This is a Scope of Work specification document for Section 260505—Selective Demolition for Electrical, part of project 25-388 CBI HVAC and Lighting Upgrade. The document outlines requirements for electrical demolition work including the removal, relocation, and extension of existing electrical installations to accommodate new construction. Specific work includes disconnecting and removing electrical systems in walls, floors, and ceilings; removing abandoned wiring and conduit; disconnecting and removing abandoned outlets, panelboards, distribution equipment, and luminaires; and handling hazardous materials such as PCB-containing equipment, DEHP-containing ballasts, and mercury-containing lamps. The specification requires coordination with utility companies for service outages and mandates that contractors maintain existing electrical, fire alarm, and telephone systems in service during construction, with service outages minimized and occurring only during switchovers and connections.
The specification requires contractors to verify field measurements and existing conditions before beginning demolition work, reporting any discrepancies to the Owner and Architect. Contractors must obtain Owner permission at least 24 hours before disabling any systems and provide temporary wiring and connections to maintain service in adjacent areas. All work must comply with federal, state, and local regulations regarding hazardous materials, including the Federal Toxic Substances Control Act (TSCA). Contractors are responsible for repairing any adjacent construction and finishes damaged during demolition and extension work, maintaining access to active electrical installations, and extending existing installations using compatible materials and methods. The document does not specify contract pricing, award dates, term duration, or renewal options.
View the file
Other files
Show all 43
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
25-388 CBI HVAC and Lighting Upgrade 260505 - 1 Selective Demolition for Electrical
SECTION 260505
SELECTIVE DEMOLITION FOR ELECTRICAL
PART 1 GENERAL
1.01 SECTION INCLUDES
A. Electrical demolition.
PART 2 PRODUCTS
2.01 MATERIALS AND EQUIPMENT
A. Materials and equipment for patching and extending work: As specified in individual sections.
PART 3 EXECUTION
3.01 EXAMINATION
A. Verify field measurements and circuiting arrangements are as indicated.
B. Verify that abandoned wiring and equipment serve only abandoned facilities.
C. Demolition drawings are based on casual field observation and existing record documents.
D. Report discrepancies to Owner before disturbing existing installation.
E. Report discrepancies to Architect before disturbing existing installation.
F. Beginning of demolition means installer accepts existing conditions.
3.02 PREPARATION
A. Disconnect electrical systems in walls, floors, and ceilings to be removed.
B. Coordinate utility service outages with utility company.
C. Provide temporary wiring and connections to maintain existing systems in service during construction. When work must be performed on energized equipment or circuits, use personnel experienced in such operations.
D. Existing Electrical Service: Maintain existing system in service until new system is complete and ready for service. Disable system only to make switchovers and connections. Minimize outage duration.
1. Obtain permission from Owner at least 24 hours before partially or completely disabling system.
2. Make temporary connections to maintain service in areas adjacent to work area.
E. Existing Fire Alarm System: Maintain existing system in service until new system is accepted.
Disable system only to make switchovers and connections. Minimize outage duration.
1. Notify Owner before partially or completely disabling system.
2. Make notifications at least 24 hours in advance.
3. Make temporary connections to maintain service in areas adjacent to work area.
F. Existing Telephone System: Maintain existing system in service until new system is complete and ready for service. Disable system only to make switchovers and connections. Minimize outage duration.
1. Notify Owner at least 24 hours before partially or completely disabling system.
3.03 DEMOLITION AND EXTENSION OF EXISTING ELECTRICAL WORK
A. Perform work for removal and disposal of equipment and materials containing toxic substances regulated under the Federal Toxic Substances Control Act (TSCA) in accordance with applicable federal, state, and local regulations. Applicable equipment and materials include, but are not limited to:
1. PCB-containing electrical equipment, including transformers, capacitors, and switches.
2. PCB- and DEHP-containing lighting ballasts.
25-388 CBI HVAC and Lighting Upgrade 260505 - 2 Selective Demolition for Electrical
3. Mercury-containing lamps and tubes, including fluorescent lamps, high intensity discharge (HID), arc lamps, ultra-violet, high pressure sodium, mercury vapor, ignitron tubes, neon, and incandescent.
B. Remove, relocate, and extend existing installations to accommodate new construction.
C. Remove abandoned wiring to source of supply.
D. Remove exposed abandoned conduit, including abandoned conduit above accessible ceiling finishes. Cut conduit flush with walls and floors, and patch surfaces.
E. Disconnect abandoned outlets and remove devices. Remove abandoned outlets if conduit servicing them is abandoned and removed. Provide blank cover for abandoned outlets that are not removed.
F. Disconnect and remove abandoned panelboards and distribution equipment.
G. Disconnect and remove electrical devices and equipment serving utilization equipment that has been removed.
H. Disconnect and remove abandoned luminaires. Remove brackets, stems, hangers, and other accessories.
I. Repair adjacent construction and finishes damaged during demolition and extension work.
J. Maintain access to existing electrical installations that remain active. Modify installation or provide access panel as appropriate.
K. Extend existing installations using materials and methods compatible with existing electrical installations, or as specified.
END OF SECTION