3 Abate BD.pdf
PDF 2 MB Posted
- Solicitation number
- 36C25522R0002
About this file
This pre-solicitation notice is for a construction project to renovate approximately 7,200 gross square feet on the second floor center of Building 52 at the Jefferson Barracks Division VA Medical Center in St. Louis, Missouri. The project scope includes renovating former procedure rooms comprising approximately 1,600 square feet, as well as light to medium renovation of administrative offices. Facility deficiencies will be corrected not to exceed 75% of the total project cost, which is estimated between $2 million and $5 million. The NAICS code for this procurement is 236220 for general commercial and institutional building construction. The contract duration is estimated at 410 calendar days from notice to proceed. This opportunity is a total small business set-aside for Service-Disabled Veteran-Owned Small Businesses. The solicitation will be posted on beta.SAM.gov on or about October 15, 2021, and a site visit is scheduled. Proposals are due in accordance with instructions in the solicitation package.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Scan_2021_11_02_14_28_13_296.pdf | ||
| 36C25522R0002 0001.docx | DOCX document | |
| 36C25522R0002_1.docx | DOCX document | |
| P09_S02 -20-028 Specifications 657-20-102JB (1448 pages) final.pdf | ||
| 2 Struct BD.pdf | ||
| 9 Elec BD.pdf | ||
| 7 Plumb BD.pdf | ||
| 4 Arch BD.pdf | ||
| 5 IntD BD.pdf | ||
| 8 Mech BD.pdf | ||
| Past Performance Questionnaire 36C25522R0002 (Project 657-20-102JB).pdf | ||
| 1 Gen BD.pdf | ||
| 6 FP BD.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ASBESTOS KEY NOTES:
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
Revisions: Date
Drawing Title:
Approved: Project Director
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
CONSULTANTS: PROJECT MANAGER:
Date Checked Drawn U.S. Department of Veterans Affairs# © COPYRIGHT Apogee - CEMS JV, LLC
1151 Kildaire Farm Rd.
Suite 120 Raleigh, NC 27511 www.acg-pa.com (919)858-7420
108 Benton Lodge Road Suite B Summerville, SC 29485 www.cemsengineering.com (843)875-3637Project Mgr: Alex Kramer (APOGEE)
An Alliance for Success
HA100
FIRST FLOOR ABATEMENT PLAN -
PHASE 3
1 4GKY RAJ
RENOVATE SECOND FLOOR
CENTER, JB BLDG 52
1 JEFFERSON BARRACKS DR, ST.
LOUIS, MO 63125
657-20-102JB20-028
RANDY GOFFIN
Scale: 1/8" = 1'-0"
FIRST FLOOR TSI ABATEMENT PLAN - PHASE 3
N O
R
TH
0 4 8 16
INSIDE A NEGATIVE PRESSURE MINI-CONTAINMENT REMOVE
ASBESTOS PIPE INSULATION AND ASBESTOS MUDDED
FITTINGS USING GLOVEBAG REMOVAL TECHNIQUES.
- 1 EACH MUDDED PIPE FITTING
A1.
ABATEMENT LEGEND
REMOVE ACM PIPE INSULATION AND FITTINGS AS
INDICATED IN KEYNOTES.
THE ABATEMENT SCOPE OF THE WORK IN BUILDING 52
CONSISTS OF REMOVING VARIOUS ASBESTOS AND LEAD
IMPACTED MATERIALS THROUGHOUT THE PROJECT LIMITS.
ALL WORK SHALL BE CONDUCTED IN ACCORDANCE WITH ALL
FEDERAL, STATE AND LOCAL REGULATIONS AND THE
CONTRACT SPECIFICATIONS.
IN BUILDING 52, ASBESTOS CONTAINING PIPE INSULATION IS
PRESENT THROUGHOUT THE WORK AREAS ON THE 1ST
FLOOR, BUT MAY NOT BE DIRECTLY IMPACTED UNLESS
INDICATED BY THE KEYNOTES. PROTECT AS REQUIRED TO
PREVENT ANY DAMAGE OR DISTURBANCE.
ASBESTOS TRANSITE PANELS SHOULD BE ASSUMED TO BE
PRESENT BEHIND RADIATORS. NO ABATEMENT OF THIS
MATERIAL IS ANTICIPATED AND SHALL BE PROTECTED AS
REQUIRED.
LEAD-CONTAINING GLAZED BLOCK WALLS ARE LOCATED
THROUGHOUT THE PROJECT LIMITS, BUT WILL ONLY BE
IMPACTED IN AREAS IDENTIFIED WITH SPECIFIC KEYNOTES.
REMAINING WALLS SHALL BE PROTECTED AS REQUIRED.
ALL ABATEMENT WORK SHALL BE CONDUCTED DURING
ADMINISTRATIVE HOURS (7:00 AM TO 5:00 PM) MONDAY -
FRIDAY EXCLUDING FEDERAL HOLIDAYS; EXCEPT THE OUT OF
PHASE WORK WHICH SHALL BE ACCOMPLISHED AT NIGHT
(5:00 PM TO 5:00 AM) OR ON A WEEKEND (5:00 PM FRIDAY TO
6:00 PM SUNDAY). DUE TO THE EXTENTS OF ABATEMENT,
MULTIPLE PHASES (INCLUDING SUB-PHASES), MULTIPLE
MOBILIZATIONS, AND MULTIPLE WEEKENDS WILL BE
REQUIRED. PROPER COORDINATION WITH ALL PARTIES WILL
BE REQUIRED.
WORK SCHEDULES AND LIMITS OF ABATEMENT SHALL BE
COORDINATED WITH THE VA COR AND VPIH FOR APPROVALS,
UNLESS OTHERWISE INDICATED ON THE KEYNOTES. THE
ABATEMENT CONTRACTOR SHALL SUBMIT A DETAILED WORK
PLAN AND ABATEMENT SCHEDULE WITH THE REQUIRED
SUBMITTALS. ANY CHANGES TO THE PROCEDURES,
CONTAINMENT LIMITS AND PHASING SHALL BE SUBMITTED TO
THE VA COR AND VPIH FOR APPROVALS.
THE LOCATIONS AND QUANTITIES SHALL BE FIELD VERIFIED
BY THE ABATEMENT CONTRACTOR. THE LIMITS OF REMOVAL
AND EXTENT OF THE CONTAINMENTS SHALL BE VERIFIED
WITH THE VA COR AND VPIH. FOR CLARITY, THE DRAWINGS
ONLY SHOW REPRESENTATIVE LOCATIONS OF PIPING.
ALL LOADOUT PROCEDURES SHALL BE COORDINATED WITH
THE VA COR.
ABATED PIPE INSULATION AND FITTINGS, EXCLUDING PIPING
THAT WILL BE DEMOLISHED, SHALL BE PROPERLY
RE-INSULATED WITH EQUIVALENT INSULATING PROPERTIES IN
ACCORDANCE WITH VA SPECIFICATION 23 07 11, HVAC AND
BOILER PLANT INSULATION.
ALL POLYETHYLENE SHEETING USED FOR THE ABATEMENT
PROJECT SHALL BE OF THE FIRE RETARDANT TYPE.
THE LOCATIONS OF ABATEMENT DECONTAMINATION UNITS
AND WASTE DISPOSAL CONTAINERS SHALL BE FIELD
VERIFIED WITH THE VA COR AND VPIH. ALL LOADOUT
PROCEDURES SHALL BE COORDINATED WITH THE VA COR
AND VPIH. SEE DEMOLITION DRAWINGS FOR TEMPORARY
PARTITION AND INFECTION CONTROL DETAILS.
ALL PERIMETER AIR MONITORING, CLEARANCE SAMPLING,
AND WIPE SAMPLING WILL BE CONDUCTED BY THE VPIH.
VA PERSONNEL SHALL BE RESPONSIBLE FOR REMOVING OR
RELOCATING ALL EQUIPMENT, COMPUTERS, SUPPLIES,
FURNITURE, DESKS, WALL HANGINGS, ETC., FROM THE
ABATEMENT AREAS.
ALL MECHANICAL SYSTEMS, INCLUDING BUT NOT LIMITED TO,
HVAC SYSTEMS, STEAM PIPING, ETC., SHALL BE SHUT DOWN
DURING ALL ABATEMENT ACTIVITIES. ABATEMENT OF
ASBESTOS PIPE INSULATION AND FITTING INSULATION FROM
THE STEAM PIPING MUST BE ACCOMPLISHED WHEN THE
STEAM PIPES ARE LESS THAN 150 DEGREES FAHRENHEIT. ALL
REQUIRED STEAM SHUTDOWNS SHALL BE PROPERLY
COORDINATED WITH THE VA TO MINIMIZE IMPACT TO THE
HOSPITAL OPERATIONS.
STRICT COORDINATION BETWEEN THE VA OCCUPANTS, VA
COR, VPIH, GENERAL CONTRACTOR AND ABATEMENT
CONTRACTOR SHALL BE REQUIRED.
ALL LEAD WASTE SHALL BE TESTED BY THE ABATEMENT
CONTRACTOR USING TCLP ANALYTICAL METHODS TO
DETERMINE PROPER WASTE DISPOSAL METHODS.
TRACE AMOUNTS OF LEAD BELOW THE EPA HUD DEFINITION
OF LEAD-BASED PAINT WERE IDENTIFIED IN THE PROJECT
AREAS. IT SHOULD BE NOTED THAT OSHA DOES NOT
RECOGNIZE THE HUD DEFINITION AS A THRESHOLD VALUE
FOR LEAD EXPOSURE. ALTHOUGH THE POTENTIAL LEAD
HAZARD FOR NORMAL DEMOLITION OR CONSTRUCTION
ACTIVITIES IS LOW, ACTUAL LEAD EXPOSURE MAY VARY
SIGNIFICANTLY DEPENDING UPON THE SPECIFIC TASK,
PROCEDURE AND OTHER WORK AREA CONDITIONS. PROPER
OSHA COMPLIANCE IS CONSIDERED PERFORMANCE BASED
AND INCLUDES EVALUATING POTENTIAL WORK EXPOSURES
WITH AIR MONITORING OR BIOLOGICAL EXPOSURE
MONITORING (BLOOD LEAD TESTING), IF REQUIRED. UNLESS
THE DEMOLITION CONTRACTOR HAS HISTORICAL DATA
DOCUMENTING THIS POTENTIAL EXPOSURE, PERSONAL AIR
SAMPLING SHALL BE CONDUCTED BY THE CPIH ON
REPRESENTATIVE TASKS.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
SHEET NOTES:
A1
PHASE 3 (NIGHTS & WEEKENDS):
LIMITS OF NEGATIVE PRESSURE MINI-CONTAINMENT
WALL RATING LEGEND
1 HR - FIRE SEPARATION
2 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREAS S S S
AUGUST 25, 2021
S
S S
S S
S S
S S
S
S
S
S S
S S
S S
S S
S SS
S S
S
S
S
S
EXAM 1
2S05
TREAT.
RM.
2S05
EXAM
2S04
CHASE
CH-S-3
HALLWAY
2N113
EXAM
2S01
STAIRWELL
NO. 2
2S02
OFFICE
2N111
OFFICE
2S11A
OFFICE
2S11
HAC
2S10
ELEC.
CLOSET
2S9
ELEVATOR
LOBBY
2S57
ELEVATOR
E2
CORRIDOR
H204
OI&T
2S53
CONFERENCE
RM
2S56
PAIN
REHAB.
CENTER
2S56A
SCI
SERVICE
REHAB.
CENTER
2N117A
CORRIDOR
H205
ELEVATOR
E3
P.T. / O.T.
2N58
EXAM
2N118
CORRIDOR
H208
WAITING
ROOM
2N112A
OFFICE
2N63
OFFICE
2N60
OFFICE
2N59
OFFICE
2N59A
WHEELCHAIR
STORAGE
2N110
HAC
2N64
CONTROL
RM.
2N110
VEST.
2N110
CHASE
CH-S-6
EXAM
2S12B
CLOSET
2N59B
S S
S S
S S
S S
S S
S
S
S
S S
S S
S S
S S
S SS
S S
S
S
S
S
EXAM 1
2S05
TREAT.
RM.
2S05
EXAM
2S04
CHASE
CH-S-3
HALLWAY
2N113
EXAM
2S01
STAIRWELL
NO. 2
2S02
OFFICE
2N111
OFFICE
2S11A
OFFICE
2S11
HAC
2S10
ELEC.
CLOSET
2S9
ELEVATOR
LOBBY
2S57
ELEVATOR
E2
CORRIDOR
H204
OI&T
2S53
CONFERENCE
RM
2S56
PAIN
REHAB.
CENTER
2S56A
SCI
SERVICE
REHAB.
CENTER
2N117A
CORRIDOR
H205
ELEVATOR
E3
P.T. / O.T.
2N58
EXAM
2N118
CORRIDOR
H208
WAITING
ROOM
2N112A
OFFICE
2N63
OFFICE
2N60
OFFICE
2N59
OFFICE
2N59A
WHEELCHAIR
STORAGE
2N110
HAC
2N64
CONTROL
RM.
2N110
VEST.
2N110
CHASE
CH-S-6
EXAM
2S12B
CLOSET
2N59B
ASBESTOS KEY NOTES: LEAD KEY NOTES:
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
Revisions: Date
Drawing Title:
Approved: Project Director
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
CONSULTANTS: PROJECT MANAGER:
Date Checked Drawn U.S. Department of Veterans Affairs# © COPYRIGHT Apogee - CEMS JV, LLC
1151 Kildaire Farm Rd.
Suite 120
Raleigh, NC 27511 www.acg-pa.com
(919)858-7420
108 Benton Lodge Road Suite B
Summerville, SC 29485 www.cemsengineering.com
(843)875-3637
Project Mgr: Alex Kramer (APOGEE)
An Alliance for Success
HA101
SECOND FLOOR ABATEMENT PLANS -
PHASE 1
2 4GKY RAJ
RENOVATE SECOND FLOOR
CENTER, JB BLDG 52
1 JEFFERSON BARRACKS DR, ST.
LOUIS, MO 63125
657-20-102JB
20-028
RANDY GOFFIN
N
O
R
T
H
0 4 8 16
Scale: 1/8" = 1'-0"
SECOND FLOOR TSI AND LEAD ABATEMENT PLAN - PHASE 1
Scale: 1/8" = 1'-0"
SECOND FLOOR FLOORING ABATEMENT PLAN - PHASE 1
N
O
R
T
H
0 4 8 16
INSIDE A NEGATIVE PRESSURE CONTAINMENT, DEMOLISH
PLASTER WALLS AND CEILINGS, REMOVE LEAD SHIELDING,
LEAD SHIELDED DOORS, DOOR FRAMES AND VIEWING
WINDOWS USING HAND TOOLS AND DISMANTLING
TECHNIQUES.
- PHASE 1A: 1,650 SF OF PLASTER WALLS, CEILINGS AND
LEAD SHIELDING, 3 EACH LEAD SHIELDED
DOORS AND FRAMES, 1 EACH LEAD SHIELDED
VIEWING WINDOW
INSIDE A NEGATIVE PRESSURE CONTAINMENT DEMOLISH
LEAD-CONTAINING GLAZED BLOCK BATHROOM STALL WALL
USING HAND TOOLS.
- PHASE 1B: 20 SF OF LEAD-CONTAINING GLAZED BLOCK
STALL WALL
INSIDE A NEGATIVE PRESSURE CONTAINMENT SAW CUT
LEAD-CONTAINING GLAZED BLOCK WALL AS INDICATED ON
ARCHITECTURAL DEMOLITION DRAWINGS.
- PHASE 1B: 80 SF SAW CUTTING OF LEAD-CONTAINING
GLAZED BLOCK WALL
L1.
L2.
L3.
INSIDE A NEGATIVE PRESSURE CONTAINMENT REMOVE
SINGLE-LAYER ASBESTOS FLOOR TILE AND ASSOCIATED
ASBESTOS MASTIC.
- PHASE 1A: 360 SF OF ACM FLOOR TILE AND MASTIC
- PHASE 1B: 135 SF OF ACM FLOOR TILE AND MASTIC
- PHASE 1C: 160 SF OF ACM FLOOR TILE AND MASTIC
- PHASE 1D: 640 SF OF ACM FLOOR TILE AND MASTIC
(NIGHTS & WEEKENDS)
INSIDE A NEGATIVE PRESSURE CONTAINMENT REMOVE
CARPET, SINGLE-LAYER ASBESTOS FLOOR TILE AND
ASSOCIATED ASBESTOS MASTIC.
- PHASE 1C: 172 SF OF CARPET, ACM FLOOR TILE & MASTIC
INSIDE A NEGATIVE PRESSURE CONTAINMENT REMOVE
ASBESTOS INTERIOR DOOR CAULKING FROM METAL DOOR
FRAMES USING HAND TOOLS.
- PHASE 1A: 51 LF X ½ " OF ACM INTERIOR DOOR CAULKING
- PHASE 1B: 102 LF X ½" OF ACM INTERIOR DOOR CAULKING
- PHASE 1C: 34 LF X ½ " OF ACM INTERIOR DOOR CAULKING
- PHASE 1D: 34 LF X ½ " OF ACM INTERIOR DOOR CAULKING
(NIGHTS & WEEKENDS)
INSIDE A NEGATIVE PRESSURE CONTAINMENT DEMOLISH
PLASTER CHASES AS REQUIRED, CLEAN-UP ANY PIPE
INSULATION DEBRIS AND THOROUGHLY CLEAN ALL SURFACES,
REMOVE ASBESTOS PIPE INSULATION, ASBESTOS MUDDED
FITTINGS, ASBESTOS BLACK TAR PIPE FITTINGS AND
ASBESTOS PIPE SADDLE INSULATION USING GLOVEBAG
REMOVAL TECHNIQUES.
- PHASE 1A: 80 SF OF PLASTER PIPE CHASE DEMO AND
CLEANING, 20 LF OF ACM PIPE INSULATION, 5
EACH ACM MUDDED PIPE FITTINGS
- PHASE 1B: 100 SF OF PLASTER PIPE CHASE DEMO AND
CLEANING, 15 LF OF ACM PIPE INSULATION, 8
EACH ACM MUDDED PIPE FITTINGS
- PHASE 1D: 30 EACH ACM MUDDED PIPE FITTINGS
(NIGHTS & WEEKENDS)
A1.
A2.
A3.
A4.
ABATEMENT LEGEND
REMOVE ACM FLOOR TILE AND MASTIC AS INDICATED
IN KEYNOTES
REMOVE ACM PIPE INSULATION AND FITTINGS AS
INDICATED IN KEYNOTES.
REMOVE LEAD SHIELDING AS INDICATED IN
KEYNOTES.
REMOVE LEAD GLAZED BLOCK WALLS AS INDICATED
IN KEYNOTES.
SHEET NOTES:
A1
A2
A1
A1
A1
A1
A1
A1
A1
A3
A3
A3
A3
A3
A3
A3
A3
A3
A4
A4
A4
L1
L1
L1
L2
L3
A4
A3
PHASE 1C:
LIMITS OF NEGATIVE PRESSURE CONTAINMENT
PHASE 1B:
LIMITS OF NEGATIVE PRESSURE CONTAINMENT
PHASE 1D (NIGHTS & WEEKENDS):
LIMITS OF NEGATIVE PRESSURE CONTAINMENT
PHASE 1A:
LIMITS OF NEGATIVE PRESSURE CONTAINMENT
PHASE 1C:
LIMITS OF NEGATIVE PRESSURE CONTAINMENT
PHASE 1B:
LIMITS OF NEGATIVE PRESSURE CONTAINMENT
PHASE 1D (NIGHTS & WEEKENDS):
LIMITS OF NEGATIVE PRESSURE CONTAINMENT
PHASE 1A:
LIMITS OF NEGATIVE PRESSURE CONTAINMENT
A1
A2 A3
WALL RATING LEGEND
1 HR - FIRE SEPARATION
2 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREAS S S S
THE ABATEMENT SCOPE OF THE WORK IN BUILDING 52
CONSISTS OF REMOVING VARIOUS ASBESTOS AND LEAD
IMPACTED MATERIALS THROUGHOUT THE PROJECT LIMITS.
ALL WORK SHALL BE CONDUCTED IN ACCORDANCE WITH ALL
FEDERAL, STATE AND LOCAL REGULATIONS AND THE
CONTRACT SPECIFICATIONS.
IN BUILDING 52, ASBESTOS CONTAINING PIPE INSULATION IS
PRESENT THROUGHOUT THE WORK AREAS ON THE 1ST
FLOOR, BUT MAY NOT BE DIRECTLY IMPACTED UNLESS
INDICATED BY THE KEYNOTES. PROTECT AS REQUIRED TO
PREVENT ANY DAMAGE OR DISTURBANCE.
ASBESTOS TRANSITE PANELS SHOULD BE ASSUMED TO BE
PRESENT BEHIND RADIATORS. NO ABATEMENT OF THIS
MATERIAL IS ANTICIPATED AND SHALL BE PROTECTED AS
REQUIRED.
LEAD-CONTAINING GLAZED BLOCK WALLS ARE LOCATED
THROUGHOUT THE PROJECT LIMITS, BUT WILL ONLY BE
IMPACTED IN AREAS IDENTIFIED WITH SPECIFIC KEYNOTES.
REMAINING WALLS SHALL BE PROTECTED AS REQUIRED.
ALL ABATEMENT WORK SHALL BE CONDUCTED DURING
ADMINISTRATIVE HOURS (7:00 AM TO 5:00 PM) MONDAY -
FRIDAY EXCLUDING FEDERAL HOLIDAYS; EXCEPT THE OUT OF
PHASE WORK WHICH SHALL BE ACCOMPLISHED AT NIGHT
(5:00 PM TO 5:00 AM) OR ON A WEEKEND (5:00 PM FRIDAY TO
6:00 PM SUNDAY). DUE TO THE EXTENTS OF ABATEMENT,
MULTIPLE PHASES (INCLUDING SUB-PHASES), MULTIPLE
MOBILIZATIONS, AND MULTIPLE WEEKENDS WILL BE
REQUIRED. PROPER COORDINATION WITH ALL PARTIES WILL
BE REQUIRED.
WORK SCHEDULES AND LIMITS OF ABATEMENT SHALL BE
COORDINATED WITH THE VA COR AND VPIH FOR APPROVALS,
UNLESS OTHERWISE INDICATED ON THE KEYNOTES. THE
ABATEMENT CONTRACTOR SHALL SUBMIT A DETAILED WORK
PLAN AND ABATEMENT SCHEDULE WITH THE REQUIRED
SUBMITTALS. ANY CHANGES TO THE PROCEDURES,
CONTAINMENT LIMITS AND PHASING SHALL BE SUBMITTED TO
THE VA COR AND VPIH FOR APPROVALS.
THE LOCATIONS AND QUANTITIES SHALL BE FIELD VERIFIED
BY THE ABATEMENT CONTRACTOR. THE LIMITS OF REMOVAL
AND EXTENT OF THE CONTAINMENTS SHALL BE VERIFIED
WITH THE VA COR AND VPIH. FOR CLARITY, THE DRAWINGS
ONLY SHOW REPRESENTATIVE LOCATIONS OF PIPING.
ALL LOADOUT PROCEDURES SHALL BE COORDINATED WITH
THE VA COR.
ABATED PIPE INSULATION AND FITTINGS, EXCLUDING PIPING
THAT WILL BE DEMOLISHED, SHALL BE PROPERLY
RE-INSULATED WITH EQUIVALENT INSULATING PROPERTIES IN
ACCORDANCE WITH VA SPECIFICATION 23 07 11, HVAC AND
BOILER PLANT INSULATION.
ALL POLYETHYLENE SHEETING USED FOR THE ABATEMENT
PROJECT SHALL BE OF THE FIRE RETARDANT TYPE.
THE LOCATIONS OF ABATEMENT DECONTAMINATION UNITS
AND WASTE DISPOSAL CONTAINERS SHALL BE FIELD
VERIFIED WITH THE VA COR AND VPIH. ALL LOADOUT
PROCEDURES SHALL BE COORDINATED WITH THE VA COR
AND VPIH. SEE DEMOLITION DRAWINGS FOR TEMPORARY
PARTITION AND INFECTION CONTROL DETAILS.
ALL PERIMETER AIR MONITORING, CLEARANCE SAMPLING,
AND WIPE SAMPLING WILL BE CONDUCTED BY THE VPIH.
VA PERSONNEL SHALL BE RESPONSIBLE FOR REMOVING OR
RELOCATING ALL EQUIPMENT, COMPUTERS, SUPPLIES,
FURNITURE, DESKS, WALL HANGINGS, ETC., FROM THE
ABATEMENT AREAS.
ALL MECHANICAL SYSTEMS, INCLUDING BUT NOT LIMITED TO,
HVAC SYSTEMS, STEAM PIPING, ETC., SHALL BE SHUT DOWN
DURING ALL ABATEMENT ACTIVITIES. ABATEMENT OF
ASBESTOS PIPE INSULATION AND FITTING INSULATION FROM
THE STEAM PIPING MUST BE ACCOMPLISHED WHEN THE
STEAM PIPES ARE LESS THAN 150 DEGREES FAHRENHEIT. ALL
REQUIRED STEAM SHUTDOWNS SHALL BE PROPERLY
COORDINATED WITH THE VA TO MINIMIZE IMPACT TO THE
HOSPITAL OPERATIONS.
STRICT COORDINATION BETWEEN THE VA OCCUPANTS, VA
COR, VPIH, GENERAL CONTRACTOR AND ABATEMENT
CONTRACTOR SHALL BE REQUIRED.
ALL LEAD WASTE SHALL BE TESTED BY THE ABATEMENT
CONTRACTOR USING TCLP ANALYTICAL METHODS TO
DETERMINE PROPER WASTE DISPOSAL METHODS.
TRACE AMOUNTS OF LEAD BELOW THE EPA HUD DEFINITION
OF LEAD-BASED PAINT WERE IDENTIFIED IN THE PROJECT
AREAS. IT SHOULD BE NOTED THAT OSHA DOES NOT
RECOGNIZE THE HUD DEFINITION AS A THRESHOLD VALUE
FOR LEAD EXPOSURE. ALTHOUGH THE POTENTIAL LEAD
HAZARD FOR NORMAL DEMOLITION OR CONSTRUCTION
ACTIVITIES IS LOW, ACTUAL LEAD EXPOSURE MAY VARY
SIGNIFICANTLY DEPENDING UPON THE SPECIFIC TASK,
PROCEDURE AND OTHER WORK AREA CONDITIONS. PROPER
OSHA COMPLIANCE IS CONSIDERED PERFORMANCE BASED
AND INCLUDES EVALUATING POTENTIAL WORK EXPOSURES
WITH AIR MONITORING OR BIOLOGICAL EXPOSURE
MONITORING (BLOOD LEAD TESTING), IF REQUIRED. UNLESS
THE DEMOLITION CONTRACTOR HAS HISTORICAL DATA
DOCUMENTING THIS POTENTIAL EXPOSURE, PERSONAL AIR
SAMPLING SHALL BE CONDUCTED BY THE CPIH ON
REPRESENTATIVE TASKS.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
S
S
S S
S
SS
S S
S S
S
S
S
S
S
OFFICE
2N111
EXAM
2S01
TREAT.
RM.
2S01
EXAM
2S04
CONTROL
RM.
2S06
EXAM 6
2N118
WAITING
2N114
P.T. / O.T.
2N58
ELEVATOR
E3
ELEVATOR
LOBBY
2S57
PAIN
REHAB.
CENTER
2S56A
CONFERENCE
RM
2S56
OI&T
2S53
CORRIDOR
H204
ELEVATOR
E2
SOILED
UTILITY
2S10
EXAM 1
2S05
OFFICE
2S11
OFFICE
2S11A
OFFICE
2N63
OFFICE
2N60
WAITING
RM.
2N112A
HALLWAY
2N113
WHEEL CHAIR
STORAGE
2N110
HAC
2N64
CORRIDOR
H208
EXAM
2S12B
ELEVATOR
E4
STAIR 2
S2
OPEN
OFFICE
2N59
CLOSET
2N59A
RESTROOM
2N59B
MEDS
2N59C
S S
S
S
S S
S
SS
S S
S S
S
S
S
S
S
OFFICE
2N111
EXAM
2S01
TREAT.
RM.
2S01
EXAM
2S04
CONTROL
RM.
2S06
EXAM 6
2N118
WAITING
2N114
P.T. / O.T.
2N58
ELEVATOR
E3
ELEVATOR
LOBBY
2S57
PAIN
REHAB.
CENTER
2S56A
CONFERENCE
RM
2S56
OI&T
2S53
CORRIDOR
H204
ELEVATOR
E2
SOILED
UTILITY
2S10
EXAM 1
2S05
OFFICE
2S11
OFFICE
2S11A
OFFICE
2N63
OFFICE
2N60
WAITING
RM.
2N112A
HALLWAY
2N113
WHEEL CHAIR
STORAGE
2N110
HAC
2N64
CORRIDOR
H208
EXAM
2S12B
ELEVATOR
E4
STAIR 2
S2
OPEN
OFFICE
2N59
CLOSET
2N59A
RESTROOM
2N59B
MEDS
2N59C
Revisions: Date
Drawing Title:
Approved: Project Director
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
Date Checked Drawn U.S. Department of Veterans Affairs# © COPYRIGHT Apogee - CEMS JV, LLC
An Alliance for Success
HA102
SECOND FLOOR ABATEMENT PLANS -
PHASE 2
3 4GKY RAJ
RENOVATE SECOND FLOOR
CENTER, JB BLDG 52
1 JEFFERSON BARRACKS DR, ST.
LOUIS, MO 63125
657-20-102JB20-028
RANDY GOFFIN
Scale: 1/8" = 1'-0"
SECOND FLOOR TSI AND LEAD ABATEMENT PLAN - PHASE 2
N O
R
TH
0 4 8 16 Scale: 1/8" = 1'-0"
SECOND FLOOR FLOORING ABATEMENT PLAN - PHASE 2
N O
R
TH
0 4 8 16
INSIDE A NEGATIVE PRESSURE CONTAINMENT SAW CUT
LEAD-CONTAINING GLAZED BLOCK WALL AS INDICATED ON
ARCHITECTURAL DEMOLITION DRAWINGS.
- PHASE 2A: 30 SF SAW CUTTING OF LEAD-CONTAINING
GLAZED BLOCK WALL
INSIDE A NEGATIVE PRESSURE CONTAINMENT REMOVE
LEAD-CONTAINING CERAMIC TILE COVE BASE USING HAND
TOOLS.
- PHASE 2A: 60 LF X 4" LEAD-CONTAINING CERAMIC TILE
COVE BASE
L1.
L2.
INSIDE A NEGATIVE PRESSURE CONTAINMENT REMOVE
SINGLE-LAYER ASBESTOS FLOOR TILE AND ASSOCIATED
ASBESTOS MASTIC.
- PHASE 2A: 790 SF OF ACM FLOOR TILE AND MASTIC
- PHASE 2B: 320 SF OF ACM FLOOR TILE AND MASTIC
- PHASE 2C: 160 SF OF ACM FLOOR TILE AND MASTIC
INSIDE A NEGATIVE PRESSURE CONTAINMENT REMOVE
CARPET, SINGLE-LAYER ASBESTOS FLOOR TILE AND
ASSOCIATED ASBESTOS MASTIC.
- PHASE 2C: 160 SF OF CARPET, ACM FLOOR TILE & MASTIC
INSIDE A NEGATIVE PRESSURE CONTAINMENT REMOVE
ASBESTOS INTERIOR DOOR CAULKING FROM METAL DOOR
FRAMES USING HAND TOOLS.
- PHASE 2A: 136 LF X ½" OF ACM INTERIOR DOOR CAULKING
- PHASE 2C: 17 LF X ½ " OF ACM INTERIOR DOOR CAULKING
INSIDE A NEGATIVE PRESSURE CONTAINMENT DEMOLISH
PLASTER CHASES AS REQUIRED, CLEAN-UP ANY PIPE
INSULATION DEBRIS AND THOROUGHLY CLEAN ALL SURFACES,
REMOVE ASBESTOS PIPE INSULATION, ASBESTOS MUDDED
FITTINGS, ASBESTOS BLACK TAR PIPE FITTINGS AND ASBESTOS
PIPE SADDLE INSULATION USING GLOVEBAG REMOVAL
TECHNIQUES.
- PHASE 2A: 150 SF OF PLASTER PIPE CHASE DEMO AND
CLEANING, 20 LF OF ACM PIPE INSULATION, 10
EACH ACM MUDDED PIPE FITTINGS
- PHASE 2B: 8 EACH MUDDED PIPE FITTINGS >6” DIAMETER, 3
EACH MUDDED PIPE FITTINGS <6” DIAMETER
A1.
A2.
A3.
A4.
REMOVE ACM FLOOR TILE AND MASTIC AS INDICATED
IN KEYNOTES
REMOVE ACM PIPE INSULATION AND FITTINGS AS
INDICATED IN KEYNOTES.
REMOVE LEAD-CONTAINING CERAMIC TILE COVE
BASE AS INDICATED IN KEYNOTES.
REMOVE LEAD GLAZED BLOCK WALLS AS INDICATED
IN KEYNOTES.
A2
A1
A1 A1
A1
A1
A1 A1
A3
A3
A3 A3
A3
A4
L1
L2
L2
PHASE 2A:
LIMITS OF NEGATIVE PRESSURE CONTAINMENTS
PHASE 2B:
LIMITS OF NEGATIVE PRESSURE CONTAINMENTS
PHASE 2C:
LIMITS OF NEGATIVE
PRESSURE CONTAINMENTS
PHASE 2A:
LIMITS OF NEGATIVE PRESSURE CONTAINMENTS
PHASE 2B:
LIMITS OF NEGATIVE
PRESSURE CONTAINMENTS
A4
L2
A3
PHASE 2C:
LIMITS OF NEGATIVE
PRESSURE CONTAINMENT
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
WALL RATING LEGEND
1 HR - FIRE SEPARATION
2 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREAS S S S
THE ABATEMENT SCOPE OF THE WORK IN BUILDING 52
CONSISTS OF REMOVING VARIOUS ASBESTOS AND LEAD
IMPACTED MATERIALS THROUGHOUT THE PROJECT LIMITS.
ALL WORK SHALL BE CONDUCTED IN ACCORDANCE WITH ALL
FEDERAL, STATE AND LOCAL REGULATIONS AND THE
CONTRACT SPECIFICATIONS.
IN BUILDING 52, ASBESTOS CONTAINING PIPE INSULATION IS
PRESENT THROUGHOUT THE WORK AREAS ON THE 1ST
FLOOR, BUT MAY NOT BE DIRECTLY IMPACTED UNLESS
INDICATED BY THE KEYNOTES. PROTECT AS REQUIRED TO
PREVENT ANY DAMAGE OR DISTURBANCE.
ASBESTOS TRANSITE PANELS SHOULD BE ASSUMED TO BE
PRESENT BEHIND RADIATORS. NO ABATEMENT OF THIS
MATERIAL IS ANTICIPATED AND SHALL BE PROTECTED AS
REQUIRED.
LEAD-CONTAINING GLAZED BLOCK WALLS ARE LOCATED
THROUGHOUT THE PROJECT LIMITS, BUT WILL ONLY BE
IMPACTED IN AREAS IDENTIFIED WITH SPECIFIC KEYNOTES.
REMAINING WALLS SHALL BE PROTECTED AS REQUIRED.
ALL ABATEMENT WORK SHALL BE CONDUCTED DURING
ADMINISTRATIVE HOURS (7:00 AM TO 5:00 PM) MONDAY -
FRIDAY EXCLUDING FEDERAL HOLIDAYS; EXCEPT THE OUT OF
PHASE WORK WHICH SHALL BE ACCOMPLISHED AT NIGHT
(5:00 PM TO 5:00 AM) OR ON A WEEKEND (5:00 PM FRIDAY TO
6:00 PM SUNDAY). DUE TO THE EXTENTS OF ABATEMENT,
MULTIPLE PHASES (INCLUDING SUB-PHASES), MULTIPLE
MOBILIZATIONS, AND MULTIPLE WEEKENDS WILL BE
REQUIRED. PROPER COORDINATION WITH ALL PARTIES WILL
BE REQUIRED.
WORK SCHEDULES AND LIMITS OF ABATEMENT SHALL BE
COORDINATED WITH THE VA COR AND VPIH FOR APPROVALS,
UNLESS OTHERWISE INDICATED ON THE KEYNOTES. THE
ABATEMENT CONTRACTOR SHALL SUBMIT A DETAILED WORK
PLAN AND ABATEMENT SCHEDULE WITH THE REQUIRED
SUBMITTALS. ANY CHANGES TO THE PROCEDURES,
CONTAINMENT LIMITS AND PHASING SHALL BE SUBMITTED TO
THE VA COR AND VPIH FOR APPROVALS.
THE LOCATIONS AND QUANTITIES SHALL BE FIELD VERIFIED
BY THE ABATEMENT CONTRACTOR. THE LIMITS OF REMOVAL
AND EXTENT OF THE CONTAINMENTS SHALL BE VERIFIED
WITH THE VA COR AND VPIH. FOR CLARITY, THE DRAWINGS
ONLY SHOW REPRESENTATIVE LOCATIONS OF PIPING.
ALL LOADOUT PROCEDURES SHALL BE COORDINATED WITH
THE VA COR.
ABATED PIPE INSULATION AND FITTINGS, EXCLUDING PIPING
THAT WILL BE DEMOLISHED, SHALL BE PROPERLY
RE-INSULATED WITH EQUIVALENT INSULATING PROPERTIES IN
ACCORDANCE WITH VA SPECIFICATION 23 07 11, HVAC AND
BOILER PLANT INSULATION.
ALL POLYETHYLENE SHEETING USED FOR THE ABATEMENT
PROJECT SHALL BE OF THE FIRE RETARDANT TYPE.
THE LOCATIONS OF ABATEMENT DECONTAMINATION UNITS
AND WASTE DISPOSAL CONTAINERS SHALL BE FIELD
VERIFIED WITH THE VA COR AND VPIH. ALL LOADOUT
PROCEDURES SHALL BE COORDINATED WITH THE VA COR
AND VPIH. SEE DEMOLITION DRAWINGS FOR TEMPORARY
PARTITION AND INFECTION CONTROL DETAILS.
ALL PERIMETER AIR MONITORING, CLEARANCE SAMPLING,
AND WIPE SAMPLING WILL BE CONDUCTED BY THE VPIH.
VA PERSONNEL SHALL BE RESPONSIBLE FOR REMOVING OR
RELOCATING ALL EQUIPMENT, COMPUTERS, SUPPLIES,
FURNITURE, DESKS, WALL HANGINGS, ETC., FROM THE
ABATEMENT AREAS.
ALL MECHANICAL SYSTEMS, INCLUDING BUT NOT LIMITED TO,
HVAC SYSTEMS, STEAM PIPING, ETC., SHALL BE SHUT DOWN
DURING ALL ABATEMENT ACTIVITIES. ABATEMENT OF
ASBESTOS PIPE INSULATION AND FITTING INSULATION FROM
THE STEAM PIPING MUST BE ACCOMPLISHED WHEN THE
STEAM PIPES ARE LESS THAN 150 DEGREES FAHRENHEIT. ALL
REQUIRED STEAM SHUTDOWNS SHALL BE PROPERLY
COORDINATED WITH THE VA TO MINIMIZE IMPACT TO THE
HOSPITAL OPERATIONS.
STRICT COORDINATION BETWEEN THE VA OCCUPANTS, VA
COR, VPIH, GENERAL CONTRACTOR AND ABATEMENT
CONTRACTOR SHALL BE REQUIRED.
ALL LEAD WASTE SHALL BE TESTED BY THE ABATEMENT
CONTRACTOR USING TCLP ANALYTICAL METHODS TO
DETERMINE PROPER WASTE DISPOSAL METHODS.
TRACE AMOUNTS OF LEAD BELOW THE EPA HUD DEFINITION
OF LEAD-BASED PAINT WERE IDENTIFIED IN THE PROJECT
AREAS. IT SHOULD BE NOTED THAT OSHA DOES NOT
RECOGNIZE THE HUD DEFINITION AS A THRESHOLD VALUE
FOR LEAD EXPOSURE. ALTHOUGH THE POTENTIAL LEAD
HAZARD FOR NORMAL DEMOLITION OR CONSTRUCTION
ACTIVITIES IS LOW, ACTUAL LEAD EXPOSURE MAY VARY
SIGNIFICANTLY DEPENDING UPON THE SPECIFIC TASK,
PROCEDURE AND OTHER WORK AREA CONDITIONS. PROPER
OSHA COMPLIANCE IS CONSIDERED PERFORMANCE BASED
AND INCLUDES EVALUATING POTENTIAL WORK EXPOSURES
WITH AIR MONITORING OR BIOLOGICAL EXPOSURE
MONITORING (BLOOD LEAD TESTING), IF REQUIRED. UNLESS
THE DEMOLITION CONTRACTOR HAS HISTORICAL DATA
DOCUMENTING THIS POTENTIAL EXPOSURE, PERSONAL AIR
SAMPLING SHALL BE CONDUCTED BY THE CPIH ON
REPRESENTATIVE TASKS.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
S S
S
OPEN
OFFICE
2N60
EQUIP
STORAGE
2N111
RESTROOM
2N114A
MEDS
2N116
TELEHEALTH
2N112
GROUP
ROOM
2S58
CONSULT
2S56ELEVATOR
LOBBY
H209
EXAM 6
2N118
RESTROOM
2N118A
EXAM 5
2S01
LOGISTICS
STORAGE
2N117
SOILED
UTILITY
2S10
OFFICE
(PSYCH)
2S11
OFFICE
(SW)
2S11A
CORRIDOR
H204
OI&T_
2S53
CONFERENCE
2S54
CORRIDOR
2N115
WAITING
2N114
CORRIDOR
H208
CHASE_
H208B
ELECT.
CLOSET
H208AELEVATOR
E4
STAIR 2
S2
ELEVATOR
E3
ELEVATOR
E2
CLOSET
2N60A
EXAM 1
2S05
RECEPTION
2N113
EXAM
2S12B
HAC
2N64
WHEELCHAIR
STORAGE
2N110
S S
S
S
S S
S
SS
S S
S S
S
S
S
S
TREAT.
RM.
2S05
EXAM
2S04
CONTROL
RM.
2S06
S S
S
S S
OPEN
OFFICE
2N60
EQUIP
STORAGE
2N111
RESTROOM
2N114A
MEDS
2N116
TELEHEALTH
2N112
GROUP
ROOM
2S58
CONSULT
2S56ELEVATOR
LOBBY
H209
EXAM 6
2N118
RESTROOM
2N118A
EXAM 5
2S01
LOGISTICS
STORAGE
2N117
SOILED
UTILITY
2S10
OFFICE
(PSYCH)
2S11
OFFICE
(SW)
2S11A
CORRIDOR
H204
OI&T_
2S53
CONFERENCE
2S54
CORRIDOR
2N115
WAITING
2N114
CORRIDOR
H208
CHASE_
H208B
ELECT.
CLOSET
H208AELEVATOR
E4
STAIR 2
S2
ELEVATOR
E3
ELEVATOR
E2
CLOSET
2N60A
EXAM 1
2S05
RECEPTION
2N113
EXAM
2S12B
HAC
2N64
WHEELCHAIR
STORAGE
2N110
S S
S
S
S S
S
SS
S S
S S
S
S
S
S
TREAT.
RM.
2S05
EXAM
2S04
CONTROL
RM.
2S06
Revisions: Date
Drawing Title:
Approved: Project Director
Project Title
Location
VA PROJECT NUMBER
Building Number
Drawing Number
Dwg of
VA FORM 08-6231
CONSULTANTS: PROJECT MANAGER:
Date Checked Drawn U.S. Department of Veterans Affairs# © COPYRIGHT Apogee - CEMS JV, LLC
1151 Kildaire Farm Rd.
Suite 120 Raleigh, NC 27511 www.acg-pa.com (919)858-7420
108 Benton Lodge Road Suite B Summerville, SC 29485 www.cemsengineering.com (843)875-3637Project Mgr: Alex Kramer (APOGEE)
An Alliance for Success
HA103
SECOND FLOOR ABATEMENT PLANS -
PHASE 3
4 4GKY RAJ
RENOVATE SECOND FLOOR
CENTER, JB BLDG 52
1 JEFFERSON BARRACKS DR, ST.
LOUIS, MO 63125
657-20-102JB20-028
RANDY GOFFIN
Scale: 1/8" = 1'-0"
SECOND FLOOR TSI AND LEAD ABATEMENT PLAN - PHASE 3
N O
R
TH
0 4 8 16
Scale: 1/8" = 1'-0"
SECOND FLOOR FLOORING ABATEMENT PLAN - PHASE 3
N O
R
TH
0 4 8 16
ASBESTOS KEY NOTES: LEAD KEY NOTES:
N
AREA OF WORK
KEY PLAN
SCALE: NO SCALE
INSIDE A NEGATIVE PRESSURE CONTAINMENT, DEMOLISH
PLASTER WALLS AND CEILINGS, REMOVE LEAD SHIELDING,
LEAD SHIELDED DOORS, DOOR FRAMES AND VIEWING
WINDOWS USING HAND TOOLS AND DISMANTLING
TECHNIQUES.
- PHASE 1A: 750 SF OF PLASTER WALLS, CEILINGS AND LEAD
SHIELDING, 1 EACH LEAD SHIELDED DOOR AND
FRAME, 1 EACH LEAD SHIELDED VIEWING
WINDOW
INSIDE A NEGATIVE PRESSURE CONTAINMENT, REMOVE
LEAD-BASED PAINTED PIPE HANGERS USING DISMANTLING
TECHNIQUES.
- PHASE 3C: 5 EACH LEAD-BASED PAINTED PIPE HANGER
(NIGHTS & WEEKENDS)
L1.
L2.
INSIDE A NEGATIVE PRESSURE CONTAINMENT REMOVE
SINGLE-LAYER ASBESTOS FLOOR TILE AND ASSOCIATED
ASBESTOS MASTIC.
- PHASE 3A: 440 SF OF ACM FLOOR TILE AND MASTIC
- PHASE 3B: 700 SF OF ACM FLOOR TILE AND MASTIC
- PHASE 3C: 1,415 SF OF ACM FLOOR TILE AND MASTIC
(NIGHTS & WEEKENDS)
INSIDE A NEGATIVE PRESSURE CONTAINMENT REMOVE
CARPET AND ASBESTOS MASTIC.
- PHASE 3B: 380 SF OF CARPET AND ACM MASTIC
INSIDE A NEGATIVE PRESSURE CONTAINMENT REMOVE
ASBESTOS INTERIOR DOOR CAULKING FROM METAL DOOR
FRAMES USING HAND TOOLS.
- PHASE 3A: 102 LF X ½ " OF ACM INTERIOR DOOR CAULKING
INSIDE A NEGATIVE PRESSURE CONTAINMENT REMOVE
ASBESTOS PIPE INSULATION, ASBESTOS MUDDED FITTINGS,
ASBESTOS BLACK TAR PIPE FITTINGS AND ASBESTOS PIPE
SADDLE INSULATION USING GLOVEBAG REMOVAL
TECHNIQUES.
- PHASE 3C: 25 EACH ACM MUDDED PIPE FITTINGS, 45 EACH
ACM PIPE SADDLE INSULATION, 4 EACH ACM
TAR PIPE FITTINGS
(NIGHTS & WEEKENDS)
A1.
A2.
A3.
A4. ABATEMENT LEGEND
REMOVE ACM FLOOR TILE AND MASTIC AS INDICATED
IN KEYNOTES
REMOVE ACM PIPE INSULATION AND FITTINGS AS
INDICATED IN KEYNOTES.
REMOVE LEAD SHIELDING AS INDICATED IN
KEYNOTES.
SHEET NOTES:
A2
A1 A1
A1
A1 A1
A1 A1 A1
A3
A3
A4
L1
L2 A4
L2
A4
L2
PHASE 3C (NIGHTS & WEEKENDS):
LIMITS OF NEGATIVE PRESSURE CONTAINMENTS
PHASE 3B:
LIMITS OF NEGATIVE PRESSURE CONTAINMENTS
PHASE 3A:
LIMITS OF NEGATIVE PRESSURE CONTAINMENT
PHASE 3C (NIGHTS & WEEKENDS):
LIMITS OF NEGATIVE PRESSURE CONTAINMENTS
PHASE 3A:
LIMITS OF NEGATIVE PRESSURE CONTAINMENT
A1
WALL RATING LEGEND
1 HR - FIRE SEPARATION
2 HR - FIRE SEPARATION
SMOKE RESISTIVE HAZARDOUS AREAS S S S
THE ABATEMENT SCOPE OF THE WORK IN BUILDING 52
CONSISTS OF REMOVING VARIOUS ASBESTOS AND LEAD
IMPACTED MATERIALS THROUGHOUT THE PROJECT LIMITS.
ALL WORK SHALL BE CONDUCTED IN ACCORDANCE WITH ALL
FEDERAL, STATE AND LOCAL REGULATIONS AND THE
CONTRACT SPECIFICATIONS.
IN BUILDING 52, ASBESTOS CONTAINING PIPE INSULATION IS
PRESENT THROUGHOUT THE WORK AREAS ON THE 1ST
FLOOR, BUT MAY NOT BE DIRECTLY IMPACTED UNLESS
INDICATED BY THE KEYNOTES. PROTECT AS REQUIRED TO
PREVENT ANY DAMAGE OR DISTURBANCE.
ASBESTOS TRANSITE PANELS SHOULD BE ASSUMED TO BE
PRESENT BEHIND RADIATORS. NO ABATEMENT OF THIS
MATERIAL IS ANTICIPATED AND SHALL BE PROTECTED AS
REQUIRED.
LEAD-CONTAINING GLAZED BLOCK WALLS ARE LOCATED
THROUGHOUT THE PROJECT LIMITS, BUT WILL ONLY BE
IMPACTED IN AREAS IDENTIFIED WITH SPECIFIC KEYNOTES.
REMAINING WALLS SHALL BE PROTECTED AS REQUIRED.
ALL ABATEMENT WORK SHALL BE CONDUCTED DURING
ADMINISTRATIVE HOURS (7:00 AM TO 5:00 PM) MONDAY -
FRIDAY EXCLUDING FEDERAL HOLIDAYS; EXCEPT THE OUT OF
PHASE WORK WHICH SHALL BE ACCOMPLISHED AT NIGHT
(5:00 PM TO 5:00 AM) OR ON A WEEKEND (5:00 PM FRIDAY TO
6:00 PM SUNDAY). DUE TO THE EXTENTS OF ABATEMENT,
MULTIPLE PHASES (INCLUDING SUB-PHASES), MULTIPLE
MOBILIZATIONS, AND MULTIPLE WEEKENDS WILL BE
REQUIRED. PROPER COORDINATION WITH ALL PARTIES WILL
BE REQUIRED.
WORK SCHEDULES AND LIMITS OF ABATEMENT SHALL BE
COORDINATED WITH THE VA COR AND VPIH FOR APPROVALS,
UNLESS OTHERWISE INDICATED ON THE KEYNOTES. THE
ABATEMENT CONTRACTOR SHALL SUBMIT A DETAILED WORK
PLAN AND ABATEMENT SCHEDULE WITH THE REQUIRED
SUBMITTALS. ANY CHANGES TO THE PROCEDURES,
CONTAINMENT LIMITS AND PHASING SHALL BE SUBMITTED TO
THE VA COR AND VPIH FOR APPROVALS.
THE LOCATIONS AND QUANTITIES SHALL BE FIELD VERIFIED
BY THE ABATEMENT CONTRACTOR. THE LIMITS OF REMOVAL
AND EXTENT OF THE CONTAINMENTS SHALL BE VERIFIED
WITH THE VA COR AND VPIH. FOR CLARITY, THE DRAWINGS
ONLY SHOW REPRESENTATIVE LOCATIONS OF PIPING.
ALL LOADOUT PROCEDURES SHALL BE COORDINATED WITH
THE VA COR.
ABATED PIPE INSULATION AND FITTINGS, EXCLUDING PIPING
THAT WILL BE DEMOLISHED, SHALL BE PROPERLY
RE-INSULATED WITH EQUIVALENT INSULATING PROPERTIES IN
ACCORDANCE WITH VA SPECIFICATION 23 07 11, HVAC AND
BOILER PLANT INSULATION.
ALL POLYETHYLENE SHEETING USED FOR THE ABATEMENT
PROJECT SHALL BE OF THE FIRE RETARDANT TYPE.
THE LOCATIONS OF ABATEMENT DECONTAMINATION UNITS
AND WASTE DISPOSAL CONTAINERS SHALL BE FIELD
VERIFIED WITH THE VA COR AND VPIH. ALL LOADOUT
PROCEDURES SHALL BE COORDINATED WITH THE VA COR
AND VPIH. SEE DEMOLITION DRAWINGS FOR TEMPORARY
PARTITION AND INFECTION CONTROL DETAILS.
ALL PERIMETER AIR MONITORING, CLEARANCE SAMPLING,
AND WIPE SAMPLING WILL BE CONDUCTED BY THE VPIH.
VA PERSONNEL SHALL BE RESPONSIBLE FOR REMOVING OR
RELOCATING ALL EQUIPMENT, COMPUTERS, SUPPLIES,
FURNITURE, DESKS, WALL HANGINGS, ETC., FROM THE
ABATEMENT AREAS.
ALL MECHANICAL SYSTEMS, INCLUDING BUT NOT LIMITED TO,
HVAC SYSTEMS, STEAM PIPING, ETC., SHALL BE SHUT DOWN
DURING ALL ABATEMENT ACTIVITIES. ABATEMENT OF
ASBESTOS PIPE INSULATION AND FITTING INSULATION FROM
THE STEAM PIPING MUST BE ACCOMPLISHED WHEN THE
STEAM PIPES ARE LESS THAN 150 DEGREES FAHRENHEIT. ALL
REQUIRED STEAM SHUTDOWNS SHALL BE PROPERLY
COORDINATED WITH THE VA TO MINIMIZE IMPACT TO THE
HOSPITAL OPERATIONS.
STRICT COORDINATION BETWEEN THE VA OCCUPANTS, VA
COR, VPIH, GENERAL CONTRACTOR AND ABATEMENT
CONTRACTOR SHALL BE REQUIRED.
ALL LEAD WASTE SHALL BE TESTED BY THE ABATEMENT
CONTRACTOR USING TCLP ANALYTICAL METHODS TO
DETERMINE PROPER WASTE DISPOSAL METHODS.
TRACE AMOUNTS OF LEAD BELOW THE EPA HUD DEFINITION
OF LEAD-BASED PAINT WERE IDENTIFIED IN THE PROJECT
AREAS. IT SHOULD BE NOTED THAT OSHA DOES NOT
RECOGNIZE THE HUD DEFINITION AS A THRESHOLD VALUE
FOR LEAD EXPOSURE. ALTHOUGH THE POTENTIAL LEAD
HAZARD FOR NORMAL DEMOLITION OR CONSTRUCTION
ACTIVITIES IS LOW, ACTUAL LEAD EXPOSURE MAY VARY
SIGNIFICANTLY DEPENDING UPON THE SPECIFIC TASK,
PROCEDURE AND OTHER WORK AREA CONDITIONS. PROPER
OSHA COMPLIANCE IS CONSIDERED PERFORMANCE BASED
AND INCLUDES EVALUATING POTENTIAL WORK EXPOSURES
WITH AIR MONITORING OR BIOLOGICAL EXPOSURE
MONITORING (BLOOD LEAD TESTING), IF REQUIRED. UNLESS
THE DEMOLITION CONTRACTOR HAS HISTORICAL DATA
DOCUMENTING THIS POTENTIAL EXPOSURE, PERSONAL AIR
SAMPLING SHALL BE CONDUCTED BY THE CPIH ON
REPRESENTATIVE TASKS.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
A1
A3
| VAJB B52 Center - Drawing HA100 (BD 8-19-2021) |
| VAJB B52 Center - Drawing HA101 (BD 8-19-2021) |
| VAJB B52 Center - Drawing HA102 (BD 8-19-2021) |
| VAJB B52 Center - Drawing HA103 (BD 8-19-2021) |
File details come from the government source that posted it. Updated .