This document contains questions and answers regarding solicitation number 36C10B21R0001 for Infrastructure as a Managed Service (IaaMS) from the Department of Veterans Affairs Technology Acquisition Center Austin. The solicitation seeks proposals for infrastructure as a managed service, including data storage and related capabilities. Key details specified include: data capacity must be measured on disk after data efficiency technologies are applied, with billing based on actual used capacity excluding redundancy impacts; unused and available capacity excludes anticipated efficiency savings; proposals are due by January 25, 2021.
View the file
Other files for this federal contract opportunity
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Request for Proposal 36C10B21R0001 - Infrastructure as a Managed Service (IaaMS) | |||
| Vendor Questions and Answers | |||
| Please be advised that any information contained herein is for informational purposes only, is offered in response to specific questions posed by prospective Offerors, and is subject to change throughout the question and answer process. Accordingly, in the event that there is any discrepancy between the information contained within this document, any subsequent Question and Answer document(s), and/or the Solicitation, Offerors are hereby advised that the terms and conditions contained within the final Solicitation control. | |||
| # | Reference | Question | Answer |
| 105 | PWS, Section B.2, IAAMS PRICE AND BILLING REQUIREMENTS, 5.2.3 IaaMS CAPACITY REQUIREMENTS, 5.2.3.1 DATA EFFICIENCY | Clarify whether Government requires the successful Offeror to measure VistA data residing on disk. | The Contractor shall measure actual capacity used on disk after data efficiency technologies (including deduplication) have been applied. For example, if VA transmits a 100GB file to the storage system and the file consumes 80GB of disk space following deduplication, the Contractor shall bill VA for 80GB of consumed space. The Contractor shall not bill VA for additional space required to meet RAID parity overhead, erasure coding overhead, or other redundancy requirements. |
| 106 | PWS, Section B.2, IAAMS PRICE AND BILLING REQUIREMENTS, 5.2.3 IaaMS CAPACITY REQUIREMENTS, 5.2.3.1 DATA EFFICIENCY | Clarify if the Government intends Offerors to measure used capacity from the server or from the storage array. | The Contractor shall measure used capacity from the storage array after data efficiency technologies have been applied. |
| 107 | PWS, Section B.2, IAAMS PRICE AND BILLING REQUIREMENTS, 5.2.3 IaaMS CAPACITY REQUIREMENTS, 5.2.3.1 DATA EFFICIENCY | Clarify how the Government intends Offerors to calculate or measure “used capacity”, “unused and available capacity” and “currently used capacity.” | a. Used Capacity – The Contractor shall measure actual capacity used on disk after data efficiency technologies have been applied, exclusive of redundancy impacts. The Contractor shall not bill VA for any data capacity that is reduced through the use of data efficiency technologies. The Contractor shall not bill VA for additional space required to meet RAID parity overhead, erasure coding overhead, or other redundancy requirements. |
b. Unused and Available Capacity – “Unused and available capacity” is any writeable capacity that exists on disk that is available for use by VA. This calculation shall not include any anticipated data efficiency savings.
| c. | Currently Used Capacity – This is identical to “used capacity”. | |||
| 108 | PWS, Section B.2, IAAMS PRICE AND BILLING REQUIREMENTS, 5.2.3 IaaMS CAPACITY REQUIREMENTS, 5.2.3.1 DATA EFFICIENCY | Clarify how and to what extent “unused and available capacity” and “currently used capacity” are dependent on data deduplication. | Unused and available capacity is any writeable capacity that exists on disk that is available for use by VA. The Contractor shall not include anticipated data efficiency savings in making this calculation. | |
| 109 | PWS, Section B.2, IAAMS PRICE AND BILLING REQUIREMENTS, 5.2.3 IaaMS CAPACITY REQUIREMENTS, 5.2.3.1 DATA EFFICIENCY | Clarify the Government requires the deduplication of redundant data, but the Contractor’s calculations shall not include data deduplication when calculating/measuring used capacity, minimum usable capacity, or currently used capacity. | a. The Government requires deduplication of redundant data as specified in PWS section 5.2.3.1. |
b. Used Capacity – The Contractor shall measure actual capacity used on disk after data efficiency technologies have been applied, exclusive of redundancy impacts. The Contractor shall not bill VA for any data capacity that is reduced through the use of data efficiency technologies. The Contractor shall not bill VA for additional space required to meet RAID parity overhead, erasure coding overhead, or other redundancy requirements.
c. “Minimum usable capacity” shall be calculated based upon the actual useable capacity on disk. The Contractor shall not include anticipated data efficiency savings in making this calculation.
d. “Currently used capacity” is identical to “used capacity”.