S02 JA Lockset Boilers 650-19-100.pdf

PDF 204 KB Posted

Attached to
Y1NB--650-19-100 Replace Boilers in Bldg 10 Federal contract opportunity
Solicitation number
36C24122R0084
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1

About this file

This document provides a justification for other than full and open competition for certain construction materials for a project to replace boilers in Building 10 at the VA Medical Center in Providence, Rhode Island. The Department of Veterans Affairs is seeking to procure door hardware consisting of Sargent 8200 mortise locksets and latch sets through a sole source award valued at $2,910. The justification cites the need to maintain consistency with the standardized Sargent brand key control system already in use throughout the medical center for security and to avoid additional costs associated with a different system. The related federal contract opportunity is a solicitation for the overall project to replace the boilers issued by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1.

View the file

Other files for this federal contract opportunity

Other files attached to Y1NB--650-19-100 Replace Boilers in Bldg 10, newest first.
File Type Posted
36C24122R0084 0007.docx DOCX document
S06 AMENDED Drawing P-601.pdf PDF
36C24122R0084 0006.docx DOCX document
S06 AMENDED Spec Section 33 16 15 07202022.pdf PDF
S06 RFI Responses 07202022.pdf PDF
S06 RFI Responses 07192022.pdf PDF
S06 IMG_4044.pdf PDF
36C24122R0084 0004.docx DOCX document
S06 AMENDED Spec Section 03 52 00.pdf PDF
S06 ARCHITECTURAL DRAWINGS BULLETIN 2.pdf PDF
S06 IMG_4010.pdf PDF
S06 IMG_0098.pdf PDF
S06 RFI Responses.pdf PDF
S06 STRUCTURAL DRAWINGS BULLETIN 1.pdf PDF
S06 ELECTRICAL DRAWINGS BULLETIN 1.pdf PDF
S06 MECHANICAL DRAWINGS BULLETIN 1.pdf PDF
S06 EXHIBIT D Calculation of Self Performed Work Amended.pdf PDF
S06 JA CCTV System Boilers 650-19-100.pdf PDF
36C24122R0084 0003.docx DOCX document
S06 EXHIBIT C Past Performance Questionnaire.pdf PDF
36C24122R0084 0002.docx DOCX document
Site Visit Sign-In Sheet.pdf PDF
36C24122R0084 0001.docx DOCX document
S02 BD03252022 Drawings - 7b_Mechanical - Part 2.pdf PDF
S02 BD03252022 Drawings - 8a_Electrical - Part 1.pdf PDF
S02 BD03252022 - 100pc Const Docs - Specs Vol I.pdf PDF
S02 BD03252022 Drawings - 1_Hazardous Materials.pdf PDF
S02 BD03252022 Drawings - 2b_Civil - Part 2.pdf PDF
S02 BD03252022 Drawings - 3_Structural.pdf PDF
S02 BD03252022 Drawings - 4_Architecture.pdf PDF
S02 BD03252022 Drawings - 8b_Electrical - Part 2.pdf PDF
S02 BD03252022 Drawings - 9_Security Electronics.pdf PDF
S02 BD03252022 - 100pc Const Docs - Specs Vol II.pdf PDF
S02 BD03252022 - 100pc Const Docs - Specs Vol III.pdf PDF
S02 BD03252022 Drawings - 2a_Civil - Part 1.pdf PDF
S02 BD03252022 Drawings - 5_Fire Protection.pdf PDF
S02 BD03252022 Drawings - 6_Plumbing.pdf PDF
S02 BD03252022 Drawings - 7a_Mechanical - Part 1.pdf PDF
S02 BD03252022 -Slope Stability Report.pdf PDF
S02 BD03252022 - Soil Erosion and Sediment Control Plan.pdf PDF
S02 JA Utility Plant Boilers 650-19-100.pdf PDF
S02 RI20220001 Wage Determinations.pdf PDF
S02 36C24122R0084 Solicitation.pdf PDF
S02 JA Fire Alarm System Boilers 650-19-100.pdf PDF
S02 VHA Supplemental Contract Requirements for Combatting COVID-19.pdf PDF
S02 EXHIBIT E VAAR Clause 852.219-77 Certificate of Compliance.pdf PDF
S02 EXHIBIT B Subcontractor Information and Consent Form.pdf PDF
S02 EXHIBIT D Calculation of Self Performed Work.pdf PDF
S02 EXHIBIT C Past Performance Questionnaire.pdf PDF
S02 EXHIBIT A Project Information Sheet for Contractors.pdf PDF
Show all 50

Y1NB--650-19-100 Replace Boilers in Bldg 10 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Last Updated: 02/01/22 Page 1 of 2

DEPARTMENT OF VETERANS AFFAIRS

Justification for Single Source Awards IAW FAR 13.106 1 For

Over Micro Purchase Threshold but Not Exceeding the SAT ($250K)

Acquisition Plan Action ID: 36C241 22 AP 1250, Sargent Key Control System

1. Contracting Activity: Department of Veterans Affairs, VISN 01, Station 650, Facilities Management Service (138) VA Medical Center, 830 Chalkstone Avenue, Providence, RI 02908. The proposed procurement, Request for Proposal (RFP) 36C24122R0084 is to Replace Boilers in Building 10, Project 650 19 100.

2. Brief Description of Supplies/ Services required and the intended use/Estimated Amount: The justification is to support the construction project to Replace Boilers in Building 10 at the VA Medical Center, Providence, RI that will be awarded as a firm fixed price contract. Contractor shall completely prepare site for building operations, including demolition and removal of existing structures, furnish labor and materials and perform work as required by drawings and specifications.

The objective of the project is to fully replace the boilers and associated equipment within Building

10. This justification is for Other Than Full and Open Competition for the procurement of certain construction materials. The use of a particular brand name for the items listed below is a small portion of the construction materials requested to accommodate standardization of these items throughout the facility for the following:

Door hardware for Sargent 8200 mortise locksets and latch sets, operational grade 1, with “Keso” standard security keying system.

Estimated value $2,910.00

3. Unique characteristics that limit availability to only one source, with the reason no other supplies or services can be used:

The items identified above in paragraph 2. and Sargent brand products have been standardized throughout the Providence, VA Medical Center located at 830 Chalkstone Avenue, Providence, RI 02908 for key control with use of their products currently being utilized to provide a secure facility at the Providence VA Medical Center for all keys, cylinders/locksets. Although there are other manufacturer(s) of access systems that can meet the Government’s minimum requirements, it is not in the best interest of the Government to replace the current standardized key control system being used in Building 10 and throughout the hospital. The 8200 Series Mortise Lock operates from 12 to 24VDC and can be used in standalone applications or as part of an integrated access control system.

Pre assembled components assist with installation to be fool proof. It is in the VA’s best interest to maintain consistency using the standardized brand name key control system in place to not incur additional costs and experience functioning issues due to non compatibility.

Last Updated: 02/01/22 Page 2 of 2

4. Description of market research conducted and results or statement why it was not conducted:

The purpose of the boiler replacement project is to replace the boiler system not the current established key control system being successfully utilized throughout an entire medical center. The current security keying system requires the same brand name manufacturer in all buildings throughout the campus. Using different manufacturers would require additional costs, new keys/door locks/hardware and new key distribution to end users. Using the Sargent brand for the current standardized key control does not incur additional expenses and maintains the continuity of the current key control system. It is not in the best interest to deviate from the established key system being used and replace all architectural hardware and locking products with an entire new key control system that would impact the entire medical center.

In accordance with the Competition in Contracting Act (CICA), the components listed above are identified as brand name; however, the overall procurement will be competed as a Service Disabled Veteran Owned Small Business (SDVOSB) Set Aside. This justification for Other Than Full and Open Competition for brand name only will be posted to Contracting Opportunities with the solicitation.

5. Contracting Officer's Certification: Purchase is approved in accordance with FAR13.106 1(b). I certify that the foregoing justification is accurate and complete to the best of my knowledge and belief. The items for which brand name approval is being requested are subsequent components to the overall construction project. This procurement will be competed and based on competition; the Contracting Officer will make a determination of fair and reasonable pricing prior to award.

Name: David Gabrysiak Date Title: Contracting Officer

David C. Gabrysiak 272636

Digitally signed by David C.

Gabrysiak 272636 Date: 2022.04.11 15:09:13 -04'00'

File details come from the government source that posted it. Updated .