3-Appendix X - DSL Design RFQu updates from previous solicitation for rebid.docx
DOCX document 23 KB Posted
- Solicitation number
- 26-04030VW
- Issued by
- Salt Lake County, Salt Lake City, Utah
About this file
This is an Appendix document detailing updates to a Request for Qualifications (RFQu) issued by the State of Utah for the Davis-SLC Community Connector Final Design and Construction Services project. The document outlines changes made to the solicitation for a rebid of design services for bus stop and end-of-line facilities with associated improvements. Key modifications to the scope of work include removal of geotechnical services and queue jump design from the project activities, clarification of the number of stations requiring design, expanded requirements for branding plan development, and addition of mechanical and plumbing (M&P) estimates and specifications for multiple facility components. The design scope now explicitly defines right-of-way processes with electronic Project Management (ePM) submittals, clarifies Transportation System Plan (TSP) needs, and includes grant assistance and meeting attendance requirements. Construction advertising is anticipated in Spring 2027.
The personnel requirements have been reduced to streamline the qualifications process. The Project Manager experience threshold was lowered from previous requirements to five years of design experience and three years of management experience, while the Lead Designer requirement was reduced to five years of relevant experience. The Lead Estimator position was removed from key personnel designations. Schedule submission requirements were modified from bar-scaled schedules to milestone-based schedules. The team experience evaluation now permits consideration of similar work completed more than five years prior, allowing for greater flexibility in demonstrating relevant project history and qualifications.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Appendix X – DSL Design RFQu updates from previous solicitation for rebid Changes made to the Request for Qualifications for Davis-SLC Community Connector Final Design and Construction Services Cover Sheet Timelines for submittal Part 1 A. General Overview
a. Removed geotechnical from work activities
b. Removed queue jump from the design scope B. No change C. Final Design Contract, Schedule, and Phasing
a. Construction advertising anticipated in Spring 2027 D. Design Scope
| 2. | a. Clarified the number of stations requiring design |
| b. Clarified the level of effort on the branding plan | |
| c. added M&P, estimate and specs |
d. clarified design needs for restroom, added permit assistance, and added M&P, estimate and specs
| e. added M&P, estimate and specs | |
| f. added M&P, estimate and specs and plans | |
| 4. | define right of way process with ePM submittals |
| 5. | clarified TSP needs |
| 6. | clarified grant assistance and meeting attendance |
Part 2
| Section 1 | |
| Removed Lead Estimator from key personnel |
A. Project Manager
a. Reduced design experience to 5 years
b. Reduced management experience to 3 years B. Lead Designer
a. Reduced experience to 5 years Section 2 A. Project Schedule
a. Changed the bar scaled schedule to a milestone based schedule Section 3 A. Team Experience
a. Allows similar work experience older than 5 years
File details come from the government source that posted it. Updated .