title Project Title
Date
Office of Construction &
Facilities Management
F
E
D o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e in c h e s o n e fo o t
1 2 3 4 5 6 7 8 9
C
B
A
Location
Checked Drawn
Drawing Number
Project Number
CONSULTANTS: ARCHITECT/ENGINEERS:
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
KEY PLAN:
NTS
VA FORM 08-6231
Contractor to Provide Seismic Bracing for All Utilities Building is Fully Sprinklered Scale: AS NOTED
ASBESTOS ABATEMENT CONSULTANT:
14 HIGH STREET
MAHWAH, NEW JERSEY 07430
Tel: (914) 320-7924
Egan Environmental Consulting, Inc. 423 EAST 23RD STREET
NEW YORK, NY 10010
VA NY HARBOR HEALTHCARE SYSTEM
MANHATTAN VAMC -
BUILDING 1 WARD RENOVATIONS
Sheet Number 113of
1-G204W
ICRA & PHASING - 3RD & 4TH FLOOR
- WEST & CENTRAL
Checker Author
630-18-101
February 12, 2021 5
SCALE: 1/16" = 1'-0"
F4
ICRA & PHASING PLAN 4TH FLOOR
SCALE: 1/16" = 1'-0"
F6
ICRA & PHASING PLAN 3RD FLOOR
SCALE: 3/32" = 1'-0"
F1
ICRA & PHASING PLAN 4TH FLOOR - PHASE 1
SCALE: 3/32" = 1'-0"
C1
ICRA & PHASING PLAN 4TH FLOOR - PHASE 2
SCALE: 3/32" = 1'-0"
A4
ICRA & PHASING PLAN 4TH FLOOR - PHASE 3
0 16' 32'0 16' 32'0 21'-4"10'-8"
0 21'-4"10'-8"
0 21'-4"10'-8"
ADDENDUM 01 1 02/12/2021
PULL
PULL
2' -1
0"3' -6
2' -2
2'
-2
2' -4
6"
9" 1'-1"
PAPER
TOWEL
DISPENSER
SOAP
DISPENSER
FULL
LENGTH
MIRROR
ACCESSIBLE
COAT HOOK
COAT
HOOK
SOAP
DISPENSER
NOTE: ALL DIMENSIONS INCLUDE ALL OPERABLE LEVERS.
DIGITAL
CLOCK
SHARPS
RECEPTACLE
PAPER TOWEL
DISPENSER
GLOVE BOX
HOLDER
CLINICAL
SERVICE
SINK
DIAGNOSTIC
SET
HAND
SANITIZER
NOTE: LIGHT SWITCH ALWAYS LOCATED ON SIDE CLOSER TO ROOM ENTRY DOOR.
CL
1'-6" 2'-11" 1" FILLER
CL1'-6"
2' -6
2' -6
" 3' -8
4' -6
3'
-6
3' -8
9" 9"
FOOT WALL
5' -0
2' -5
1' -3
M
IN
DIAPER
CHANGING
TABLE
NAPKIN
DISPENSER
4' -0
NOTE: CONTRACTOR TO COORDINATE IN FIELD TO ASSURE THAT A 2'-0"
SPACING IS MAINTAINED BETWEEN RECEPTACLES THAT ARE BACK TO BACK
WITHIN THE SAME PARTITION AT THE SAME MOUNTING HEIGHT.
5' -6
CL
5' -0
1'
-6
TELEVISION
5' -6
CL
MIRROR
INSULATE DRAIN
AND WATER PIPES
DASHED AREA
INDICATES
ACCESSIBLE KNEE
AND TOE CLEARANCE
SPACE
WALL MOUNTED LAVATORY
8" MIN
M
IN
N O
N A
C C
E S
S
IB
L E
A C
C E
S S
IB
L E
M
A X
1'-3" MIN
TOP OF
SPOUT
EQUIPMENT
PERMITTED IN
AREA SHOWN
DASHED
ELECTRIC WATER COOLER
"4
A5145.2
18" WIDE STAINLESS
STEEL SHELF
MOP HOLDER
SERVICE
FAUCET AND
CONTROLS
MOP BASIN
HAC
5" MAX
1'-3" MIN
PAPER TOWEL DISPENSER
6" MAX
FLOOR MOUNTED TOILET WITH
RETRACTABLE GRAB BARS
GRAB BARS
(ACCESSIBLE
ONLY)
SIDE
VIEW
FRONT
VIEW
SIDE
VIEW
FRONT
VIEW
SIDE
VIEW
FRONT
VIEW
1'-6" MIN
1'-8" MAX
TOILET PAPER
DISPENSER
NOTE: ACCESSIBLE AND NON-ACCESSIBLE PLUMBING FIXTURES ARE INDICATED IN THE PLUMBING DRAWINGS.
M
IN
6" MAX8" MIN
A
C C
E S
S
IB
L E
S T
A N
D A
R D
M
IN
PERPENDICULAR WALL OR
PROJECTING ELEMENT 4" MAX PROJECTION
/4
/4
1'-8" MAX
1'-6" MIN
S
T A
N D
A R
D
A
C C
E S
S
IB
L E
GRAB BARS
TOILET PAPER
DISPENSER
WATER
CLOSET
LOW HEIGHT
FLUSH VALVE
FLOOR MOUNTED TOILET
1'-0" 6"2'-0"1'-0" 3'-6"
SIDE
VIEW
FRONT
VIEW
2' -1
0"
1'-1"
A L
IG
N
CL
4' -8
WALL MOUNTED
LIGHT FIXTURE
9" ±
M
IN
". 2' -1
0"
M
IN
1' -3
" 2' -1
0"
1' -5
7"-9". 7"-9"
1'-3"
SOAP DISPENSER
PAPER TOWEL
DISPENSER
NC
1'-8"
3' -8
NURSE CALL
SOAP DISPENSER
1'-8"EQ EQ
"5
HALL LANTERNS
RAISED
BRAILLE
CHARACTERS
ON HOISTWAY
ENTRANCES
HALL CALL
BUTTON
BULLETIN
BOARD
INTERACTIVE
WHITE BOARD
LENGTH VARIES 2
C
L E
A R
FIRE ALARM
PULL BOX
M A
X
IM
U M
FIRE
EXTINGUISHER
WALL HUNG
FIRE EXTINGUISHER
IN RECESSED
CABINET
PULL HANDLE
LINE MOUNTED AT
TOP OF BASE
FIRE ALARM
SPEAKER
7' -6
U
.O .N
ALIG
N
FIRE ALARM
COMBINATION
SPEAKER/STROBE
OR STROBE
W.1 V
VAV BOX
LOCATION
CABLE TRAY
C L E
A R
VAV BOX
LOCATION
EQ EQ
ACCESS ZONE
2'-0"
ZONE
LIGHT FIXTURE
ACCESS ZONE
2'-0"
MECHANICAL
PIPING
FIRE PROTECTION
PIPING
M
IN
ELECTRICAL
CONDUIT
SCHEDULED
CEILING FINISH
M E
P Z
O N
E
/4
V
IF
SMOKE AND ACOUSTIC
SEALANT AT ALL
PERIMTER AND
PENETRATIONS OF
CORRIDOR FACING
WALLS. (TYP)
SCHEDULED
FLOOR FINISH
SCHEDULED SMOKE
BARRIER PARTITION.
TYPICAL AT
CORRIDORS
MECHANICAL
DUCT TRUNK
TYPICAL
CORRIDOR11
F
LO
O
R T
O U
N D
E R
S
ID
E O
F D
E C
K
N O
T E
D O
T H
E R
W
IS
E
U
N L E
S S
AUDIO FIRE
ALARM ONLY
EXIT SIGN FIRE ALARM
PULL STATION
(GENERALLY
LOCATE UNDER
A/V ALARM)
W
IT
H O
W N
E R
C O
O R
D
IN
A T
E
8"
COMBINATION
POWER/SIGNAL/OUTLET
FOR WALL MOUNTED
TELEVISION OR
MONITOR
T.V./DATA/
PHONE
POWER
RECEPTACLES
LIGHT
SWITCHES
DOME
LIGHT
OCCUPANCY
SENSOR
CARD
READER
POWER
DISCONNECT
REMOTE DOOR
RELEASE
"5
M
A X
RECEPTACLES AT
TYPICAL CASEWORK
ASSEMBLY
TYPICAL
WORKSTATION
ASSEMBLY
".3
CLEAR
2'-6"
TV
D/V
TV E
E
ED/V
L L OS CR DR E
E
E
D/V
EM
T
EQ EQ
ALIGN
THERMOSTAT AT
PERIMETER CONVECTOR
POWER/DATA
RECEPTACLES AT WALL
MOUNTED COMPUTER
STATIONS
P D
AUDIO/VISUAL FIRE ALARM,
NURSE CALL, THERMOSTAT,
HAND SANITIZER, WALL
SWITCH
NOTE: DOME LIGHTS AT END OF CORRIDORS ARE CEILING MOUNTED. DOME LIGHTS OUTISDE OF PATIENT TOILETS ON 10TH FLOOR ARE WALL MOUNTED.
EQ EQ
ALIGN
1' -6
3' -6
6' -5
/2
4' -6
NC
ALIGN
6"
D O
O R
F R
A M
E 1"
A B
O V
E
EQ EQ
DOME LIGHT ABOVE
DOOR FRAME
NOTE: CONTRACTOR TO COORDINATE IN FIELD TO ASSURE THAT A 2'-0" SPACING IS MAINTAINED BETWEEN RECEPTACLES THAT ARE BACK TO BACK WITHIN THE SAME PARTITION AT THE SAME MOUNTING HEIGHT.
NEW METAL
CONVECTOR
COVER
WINDOW
NIGHT LIGHT, THERMOSTAT,
WALL SWITCH, AND FIRE
ALARM WHERE APPLICABLE
AT PATIENT BATHS, PUBLIC
TOILET, AND STAFF TOILET.
6"
1' -6
3' -6
" 4' -6
NIGHT
LIGHT
PANIC
BUTTON
NC
3' -8
NURSE CALL
PULL
STATION
NC
PULL
STATION AT
SHOWER
PULL
STATION AT
WATER
CLOSET
6' -0
1' -6
ALIGN
TT
CL
M
IN
LOCATE
SIGN ON
LATCH SIDE
OF DOOR
D
IM
E N
S
IO
N S
S E
E C
O D
E S
IG
N
A G
E
A D
A D
E T
A
IL
S F
O R
2"
WALL MOUNTED
EXIT SIGN
NOTE: REFER TO 1-AG DRAWING SERIES (WAYFINDING)
FOR ADDITIONAL INFORMATION.
TACTILE CHARACTERS
BASELINE ZONE: 48" - 60"
MIN.
9"
CL
SINGLE DOOR
POSITION ON LATCH SIDE OF DOOR OR NEAREST
ADJACENT WALL, AT A 9" MIN DISTANCE FROM THE
CNTER OF THE RAISED CHARACTERS ON THE SIGN.
EXCEPTION: PERMITTED ON THE PUSH SIDE OF DOORS
WITH CLOSERS BUT WITHOUT HOLD OPEN DEVICES.
CL
INACTIVE ACTIVE
MIN.
9"
CL
MIN.
9"
LOWEST TACTILE CHARACTER
BASELINE NOT PERMITTED BELOW
CHARACTER BASELINE ZONE
DOUBLE DOOR
POSITION ON INACTIVE DOOR LEAF. IF TWO
ACTIVE LEAFS, SIGN GOES TO RIGHT OF RIGHT
HAND DOOR. IF NO SPACE THERE, THEN ON
NEAREST ADJACENT WALL.
LOREM
IPSUM
HIGHEST TACTILE
CHARACTER BASELINE
LOWEST TACTILE
CHARACTER BASELINE
SIGN
HIGHEST TACTILE CHARACTER
BASELINE NOT PERMITTED ABOVE
CHARACTER BASELINE ZONE
VACUUM BREAKER
SHOWER SLIDE WITH
HAND HELD SHOWER
AND 60" HOSE
1'-6" 6"
RECESSED SST
SHELF
CONTROL WALL
THERMOSTATIC
MIXING VALVE
4" 1'
-6
6"
3'-0"
2' -1
0"
SIDE WALL
1'-6" 6"
2' -1
0" 5"
NOTE: SHOWER HOSE VACUUM BREAKER SHALL BE LOCATED A MINIMUM OF
6" ABOVE HAND SPRAY AT UPPERMOST POSITION ON SLIDE BAR.
NC
6"
9 1/2" 1'-5"
1'-6"
6"
9 1/2"
/4
/4
/4
" 6"
RED
WHITE TEXT
1/32" THK RAISED LASER CUT AND
APPLIED LETTERING
ROWMARK BLACK - ADA ALTERNATIVE
CLEAR RASTER BRAILLE
REDUNDANT, GRADE II
3/16" THK CLEAR NON-GLARE ACRYLIC LENS WITH
2ND SURFACE FLANGE AT TOP AND BOTTOM
1/4 W X 3/8" D FABRICATED ALUMINIUM OUTER
FRAME. SATIN ANODIZED FINISH
/4
/4
/4
2 3 4 1
1'-6"
ELEVATOR
3002.3 EMERGENY SIGNS
TOILET FACILITY
1111.1 ACCESSIBILITY SIGNAGE
BUILDING EXITING LOCATION MEANS OF EGRESS
1011 EXIT SIGNAGE
MEANS OF EGRESS
1023.9 STAIRWAY
IDENTIFICATION SIGNS
MEANS OF EGRESS
1007.9 SIGNAGE
CORRESPONDING GRADE II BRAILLE.
1/10" WITHIN CELL. 2/10" BETWEEN CELLS,
1/40" MIN. RAISE ABOVE THE
BACKGROUND. LOCATED 3/8" MIN. BELOW
TACTILE CHARACTERS
WALL MOUNTED SIGNAGE TO BE LOCATED ON LATCH SIDE
OF DOOR, CLEAR OF DOOR SWING. TACTILE CHARACTERS
SHALL BE CENTERED ON A MIN 18"X18" AREA LOCATED
OUTSIDE THE ARC SWING OF THE DOOR. BRAILLE SHALL
COMPLY WITH ADAAG 703.3.1, 703.3.2, FIGURE 703.31, AND
TABLE 703.3.1
AREA OF
RESCUE
ASSISTANCE
H
IG
H E
S T
L
IN
E O
F T
E X
T
M A
X T
O B
O T
T O
M O
F
O F
L O
W E
S T
L
IN
E O
F
M
IN
T O
B O
T T
O M
T A
C T
IL
E
C H
A R
A C
T E
R S
T A
C T
IL
E
C H
A R
A C
T E
R S
360 Madison Avenue, New York, New York 10017 212.972.9800 o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
Revisions:
Date o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t
Building Number
Approved:
Drawing Title Project Title
Date
Office of Construction &
Facilities Management
F
E
D o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e in c h e s o n e fo o t
1 2 3 4 5 6 7 8 9
C
B
A
Location
Checked Drawn
Drawing Number
Project Number
CONSULTANTS: ARCHITECT/ENGINEERS:
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
KEY PLAN:
VA FORM 08-6231
Contractor to Provide Seismic Bracing for All Utilities Building is Fully Sprinklered Scale: AS NOTED
ASBESTOS ABATEMENT CONSULTANT:
14 HIGH STREET
MAHWAH, NEW JERSEY 07430
Tel: (914) 320-7924
Egan Environmental Consulting, Inc. 423 EAST 23RD STREET
NEW YORK, NY 10010
VA NY HARBOR HEALTHCARE SYSTEM
MANHATTAN VAMC -
BUILDING 1 WARD RENOVATIONS
Sheet Number 113of
1-A002
TYPICAL MOUNTING HEIGHTS
GV LP
630-18-101
February 12, 2021 12
SCALE: 1/4" = 1'-0"
EQUIPMENT AND ACCESSORIES
SCALE: 1/4" = 1'-0"
ACCESSORIES AND PLUMBING FIXTURES
SCALE: 1/4" = 1'-0"
ELEVATOR CONTROLS
SCALE: 1/4" = 1'-0"
VISUAL DISPLAY BOARDS
SCALE: 1/4" = 1'-0"
FIRE PROTECTION EQUIPMENT
0 4' 8'
0 4' 8'
0 4' 8'
0 4' 8' 0 4' 8'
0 4' 8'
0 4' 8'
0 4' 8'
SCALE: 1/2" = 1'-0"
TYPICAL CORRIDOR SECTION
SCALE: 1/4" = 1'-0"
ELECTRICAL CONTROL DEVICES
SCALE: 1/4" = 1'-0"
SPACE SIGNAGE
SCALE: 1/4" = 1'-0"
ACCESSIBLE SHOWERS
SCALE: 1" = 1'-0"
1-A002_3_
0 2' 4'
0 2'1'
UP
UP
UP
DN
DN
UP
18.716.816.9
A
B
C
D
E
G
F
J.2
H
J
L
N
O
Q
E.9
F.5
12.1 13 15.1 16
F5/1-A104W
W a
W a
W a
W
W
W a
W a
W a
W
W
W
W
W
W b
W b
W a .1
W
4001aW a .1
W
4002aW
4009aW
4033W
4032W
4029W
4023W 4014W
4022W 4016W
4020W 4017W
W
W
W
4202W
4021W
4030W
4031bW
4002W
4001W a
W
4031aW
EG1A
EG1E
EG1A
EG1A
EG1K
EG1A
EG1A
EG1A
EG1A
EG1E
EG1A
EG1A
EG1E
EG1A
EG1A EG1A
EG1A
EG1A
EG1A
EG1A
EG1F
EG1A
EG1D
EG1H
EG1H
EG1H
EG1G EG1H EG1H EG1H EG1H
EG1A EG1E EG1F EG1A
EG3B
EG5C
10"
6'-2 3/4"
1'-1"
6'-0 3/4" 1'-5 3/4"
HOLD
8'-0" 1'-1" 6'-8 3/4"
1'-1"
3/
4"
'-7
/4
8' -6
/4
'-6
/2
'-1
1" 8'
-3
4' -8
'-5
'-6
'-4
3"
'-9
8' -3
'-2
/2
'-0
/4
8'
-0
/4
'-9
/4
'-9
/4
8' -0
/4
'-0
/4
'-7
/4
8'
-3
'-5
/2
4STC
4013W
4STW
4015W
11a
27 2727
21a
12a
18 18
14bs
14b 11b
12a
42bs
41bs
11b 27
20 27 22
12a
11b11b
11b
11b
11b
11b11b
W 15a
11a
11a
12a
20a11b
41b
11a
41b
12a30
12a
27 21
12a
11a
12a
17a
12a
17a
12a
12a
11a
12a
12a
12a
21a
12a
11a
41bs41bs
12a
11a
12a
11a
12bs
12bs
20a
12a
21a
27 27
12 12a
12 20
F5/1-A104W
'-0
'-0
'-0
'-0
'-0
'-0
'-0
'-0
'-0
SERVICE WALL TYP.
11'-0" HOLD
1'-7 1/4" HOLD
2'-10 3/4"
8'-6 3/4"
1" 14'-5" 3'-6 3/4"
2'-1"
2'-11"
7' -1
1"
1' -1
4' -1
1"
2' -0
/2
H O
LD
8' -0
HOLD
2'-6"
6'-0" 1'-1"
8'-2" 9'-9 1/2" 18'-10"
15'-8"
HOLD
8'-0"
212121
10"
SERVICE WALL, TYP.
11'-0" 1'-7 1/4"1'-7 1/4"
SERVICE WALL, TYP.
11'-0" 7" 12'-11 3/4"
S E
R V
IC
E
W A
LL
8' -6
" 1' -7
/4
1-A607D1 1-A607 F1
1-A607 E1
BATH
4032aW
BATH
4033aW
MEDS
4028W
BATH
4029aW ANTE
4002aW
STF. TLT.
4005W
CLEAN
UTILITY
4006W
STORAGE
4007W
CLEAN
LINEN
4008W
BATH
4009aW
BATH
4011aW
DATA
4012W
PCTC
4025W
NOUR.
4024W
MED/SURG
1 BED
4023W
MED/SURG
1 BED
4014W
BATH
4022aW
BATH
4014aW
BATH
4016aW
BATH
4020aW
BATH
4018aW
BATH
4017aW
NURSE
STATION
4026W
MED/SURG
1 BED
4033W
ISO. BATH
4001bW
ANTE
4001aW
MED/SURG
ISOLATION
BED
4001W
MED/SURG
BARIATRIC
1 BED
4032W
MED/SURG
ISOLATION
BARIATRIC
BED
4002W
MED/SURG
1 BED
4029W
SOIL. UTL.
4003W
MED/SURG
1 BED
4011W
MED/SURG
1 BED
4009W
MED/SURG
1 BED
4016W
MED/SURG
1 BED
4017WMED/SURG
1 BED
4020W
MED/SURG
1 BED
4022W
MED/SURG
1 BED
4019W
ISO. BATH
4002bW
HAC
4004W
EXIST.
ELEC.CL.
4013W
EX. FEC
4015W
ELEC.
CLOSET
4030W
EQUIPMENT
ALCOVE
4201kW
ALCOVE
4201bW
FOOD
CART
ALCOVE
4010W
ELEC.
CLOSET
4031bW
BATH
4019aW
MACERATOR
ROOM
4021W
ALCOVE
4201cW
BATH
4023aW
CORRIDOR
4201W
CORRIDOR
4202W
ELEC.
CLOSET
4031aW
PATIENT
MONITORING
4026aW
1-A602 B1
1-A602 F1
EG1A
EG1A
EG1F
1-A603 B1
11a
C
H O
LD
4'
-1 0"
2"
TYP.
1'-7 1/4"
SERVICE WALL TYP.
11'-0"
H O
LD
4' -0
2' -1
T
Y P
3' -1
1"
'-6
6' -2
H
O
LD
2' -0
3'
-6
/2
'-5
/4
11b
1'-7 1/4"
12a
12a
11bs
TYP.
4'-6"
135° ALIGN
3' -0
4'-2 1/4"
1'-0"
A L
IG
N T
Y P
2' -1
S E
R V
IC
E
W A
LL
'-0
21a
2' -0
ALIGN
1' -3
/4
8'
-5
/4
'-0
'-7
/2
8' -3
8'
-3
/4
H O
LD
8' -0
1' -1
1"
7' -4
/2
1'-6" 3'-8 1/4"
5"A L
IG
N
3/
4"
ALIGN
7'-9 1/2" 4'-11"
2' -0
/2
2'
-6
12'-2"
1'-7 1/4" TYP.
SERVICE WALL TYP.
11'-0"
1'-1" 6'-1 1/2"
1'-11 1/4"
8'-0" HOLD 2'-5" 5'-9 1/2"
1'-1"
11 1/4"
SERVICE WALL TYP.
11'-0"
1'-7 1/4" TYP.
TYP.
TYP.
4'-6"
2' -1
T
Y P
.4' -7
/4
1' -4
4' -0
2'
-2
/4
2' -1
/4
2'
-6
4' -0
H
O
LD
1'-6 1/2"
5'-4 1/2" 1'-10"
8'-6"
1' -6
2'
-3
/4
3' -8
T
Y P
2' -8
/2
4'
-1
ALIGN
TYP.
2 222
10.2
10.1
10.1
10.1
10.1
10.1
1-A604
E7
1-A602 D1
1-A603 E1
1-A603 F1
11c
1'-7 1/4" HOLD
SERVICE WALL TYP.
11'-0" HOLD
1' -2
4'
-8
/4
2'-5" 4'-6"
A L
IG
N
T Y
P
27a
A L
IG
N
T Y
P
ALIGN
10"
3' -1
1"
2' -6
/2
3'-10"
10'-1 1/4"
41bs
CONNECTION
TO OR'S
(BUILDING 6)
OPEN TO
BELOW
A L
IG
N T
Y P
SERVICE WALL TYP.
11'-0" 1'-7 1/4"
1'-1"
6'-3 3/4"
11"
1-A801 F6
SIM
12a
11a
4011aW
TYP.
TYP.
TYP.
TYP.
TYP.
1-A606 E1
A L
IG
N
2'-1"
EG1A
1-A801 F8
1-A801 F8
1-A801 F8
1' -7
1-A605 F1
1-A606
F1
CRASH
CART
ALCOVE
4201mW
1' -4
/4
4'
-0
MED/SURG
1 BED
4018W
ALCOVE
4201aW
ALCOVE
4201jW
ALCOVE
4201dW
ALCOVE
4201eWALCOVE
4201hW
DAY
LOUNGE
4201fW
4019W 4018W
12a
12a
12 21
12a
21a
12a 12a
12a
27a
12a12a
12a
12211221a
27 27
12 21 12 21
12211220 a
W a
W a
W a
W
4 STAIR
WEST
4STW
4 STAIR
CENTER
4STC
2' -1
T
Y P
. 9' -3
/4
5'
-1
1/ 2"
ALIGN
10"
1'-9 1/4" 1'-1" 6'-1 1/2"
1'-1 1/4"
1'-4" 5'-9 1/2" 1'-1"
1'-10 1/2"
3' -6
/2
"1 '-4
ALIGN
1' -0
1' -0
10.1 10.1
10.1
10.110.1
10.110.1
10.110.1
TYP
CORRIDOR
4200aW
1-A607C1 F1
14 18 2012.8 15.2
18.716.8
17.1
16.9
16.2
O
Q
R
S S.1
T
U.6
15.3
U.1
W.1
18.1
12.1
12.1
13 15.1 16
V
1-A606
F4
.1 C
C
4076bC
4079C
4076aC
C
C
C
4034W
4051C
4052C
EG1A EG1A EG1A EG1A EG1A EG1A
EG1A
EG1A
EG1A
EG1A
8' -2
/4
1'
-1
/4
4049C
C
C
.2 C
4000.1C
4203C
11bs
11b
17a
212121
11a
11a
11a
41b
40c
40c
40c
11b
11b11b
41bs
11a
10 12
12a
11a
11a
20'-0" 20'-0" 20'-0" 20'-0"
1'-5 3/4"
27'-11 1/4"
1'-4 3/4"
18'-1 3/4" 12'-6 1/2"
ALIGN
1-A607
A1
A5
SHARED
STOR.
4080C
4S
STORAGE
4075C
TEAM
ROOM
4034W
MED/SURG
1 BED
4033W
PUB. TLT.
4037C
EXIST. IT
CLOSET
4052C
DAY
RM./FAMILY
LOUNGE
4035C
EXIST. FHC
4053C
EX. ELEC.
CLOS.
4049C
EXIST.
DISTRIBUTION
4127C
ELEVATOR
LOBBY
4000C
STORAGE
4036C
SERVICE
ELEVATOR
LOBBY
4076C
CORRIDOR
4208C
CORRIDOR
4200C
CENTRAL
COR. B
4203C
STAFF
LOUNGE
4079aC
EXIST. IT
CLOSET
4051C
F1/1-A104W
1-A604 E1
A L
IG
N T
Y P
2' -4
5'
-9
2' -7
/2
H O
LD
8' -0
ALIGN
21a
TYP.
TYP.
9 ALIGN
A L
IG
N
2' -7
/2
H
O
LD
8' -0
3'-1 1/2" 7'-9 1/4" 12'-11 3/4"
HOLD
6'-0"
3'-3 1/2"
HOLD
3'-6"
11bs
3'-5 1/2"
ALIGN
8'-7 1/4"
HOLD
8'-0"
12a
ALIGN
4'-7" 8'-0" HOLD
1'-9 1/4"
20a
1-A606 D1
4'-8 1/2"
1'-6" MIN.
41b
40c
X.1
1-A801 F6
SIM
CONNECTION TO OR'S
(BUILDING 6)
1-A604 C1
C
4'-0"
8" 7'
-4
EQ 5'-0" EQ
1' -6
/4
8'
-0
M
IN
4STC
1-A801 F2
SIM
1-A801 B1
SIM
AREA OF 4S IS NOT IN
CANNONDESIGNS SCOPE OF
SERVICES. GRAPHICS INDICATED
REFLECT THE PROPOSED
DESIGN BY OTHERS AT THE TIME
OF DOCUMENT PRODUCTION.
ACTUAL SCOPE MAY VARY
PENDING CONSTRUCTION
COMPLETION. COORDINATE 4S
SCOPE TIE-IN WITH OWNER.
AREA OF 4N IS NOT IN CANNONDESIGNS
SCOPE OF SERVICES. GRAPHICS
INDICATED REFLECT THE PROPOSED
DESIGN BY OTHERS AT THE TIME OF
DOCUMENT PRODUCTION. ACTUAL SCOPE
MAY VARY PENDING CONSTRUCTION
COMPLETION. COORDINATE 4N SCOPE TIE-
IN WITH OWNER.
F1/1-A104W
1-A607C1 F1
1. ALL DIMENSIONS ARE TO FINISHED FACE OF PARTITION UNLESS
NOTED OTHERWISE.
2. ALL DIMENSIONS SHOWN IN RENOVATED AREAS ARE TO BE
VERIFIED IN THE FIELD BEFORE PROCEEDING WITH WORK.
3. WHERE A FIXED RATED PARTITION IS SHOWN ABUTTING
EXTERIOR WALLS, THE FIRE RATED ASSEMBLY IS TO EXTEND TO
THE EXTERIOR WALL CONSTRUCTION.
4. IN ALL ROOMS BELOW AREAS WHICH RECEIVE UNDER FLOOR
SERVICES, REMOVE A PORTION OF EXISTING CEILING AS
REQUIRED. PATCH FINISHES TO MATCH EXISTING OR AS
INDICATED ON ROOM FINISH SCHEDULE.
5. REFER TO M.E.P. DRAWINGS FOR EXISTING AND NEW FIXTURES
AND SERVICES TO BE REMOVED AND/OR INSTALLED. EXISTING
FINISHES DISTURBED BY THIS WORK SHALL BE PATCHED TO
MATCH ADJACENT UNDISTURBED FINISHES.
6. WHENEVER EXISTING EQUIPMENT, PIPING, DUCTS, ETC ARE
REQUIRED TO BE REMOVED, SUCH REMOVAL SHALL INCLUDE ALL
ANCHORS, HANGERS, ETC. AFTER REMOVAL, FLOORS, WALLS
AND CELINGS SHALL BE FINISHED TO MATCH ADJOINING
SURFACES OR AS INDICATED ON ROOM FINISH SCHEDULE.
7. ALL PENETRATIONS THROUGH NEW & EXISTING RATED
CONSTRUCTION TO BE FIRESTOPPED W/ U.L. APPROVED
SYSTEMS. FIRESTOP AT ALL OPENINGS RESULTING FROM THE
RENOVATIONS OF EXISTING M.E.P. SYSTEMS. SEE M.E.P.
DRAWINGS TO DETERMINE FULL SCOPE OF WORK. REFER TO
E8/1-A1002 FOR DETAILS AND SCHEDULE OF THROUGH
PENETRATION FIRESTOPPING REQUIREMENTS. CONTRACTOR TO
MAINTAIN THE INTEGRITY OF THE RATED ASSEMBLY AT ALL
PENETRATIONS.
8. PATIENT BEDS ARE SHOWN IN PLAN FOR REFERENCE. REFER
TO '1-A1200' DRAWING SERIES FOR FURNITURE AND '1-Q104W'
DRAWING SERIES FOR EQUIPMENT PLANS FOR REFERENCE AND
COORDINATION. PROVIDE BLOCKING AT ALL EQUIPMENT AND
ACCESSORIES, REFER TO DETAIL E8/1-A901.
9. PROVIDE PARTITION TYPE 32 AT THE INTERIOR FACE OF WALL
ALONG THE PERIMETER U.O.N. SPRAY FOAM INSULATION TO BE
APPLIED ALONG EXTERIOR PERIMETER IN LINE WITH DETAILS IN
1-A400 SERIES.
10. FLOAT ENTIRE SLAB WITH HYDRAULIC CEMENT
UNDERLAYMENT. PROVIDE BONDING AGENT. REFER TO
SPECIFICATION SECTION 03 54 16 FOR ADDITIONAL INFORMATION.
11. PROVIDE ALL NEW EXTERIOR WINDOWS, HEAD/JAMB/SILL
RECEIVERS, TRIM, HARDWARE, INTEGRAL SHADES, OPERATORS,
INSECT SCREENS, ETC. REFER TO WINDOW SCHEDULES,
SECTIONS, DETAILS AND RELATED SPECIFICATIONS FOR
ADDITIONAL INFORMATION. CONTRACTOR IS TO FIELD VERIFY ALL
EXISTING CONDITIONS INCLUDING WINDOW SIZES, QUANTITY,
ETC. PROTECT ALL EXTERIOR WALL OPENINGS AND ADJACENT
CONDITIONS INCLUDING ORIGINAL STEEL WINDOW FRAMES TO
REMAIN, MASONRY, FLASHING, SEALANT ETC. PATCH, INFILL,
REPAIR, AND RESECURE EXISTING MATERIALS AND
ATTACHMENTS IN KIND AND AS REQUIRED FOR NEW WORK.
12. REFER TO SPECIFICATION SECTION 13 05 41 AND SEISMIC
DESIGN PARAMETERS LISTED IN STRUCTURAL DRAWINGS FOR
ALL SEISMIC BRACING REQUIREMENTS.
13. ALL LOOSE EXISTING CONCRETE MATERIAL AROUND BEAMS
AND/OR COLUMNS TO BE REMOVED TO EXPOSE BARE
STRUCTURAL STEEL. PREPARE STRUCTURAL STEEL TO RECEIVE
AND APPLY FIREPROOFING. ALL CRACKS TO BE FILLED WITH NON-
SHRINK GROUT.
14. REPAIR UNDERSIDE OF EXISTING CONCRETE SLAB WHERE
REQUIRED. REFER TO DRAWING 1-S001 FOR ADDITIONAL
INFORMATION.
15. PROVIDE SOLID SURFACE SILL AT ALL NEW WINDOWS. REFER
TO DRAWING 1-A400 FOR ADDITIONAL INFORMATION.
16. PROVIDE PERMANENT SIGNAGE ABOVE ALL SMOKE BARRIERS
AND RATED PARTITIONS TO COMPLY WITH 2012 IBC 703.7.
17. CONTRACTOR IS TO REVIEW AND FIELD VERIFY ALL
DIMENSIONS AND CONDITIONS RELATING TO THE EXISTING
BUILDINGS THAT INTERFACE WITH THE NEW CONSTRUCTION.
PRIOR TO COMMENCEMENT OF SCOPE OF WORK NOTIFY THE
ARCHITECT OF RECORD AND OWNERS REPRESENTATIVE WHEN
EXISTING CONDITIONS VARY FROM THE CONSTRUCTION
DOCUMENTS.
18. DIMENSIONS ALONG EXTERIOR WALL ARE ANCHORED TO GRID
LINES, U.O.N.
19. REFER TO 1-H SERIES FOR ADDITIONAL ASBESTOS
ABATEMENT REQUIREMENTS PRIOR TO COMMENCEMENT OF
WORK.
20. ALL CABINETRY WITHIN PATIENT SPACES, OTHER THAN THE
PATIENT WARDROBE, SHALL BE LOCKABLE WITH STAINLESS
STEEL CAM LOCK.
DRAWING SERIES ORGANIZATION FOLLOWS THE ORDER NOTED
BELOW. SEE DETAILED DRAWING INDEX FOR DETAILED LIST.
A100'S - ARCHITECTURAL PLANS
A200'S - VOID
A300'S - VOID
A400'S - EXTERIOR SECTION DETAILS
A500'S - VOID
A600'S - INTERIOR ENLARGED PLANS AND ELEVATIONS
A700'S - REFLECTED CEILING PLANS AND DETAILS
A800'S - INTERIOR DETAILS
A900'S - MILLWORK
A1000'S - PARTITION TYPES, OPENING SCHEDULES AND DETAILS
A1100'S - VOID
A1200'S - FINISH LEGEND AND PLANS
A1300'S - SIGNAGE AND WAYFINDING
A1400'S - FURNISHINGS
ALTERNATE #1
ALTERNATE #2
4000C, 4034C, 4035C, 4036C, 4037C, 4049C, 4051C,4052C, 4200C, 4203C, 4204C, 4208C
4075C, 4076C, 4079C, 4080C
CONSTRUCTION PLAN LEGEND
EXISTING CONDITIONS REMAIN
NEW CONSTRUCTION
EXISTING WINDOW ASSEMBLY TO REMAIN
GENERAL CONSTRUCTION NOTES
NEW DOOR ASSEMBLY
EXISTING DOOR ASSEMBLY TO REMAIN
MATCH LINE
CURTAIN TRACK (CEILING MOUNTED)
F1/1-AXXXX-X
F1/1-AXXXX-X
PATIENT LIFT TRACK (CEILING MOUNTED)
NEW WINDOW ASSEMBLY
DEDUCT ALT #1 - SERVICE CORE SCOPE REMOVAL.
REFER TO SPEC SECTION 012300 ALTERNATES
DEDUCT ALT #2 - CENTRAL CORE SCOPE REMOVAL.
REFER TO SPEC SECTION 012300 ALTERNATES
PROVIDE AUTOMATIC DOOR OPENER. REFER TO 1-A600
DRAWING SERIES, AND ELECTRICAL AND
TELECOMMUNICATION DRAWINGS FOR ADDITIONAL
INFORMATION.
PROVIDE NEW EXPANSION JOINT COVER AT FLOOR, WALLS,
AND CEILING. REFER TO DETAILS B2/1-A801 & C2/1-A801 FOR
ADDITIONAL INFORMATION.
PROVIDE NEW FIRE EXTINGUISHER BRACKET WITHIN
EXISTING FIRE HOSE CLOSET.
PROVIDE NEW METAL LOCKERS. REFER TO SPECIFICATION
SECTION 10 51 13 FOR ADDITIONAL INFORMATION.
SECURE STAIR DURING CONSTRUCTION. PROVIDE
TEMPORARY LOCK TO RESTRICT RE-ENTRY INTO THE UNIT,
BUT PROVIDE FREE EGRESS INTO THE STAIRWELL.
PROVIDE RATED SHAFTWALLWITHIN EXISTING STEEL
WINDOW SURROUND, AS SHOWN IN DETAIL F8/1-A452.
PROVIDE PEDESTRIAN PROTECTION SCAFFOLDING BELOW
DURING WINDOW REPLACEMENT. COORDINATE EXTENT
WITH VA PROJECT TEAM.
SPECIFIC CONSTRUCTION NOTES
PROVIDE AND INSTALL EXTENSION BACK BOXES FOR ALL
ELEVATOR CALL BUTTON ASSEMBLIES AND CALL LIGHTS,
AND EXTEND CONDUIT AND POWER TO BE FLUSH WITH NEW
FACE OF ELEVATOR WALL. REFER TO SHEET 1-A803 AND
ELECTRICAL DRAWINGS FOR ADDITIONAL INFORMATION.
PROVIDE NEW CONVECTOR ENCLOSURE.
NEW RATED WALL ACCESS PANEL. MATCH RATING OF
EXISTING WALL.
NEW DRINKING FOUNTAIN. REFER TO PLUMBING DRAWINGS
FOR ADDITIONAL INFORMATION.
EXISTING NOTIFIER FIRE ALARM CONTROL PANEL AND
WIREWAY TO REMAIN AND BE ACCESSIBLE. REFER TO
DRAWING 1-A803 AND ELECTRICAL DRAWINGS FOR
ADDITIONAL INFORMATION.
INFILL EXISTING SHAFT. REFER TO DETAIL B8/1-S001.
PAINT ALL EXPOSED PIPING WITH NEW COAT OF PAINT TO
MATCH EXISTING. SPRINKLER PIPING TO BE PAINTED RED.
PROVIDE NEW SKIM COAT OF SETTING TYPE JOINT
COMPOUND ALONG EXISTING WALL.
NEW FIN TUBE ENCLOSURE. REFER TO DETAIL E6/1-A451.
PROVIDE NEW PREFABRICATED PATIENT BED SERVICE WALL
TYPE 1A. REFER TO D6/1-A601 AND SPECIFICATION SECTION
10 25 13 FOR ADDITIONAL INFORMATION.
PROVIDE NEW PREFABRICATED PATIENT BED SERVICE WALL
TYPE 1B. REFER TO F6/1-A601 AND SPECIFICATION SECTION
10 25 13 FOR ADDITIONAL INFORMATION.
PROVIDE ACCESS PANEL IN NEW PARTITION FOR EXISTING
ELECTRICAL SERVICES. REFER TO ELECTRICAL DWGS FOR
ADDITIONAL INFORMATION. COORDINATE EXACT SIZE/
LOCATION WITH EXISTING EQUIPMENT.
PATIENT LIFT CABINET PROVIDED AS PART OF
PREFABRICATED PATIENT BED SERVICE WALL. REFER TO
'1-A601' DRAWING SERIES AND SPECIFICATION SECTION 10
25 13 FOR ADDITIONAL INFORMATION.
REFER TO M.E.P. DWGS FOR ADDITIONAL SCOPE OF WORK
IN THIS AREA. PATCH AND REPAIR EXISTING FINISHES TO
ACCOMMODATE INFRASTRUCTURE SCOPE.
10.1
10.2
WEST
SOUTH NORTH
360 Madison Avenue, New York, New York 10017 212.972.9800 o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
Revisions:
Date o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t
Building Number
Approved:
Drawing Title Project Title
Date
Office of Construction &
Facilities Management
F
E
D o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e in c h e s o n e fo o t
1 2 3 4 5 6 7 8 9
C
B
A
Location
Checked Drawn
Drawing Number
Project Number
CONSULTANTS: ARCHITECT/ENGINEERS:
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
KEY PLAN:
NTS
VA FORM 08-6231
Contractor to Provide Seismic Bracing for All Utilities Building is Fully Sprinklered
ASBESTOS ABATEMENT CONSULTANT:
14 HIGH STREET
MAHWAH, NEW JERSEY 07430
Tel: (914) 320-7924
Egan Environmental Consulting, Inc.
Scale: 1/8" = 1'-0"
PARTITION FIRE RATING LEGEND
1 HOUR FIRE
1 HOUR FIRE /
SMOKE BARRIER
423 EAST 23RD STREET
NEW YORK, NY 10010
VA NY HARBOR HEALTHCARE SYSTEM
MANHATTAN VAMC -
BUILDING 1 WARD RENOVATIONS
Area Not in Scope =
45 MIN. RATED DOOR
ASSEMBLY, TYP.
20 MIN. RATED DOOR
ASSEMBLY, TYP.
2 HOUR FIRE
90 MIN. RATED DOOR
ASSEMBLY, TYP.
2 HOUR FIRE /
SMOKE
BARRIER
90 MIN. RATED DOOR
ASSEMBLY, TYP.
Sheet Number 113of
1-A104W
ARCHITECTURAL PLAN 4TH FLOOR -
WEST & CENTRAL
AH/JKC CJO
630-18-101
February 12, 2021 13
0 8' 16'SCALE: 1/8" = 1'-0"
F1
ARCHITECTURAL PLAN 4TH FLOOR - WEST
SCALE: 1/8" = 1'-0"
F5
ARCHITECTURAL PLAN 4TH FLOOR - CENTRAL
0 8' 16'
ADDENDUM 01 1 02/12/2021
R.O.
+/- 7'-1"
R .O
- 6
'-9
2' -3
- 6
2' -9
9' -6
RELOCATE STEEL CHANNELS AS REQUIRED
TO ACCOMMODATE NEW HEATING UNIT, MAINTAIN
CHANNELS FOR SILL SUPPORT
EXISTING ORIGINAL STEEL WINDOW FRAME/ STEEL
SURROUND AND STEEL CHANNEL
ASSEMBLY TO REMAIN
EXTENT OF WINDOW REMOVAL, SEE DEMO DETAIL FOR ADDITIONAL INFO.
NEW DEMO
NOTE: VIEW SHOWN IS TYPICAL FROM THE INTERIOR AND
NEGATES EXISTING FINISHES AND RADIATOR COVER TO BE
REMOVED FOR DIAGRAMMATIC PURPOSES. SEE FLOOR
PLANS AND SCHEDULES FOR ADDITIONAL INFORMATION.
LOCATION/ CONFIGURATION OF PROPOSED
METAL RADIATOR COVERCOORD WITH MECH
+/- 4'-0"
LOCATION/ OF PROPOSED RADIATOR
B6
1-A451
OPH
SCOPE OF WORK AT EXISTING ORIGINAL WINDOW FRAMES AND STEEL SURROUND TO REMAIN:
- PATCH, INFILL, AND REPAIR EXISTING MASONRY WALL CONSTRUCTION IN KIND - AS REQUIRED
TO MAKE READY FOR NEW WORK. SEE SECTION AND WINDOW DETAILS FOR ADDITIONAL INFO.
-REINFORCE, RE-ATTACH, OR REPLACE DETERIORATED STEEL TABS, CLIPS, ANGLES, AND
ANCHORS FOR STEEL WINDOW FRAMES IN KIND - AS REQUIRED TO MAKE READY FOR NEW
WORK.
+/- 8"
- 5
+/- 8"
F1
1-A451
F5
1-A451
SCOPE OF WORK FOR EXISTING ORIGINAL STEEL WINDOW MULLION/ SUPPORT MEMBER TO REMAIN:
-REINFORCE, RE-ATTACH, AND REPLACE DETERIORATED STEEL CLIPS, ANGLES, AND ANCHORS FOR STEEL MULLION IN KIND - AS REQUIRED TO MAKE READY FOR NEW WORK. SEE TYPICAL WINDOW CENTER MULLION DETAIL FOR ADDITIONAL INFO. INCLUDE (1) 2X6 INTERMEDIATE VERTICAL MULLION
(ALUMINUM TUBE, 6063-75 MATERIAL MIN.)
F8
1-A451
1'-4 3/4" +/-
CL
+/- 1'-3 1/2"
+/- 1'-3 1/2"
HEAD
JAMB
SILL
- 2
'-8
/4
- 6
- 5
- 1
/2
- 2
'-6
- 2
/4
3"
E X
IS
TI
N G
M .O
- 7
'-0
- 1
/2
REMOVE ALUMINUM WINDOW
SYSTEM AND ASSOCIATED
EXTERIOR AND INTERIOR TRIM,
INCLUDING ATTACHMENTS,
CAULKING, BACKER ROD, ETC.
EXISTING ORIGINAL STEEL
WINDOW FRAME/ STOOL
ASSEMBLY TO REMAIN
EXISTING MASONRY
WALL CONSTRUCTION
EXISTING ALCOA SILL
TO REMAIN, REMOVE
ALL CAULK, CLEAN
AND PREP FOR NEW
WORK
REMOVE CEILING SYSTEM,
SUPPORTS AND
ATTACHMENTS IN ITS
ENTIRETY
R .O
REMOVE EXISTING
RADIATOR COVER AND
ATTACHEMENTS AS
REQUIRED FOR NEW
WORK
SILL BELOW TO REMAIN
EXISTING ORIGINAL STEEL
WINDOW FRAME AND STEEL
CHANNEL FRAMING ASSEMBLY TO
REMAIN
EXISTING ORIGINAL STEEL
WINDOW FRAME AND STEEL
CHANNEL FRAMING ASSEMBLY TO
REMAIN
REMOVE ALUMINUM WINDOW
SYSTEM AND ASSOCIATED
EXTERIOR AND INTERIOR TRIM,
INCLUDING ATTACHMENTS,
CAULKING, BACKER ROD, ETC.
+/- 9 1/2"
1'-4 3/4" +/-
+/- 1'-3 1/2"
+/- 1'-3 1/2"
HEAD
- 5
WORK POINT
GWB AT JAMB BEYOND
REFER TO REFLECTED CEILING
PLANS AND DETAILS FOR
CEILING/ SOFFIT CONFIGURATION
2 1/2" METAL STUD FURRING AT
16" O.C., MECHANICALLY
FASTENED TO EXISTING STEEL
WINDOW SURROUND TO REMAIN
INFILL STUDS WITH 1 1/2" SPRAY FOAM
INSULATION, INSTALL CONTINUOUS 1" SPRAY
FOAM INSULATION BEHIND FURRING, TOTAL
= 2 1/2" SPRAY FOAM INSUALTION
4" SPRAY FOAM INSULATION
SCHEDULED BASE
GWB WITH 1 5/8" METAL STUD
FURRING, 16" O.C., INSTALL STUDS
1" MIN. FROM EXISTING MASONRY
EXTERIOR WALL
EXISTING
MASONRY WALL
CONSTRUCTION
EXISTING ORIGINAL GROUTED STEEL
WINDOW FRAME/ SURROUND ASSEMBLY AND
ATTACHMENTS TO REMAIN
NOTE:
CONTRACTOR IS RESPONSIBLE TO INFILL,
REPAIR, REPLACE, OR RE-ATTACH
MATERIALS AS REQUIRED FOR NEW WORK.
SEE DETAIL B1 THIS SHEET FOR ADDITIONAL
INFO.
FACE OF EXISTING WALL
1/ 2"
S E
E S
C H
E D
U
LE
W
IN
D O
W
- 3
S E
E S
C H
E D
U
LE
R O
U G
H O
P E
N
IN
G
1/
2" 2'
-6 " 2' -9
/2
5/8" GWB TO DECK ABOVE, SPACKLED AND SANDED
3/ 4"
1/ 4"
PAINT EXPOSED JOINT
CONT 'J' BEAD
EXISTING ORIGINAL GROUTED STEEL WINDOW
FRAME/ SURROUND ASSEMBLY AND
ATTACHMENTS TO REMAIN
NOTE:
CONTRACTOR IS RESPONSIBLE TO INFILL,
REPAIR, REPLACE, OR RE-ATTACH MATERIALS
AS REQUIRED FOR NEW WORK. SEE DETAIL
B1 THIS SHEET FOR ADDITIONAL INFO.
EXISTING ORIGINAL GROUTED STEEL WINDOW
FRAME/ SURROUND ASSEMBLY AND
ATTACHMENTS TO REMAIN
NOTE:
CONTRACTOR IS RESPONSIBLE TO LEVEL, INFILL,
REPAIR, REPLACE, OR RE-ATTACH MATERIALS
AS REQUIRED FOR NEW WORK. SEE DETAIL B1
THIS SHEET FOR ADDITIONAL INFO.
EXISTING CONCRETE
CURB
SILL
FIRESTOPPING
2 1/2" SPRAY FOAM INSULATION
WOOD BLOCKING
GWB, PTD.
5/8" GWB, SPACKLED
AND SANDED
1/ 2"
3 1/4" FROM FACE OF EXISTING STEEL SURROUND
FACE OF FURRED OUT WALL-VARIES,
REFER TO FLOOR PLANS
METAL STUD FURRING TO DECK ABOVE,
INFILL STUDS WITH 1 1/2" SPRAY FOAM
INSULATION
JAMB
SOLID SURFACE SILL WITH EASED EDGES
ON FIRE RETARDENT PLYWOOD
ALUMINUM WINDOW SYSTEM
ALUMINUM WINDOW SYSTEM
3 5/8" BATT INSULATION
3 1/4" FROM FACE OF EXIST STEEL SURROUND
3 1/4" FROM FACE OF
EXISTING STEEL SURROUND
COL
1" GAP, MIN.
1 5/8" METAL STUD FURRING AT
16" O.C., MECHANICALLY
FASTENED TO EXISTING STEEL
WINDOW SURROUND TO REMAIN
SEALANT
1" GAP
1-A453 B7
1-A453 F7
EXIST. STL CHANNEL BEYOND
EXIST.
EXTERIOR
MASONRY WALL
FACTORY PTD. MTL
RADIATOR REMOVABLE
COVER
FIN TUBE RADIATOR,
REFER TO MECH DWGS.
MTL TOE CLIP
EXIST. CONC.
OPEN BACK DESK WHERE OCCURS,
REFER TO FLOOR PLANS
SCHEDULED BASE
FIRE RETARDENT WD.
BLOCKING ON 1-5/8" MTL.
STUDS @ 16" O.C.
SEALANT
1 1/4" FLUID APPLIED THERMAL
BARRIER COATING OVER 4"
SPRAY FOAM INSULATION.
NEW WINDOW SYSTEM
NOTE: REFER TO SECTION DETAILS AND
WINDOW SCHEDULE FOR WINDOW
TYPES, DIMENSIONS, AND TYPICAL NOTES
BENT SHEET MTL SPACED
1" FROM FIN TUBE
1-5/8" MTL. STUDS
3/ 4"
1/ 4"
4" 6"
4" 6"
4"
TO FACE OF NEW WALL
1'-7 1/2"
6"
R A
D
IA
T O
R C
O V
E R
2' -0
1"
2 1/2" SPRAY FOAM INSULATION
1" 1"
B6
1-A451
/2
EXIST. STL CHANNEL TO REMAIN
EXIST. EXT MASONRY WALL
FACTORY PTD. METAL
RADIATOR REMOVABLE COVER
FIN TUBE RADIATOR,
REFER TO MECH DWGS.
PTD. FIRE RETARDANT WD.
BLOCKING AND SHIMS
5/8" GWB PTD.
1-5/8" MTL STUDS @ 16"
OC
A L
IG
N
J-BEAD
4" SPRAY FOAM INSULATION
OVER EXISTING MASONRY WALL
REFER TO SECTION VIEW, PROVIDE
SHEET METAL BETWEEN SPRAY
FOAM INSULATION AND FIN TUBE
LINE OF EXIST. CONCRETE CURB
BELOW
1. SPRAY FOAM INSULATION IS TO BE INSTALLED CONTINUOUSLY AS
INDICATED, NOT LESS THAN 2 1/2" THICK OR IN THICKNESS INDICATED
AT ALL EXTERIOR WALLS FROM FLOOR TO DECK ABOVE WITHIN
PROJECT SCOPE AREA U.N.O.
2. SPRAY FOAM INSUALTION AT ALL LOCATIONS INSTALLED IS TO BE
COMPLETELY ENCLOSED AND SEALED WITH 5/8" GYPSUM BOARD TYPE
"X", OR ALTERNATE THERMAL BARRIER APPROVED BY RE, FROM
FLOOR TO DECK ABOVE, AT AND AROUND MASONRY OPENINGS.
3. REFER TO 1-A453 FOR H/J/S DETAILS UNLESS OTHERWISE NOTED.
4. REFER TO SPECIFICATION SECTION 072129 FOR ADDITIONAL
INFORMATION ON FLUID APPLIED THERMAL BARRIERS.
GENERAL NOTES
360 Madison Avenue, New York, New York 10017 212.972.9800 o n e q u a rt e r in c h o n e fo o t o n e e ig h th in c h o n e fo o t
Revisions:
Date o n e h a lf in c h o n e fo o t th re e e ig h th s in c h o n e fo o t th re e q u a rt e rs in c h o n e fo o t
Building Number
Approved:
Drawing Title Project Title
Date
Office of Construction &
Facilities Management
F
E
D o n e a n d o n e h a lf in c h e s o n e fo o t o n e in c h o n e fo o t th re e in c h e s o n e fo o t
1 2 3 4 5 6 7 8 9
C
B
A
Location
Checked Drawn
Drawing Number
Project Number
CONSULTANTS: ARCHITECT/ENGINEERS:
F
E
D
C
B
A
1 2 3 4 5 6 7 8 9
KEY PLAN:
VA FORM 08-6231
Contractor to Provide Seismic Bracing for All Utilities Building is Fully Sprinklered Scale: AS NOTED
ASBESTOS ABATEMENT CONSULTANT:
14 HIGH STREET
MAHWAH, NEW JERSEY 07430
Tel: (914) 320-7924
Egan Environmental Consulting, Inc. 423 EAST 23RD STREET
NEW YORK, NY 10010
VA NY HARBOR HEALTHCARE SYSTEM
MANHATTAN VAMC -
BUILDING 1 WARD RENOVATIONS
Sheet Number 113of
1-A451
EXTERIOR SECTION DETAILS
AH/GV GP
630-18-101
February 12, 2021 14
SCALE: 1/2" = 1'-0"
B1
WALL ELEVATION AT WINDOW DEMOLITION
SCALE: 1 1/2" = 1'-0"
F1
SECTION DETAIL AT TYPICAL WINDOW DEMOLITION
SCALE: 1 1/2" = 1'-0"
F5
SECTION DETAIL: AT TYPICAL WINDOW REPLACEMENT
SCALE: 1 1/2" = 1'-0"
F8
RADIATOR DETAIL - TYPICAL
SCALE: 1 1/2" = 1'-0"
B6
RADIATOR PLAN DETAIL - TYPICAL
0 2' 4'
0 8" 16" 0 8" 16" 0 8" 16"
0 8" 16"
12.8
1'-9"2'-0"3'-6"2'-0"1'-9"
11'-0"
2' -0
6"
6" 1'
-8
1' -4
6"
1' -6
EQEQ
2' -0
2'
-0
6"
T O
T O
P O
F E
Q U
IP
. R
A
IL
3' -6
NOTE: OPPOSITE HANDED ROOMS INCLUDE 4009W
8' -0
WORKSURFACE PROVIDED
AS PART OF PATIENT BED
SERVICE WALL
REVEAL
PATIENT LIFT CABINET
PROVIDED AS PART OF
PATIENT BED SERVICE WALL
EQ 6" 6" 6" EQ
9"
EQ 6" 6" 6" EQ3"
2' -3
1'
-1
3"
PATIENT LIFT TRACK
OPENING
AOVVVVOA
1'-6" 1'-9" 3'-6" 1'-9"
8'-6"
1' -6
1'
-1 0"
1' -8
6"
6" 2'
-0
EQ 5" 5" 5" EQ
2' -0
2'
-0
6"
T O
T O
P O
F E
Q U
IP
. R
A
IL
3' -6
8' -0
REVEAL
PATIENT LIFT CABINET
PROVIDED AS PART OF
PATIENT BED SERVICE WALL
WORKSURFACE PROVIDED
AS PART OF PATIENT BED
SERVICE WALL
EQ EQ
3"
EQ 5" 5" 5" EQ
2' -3
PATIENT LIFT TRACK
OPENING
AOVVVVOA
TELECOMMUNICATIONS OUTLETS, REFER TO
TELECOMMUNICATION DRAWINGS FOR ADDITIONAL
INFORMATION
1. PATIENT BED SERVICE WALLS TO BE PREFABRICATED
MODULAR UNITS; COORDINATE INSTALLATION WITH
MANUFACTURER. CONTRACTOR TO COORDINATE ALL
WALL MOUNTED EQUIPMENT AT PATIENT BED SERVICE
WALL. REFER TO 1-A1200 SERIES FOR FINISH
INFORMATION. REFER TO CONSTRUCTION PLANS AND
SPECIFICATION SECTION 10 25 13 FOR ADDITIONAL
INFORMATION.
2. REFER TO 1-A1400 SERIES FOR FURNITURE PLANS.
3. A5145 GARMENT HOOKS ARE TO BE INSTALLED
CENTERED ON DOORS WITHIN ALL TOILET AND BATH
ROOMS, AS WELL AS IN PCTC ROOMS.
4. REFER TO SHEET 1-A002 FOR ALL TYPICAL MOUNTING
HEIGHTS.
5. A5135 STAINLESS STEEL SHELF, 18" WIDE, AND MOP
HOLDER RACK IS TO BE INSTALLED WITHIN ALL
HOUSEKEEPING AIDE CLOSETS (HAC). INSTALL
ADJACENT TO MOP SINK.
6. REFER TO 1-A700 DRAWING SERIES FOR REFLECTED
CEILING PLAN LEGENDS.
7. REFER TO FINISH LEGEND 1-A1200 SERIES FOR
ABBREVIATIONS OF FINISHES.
8. REFER TO SHEET 1-Q001 FOR EQUIPMENT LIST AND
THE 1-Q100 SERIES FOR EQUIPMENT PLANS.
GENERAL CONSTRUCTION NOTES
PATIENT BED SERVICE WALL
ELEVATION LEGEND
ELECTRICAL OUTLETS, REFER TO ELECTRICAL
DRAWINGS FOR ADDITIONAL INFORMATION
OXYGEN MEDICAL GAS OUTLET, REFER TO PLUMBING
DRAWINGS FOR ADDITIONAL INFORMATION
O
VACUUM OUTLET, REFER TO PLUMBING DRAWINGS
FOR ADDITIONAL INFORMATION
V
MEDICAL AIR OUTLET, REFER TO PLUMBING DRAWINGS
FOR ADDITIONAL INFORMATION
A
VACUUM SLIDE
DIALYSIS UNIT
MONITOR RAIL
AUDIO STATION BED CONNECTOR
EQUIPMENT RAIL
ELECTRICAL SWITCH REFER TO ELECTRICAL
DRAWINGS…