S06 SOW Construct Perimeter Fence 631-17-006-Revised 2021.12.27.pdf

PDF 212 KB Posted

Attached to
Y1PZ--631-17-006 Construct Perimeter Fence Federal contract opportunity
Solicitation number
36C24122B0001
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1

About this file

This statement of work outlines requirements for constructing a perimeter fence at the Edward P. Boland VA Medical Center campus in Massachusetts. Key details include constructing a secure perimeter fence with vehicular and pedestrian gates, architectural fencing, brick fence pillars, and foundations per the contract plans and specifications. Additional requirements involve tree and brush removal, camera and gate controls, and project management and safety plans. The contractor must provide site access and safety measures, coordinate any necessary utility work or shutdowns, and complete all work within 315 calendar days of the notice to proceed. The related federal contract opportunity is solicitation number 36C24122B0001 for the perimeter fence construction project numbered 631-17-006 being conducted by the Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 1.

View the file

Other files for this federal contract opportunity

Other files attached to Y1PZ--631-17-006 Construct Perimeter Fence, newest first.
File Type Posted
S07 Abstract - Written.pdf PDF
36C24122B0001 Special Notice.pdf PDF
S07 OF 1419_1.pdf PDF
S06 36C24122B0001 0003.pdf PDF
S06 Site Visit Roster.pdf PDF
S06 VHA Supplemental Contract Requirements for Combatting COVID-19 Updated 12-14-2021.pdf PDF
S06 014500 Perimeter Fence Quality Control Specification.pdf PDF
S06 Specification Table of Contents Revised.pdf PDF
S06 CS141 Detail Sheet REV01.pdf PDF
S06 36C24122B0001 0002.pdf PDF
36C24122B0001 0002.docx DOCX document
S06 Pole Foundation Detail.pdf PDF
36C24122B0001 0001.docx DOCX document
S02 Construction Safety guide book.pdf PDF
S02 Drawings 5 of 5 Construct Perimeter Fence 631-17-006.pdf PDF
S02 Construction Safety Manual.pdf PDF
S02 Equipment_Data_Record_sample.pdf PDF
S02 SOW Construct Perimeter Fence 631-17-006.pdf PDF
S02 Specifications Construct Perimeter Fence 631-17-006.pdf PDF
S02 PRE-AWARD CONTRACTOR EVALUATION FORM.pdf PDF
S02 631-17-006_Submittal Register.xls XLS spreadsheet
S02 Construct Perimeter Fence 631-17-006 Supplemental Specifications.pdf PDF
S02 Hot_Work_Permit.pdf PDF
S02 WD MA20210010 11122021.pdf PDF
S02 36C24122B0001 Solicitation.pdf PDF
S02 Drawings 1 of 5 Construct Perimeter Fence 631-17-006.pdf PDF
S02 Guidance for Federal Contractors and Subcontractors.pdf PDF
S02 Drawings 2 of 5 Construct Perimeter Fence 631-17-006.pdf PDF
S02 Drawings 4 of 5 Construct Perimeter Fence 631-17-006.pdf PDF
S02 Life_Safet_ Risk_Assessment.pdf PDF
S02 Electrical_Panel_Schedule_sample.pdf PDF
S02 RFI_Form.pdf PDF
S02 VHA Supplemental Contract Requirements for Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors rev2.pdf PDF
S02 Daily_Construction_Log_sample.pdf PDF
S02 Drawings 3 of 5 Construct Perimeter Fence 631-17-006.pdf PDF
S02 VAAR Clause 852.219-77 Certificate of Compliance.pdf PDF
Show all 36

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Edward P. Boland VAMC, Central Western Massachusetts Healthcare System

421 N Main Street

Leeds, MA 01053 December 27, 2021

631-17-006-SOW-C Page 1 of 7

VHA-NHM-STC_SOW-Template Draft

Construction Statement of Work for Construct Perimeter Fence

Project Number: 631-17-006

Location(s):Perimeter of Campus

1 Overview

1.1 General Intent

The Contractor provide professional services to include all labor, transportation, materials, apparatus, tools, equipment and permits necessary to in accordance with this construction scope of work.

All work must meet VHA, OSHA, EPA, and Mass DEP standards

1.2 Project Specific Scope of Work - Construct Perimeter Fence

After award, but prior to the start of any field work, the contractor shall contact Contracting Officer’s Representative (COR) to review proposed methods and plans for completion of work and to review infection control procedures, interim life safety procedures, above ceiling and wall penetration permits and hot permits. Field work may not commence until these plans have been approved as detailed below.

The project includes constructing a fence per the contract documents that establishes a secure perimeter for the Edward P. Boland VAMC campus. The project includes vehicular and personnel gates, architectural fencing, brick fence pillars, fence foundations, tree and brush removal and camera and gate controls.

-The clearing limits noted in the contract documents have been extended. Clearing limits for fencing to be 20 feet on each side of the fence. Any variance from the clearing limits to be approved in writing by the COR.

-All gates, vehicular or pedestrian, shall include mortise locksets. Lockset to meet specifications.

-Provide Superintendent per attached supplemental specification SUP-01requirements.

-Provide UTV per attached supplemental specification SUP-02 requirements.

1.2.1 Sole-Source Services/Contractors

The following are contracting or subcontracting constraints for this project:

1. BEST Locks

1.3 General Scope Items

The following is a list of general scope considerations:

1. Meet with VA Facilities staff, review existing drawings and estimates, and perform field work necessary to determine required materials and equipment.

631-17-006-SOW-C Page 2 of 7

2. When conflict exist between documents the order of precedence shall be specifications then drawings. Any conflicts shall be identified to the COR and be resolved using the RFI process to allow for proper documentation and correction as necessary.

3. For programming of fire alarm systems, coordinate with Northeast Integrated Systems - Tel.781-321-7777 Fax.781 322-6299 located at 17 Lincoln Street, Malden, MA 02148.

4. Comply with CCURE 9000 for security devices/systems

5. Permitting (external to VA):

a. City of Northampton permits, and waivers are the responsibility of the contractor. The contractor must be prepared to attend City of Northampton committee meetings as required.

b. All Massachusetts Department of Environmental Protection permits, and waivers are the responsibility of the contractor. This includes, but not limited to all environmental and hazardous material permits.

6. All field work shall be scheduled at least 72 hours in advance with VA Facilities Management.

7. The site shall be left clean of all construction debris and hazardous materials.

8. Coordinate with VA CWM HCS GEMS coordinator Rob Michalik at 413-584-4040 x 2330 for the signing of the waste manifests.

9. Design and installation to meet latest edition of the NEC, NFPA, and all applicable building codes.

10. Submit product data and shop drawings for all materials prior to installation. Submittals and shop drawings shall be approved by COR in accordance with the contract documents.

11. All work shall be performed in accordance with Massachusetts DLS regulations and OSHA codes.

12. Contractor shall submit for approval a submittal register within 30 calendar days of the NTP of the project.

1.4 Site Access and Management Requirements

The contractor shall be solely responsible for the management, including all associated labor, equipment, materials, mailing costs, and inspection, to meet the requirements of the project.

The contractor must have the following additional requirements before working on site:

1. Contractor badge must be obtained and visibly worn by contractor or representative at all times while on campus

631-17-006-SOW-C Page 3 of 7

2. Negative TB Test, within the past calendar year

3. Clear Face Shield or Safety Glasses in patient care areas

4. Annual influenza shot is required to perform work on campus.

5. Covid-19 Requirements (subject to frequent change):

a. Approved surgical or 2-layer cloth mask with no vent. Must be replaced when damaged or soiled

b. Pre and weekly negative COVID test while working in patient care areas (test available onsite free of charge to contractor)

c. Daily visit at check-in station for COVID and temperature screening

d. Staff experiencing any symptoms of illness will refrain from any on-site work until asymptomatic

e. Temperature checks are currently performed at Liberty Building 1. If at any time an employee of the A/E firm is found in deficiency of the listed a stop work order will be issued for safety of the campus.

These requirements are applicable to all contractor employees and subcontractors working in and around campus building unless stated otherwise by COR. The contractor is ultimately responsible for the behavior of employees and subcontractors.

Questions or concerns may be addressed by the COR.

1.5 List of Attachments

The following list of documents are attached to this SOW for Contractor use and incorporation into the project documents:

1. Construct Perimeter Fence 631-17-006 Plans Bid Set

2. Construct Perimeter Fence 631-17-006 Plans Bid Set Specifications

3. Construct Perimeter Fence 631-17-006 Supplemental Specifications

4. RFI Form

5. Hot Work Permit

6. Life Safety Risk Assessment

7. Submittal Register

8. Daily Construction Log (Sample Form)

9. Electrical Panel Schedule (Sample Form)

10. Equipment Data Record (Sample Form)

11. Construction Safety Guidebook | Healthcare Environment and Facilities Programs (va.gov)

12. Construction Safety Manual

Note list is not necessarily exhaustive of necessarily exhaustive.

2 Submittals

Submittals may be sent after the administrative notice to proceed (Admin NTP) is received by the contractor.

Submittals and RFIs shall be administered through a project management software such as Procore or equal.

631-17-006-SOW-C Page 4 of 7

The contractor shall provide the following submittals as soon as they are available or by the required date(s) communicated by the COR:

• All submittal items listed in the contract documents.

• Certification from the Contractor/Installer that the system(s) specified meets all applicable codes as well as manufacturer, designer, and insurance requirements as required by the Government.

• Safety Data Sheets (SDS)

• Operation and Maintenance Manuals for new equipment

• As-built drawings

• Coordination Drawing Checklist

3 Proposed Schedule

All on-site work (including cleanup) shall take place during the following times, unless otherwise approved by the COR:

07:00-16:30h Monday through Friday

Off-hour work for activities impacting normal operations or scheduling conflicts are generally 17:00- 06:00 Monday- Friday and anytime Saturday and Sunday.

Holidays excepted unless other times are arranged in advance and approved in writing by the Project

COR.

The period of performance for this project is 315 calendar days; the first 45 calendar days shall be utilized for administrative time to complete preconstruction submissions and other preparation prior to the start of construction. The remaining work shall be completed with the

3.1 remaining period of performance of 270 calendar days.Project Coordination

The following tasks are anticipated to have significant campus impact or conflicts and may require special consideration and coordination to ensure satisfactory completion:

1. Construction of gate on main road into campus

2. Any utility outage or road closure

3. Significant material deliveries

4. Others as determined by COR and contractor

4 Warranties

See FAR clause 52.246-21.

631-17-006-SOW-C Page 5 of 7

5 Work Location and Restrictions

The work site location is at the Edward P. Boland Campus- VA Central Western Massachusetts Healthcare System. The contract work is intended to be limited to Perimeter of Campus.

When the contractor’s work interferes with hospital functions, such as when work produces excessive noise, odors, dust, utility service interruptions, or other interferences with normal hospital operations that cannot be contained within the area of work, the contractor shall schedule said work at other than normal hours and as directed by the COR.

5.1 Project Safety

Contractor shall comply with the Contractor Safety Manual of the site and other applicable standards as noted in the sections 1 and Error! Reference source not found. and their subsections.

FAR Clause 52.236-13 subparagraph (f) is invoked:

5.2 Interim Life Safety Protection Measures

Contractor shall participate with the VA in the preparation of an interim life safety measures and fire protection Plan that will be implemented during construction of this project. At a minimum, contractor shall comply with the following requirements of an interim life safety measures and fire protection plan:

• Ensure exits provide free and unobstructed egress for all building occupants. If required by contractor’s operations, establish and mark alternate means of egress for all building occupants.

• Contractor shall maintain escape facilities from the work area for construction workers at all times. Means of egress in construction areas will be inspected daily.

• Ensure free and unobstructed access to all areas of the project site for emergency services and for emergency forces.

• Ensure that means of egress and existing fire alarm, detection, and suppression systems are not impaired by contractor’s operations.

• Do not impair means of egress, automatic sprinklers, smoke and heat detection, and fire alarm systems, except for portions immediately under construction, and temporarily for connections.

Provide fire watch in accordance with NFPA standards for impairments. Request approval of impairments from the COR in writing a minimum of 72 hours in advance.

631-17-006-SOW-C Page 6 of 7

• When required, a fire watch shall be by a qualified person provided by the contractor who shall maintain constant observation of the affected area and have no other duties. The person providing the fire watch shall be trained in fire prevention and in the use of fire extinguishers, occupant hose lines, occupant fire protection system, in sounding the building fire alarm and in notifying the local fire department, and in understanding the particular fire safety situation for the project.

• Provide written procedures and guidelines for construction personnel and post in the immediate areas of construction detailing what to do and who to call in the event of fire or emergency.

• Maintain the construction area to minimize the potential for fire or safety hazards resulting from storage of construction material, construction waste and debris during construction operations.

• All temporary construction shall be built of noncombustible/fire retardant materials and shall be smoke tight.

Contractor shall comply with the requirements and ensure efforts to prevent false fire alarms.

5.3 Parking

Parking is rigidly controlled throughout the Medical Center. Contractor parking is only allowed in designated areas (subject to change). Parking in designated patient parking areas is strictly prohibited.

Parking on grass is also prohibited. Parking for equipment necessary to perform the work will be authorized in advance of starting the project. Parking passes will be issued by the COR.

5.4 Storage of Equipment and Materials

The contractor shall arrange with the COR for allocation of required workspace and for the storage of equipment and material to be used for this project. Storage space is very limited. There are no exclusive areas within the campus that can be given to the contractor for their storage needs. The Contractor should schedule delivery of materials to limit the amount of storage space and time. The warehouse CANNOT accept or store deliveries.

5.5 Debris Removal

The Contractor/Installer shall be required to remove waste materials and debris daily (unless otherwise authorized by COR) from the campus. All waste material and debris shall be removed off the site by the contractor and shall be disposed of in accordance with applicable State and Federal regulations.

631-17-006-SOW-C Page 7 of 7

5.6 Site Utilities

The Contractor/Installer should note this scope of work does not detail all existing structures, utilities, or components that may potentially interfere with the contract work required. The contractor shall note any obstruction, utility, or condition that may hinder or interfere with the execution of this contract and the contractor shall make provisions in their contract price to resolve such interferences and other conditions that may hinder the proper completion of the work. All proposed utility relocations, reallocations, and shutdowns shall be approved by the COR prior to commencing such work. The contractor shall verify all existing utility installations and take appropriate action prior to working around any potential utility installation.

In the event a shutdown, restriction, or interruption of any utility services is required, a written request must be submitted (at least 14 calendar days in advance) and approved by the VA COR. All utility shutdowns must be reviewed and approved by the VA.

6 Material and Workmanship Quality

All materials and workmanship shall comply with all codes, standards, and requirements of all Authorities Having Jurisdiction (AHJ). All work shall be done in accordance with contract terms and conditions and in a professional manner according to the best trade practices and to the satisfaction of the COR. This includes work performed by subcontractors.

**************** End SOW ****************

File details come from the government source that posted it. Updated .