This is a Performance Work Statement (PWS) for the operation and maintenance of eight NAVAJO Class (T-ATS) towing, salvage, and rescue vessels operated by Military Sealift Command. The contractor shall provide ship officers and crews, operational and technical support both ashore and afloat, equipment, tools, provisions, and supplies to operate, maintain, and repair the vessels. The ships are identified as T-ATS 6 (NAVAJO), T-ATS 7 (CHEROKEE NATION), T-ATS 8 (SAGINAW OJIBWE ANISHINABEK), T-ATS 9 (LENNI LENAPE), T-ATS 10 (MUSCOGEE CREEK NATION), T-ATS 11 (BILLY FRANK JR), T-ATS 12 (SOLOMON ATKINSON), and T-ATS 13 (JAMES D. FAIRBANKS), with delivery dates specified in Section F of the contract.
The contractor must maintain vessels in full operating status (FOS) or reduced operating status (ROS) as directed, with FOS crews working eight hours per day, seven days per week, including holidays. Ships shall be capable of deployment worldwide within 24 hours of notification and must maintain mission readiness at all times excluding scheduled maintenance periods. Key operational requirements include compliance with USCG Certificate of Inspection and American Bureau of Shipping classifications, operation of Global Maritime Distress and Safety System (GMDSS) equipment, maintenance of secure communications systems, and conduct of diving, towing, and salvage operations. The contractor must provide comprehensive hotel services including meals for crew and up to 12 permanently embarked personnel (PEP), medical advisory services available 24/7, communications security management including COMSEC Local Element administration, and maintain detailed records for medical, regulatory, and operational compliance. Fixed-price elements cover crew wages, food services, standard maintenance, and basic hotel services, while port services, industrial assistance, certain repairs, and mission-specific support are reimbursable through invoicing per Section G of the contract.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment 1: T-ATS Performance Work Statement (PWS)
Table of Contents C-1. Operations
C-1.1. General Operations
C-1.2. Shipboard Operations
C-1.3. Hotel Services
C-1.4. Medical Requirements
C-1.5. Communications
C-1.6. Antiterrorism and Physical Security
C-1.7. Manning
C-1.8. Training Requirements
C-1.9. Damage Control Program
C-2. Engineering
C-2.1. Technical Authority
C-2.2. Maintenance Management
C-2.3. Technical Engineering Administration
C-2.4. Fleet Compliance
C-2.5. Life Cycle Engineering
C-3. Contract Administration
C-3.1. General
C-3.2. Shore Facilities
C-3.3. DoDI 5200.48: Controlled Unclassified Information (CUI)and DD Form 254, DOD Contract Security Classification Specification. The requirements in each of the following paragraphs apply to classified material.Information Security Requirements (InfoSec)
C-3.4. Adverse Personnel Security Determinations
C-3.5. Commercial Layberth Contract
C-3.6. Personnel Qualification, Performance, conduct (Shore Side and Afloat)
C-3.7. Changes to the Contractor’s Shore Side Organization
C-3.8. Qualifications for Shore Side Personnel
C-3.9. Training for Shore Side Personnel
C-3.10. Ship Delivery, Delivery of Government Property, and Familiarization
C-3.11. Orientation Visits, and Meetings
C-3.12. Management Control System/Accounting System
C-3.13. Common Access Cards (CAC)
C-3.14. Special Inspection
C-3.15. Financial Audits
C-3.16. Procurement Audits
C-3.17. Reports, Logs and Records
C-3.18. Prohibited Substances and Practices
C-3.19. Alcoholic and Illegal Substance Reporting
C-3.20. Narcotics, Controlled Substances, and Marijuana
C-3.21. Smoking Policy
C-3.22. Sexual Assault and Sexual Harassment Policy
C-3.23. Control of Firearms/Knives
C-3.24. Quality Management System (QMS)
C-4. Budget and Financial Management
C-4.1. Reserved
C-4.2. Annual Operation & Maintenance (O&M) Budget
C-4.3. Directly Funded Items
C-4.4. Budget Management, Reporting, And Audits
C-5. Government Property and Logistics
C-5.1. General
C-5.2. Property Management Overview
C-5.3. Asset Management Requirements and Standards
C-5.4. Life Cycle Logistic Management Requirements and Standards
C-6. Reserved
C-7. Ship / Class Specific
C-7.1. REQUIRED OPERATIONAL CAPABILITIES AND PROJECTED OPERATIONAL ENVIRONMENT
(ROC/POE)
C-1. Operations C-1.1. General Operations The purpose of this contract is to provide for the operation and maintenance of the NAVAJO Class (T- ATS) towing, salvage and rescue vessels. The Contractor shall provide ship officers and crews, operational and technical support ashore and afloat, equipment, tools, provisions and supplies, to operate, maintain and repair the vessels. The Contractor’s organization and business processes in support of this contract, including project management and oversight, crewing, vessel operations, husbanding, purchasing, logistics support, maintenance and lifecycle management, and quality system management, shall be developed and aligned in such a manner as to meet the high operational availability requirements as required by the Fleet and mission sponsors. Throughout the life of this contract, the contractor shall utilize a proactive management approach in support of this program and provide prompt, accurate, and consistent communication with MSC staff.
Scope of Work/Mission The contractor shall operate and maintain NAVAJO Class (T-ATS) towing, salvage and rescue vessels (hereinafter ship or ships) identified in C-1.1.2.1. The ships shall be operated in a professional manner and maintained in good operable condition. Ships shall also be mission-ready at all times (excluding scheduled maintenance, repair, and overhaul periods.) The contractor shall operate the ships and related ship systems and equipment in accordance with (IAW) all relevant laws and the terms of this contract. The contractor shall operate the ships and related ships systems and equipment IAW United States Coast Guard (USCG) and American Bureau of Shipping (ABS) rules and regulations that would apply as if it is owned by a non-government entity, which includes but is not limited to maintaining a valid USCG Certificate of Inspection (COI) and ABS Classifications (including all statutory certificates) at all times. Additionally, the contractor shall obtain and maintain the certificates listed in C-1.1.2.2.
The Government reserves the right to increase or decrease the number of vessels at any time during the performance period under this contract subject to the mutual agreement of the parties. The contractor shall plan, schedule, coordinate, and assure effective completion of all services described herein. All mechanical, electrical, automation, structural, corrosion control and auxiliary systems shall be maintained at an acceptable level throughout the contract performance period. The contractor is responsible for performing scheduled and unscheduled maintenance and repairs, as necessary, on a 24-hour, 7-day basis.
Crews will report to constructing shipyards for familiarization in advance of delivery. The Government will accept delivery of the ships from the shipyard upon completion of construction. The Government with then deliver the ships to the company for contract operation. Following delivery, the ships will conduct post-delivery tests & trials (PDT&T) in Gulf of America and vicinity of Norfolk, VA. The ships will each complete a Post-Shakedown Availability (PSA) before deploying to the fleet. NAVAJO Class vessels are employed worldwide to support towing, salvage, and rescue missions as defined in C-7. The first four ships are scheduled to deploy to the Far East, US West Coast, and one to the Middle East operating area.
C-1.1.1.1. C-1.1.1.2List of Ships
List of eight NAVAJO Class ships. Anticipated delivery dates for these vessels can be found in Section F of the contract:
Hull Ship Name
T-ATS 11 BILLY FRANK JR
T-ATS 6 NAVAJO
T-ATS 12 SOLOMON ATKINSON
T-ATS 7 CHEROKEE NATION
T-ATS 13 JAMES D. FAIRBANKS
T-ATS 8 SAGINAW OJIBWE ANISHINABEK
T-ATS 10 MUSCOGEE CREEK NATION
T-ATS 9 LENNI LENAPE
C-1.1.1.2. Certificates The following List of Certificates for NAVAJO class vessels is provided as a sample. Specific dates for each vessel will be provided at award or upon ship delivery.
Certificate and/or document Regulatory Body
Certification Periodicity
I. USCG – INSPECTION and TITLING Certificate of Inspection [1.2] USCG Annual
5 Year Certificate of Ownership: (Registry for Public vessels) [1.1] USN Once
Continuos Synopsis Record (CSR) : >500 tons, international voyages. Ref: SOLAS XI-1, Reg. 5 [2.15] USCG Contract
Commencement
II. CLASS – CONSTRUCTION & MACHINERY
Certificate of Classification: [1.3] ABS Annual
5 Year Cargo Gear Certificate (annual): [4.21] ABS Annual International Load Line (ILL): [1.5] ABS Annual
5 Year Cargo Gear Statement of Fact ABS Register of Lifting Appliances ABS Voluntary Safety Management Certificate ABS Vessel General Permit SOF ABS Bollard Pull Certificate ABS Dynamic Positioning System (ABS Approved)
a) DP Operations Manual
b) DPS-2 FMEA
c) DPS PSTP
ABS
d) Wartsilla Technical Manual
III. SOLAS
Cargo Ship Construction (SOVC SLC): [3.0] ABS Annual
5 Year Cargo Ship Safety Equipment: (SOVC HSSC SLE): [4.0] ABS Annual
5 Year Cargo Ship Radio (SOVC - HSSC SLR): [5.0] ABS Annual
5 Year Declaration of shore base maintenance (GMDSS): [5.5] ABS Agent 5 Year EPIRB Hydrostatic Release EPIRB Registration (SOVC): [4.4] NOAA 2 Year VDR & S-VDR Annual Performance Certificate: [4.8] ABS Agent Annual Life Rafts Hydrostatic Release Life Raft Inspection Certs (Annual): [4.13] USCG Agent Annual Safety Equipment Form SOLAS Training Manual ABS Certificate of Deadweight ABS Certificate of Admeasurement [CG-1414] USCG RHIB/HSL Wire Certificates: [4.11] ABS 5 Year Rescue Boat Inspection Certificates: [4.14] ABS Annual
IV. MARPOL
International Oil Pollution Prevention (SOVC OPPC):
[2.3] ABS 5 Year
International Sewage Pollution Prevention (SPPC SOVC): [2.12] ABS 5 Year
International Air Pollution Prevention (SOVCAPP): [2.4] ABS 5 Year International Energy Efficiency Certificate (IEEC) SOVC Shipboard Oil Pollution Emergency Plan (SOPEP): [2.9] USCG 5 Year Oil Content Meter Calibration-Engine Room.
Ref: MEPC 107(49), new installations 01 JAN 05 or later.
[2.8]
USCG Agent Annual
Garbage Management Plan Garbage Record Book Oil Record Book - Deck Oil Record Book - Engine Anti-Fouling System SOVC ABS USCG Vessel Response Plan USCG Ballast Water Management SOVC ABS MARPOL I / 37.4 - SUPSALV Letter
V. ISM
Safety Management Certificate (SMC): [2.0] ABS Annual
5 Year Document of Compliance (DOC): [2.2] ABS Annual
5 Year Document of Vessel Compliance (SQE): [2.0] ABS Annual
5 Year
VI. DAMAGE CONTROL
Annual Firefighting Equipment Certificate/CO2/Fire&Smoke/Portable: [4.15 and 4.16] ABS Agent Annual
Record of Safety Equipment ABS Fire Control Plan ABS Main Space Fire Doctrine MSC FOAM analysis Certificate: 4.19] ABS Agent Annual SCBA Air Compressor (Air Sample) Certificate: [4.17] ABS Agent Annual
VII. USCG SPECIAL PERMITS & Dangerous Goods (as applicable)
RESERVED
VIII. OTHER
Ship Sanitation Control Exemption Certificate (SOVC):
(Medical – semiannual, not req’d for exclusive CONUS) [2.18]
USN 6 months
Compass Deviation Card: [4.5] Vessel Annual
Information Technology (IT) Site Approval to Operate
(ATO)
Vessel Security Plan
IX. PERMANENT DOCUMENTS
Ship Radio Station Authorization 47CFR 80.13 (non-public vessels) FCC
International Tonnage Certificate: [1.6] ABS Certificate of Sanitary Construction: 21CFR 1240.20 & 21CFR1250.20. All vessels, interstate traffic: [2.17] USPHS FDA
OWS Type Approval Letter: (refs 46CFR162.050 and MEPC 60 (33) or MEPC 107 (49)) : [2.] (ER/PR) USCG
OWS Content Meter Type Approval Letter Ref: MEPC 60 (33) or MEPC 107 (49): [2.6 and 2.7] USCG
ABS Record of Equipment for the Cargo Ship Radio Certificate (Form R): [5.1] ABS
ABS Record of Approved Cargo Ship Safety Equipment (Form E): lists lifeboat rafts buoys davits, extinguishers, etc (SLE Record): [4.1]
ABS
Stability Letter: As per 46 CFR170.20, no stability letter is required if the information can be placed on the COI or the Load Line Certificate. [3.1]
USCG
Trim & Stability Book MSC Suez Canal Special Tonnage Certificate: [1.8] Suez Canal Panama Canal Special Tonnage Certificate: [1.9] Panama
Canal
C-1.1.1.3. Directives The contractor shall comply with the COMSCINST 3121.9 (series), The U.S. Navy’s Military Sealift Command Standard Operating Manual (SOM) and directives referenced in this contract. In cases where the SOM, directives, and this Contract conflict, the contractor shall notify the COR, and the Operational Commander immediately.
Operational Control (OPCON) Operational control of the ships covered under this contract is normally exercised by a designated operational commander who may or may not be the cognizant MSC Area Commander. The contractor shall comply with Operational Commander's and MSC Area Commander’s operational control direction.
If there is a conflict between the Operational Commander and the MSC Area Commander then the contractor shall follow the direction of the Operational Commander. In exercising command authority commanders are not authorized to make changes to the scope of the contract. If compliance will result in expenses that will exceed available funding obligated to the contract, then the Contractor shall obtain preapproval IAW section G-7, prior to incurring the expense.
The contractor shall comply with all anti-terrorism/force protection (AT/FP) and other security requirements for the ships while at sea and in port that the Operational Commander requires MSC ships follow. Expenses incurred in performance of meeting AT/FP and other security requirements will be reimbursable when the contractor obtains contracting officer approval prior to incurring the expense. If a situation arises which prevents the operator from complying with mission tasking, the contractor shall immediately notify the Operational Commander and provide an information copy to COMSC and the cognizant MSC Area Commander.
The Operational Commander or Area Commander will obtain clearances to call at foreign ports for each ship. Each operational mission will be the subject of a classified Operational Order (OPORD) or Sailing Order (SAILORD) that specifies exactly how the mission will be accomplished. The contractor shall comply with all direction and instructions in OPORDs. The Master is authorized to make minor deviations from sailing orders to meet mission requirements, provided the Master immediately notifies all commands within the operational chain of command of the deviation.
The contractor shall immediately report any delay of any ship and/or diversions from operations to the Operational Commander.
C-1.1.2.1. Tactical Control (TACON) OPCON authority includes TACON, which is the detailed and local direction and control of ship movements necessary to accomplish the missions and is normally delegated to the cognizant MSC Area Commander or office by the Operational Commander. The command exercising TACON will issue sail orders IAW the established ship schedules. The contractor shall comply with all sail orders. However, the Master is authorized to make minor deviations from sailing orders to meet mission requirements, provided the Master immediately notifies all commands within the operational chain of command of the deviation.
C-1.1.2.2. Administrative Control (ADCON) Administrative control of the ship will be exercised by the Program Management (PM) Office, Military Sealift Command Headquarters (MSC HQ).
Area of Operations The contractor shall plan to operate the ships worldwide. At time of solicitation issuance the ships are under construction. Anticipated delivery dates are noted in C-1.1.2.1. but subject to change. Initial operation plans are noted in C-1.1.4.1. Both the ship and equipment are designed for extended, independent underway operations in remote geographic areas. Therefore, self-sufficiency in operations and maintenance is an important mission objective.
C-1.1.3.1. Vessel Operating Areas These vessels will operate worldwide. For planning purposes and without guarantee, following delivery, PDT&T, and PSA, the Government anticipates operating one vessel in the Far East, three vessels in Eastern Pacific (two off of US West Coast and one out of Hawaii), one vessel in the Middle East (hubbed in Bahrain), and three vessels the Atlantic (off of US East Coast). Deviations from projected ship operational locations shall not be the basis for adjustment to the Contract price.
Concept of Operations:
At commencement of Contract performance and throughout the performance period of this contract, it is anticipated all of the ships will be operated as indicated in C-1.1.4.2. However, the Government may direct ships to be placed into a Full Operating Status (FOS), Reduced Operating Status (ROS), Repair Availability Status (RAV) at any time and offerors shall account for this risk in their pricing.
C-1.1.3.2. Operating Tempo (OPTEMPO) Normal OPTEMPO for each ship in FOS is based on its geographic location. The below percentages do not include vessels transits to/from CONUS to deploy or conduct maintenance:
Underway DP/Loitering 65% Underway Transit Speed (~ 12 kts) 15%
In Port On generator 5% In Port On shore power 15%
Actual OPTEMPO may vary for any of the ships. The vessels shall be capable of deployment to worldwide locations within 24 hours of notification by the Operational Commander designated by the U.S. Navy.
Underway periods shall consist of independent steaming, towing / salvage / diving operations, convoy operations, transit to/from selected locations and ports for vessel operations, maintenance, bunkering, or for salvage equipment discharging/loading operations.
C-1.1.3.3. General Operations The contractor shall ensure that the ship(s) and all equipment, systems, and appurtenances are continuously maintained in good working order and repair regardless of the frequency or importance of use.
In case of emergency, nothing in this Contract shall be construed as preventing the Master from taking the most effective action to safeguard life, property and the ship. The Master will have authority to abort operations temporarily on the basis of clear and present danger to life at sea, and shall inform the OPCON with an information copy to COMSC and the cognizant MSC Area Commander. The Master shall provide a written report of the action taken, rationale, and recommendations as soon as possible. Under normal operating conditions the Master shall not take any mission-aborting action without the prior approval of the OPCON.
C-1.1.3.3.1. Crew Maintenance Overtime The contractor shall electronically submit a ship's force work list for each ship, for the upcoming month, no later than five business days prior to the end of the current month IAW Section Error! Reference source not found., Monthly Budget Status Report. The contractor shall submit the ship’s force work list to the COR and include the following minimum information within it:
A prioritized list of repairs and other corrective maintenance actions that each ship intends to accomplish during the upcoming month (regularly scheduled Shipboard Automated Maintenance Management (SAMM) PM tasks are not to be included in this list). This list shall be generated using the open ship’s force (SF) and Voyage Repairs (VR) items in each ship's SAMM Repair Module.
A cost estimate of additional maintenance overtime hours or additional crew (if any), by work item, required to perform each task with clearly stated justifications for incurring the additional costs.
An estimate of any industrial assistance (IA) costs associated with completing any proposed corrective maintenance tasks with clearly stated justifications for incurring the additional costs.
If requested by the COR, for each task requiring overtime (OT) or additional ship's force, the contractor shall include a cost comparison demonstrating that the estimated costs for additional OT or personnel is lower than the estimated costs associated with subcontracting IA to perform the identical work. All assumptions and calculations used in the cost comparison are to be clearly identified.
The contractor shall not incur OT listed above without COR approval.
If additional OT, ship's force, or IA is requested for the upcoming month, the contractor shall obtain COR approval and funding confirmation.
C-1.1.3.4. Full Operating Status (FOS) The Government estimates that the ships will spend the majority of the time fully manned in FOS status during the Contract performance period. Actual in port and underway percentages may vary. During FOS, contractor shall conduct at sea operations 24 hours a day, seven days a week. The contractor shall crew ships in FOS with crew in accordance with Section C-1.7.1.1. FOS crews shall work eight hours per day, seven days a week, including national holidays (overtime incurred during this time shall be part of the fixed price). The contractor shall maintain the FOS crew twenty-four hours a day, seven days a week.
C-1.1.3.5. Reduced Operating Status (ROS)
The Government does not expect to place any of the ships in ROS.
However, for ships directed into ROS; the Government estimates that the ships may spend a majority of the time in ROS status with reduced manning during the Contract performance period. This status includes time spent in shipyard availabilities in ROS/ RAV status. ROS OPTEMPO typically consists of 100% in port operations (pier side or on dry dock). The contractor shall man ships in ROS with crew according to Section C-1.7.1.1. Contractor ROS crews shall work eight hours per day, five days a week (these hours shall be part of the fixed price). The contractor shall maintain a duty watch of two mariners (one engine and deck watch stander of which one shall be a licensed officer) on weekends and holidays.
When ship is directed to transition to FOS, an activation notice will be issued by MSCHQ.
C-1.1.3.6. Ships in ROS The contractor shall work within the approved budget to maintain the ships in a mission ready state and be able to transition to FOS within the applicable reactivation timeframe. If additional funding is necessary, the contractor shall make formal request to the Government with intent and justification prior to executing maintenance work. The contractor shall ensure that the ship(s) and all equipment, systems, and appurtenances are continuously maintained such that the ROS to FOS transition schedule can be met in a cost-effective manner. The contractor shall perform scheduled and unscheduled maintenance actions and repairs necessary to maintain mission readiness, safety, environmental protection, regulatory compliance, or the reactivation schedule. The contractor shall follow its standardized transition plan to meet established milestones for transitioning to FOS. The contractor shall perform maintenance and repair planning in a manner that provides shipboard readiness and seamless transitions.
Perform Maintenance and Repairs (ROS) The contractor shall use ship's force to accomplish all maintenance and repairs that are customarily accomplished by the ships’ crew within the industry.
C-1.1.3.7. Ship Transition – ROS to FOS During the ROS to FOS transition period, the contractor shall indoctrinate all assigned crewmembers concerning a ship’s operation and mission as described in Section C-1.1.2 – Scope of Work/Mission. All ROS crewmembers assigned to a ship upon its activation shall sail with the ship in FOS for a minimum of 30 days or for the duration of the activation, whichever is less. The contractor shall ensure consumable stores and provisions on an activated ship are sufficient for the intended voyage. When directed by the Government, the contractor shall arrange for bunkers. The contractor shall prepare the ship for departing its lay berth and getting underway at the end of the ROS to FOS activation period. Then contractor shall proceed as ordered. The contractor shall not be paid the per diem FOS rate until the first non-ROS crew member has arrived onboard the ship and has been onboard the ship for at least one calendar day. The contractor will notify the COR and Contracting Officer once the first non-ROS crew member has arrive onboard the ship. The contractor will reduce the FOS per diem rate, when invoicing, based on the number of FOS crew that have not arrived onboard the ship.
C-1.1.3.8. ROS – FOS – RAV Transition Requirements The contractor shall submit a transition plan that states the actions, in chronological order, the contractor will take to prepare a ship for transition from ROS to FOS, FOS to ROS, and FOS or ROS to RAV and provide an explanation of what each action entails.
Transition to FOS: For ships in ROS at time of award, the transition plan shall be submitted to the COR within 30 days of award. Otherwise, transition plans shall be submitted to the COR within 30 days of notification of the intent to place a ship in FOS. Transition plans shall include the contractor’s internal administrative functions and detailed explanations of the actions needed to carry out the plan. The transition plan, shall include a checklist that contractor shall submit daily throughout the activation that indicates status of the following ship systems:
Full crew aboard IAW terms of contract Review of physical security, bomb threat procedures completed by Master Small arms and ammunition aboard Reviewed pertinent instructions of MSC Area Command under whose TACON ship will be Assignments made for FOS crew to fire bill and lifeboat stations Ensure crewmembers provided with ship familiarization briefing upon arrival Arrangements made for disconnecting shore water and electric power hoses/cables Watch schedules posted Line handlers, tugs and pilots arranged Provide crew list to MSC Rep, and identify ROS crew All navigational equipment, including radars, satellite navigation, RDF, fathometer, and speed log tested and operational Required charts for mission onboard All communications equipment tested and operational including bridge to bridge VHF All cranes tested satisfactorily Anchors walked clear of hawse and returned to stowed position Adequate fuel aboard or bunkering arrangements made for next port Anchor and navigation lights verified operable Ship’s whistles, bell, and gong tested (local regulation permitting) Test mooring winches Certified Lifejackets (required number onboard) Test lifeboat/rescue boat lowering motors Check gyro repeaters against master gyro Test general announcing system/loud hailers Ensure all ship’s clocks synchronized Communications guard shift, weather routing, and mail routing messages sent All hand-held radios and sound powered communications tested and operational Test general alarm Medical supplies onboard, distributed in first aid or medical lockers as required all expiration dates shall be validated
Ensure all IA materials are removed from ship or stowed clear of cargo stowage areas Main engine(s) fully operational Controllable Pitch Propeller (CPP) system operational and tested satisfactorily (If applicable) 95% capacity potable water aboard Ship’s service generators on line and fully operational Emergency diesel generator tested satisfactorily Steering engines, alarms, and rudder angle indicators tested satisfactorily from bridge and after steering Shipboard chemicals aboard sufficient for the duration of voyage and intact, unexpired (check with OEM as necessary)" Dehumidifier hoses removed from equipment as necessary Starting air, control air, and ship’s service air system functioning properly CO sensor systems tested satisfactory Lube oil purifying system on line and fully operational Main engine throttles tested satisfactory.
Bridge, Engine Room, Local Test bridge alarm system Ensure P/S main circulating pumps/motors controllers fully operational Test fire main system Validate all damage control equipment Bilges and equipment surfaces free of lube oil and fuel oil All required flange spray shields properly installed on oil systems Test main console alarm systems Charts and pubs for intended voyage are onboard Galley/ hotel services equipment fully functional Operate Mission related Deck Equipment
Transition to ROS: A transition plan to transition a ship from FOS or RAV to ROS shall be submitted to the COR within 30 days of award. Transition plans must be updated to the COR, engineering type desk and GPE(s) within 30 days of notification of the intent to place a ship in ROS. Transition plans shall include the contractor’s internal administrative functions and detailed explanations of the actions needed to carry out the plan. This is to include the following administrative or logistics verifications:
ROS crew aboard IAW terms of contract Review of physical security, bomb threat procedures completed by master Small arms and ammunition aboard Reviewed pertinent instructions of MSC Area Command under whose TACON ship will be Assignments made for ROS crew to fire bill and lifeboat stations Ensure crewmembers provided with ship familiarization briefing upon arrival Arrangements made for connecting shore water and electric power hoses/cables
Watch schedules posted Line handlers, tugs and pilots arrangement plans for weather or security events Provide crew list to MSC Rep, and identify ROS crew Navigational Charting updates (ECDIS and/or paper) Certified Lifejackets (required number onboard) Communications guard shift, weather routing, and mail routing messages sent Medical supplies onboard, distributed in first aid or medical lockers as required all expiration dates shall be validated Shipboard chemicals aboard sufficient and unexpired for the duration of ROS period Damage control equipment
The transition plan must include daily, weekly, and monthly system operability tests of the following ship systems:
All navigational equipment, including radars, satellite navigation, RDF, fathometer, and speed log
ECDIS
All communications equipment including bridge to bridge VHF Cargo and stores handling cranes Adequate fuel aboard or bunkering arrangements made for expected duration Anchor and navigation lights Ship’s whistles, bell, and gong (local regulation permitting) Mooring winches Lifeboat/rescue boat lowering motors Gyro repeaters against master gyro General announcing system/loud hailers Ship’s clocks synchronization All hand-held radios and sound powered communications tested and operational General alarm and bridge alarm system Main engine(s) dock tests Controllable Pitch Propeller (CPP) system potable water system Ship’s service generators and switchboard automatic and manual functions Emergency diesel generator Steering engines, alarms, and rudder angle indicators from bridge and after steering Starting air, control air, and ship’s service air system CO sensor systems tested satisfactory Lube oil purifying system Main engine throttles from all control stations (Bridge, Engine Room, Local) Seawater and cooling water pumps/motors controllers Fire main system Bilges and equipment surfaces free of lube oil and fuel oil
All required flange spray shields properly installed on oil systems Test main console alarm systems Galley/ hotel services equipment fully functional Mission related Deck Equipment
The transition plan must include procedures to deenergize, layup, or secure ship systems to include:
Dehumidifier hoses Hot air layup Desiccant bags Freshwater layup and changeout of condensers and tanks Systems to be drained, cleaned, and dried
C-1.1.3.9. Repair Availability (RAV) For ships in a RAV status, contractor crews shall work a minimum of seven (7) days a week [including national holidays (overtime incurred during this time shall be part of the fixed price)], ten (10) hours per day, which shall be included in the contractor’s firm fixed price. The contractor shall provide a deck officer onboard the ship who shall make hourly rounds, twenty-four (24) hours a day, including weekends and holidays. Contractor crews shall maintain and operate ship equipment in support of the RAV and IAW C.
Weather Operations C-1.1.4.1. Weather Information and Ship Routing IAW COMSCINST 3121.9 (series), Standard Operating Manual (SOM), and prior to ship’s departure, the Master shall include in the MOVREP a request for the Naval Oceanography Centers to provide Optimum Track Ship Routing (OTSR). Routes assigned by the OTSR via formal naval message program are in the form of recommendations to the ship Master. Ship’s routing information provided by the cognizant MSC Area Command or COMSC shall be considered the same as receiving OTSR by Navy Meteorological and Oceanography Command recommendations. All restrictions and/or delays due to weather shall be logged in the ship’s deck log and include OTSR message identifiers and/or other justifications.
C-1.1.4.2. Severe and Destructive Weather Plan The contractor shall maintain and implement the Severe Weather Procedures IAW Operational Commanders’ guidelines and COMSCINST 3121.9 (series), Standard Operating Manual (SOM), for all ships. For ships in ROS, Government will authorize additional manning to support underway sorties scheduled to commence within 48 hours from receipt of the order. When a hurricane condition is set in the area of operations (AOR), and any ship is in port or underway within the storm-related area, contractor shall submit an initial hurricane status report for all ships within one hour of notification of the condition being set. In addition, contractor shall request OTSR IAW Section C-1.1.4.1 above. The Master shall request OTSR program routes during severe and destructive weather conditions.
Notification calls from the cognizant MSC Area Command or COMSC will be considered the same as receiving formal notification via naval message including Optimum Track Ship Routing (OTSR).
C-1.1.4.3. Weather Monitoring At all times, the contractor shall ensure the ships use all means at their disposal to continually monitor and maintain situational awareness of current and forecast weather conditions. The contractor shall ensure that all ships utilize all means at their disposal to ensure the safety of the vessel during all weather conditions. The contractor shall ensure that all duty personnel make themselves familiar with the prevailing and forecasted weather conditions for the duration of their shift.
Port Services The Government will furnish port services or reimburse the contractor for actual costs of port services IAW Section G. Port services include but are not limited to tugs, pilots, berthing, potable water, feed water, shore power, spill-booms, docking, trash and garbage removal, oily waste removal, sewage removal, hazardous materials removal, line handlers, shore services, and launch services. The contractor may use Government services or commercial for port or agent services. If utilization of Government contracts for agent or port services will adversely impact the mission of the ship(s), then the contractor may obtain such through commercial means, with prior COR approval. The contractor shall exercise due diligence to obtain the fairest and most reasonable port services and shall notify the Contracting Officer if such charges appear excessive prior to the ship entering port. As a part of the budgeted amount for port services, the Government will reimburse canal tolls, port/local dues and taxes (provided the contractor exercises due diligence in seeking on behalf of the Government immunity from such dues and taxes pursuant to contract section C-1.1.9.1.1), entering/leaving port fees, customs broker fees, ballasting or shifting berths pursuant to Government orders and any other similar port charges for ports visited at the Government's direction. The contractor shall submit separate invoices for each port call, along with the supporting documentation. The Government will reimburse the contractor for costs of port services associated with supporting Sponsor mission operations including but not limited to supporting all Sponsor requested work, when preapproved by the COR. The Government will not reimburse the contractor for expenses incurred by the contractor for services rendered for the convenience of the ship or the contractor, its crew, or in connection with the contractor's business such as the fees of underwriters.
Diplomatic Clearances The Government will obtain diplomatic clearances, operational area clearances, and explosive event waivers when and where required. The Government will secure port visit clearances.
Husbanding Agent Appointments The Government will reimburse the contractor, IAW Section G, for the customary fee paid to port husbanding agents in conjunction with the port visits of the ships, including the fees of agents appointed for canal transits and at bunkering ports IAW Section G. The Government may disapprove proposed agents and require the contractor discontinue using an agent. The Government shall have the option of directing the contractor to use a specific commercial or Government agent in any port for the reimbursable elements.
Ship’s Operations C-1.1.8.1. Government Ships in Foreign Ports
The contractor shall comply with the following requirements while docked, anchored or transiting foreign waters Outside Continental United (OCONUS):
Sovereign Immunity While performing ship operations, the contractor shall ensure the Master advises foreign authorities and husbanding agents that each vessel under this Contract is a sovereign immune vessel of the United States. These privileges include immunity from arrest or search (whether in foreign internal or territorial waters, or in international waters), immunity from foreign taxation, exemption from any foreign state regulation requiring flying the flag of such foreign state either in its ports or while passing through its territorial sea, and entitlement to exercise exclusive control over persons on board such vessels with respect to acts performed on board. The contractor shall observe all guidelines found in NAVADMIN 158/16, Sovereign Immunity Policy, ALMSC 020/06 Sovereign Immunity Guidance for MSC Masters, and ALMSC 026/09, Supplemental Sovereign Immunity Guidance, all of which shall be provided upon Contract award. The contractor shall contact the Area Command for the area of operations (AO) should any foreign authority or husbanding agent request information (submission of documents or completion of forms) contrary to the US Navy and MSC sovereign immunity policies.
Foreign Law Enforcement Masters shall refuse requests from foreign authorities for documents, physical evidence, interviews of personnel, statements, any request to board, examine, inspect, or search a ship, and any request for the physical delivery of persons on a ship to foreign authorities. The requirements in this paragraph are in addition to the requirements in FAR 52.229-6 Foreign Fixed-Price Contracts, and any other applicable FAR clauses incorporated into this contract.
Foreign Port Visits The Master may provide a Shore Party List of individuals who will go ashore to the host nation before granting liberty if such a list is requested. The Shore Party List may contain only the names and passport numbers of those personnel. The contractor or its employed Master shall not provide any other information. Masters shall comply with applicable U.S. and host nation agreements, such as Status of Forces Agreements (SOFA), that specify specific procedures for port visits in that country.
Casualty, Incident, Injury and Weekly Status Reporting The contractor shall ensure all casualties, incidents and injuries (or death) are reported IAW Navy Regulations via naval message IAW COMSCINST 3121.9 (series), Standard Operating Manual (SOM), and format of NWP 1-03.1 (series), and notification provided to the COR as provided below. The contractor shall ensure all casualties, incidents and injuries (or death) are reported to the USCG as required by 46
CFR 4.05.
C-1.1.9.1. Casualty Report (CASREP) The contractor shall report all mechanical, structural, electrical or equipment casualties in the Navy standard format of a CASREP IAW NWP 1-03.1 (series). Contractor’s Navy message format reports shall consist of the initial CASREP and shall be followed by updates and a final correction (CASCOR) of the casualty. If a casualty is mission degrading(C-3/C-4), contractor shall report it within 12 hours of occurrence. If a casualty is not mission degrading but cannot be corrected within 48 hours, contractor shall report it not later than 24 hours after the occurrence. IAW COMSCINST 3121.9 (series), Standard Operating Manual (SOM), CASREP reports shall be included in a Defense Readiness Report System for Navy vessels (DRRS-N), established by NTRP 1-03.5, (series) to assess a unit's ability to accomplish their assigned mission(s) and essential tasks associated with those missions.
C-1.1.9.2. Special Incident Reporting The contractor shall inform the USCG of “special incidents” in accordance with USCG regulations (e.g.
USCG form 2692). The contractor shall report all accidents or occurrences resulting in damage by the ship or to the ship. Additionally, contractor shall report all damage to gear or cargo, injury to person(s), and loss of life IAW COMSCINST 3121.9 (series), Standard Operating Manual (SOM). Reportable incidents include, but are not limited to collision, stranding, grounding, foundering, heavy weather damage, fire, explosion, failure of gear and equipment, and any other damage affecting the seaworthiness of the ship.
C-1.1.9.3. Marine Casualty Investigations The contractor shall report all marine casualties IAW 46 CFR 97 and MSC/USCG Memorandum of Agreement. If the Coast Guard investigates casualties, then the contractor shall provide the Contracting Officer, COR, and ABS with the USCG Casualty Investigation Report and all correspondence regarding the marine casualty investigation no later than two business days from receipt of the investigation report.
C-1.1.9.4. Weekly Ship Status Report The contractor shall submit a weekly email summary to the COR and/or other Program personnel as directed using the Weekly Ship Status Report template, which will be provided after award.
Emergency Sorties Emergency sorties may be required by the ship’s Operational Commander at any time the Government determines such a sortie is appropriate (i.e., to avoid hazardous weather). If compliance will result in expenses that will exceed available funding obligated to the contract, then the Contractor shall obtain preapproval IAW section G-7, prior to incurring the expense.
Reserved
Design Speed Trials The contractor shall conduct periodic speed trials to demonstrate ship(s) are able to obtain design speed. Speed trials are to be conducted (1) Every six months; (2) First opportunity following hull cleaning or propeller polishing; and (3) When directed by Numbered Fleet Commander, Squadron Commander, or MSC. The contractor shall submit to the contracting officer and COR a completed copy of the Design Speed Trials Report. The template for the report will be per SAMM test memorandums.
Salvage/Rescue Assistance The contractor shall immediately notify COMSC, the local MSC Area Commander and COR when any ship suffers a casualty or becomes disabled at sea. The contractor shall comply with the guidance provided in COMSCINST 5420.2 (series).
C-1.1.13.1. Rescue Assistance Report In the event of a rescue assistance situation, the contractor shall submit a Salvage or Rescue/Assistance Request in accordance with the provisions of NWP 1-03.1 (series). The contractor shall submit this report in conjunction with any CASREP and Reports of Required Emergency Repairs. At a minimum contractor shall include the following in the report:
Ship Location Weather Conditions Description of casualty, including cause and action being taken by the crew to control damage Type of assistance required As applicable, this report shall also include:
o Draft forward and aft prior to casualty o Draft forward and aft after casualty o Amount of potable water, ballast, and bunkers on ship by tanks, and ruptured, distorted, or otherwise disrupted strength members o Type of bottom, if aground o Range of tide and time of next tide, if aground
Diver support The contractor shall request and receive the approval of the COR prior to utilizing diver services.
Cargo Operations C-1.1.15.1. Material Handling Equipment (MHE) The Contractor shall operate the MHE IAW manufacturer’s instructions and ensure safe operating conditions and peak efficiency. Cargo cranes shall be operated IAW ABS Cargo Registry requirements.
C-1.1.15.2. Government Stevedore Damage Damage by military or Government-provided stevedore Contractors to ships or ships’ equipment during load or discharge operations shall be repaired at the Government’s expense. The contractor shall report this damage on MSC FORM 5880/1 to the local MSC Representative on scene, Contracting Officer, COR, and shall also provide additional investigative assistance when directed by the Contracting Officer.
Upon approval, the Contractor shall take necessary action to correct the stevedore damage which will be reimbursable.
Explosives Handling The contractor shall stow and handle explosives and ammunition, including pyrotechnics, IAW USCG regulation, 49 CFR parts 171 through 176 and applicable Navy requirements set forth in: OPNAVINST 8023.2C (series), U.S. Navy Explosives Safety Policies, Requirements, and Procedures, OP 1810, Ordnance Equipment Handling and Shipping Instruction, OP 3347, U.S. Navy Ordnance Safety Precautions, and NAVSEA OP 3221, Loading and Stowage of Military Ammunition and Explosives Aboard Break Bulk Merchant Ships.
Post and Maintain Sailing Board The contractor shall post and maintain a Sailing Board in accordance with its prevailing labor agreements. The exact sailing time shall be coordinated with the Operational Commander.
Set Sea Detail The contractor shall comply with administrative requirements and procedures for entering U.S. and foreign ports that are included in COMSCINST 3121.9 (series), Standard Operating Manual (SOM).
During anchoring operations and sailing and arrival operations, the contractor shall set and man a sea detail which shall consist of, at a minimum, one licensed deck officer and one unlicensed deck department crewmember assigned to the anchor detail, and one unlicensed crewmember from both the deck and engine departments assigned to the steering gear room.
Maneuvering The contractor shall require the ship Master’s presence on the bridge when docking or undocking the ship; when entering or leaving port; when maneuvering in close waters or near other ships, or at any other time when conditions are such that the possibility of danger warrants his presence on the bridge.
Ship Crew List The contractor shall maintain a current crew list for each ship. This list shall include the mariner's name, position, license held, security clearance level, and training. The contractor shall submit to the COR, a crew list upon each change of Master and Chief Engineer.
Reserved Provisions of Assessments and Studies
Upon government demand, the contractor shall provide specialized technical or IA to perform studies and/or assessments of prepositioning matters that include, but are not limited: to feasibility of calling potential ports, capability of vessel(s) performing certain types of cargo operations, root cause analyses, failure analysis, and the ability of the vessel(s) to perform unique missions. Any direct costs beyond those otherwise in the fixed rate shall require prior approval of the Contracting Officer.
Provide Mission Support The contractor shall provide support to the Sponsor to meet mission requirements. Such support may be required on a 24-hour basis with the understanding that STCW requirements may preclude 24-hour operations for extended periods of time. Overtime incurred because of these efforts is reimbursable in accordance with G-7.
C-1.1.23.1. Conduct Diving, Towing, & Salvage Operations The contractor shall operate the ships in support of assigned diving, towing, and salvage operations.
Operations shall be conducted in accordance with applicable laws & regulations, Navy & MSC policy and instructions, QMS & SMS procedures, vessel operation manuals, and current United States Navy Towing and Salvage Manuals.
The contractor shall have two experienced and accomplished Towing & Salvage Subject Matter Experts (SME) who are responsive and available globally to support planned and emergent operations. These SMEs shall provide the expertise needed to support the day-to- day activities and operational support to ship’s crews and embarked Mobile Diving and Salvage Unit (MDSU), SUPSALV and other mission sponsors as required. The support required includes but is not limited to; rigging and executing planned and emergent open-ocean tows, tow and be-towed exercises with fleet assets, de-beaching (training and real-world) of grounded or stranded vessels, salvage of submerged equipment or aircraft recoveries at sea, Dynamic Positioning (DP) and multi-point mooring, liaison support for the Supervisor of Salvage Deep Ocean Salvage Systems, Oil Spill Response systems and Undersea Rescue Command (URC) embarkations onboard NAVAJO Class T-ATS ships.
Salary for the two Towing & Salvage Subject Matter Experts shall be included in the daily charter rate.
Required travel requires COR approval and travel per diem shall be reimbursable in accordance with G-
7. Upon request and with COR approval additional support may be authorized.
Comprehensive Tow Plan.
The contractor shall submit a comprehensive tow plan to COR for approval one (1) to two (2) days prior to the start of a towing mission. Utilize Attachment S, which is the approved format of plan.
Towing Performance Report.
The contractor shall submit a towing performance report to COR within five (5) calendar days after completion of tow mission. Utilize Attachment T, approved format of plan.
C-1.1.23.2. Installation & Removal of Mission Equipment Different missions will require Government provided equipment to be installed and/or removed. The contractor shall provide support for installations, removals, and restorations in accordance with C-2.
Support will be reimbursed by the Government IAW Sections C-2.5.7 (Industrial Assistance), and Section G (Invoicing Requirements).
C-1.1.23.3. Maintenance & Operation of Installed Mission Equipment Government provided mission equipment may be maintained and operated by embarked mission personnel. Otherwise, installed mission equipment shall be maintained and operated by ship’s crew.
Responsibility for maintenance and operation shall be established during mission planning and installation.
C-1.1.23.4. Sponsor Directed Work Mission sponsors may require additional support from crew to perform missions. Any support requests not defined in this contract shall be reviewed and approved by the COR prior to undertaking of work.
C-1.1.23.5. Hazardous Material Handling and Disposal of Sponsor Materials Sponsor’s mission equipment may include hazardous material. Ship’s crew shall assist Sponsor to ensure proper stowage and handling of Sponsor hazardous material. All Sponsor hazardous material shall be managed in accordance with C-2.3.13.1 and applicable regulations.
C-1.1.23.6. Post Delivery Tests & Trials (PDT&T) Following new construction ship delivery and prior to the Post Shakedown Availability/fleet deployment, each ship will have a PDT&T period. During the PDT&T, the ship and crew will test & demonstrate the ship’s mission capabilities. During this period, the crew will train and develop proficiency on the various missions as well as help refine the operating procedures based on lessons learned.
C-1.1.23.7. Provide Special Project Support
Assigned missions may require project support not anticipated or defined in this contract. If this occurs, the contractor shall present the matter to the COR and shall not undertake work without prior COR approval.
C-1.1.24. Provisions of Assessments and Studies Upon government demand, the contractor shall provide specialized technical or IA…