This document is Division 1 of the General Requirements Specifications for a new U.S. Courthouse in Hartford, Connecticut, a design-build project estimated at 281,000 gross square feet. The General Services Administration (GSA) Public Buildings Service is procuring comprehensive site development, design, and construction services. The specifications establish administrative and procedural requirements across 28 sections covering project management, quality assurance, submittals, scheduling, safety, commissioning, and closeout procedures. Key deliverables include a Critical Path Method (CPM) schedule with cost-loading and resource allocation, Building Information Modeling (BIM) with Common Data Exchange (CDX) and Construction Operations Building Information Exchange (COBie) data, construction progress documentation with photographic records, submittal procedures through the GSA Project Management Information System (PMIS), and comprehensive operation and maintenance documentation. The Design-Build Contractor must maintain a full-time project superintendent, safety and health officer, and BIM coordinator; conduct partnering meetings and pre-construction conferences; provide temporary facilities and utilities; and comply with sustainable design requirements per the Energy Independence and Security Act (EISA) 2007 and Energy Policy Act (EPAct) 2005, including ASHRAE 90.1-2019 baseline compliance with 30 percent improvement where life-cycle cost effective.
Quality control requirements mandate a Construction Quality Control Plan with three-phase control (preparatory, initial, and follow-up), independent testing agency services for structural work and air barrier systems, and commissioning of all systems prior to beneficial occupancy. The contractor must provide warranty management, record documents including marked-up drawings and specifications, as-built BIM models, final cleaning to commercial standards, and demonstration and training of operations personnel. Payment procedures require a Schedule of Values cost-loaded CPM schedule submitted within 30 days of Notice to Proceed, with monthly progress payments based on approved schedule updates. Substantial Completion requires completion of punch-list items, Final Acceptance requires submission of all closeout documentation and COBie deliverables, and warranty periods begin upon project acceptance. The specifications emphasize interface management for government-furnished equipment integration, early access coordination for IT systems, protection of existing artwork and vegetation, construction indoor air quality (IAQ) management with flush-out or pre-occupancy air quality testing, and building enclosure commissioning to verify air barrier continuity and performance.
View the file
Other files
Show all 26
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIVISION 1 - GENERAL REQUIREMENTS
TABLE OF CONTENTS
SECTION
01 11 00 Summary of Work 01 14 00 Work Restrictions 01 21 00 Allowances 01 23 00 Alternates 01 24 00 Options 01 25 00 Substitution Procedures 01 26 00 Contract Modification Procedures 01 27 00 Unit Prices 01 30 00 Project Management Information Systems (PMIS) 01 31 00 Project Management and Coordination 01 31 10 Critical Path Method (CPM) Scheduling for Prospectus Projects 01 32 00 Construction Progress Documentation 01 32 20 Photographic Documentation 01 33 00 Submittals 01 36 00 Construction Operations Building Information Exchange (COBie) 01 40 00 Quality Assurance & Quality Control Requirements 01 40 25 Quality Control Testing for Air Barrier Systems 01 40 50 System Quality Control 01 41 00 Structural Testing Laboratory Services 01 42 00 General References 01 50 00 Temporary Facilities and Controls 01 51 00 Artwork Protection 01 56 39 Tree and Plant Protection 01 59 30 Security Regulations 01 59 50 Safety and Health 01 60 00 Product Requirements 01 70 00 Execution Requirements 01 73 10 Cutting and Patching 01 73 20 Selective Demolition 01 73 50 Fire Prevention Precautions for Hot Work 01 74 10 Construction Indoor Air Quality (IAQ) Management 01 77 00 Closeout Procedures 01 78 10 Project Record Documents 01 78 22 Operation and Maintenance Documentation 01 78 25 Building Information Modeling (BIM) with CDX & COBie National Standard 01 81 11 Sustainable Design Laws 01 82 00 Demonstration and Training 01 91 13 General Commissioning (CX) Requirements
01 91 19 Building Enclosure Commissioning
Division 1 Specifications FY26 DRAFT U.S. General Services Administration New U.S. Courthouse Hartford, CT Public Buildings Service Project No.: 000000373 Office of Architects and Engineers
Office of Program and Project Management
DRAFT
Division 1 Specifications FY26 DRAFT U.S. General Services Administration New U.S. Courthouse Hartford, CT Public Buildings Service
SECTION 01 10 00 – SUMMARY
PART 1 GENERAL
1.1 PROJECT INFORMATION
A. Project Name and Location
New U.S. Courthouse. Hartford, CT.
B. Project Summary Description
The U.S. General Services Administration (GSA), Public Buildings Service (PBS) is seeking a highly qualified Design-Build Firm to provide comprehensive site development, design and construction services for a new U.S. Courthouse in Hartford, CT. The proposed new courthouse is estimated to have a maximum total area not to exceed 281,000 gross square feet of office, storage, and special use space. The site selection for a new project site has been completed. The site consists of a 2.19 acre parcel located at 180 Allyn Street in Hartford. The new facility is to be designed to accommodate all court functions, specifically up to 11 total courtrooms, and up to 18 separate chambers, US District Court and US Bankruptcy Court judges. The design shall reflect the judiciary’s intent for a collegial chambers layout, locating judges’ chambers in close proximity to one another with shared reference and conference spaces to promote collaboration and operational efficiency among the court units. The facility will also house the US District Clerk, US Bankruptcy Clerk, the US Probation and Pretrial Services Offices, and the US Marshals Service (USMS).
C. Design Build (DB) Contractor:
The DB is the prime contractual entity and Designer of Record (DOR) responsible for the proper execution of the work. Responsibility for accuracy and completeness of the final design, delivering high-quality construction, and demonstrating functional performance of all systems lies solely with the DB. Reference to the DB and DOR (regarded as one entity) are used interchangeably. “Contractor,” “DB Contractor,” “DB team,” or “DB” may be used throughout this text with the same meaning.
D. Project Delivery Method:
Design Build
E. Construction Manager Agency (CMa):
AECOM
F. Partnering Consultant
Partnering Facilitator is provided by AECOM
1/13/2026 SUMMARY 011000 Page 1 of 316
G. Commissioning Provider (CxP):
AECOM
H. GSA Contracting Officer (CO)
Douglas Tumbrello
J. GSA Project Manager (PM)
Joseph Mulligan
K. Building Manager (BM)
Derek Lata
L. Contracting Officer’s Representative (COR)
Ryan Haley
1.2 WORK BY OTHER CONTRACTORS
A. The Contractor shall cooperate with other contractors performing related work, including providing labor, materials and other costs necessary to satisfactorily coordinate the Contract work with work performed under other contracts. Work by others includes Government contractors.
1.3 MISCELLANEOUS PROVISIONS
A. Alterations to Existing Conditions: Existing conditions shall be cut, drilled, removed, temporarily removed, or removed and replaced, as necessary for performance of Work under the Contract and in conformance with Health and Safety requirements outlined in Section 015950 - Safety and Health. Existing conditions that are out of alignment (incomplete or substandard) and where exposed by removal of existing work shall be noted and brought to the attention of GSA. Necessary corrective work shall be as directed.
1. Replacements of existing conditions that are removed shall match similar existing conditions.
2. Unless otherwise indicated, existing structural members shall not be cut or altered without authorization by the Contracting Officer.
3. Conditions remaining in place, which are damaged or defaced during the Work, shall be restored to the condition existing at time of award of Contract.
4. Discolored or unfinished surfaces exposed by removal of existing conditions, that are indicated to be final exposed surfaces, shall be refinished or replaced as necessary to produce uniform and harmonious contiguous surfaces.
1/13/2026 SUMMARY 011000 Page 2 of 316
B. Existing structures shall remain in place.
1. See requirements for existing sewer line relocation. The sewer line's new location and easement are to be determined during the design phase.
C. Existing utility services with related meters and equipment shall remain in place.
The DB Contractor is to contact the utility companies directly. See partial list below:
Table 1 Existing Utility Infrastructure
Utility (Provider)
Allyn Street Church Street High Street
Water
(MDC)
12" Main, laid in 1911 16" Main, laid in 1854-5 6" domestic service, laid in
1854-5
24" main, laid in
Combined Storm/Sewer (MDC) slopes/drains east 15" tile, grade 1.5% to 18" tile, grade 0.5% slopes/drains south 72" PVC lined RCP, grade 0.08% slopes/drains south
24" brick 72" PVC lined
RCP,
grade 0.08%
Gas (CT Natural Gas)
6" MDPE Main 4" MDPE Main 6" Main (potentially abandoned, TBC)
Electrical Power (Eversource)
Three-phase, underground
Three-phase, underground
Three-phase, underground
Communications (varies) Underground (Frontier & Comcast
Xfinity)
Underground (Frontier & Verizon)
Underground (Frontier & Comcast
Xfinity)
Steam (Hartford Steam Company)
None 8" Steam within 18" conduit
None
Chilled Water (Hartford Steam Company)
None (2) 18" within 22" jackets
None
1/13/2026 SUMMARY 011000 Page 3 of 316
Table 2
Utility Contact Information
Utility Contacts
MDC Mike Curley Manager of Engineering 555 Main Street Hartford, Connecticut 06103 T: (860) 278-7850 x3445 C: (860) 818-5572 E: mcurley@themdc.com
Jessica Coelho Technical Services Senior Project Manager E: jcoelho@themdc.com
CT Natural Gas Mr. Jonathan Gould Gas Engineer 76 Meadow Street Hartford, CT 06108 O: (860) 727-3044 E: jgould@ctgcorp.com
Eversource
Mr. Orwin Watson Supervisor, Field Engineering Design 410 Sheldon Street Hartford, CT 06106 O: (860) 280-2445 C: (860) 655-7787 E: orwin.watson@eversource.com
Mr. David Noble david.noble@eversource.com
Frontier Ms. Lynne DeLucia Manager - Engineering & Construction 1441 North Colony Road Meriden, CT 06450-4101 O: (203) 238-5000 C: (860) 967-4389 E: Lynne.m.delucia@ftr.com
Verizon (MCImetro)
Steven Brito Outside Plant Engineer Verizon Business Group 1 Gold St Hartford, CT 06103 C: (860) 573-9013 E: steven.brito@verizon.com
1/13/2026 SUMMARY 011000 Page 4 of 316
Comcast Xfinity
Mr. Christopher Simeone Construction Manager CT/NY 222 New Park Drive Berlin, CT 06037 C: (860) 491-6701 E: christopher_simeone@cable.comcast.com
The Hartford Steam Company
Clifton P. Stalph, PMP President and General Manager Hartford Steam Company, LLC A Cartier Energy/Vauban Infrastructure Partners Company Plant: 60 Columbus Blvd, Hartford, CT 06103 Corporate Offices: 77 Hartland Street, East Hartford, CT 06108 C: (860) 798-3328 O: (860) 548-7343 F: (860) 548-7360 E: Cstalph@hartfordsteam.com
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION 01 10 00
1/13/2026 SUMMARY 011000 Page 5 of 316 mailto:christopher_simeone@cable.comcast.com
SECTION 01 14 00 - WORK RESTRICTIONS
1.1 CONTRACTOR USE OF PREMISES
A. Contracting Officer approval of a Site Logistics Plan is required prior to any on-site activity by the Contractor. At a Minimum the Site Logistics Plan shall contain a written and illustrated document that addresses the following sections.
1. Document Existing Conditions surrounding the project premises
2. Indicate Pathways of material and worker travel
B. Review and document the existing conditions surrounding the project premises. Provide documentation to GSA prior to the commencement of any construction activity.
C. The Contractor shall limit use of the premises to the work in areas indicated, and to allow for Government occupancy, and public use, if required.
1. Confine operations at the site to areas indicated in plans. Do not disturb portions of the site beyond the areas in which Work is indicated.
2. Keep driveways and entrances serving the premises clear and available at all times to the Government, Government employees and to visitors. Do not use these areas for parking or storage of materials.
3. Schedule deliveries to minimize space and time requirements for storage of material and equipment on site.
4. Maintain facility operations in a safe and functional condition throughout the construction period. Repair damage caused by construction operations to the satisfaction of the Government. Take precautions to protect the facility, its occupants and the public during the construction period. A representative of the Contractor shall be available to arrive on site within one (1) hour of notice should an emergency occur. See SECTION 01 59 50 - SAFETY AND HEALTH for additional requirements.
5. Keep active roadways and work areas free from accumulation of waste material, rubbish, construction debris and construction materials.
6. Space on the premises will be made available for the Contractor's storage and related activities, provided that its use will not interfere with operations of the Government. Arrange with the GSA, Property Management representative and gain approval for use of this space through the Contracting Officer.
7. Use of the existing site access will be shared with Government activities on a first-come-first-served, wait-your-turn basis.
1/13/2026 WORK RESTRICTIONS 011400 Page 6 of 316
8. Existing materials and equipment that are removed as part of the construction operations, and that are not reused or designated to be salvaged as Government property, shall become the property of the Contractor and shall be removed from the site. Storage or sale of excess salvageable materials and equipment is not permitted on site.
9. Pollution producing equipment shall not be located near air intakes where airborne smoke or fumes could be drawn into buildings. When not required for powering unloading operations, turn off engines when parked.
10. The contractor shall submit a silica work exposure plan that must be sufficient to minimize the release of visible dust and minimize the accumulation of visible airborne dust before commencing construction activities. See SECTION 01 59 50
- SAFETY AND HEALTH for additional requirements.
11. Smoking is not permitted in or around buildings, see Facilities Management Regulation (FMR) Case 2008-102—3. Also see Code of Federal Regulations (CFR) 41 CFR Part 102-74.
12. Limited parking will be available on site during working hours for building occupants. The Contractor and Contractor's employees shall make their own arrangements for vehicle parking off site as necessary.
13. Cell Phones: Contractor is to provide company cell phones to its employees during this contract. Cell phones are only permitted in construction areas and contractor’s office space.
14. No apparatus with an open flame is allowed to be used within the project site without the prior receipt of a burn permit. Burn permits are required for each separate occurrence.
15. Permits: Refer to FAR 52.236-7
16. The work shall be sequenced to minimize disruption to abutters , visitors, and maintenance activities. To the greatest extent feasible, demolition work should not take place until supplies are on hand to perform new work.
17. All facility systems outside the immediate construction area shall be kept fully operational .
18. Protect abutters facilities from flying debris.
19. Protect building site from flying debris.
20. Coordinate with the GSA Contracting officer as to the use of cameras on site.
21. All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may require, in writing, that the DBC remove from the work any employee the Contracting Officer deems incompetent, careless, or otherwise objectionable.
22. The DBC shall, under regulations prescribed by the Contracting Officer, use only established roadways, or use temporary roadways constructed by the DBC when and as authorized by the Contracting Officer. When materials are transported in
1/13/2026 WORK RESTRICTIONS 011400 Page 7 of 316 prosecuting the work, vehicles shall not be loaded beyond the loading capacity recommended by the manufacturer of the vehicle or prescribed by any Federal, State, or local law or regulation. When it is necessary to cross curbs or sidewalks, the DBC shall protect them from damage. The DBC shall repair or pay for the repair of any damaged curbs, sidewalks, or roads. 25. The DBC shall at all times keep the work area, including storage areas, free from accumulations of waste materials. Before completing the work, the DBC shall remove from the work and premises any rubbish, tools, scaffolding, equipment, and materials that are not the property of the Government. Upon completing the work, the DBC shall leave the work area in a clean, neat, and orderly condition satisfactory to the Contracting Officer.
23. The DBC shall coordinate any street closures or restrictions with the City of Hartford and would be impacted property owners.
1.2 GOVERNMENT OCCUPANCY
a. GSA reserves the right to occupy, place, and install equipment in completed areas of the construction prior to Substantial Completion, provided such occupancy does not interfere with completion of the Work. The GSA's installation of equipment and partial occupancy shall not constitute acceptance of the total Work.
i. Upon occupancy, GSA will assume responsibility for maintenance and custodial service for the occupied portions of the work site.
1.3 WORKING HOURS
b. Contractor's General Working Hours: The Contractor working hours shall be generally established to occur 7 AM to 4 PM. d
c. It is contemplated that all work will be performed during the customary working hours of the trades involved unless otherwise specified in this contract. Work performed by the DBC at his own volition outside such customary working hours shall be at no additional expense to the Government.
d. The DBC must conform to all City of Hartford work restrictions, including hours of work, sight pollution, and noise pollution.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION (Not Applicable)
END OF SECTION 01 14 00
1/13/2026 WORK RESTRICTIONS 011400 Page 8 of 316
SECTION 01 21 00 - ALLOWANCES
1.1 RELATED DOCUMENTS
A. GSA is providing the references included in this sub-section for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and general provisions of the Contract, including Federal Acquisition Regulations (FAR) and General Services Administration Acquisition Regulations (GSAR) contract clauses, and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
1. Certain items may be described in the Contract Documents as allowance items.
The purpose of allowance items is to defer selection of actual products and systems to a later date when direction will be provided to the Contractor. Any Allowances included must be part of the total evaluated price and the award amount. Refer to Agreement section 2b and pricing sheet. The Contracting Officer will issue Modifications to incorporate allowance items in the Work after actual products and systems have been determined.
B. Types of allowance items may include the following:
1. Lump-sum allowance items
2. Unit-price allowance items
3. Quantity allowance items
1.3 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise the contracting officer of the date when final selection and purchase of each product or system described by an allowance item must be completed to avoid delaying the Work. Allowances and allowance items must be included in all schedule submissions
1.4 ACTION SUBMITTALS
A. Submit proposals for products or systems described by allowance items in the form specified for Change Orders.
1.5 INFORMATIONAL SUBMITTALS
1/13/2026 ALLOWANCES 012100 Page 9 of 316
A. Submit copies of invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each unit-price and quantity allowance item.
B. Coordinate and process submittals for allowance items in the same manner as for other portions of the Work.
1.6 COORDINATION
A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.
B. Modifications based on an allowance item shall include cost to Contractor of specific products and systems selected by the contracting officer under allowance and shall include taxes, freight, delivery to Project site, Contractor's costs for receiving and handling at Project site, labor, installation, overhead, and profit.
1. If requested by the contracting officer, purchase additional quantities under unit-price or quantity allowances and prepare unused material for storage by the Contracting officer. Deliver unused material to the Contracting officer's storage space as directed.
1.7 ADJUSTMENT OF ALLOWANCE ITEMS
A. Modifications to an allowance item shall comply with the changes clauses and any other contract modifications procedures found in the Contract Documents.
B. Contracting Officer reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance item promptly on delivery for damage or defects. Return damaged or defective products to the manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance item with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCE ITEMS
1/13/2026 ALLOWANCES 012100 Page 10 of 316
A. No Allowance Items Included.
END OF SECTION 01 21 00
1/13/2026 ALLOWANCES 012100 Page 11 of 316
SECTION 01 23 00 - ALTERNATES
1.1 SUMMARY
A. An “alternate” is a defined portion of the Work that is priced separately and provides GSA an option for GSA in determining the final scope of the Project.
B. The amount for an alternate is the total net adjustment to the Base Bid to incorporate the alternate work into the project.
C. Alternate work shall include miscellaneous devices, accessory objects and similar items incidental to or required for a complete installation, whether or not mentioned as part of the alternate description.
1.2 PROCEDURES
A. Selection: Acceptance or rejection of each alternate will be made by GSA prior to award of the Contract, and the Base Bid amount will be adjusted accordingly for accepted alternates to establish the contract price.
B. Coordination: The DB Contractor shall modify or adjust affected work as necessary to completely and fully integrate the accepted alternate work into the project Work.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 SCHEDULE OF ALTERNATES
No Alternates Included.
END OF SECTION 01 23 00
1/13/2026 ALTERNATES 012300 Page 12 of 316
SECTION 01 24 00 – OPTIONS (Coordinate this section with CO and Contract Agreement)
1.1 SUMMARY
A. “Option” means a unilateral right in a contract by which, for a specified time, GSA may elect to purchase additional scope of work, products, materials, equipment, systems or installation methods described in the Contract Documents.
B. The amount for an option is the total adjustment from the Base Bid to incorporate the option work into the project. Enter the total cost of Option No, 1 on the Bid Sheet. Bids are evaluated on the Total of the Base Bid and Option 1.
C. Execution of Option No. 1: The government reserves the right to exercise or not to exercise Option 1. If used, the government will exercise this within 90 days of the Contract Award. The contract days for completion remain unchanged if this Option is exercised.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION
3.1 SCHEDULE OF OPTIONS
No Options Included.
END OF SECTION 01 24 00
1/13/2026 OPTIONS 012400 Page 13 of 316
SECTION 01 25 00 SUBSTITUTION PROCEDURES
1.1 RELATED DOCUMENTS
A. The Government is providing the references included in this subsection for information purposes only and is not intended to provide a comprehensive, all-inclusive list of any and all potentially relevant portions of the Contract Documents. Drawings and general provisions of the Contract and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This section includes administrative and procedural requirements for substitutions.
B. Related Sections:
1. Section 01 21 00 ALLOWANCES for products selected under an allowance.
2. Section 01 23 00 ALTERNATES for products selected under an alternate.
3. Section 01 24 00 OPTIONS for products selected under an option.
4. Section 01 60 00 PRODUCT REQUIREMENTS for requirements for submitting comparable product submittals for products by listed manufacturers.
1.3 DEFINITIONS
A. Substitutions: Proposed changes to the Contract Documents by the Contractor for products, materials, equipment, and methods of construction.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms
2. Substitutions for Convenience: Changes proposed by Contractor or GSA that are not required in order to meet other Project requirements but may offer advantage to Contractor or GSA
1.4 SUBMITTALS:
A. Substitution Requests: Submit electronic copies through PMIS of each request for consideration. Identify product or fabrication or installation method to be replaced.
Include Specification Section number and title and Drawing numbers and titles.
1. Substitution Request Form: Submit requests for substitutions on company
1/13/2026 SUBSTITUTION PROCEDURES 012500 Page 14 of 316 letterhead. Substitutions proposed or indicated on shop drawings and submissions are prohibited and shall be rejected.:
2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by the Government and separate contractors that will be necessary to accommodate proposed substitution.
b. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Include annotated copy of applicable specification section. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, sustainable design characteristics, energy and resource performance goals, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
c. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
d. Samples, where applicable or requested.
e. Certificates and qualification data, where applicable or requested.
f. List of similar installations for completed projects with project name, location and contact information of owner and architect/engineer of record.
g. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
h. Research reports evidencing compliance with building code in effect for the project, when applicable for the proposed substitution.
i. Detailed comparison of Contractor's construction schedule using proposed substitution with products specified for the Work. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery. Provide a schedule fragnet with a time impact analysis to allow the Government to consider the proposed substitution.
j. Cost information, including a proposal of change, if any, in the Contract Sum.
k. Proposed substitution complies with requirements in the Contract Documents except as indicated in the substitution request, is compatible with related materials, and is appropriate for applications indicated.
l. The Contracting Officer may require the Contractor to provide a contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed
1/13/2026 SUBSTITUTION PROCEDURES 012500 Page 15 of 316 substitution to produce indicated results.
3. The Contracting Officer or Contracting Officer’s Representative (CO) or (COR) Action: If necessary, the Contracting Officer or COR will request additional information or documentation for evaluation. The Contractor shall be entitled to receive notice of action on submittals within a reasonable time, given the volume or complexity of the submittals and the criticality of the affected activities to Substantial Completion as may be indicated in the Project Schedule. The Contractor shall not be entitled to receive notice of action on submittals containing variations from Contract requirements in less than twenty working days.
a. Failure by the government to respond does not constitute acceptance of the proposed substitution.
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage qualified testing agencies to perform compatibility tests recommended by manufacturers.
1.6 PROCEDURES
A. Coordination: Modify or adjust affected work as necessary to integrate work of the approved substitutions.
PART 2 PRODUCTS
2.1 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately upon discovery of need for change, but not later than fifteen (15) calendar days prior to time required for preparation and review of related submittals.
1. Conditions: The Contracting Officer (CO) will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, the CO will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. The substitution request is fully documented and properly submitted.
c. If requested substitution involves schedule impact Contractor has identified time impact and a mitigation plan.
d. Requested substitution has received necessary approvals of authorities
1/13/2026 SUBSTITUTION PROCEDURES 012500 Page 16 of 316 having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.
f. Requested substitution has been coordinated with other portions of the Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
i. Source Limitations: To the fullest extent possible, provide products of the same kind from a single source. Equipment of the same function shall be manufactured by the same entity, unless otherwise indicated.
j. Compatibility of Options: When the Contractor is given the option of selecting between 2 or more products for use on the Project, the product selected shall be compatible with products previously selected.
B. Substitutions for Convenience: The Contracting Officer (CO) will consider requests for substitution if received within 30 calendar days of contract award, submittals received after that time may be considered or rejected at discretion of the CO or the COR.
1. Conditions: The CO will consider Contractor's request for substitution when the following conditions are satisfied.
a. Requested substitution offers the Government a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional obligations the Government incurs.
b. Requested substitution does not require extensive revisions to the Contract Documents.
c. Requested substitution is consistent with the Contract Documents and will produce indicated results.
d. The substitution request is fully documented and properly submitted.
e. Requested substitution has received necessary approvals of authorities having jurisdiction.
f. Requested substitution is compatible with other portions of the Work.
g. Requested substitution has been coordinated with other portions of the Work.
h. Requested substitution provides specified warranty.
i. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is
1/13/2026 SUBSTITUTION PROCEDURES 012500 Page 17 of 316 acceptable to all contractors involved.
PART 3 EXECUTION (Not Used)
END OF SECTION 01 25 00
1/13/2026 SUBSTITUTION PROCEDURES 012500 Page 18 of 316
SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES
1.1 PROJECT INFORMATION
Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
The CONTRACT MODIFICATION or Change Order is fundamental to construction contracting as the primary means to modify the contract for construction and is defined as “A written instrument prepared by the CMa (A/E) and signed by the Owner, Contractor, and Architect stating their agreement upon all of the following: 1) the change in the Work; 2) the amount of the adjustment, if any, in the Contract Sum; and 3) the extent of the adjustment, if any, in the Contract Time.” The operative language is that a change order is an “agreement” amongst the parties and, therefore, the terms are settled and become a part of the contract.
A. This Section specifies administrative and procedural requirements for handling and processing contract modifications.
B. There are two primary types of modifications: bilateral, signed by the GC and the CO; and unilateral, signed only by the CO.
C. Related Sections include the following:
1. GSA FY25 01 27 00 UNIT PRICES for administrative requirements for using unit prices.
2. GSA FY25 01 25 00 SUBSTITUTION PROCEDURES for administrative procedures for handling requests for substitutions made after Contract award.
3. GSA FY25 01 31 00 PROJECT MANAGEMENT & COORDINATION
4. GSA FY25 01 21 00 ALLOWANCES
D. Contract Modification Process
1. Initiated by one or more of the following actions:
a. Proposal Request: A proposal request is issued by the CO/CS to the contractor requesting a proposal for a change, or a modification to the scope of the contract and is issued on behalf of the owner, to determine the cost of a change it is contemplating or that may be required to properly perform the Work. [Editor: Refer to SECTION 1.6 PROPOSAL REQUESTS A. Contracting Officer-Initiated Proposal Requests]
b. Architect’s Supplemental Instructions (“ASI”): The ASI is a directive issued by the CMa (A/E) to the contractor providing additional information within the scope of the contract documents or to make minor changes to the work that, in the CMa’s opinion, will not result in an adjustment to the contract sum or time.
1/13/2026 CONTRACT MODIFICATION PROCEDURES 012600 Page 19 of 316
c. Construction Change Directive (“CCD”): A CCD directs the contractor to immediately commence additional work or to implement a change to the work. This tool may be used where GSA and contractor have not agreed on proposed changes in the contract sum or time, or to direct changes in the work which, if not expeditiously implemented, might delay the project. It is important to understand, however, that while a CCD directs work and binds the contractor to perform such work, the modifications to the scope, cost and time still must be incorporated into the contract by change order.
d. Request for Information (“RFI”):
e. Request for a Change Order: A Change Order Request is a proposal issued by the contractor either as a self-initiated claim, or in response to a proposal request, RFI or ASI if, in the Contractor’s opinion, the RFI or ASI modifies the scope of the Contract. [Editor: Refer to SECTION 1.6 PROPOSAL REQUESTS B. Contractor-Initiated Proposals]
2. Contractor Submits a Change Order Proposal
a. The contractor will submit to the CMa its proposal documenting the cost and time impact of the proposed change.
b. It is an important duty of the CMa to carefully review the contractor’s proposal and advise the CO of its reasonableness. Most important is to confirm that the contractor is not asserting a claim for work that is already required of the Contract Documents and is not including costs such as general conditions and overhead that are included in the OH&P percentage, or for other work already contracted for.
c. Additionally, the CMa will consider the proposed impact on cost and time and will analyze the schedule logic, and assess whether the proposed schedule impact is reasonable. In reviewing the impact on time, the CMa will consider a number of factors, including:
i. Does the proposed change impact the schedule’s critical path?
ii. Could the contractor mitigate delays by adjusting other activities?
iii. Are there concurrent delays that are already the responsibility of the contractor?
If the CO does not fully agree with the contractor’s proposal, the CO must respond in writing to the contractor, detailing its reasons, and then endeavor to reach mutually agreeable terms with the contractor.
3. Change Order Finalization
Once all parties agree, the CMa prepares the change order. The description of the change should be clear, succinct, and complete. It should be adequate for a third-party to generally understand the change and its impacts. There are three parts to the description that coincide with the definition of the change order – the scope, the impact on cost, and the impact on time. For the scope, the change
1/13/2026 CONTRACT MODIFICATION PROCEDURES 012600 Page 20 of 316 order should reference the specific Contract Documents that are to be changed as well as the documents prepared and issued by the A/E that describe and detail the change. For the cost and time, the change order should state the contractor’s proposed change to the contract sum and contract time, referencing its proposal.
After describing the change and the impacts on the contract sum and time, the change order should list any attachments, including each of the supporting documents, with the date of each. Upon completing the change order form, the CMa will compile all attachments and issue with the change order.
4. Change Order Issuance
Once the change order is finalized, it is signed first by the contractor and then by the CO.
1.3 CONTRACT MODIFICATION PROCESSING SYSTEM
A. The CMa should establish a contract modification processing system consistent with GSA’s procedures and regulations and “modify this SECTION accordingly before issuance”. The system must encompass potential, ongoing, and completed contract modifications and encompass the following:
1. Defining the roles and responsibilities of the parties involved
2. Identifying, evaluating, and justifying the need for modifications
3. Defining the scope of modifications
4. Tracking modifications through a numbering system
5. Prescribing all steps necessary to process modifications
6. Listing all required documents and forms
7. Identifying cost impacts of modifications on the project budget
8. Establishing time impacts of modifications on the project
1.4 CHANGES IN THE WORK
A. The Contracting Officer or designated representatives are the only entities authorized to direct work or change the contract.
1.5 MINOR CHANGES IN THE WORK
A. The Contracting Officer or his/her designated representative as directed by GSA will issue supplemental instructions authorizing Minor Changes in the Work, not involving adjustment to the Contract Sum or the Contract Time.
1.6 PROPOSAL REQUESTS
1/13/2026 CONTRACT MODIFICATION PROCEDURES 012600 Page 21 of 316
A. Contracting Officer-Initiated Proposal Requests
The Contracting Officer or designated representative will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications. Proposal Requests issued by Contracting Officer or designated representative are for information only. Do not consider them instructions either to stop work in progress or to execute the proposed change.
1. Within fifteen (15) calendar days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
B. Contractor-Initiated Proposals
If latent or unforeseen conditions require modifications to the Contract, the Contractor may propose changes by submitting a request for a change to the Construction Manager Agency (CMa).
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change.
Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Submit a complete cost proposal and TIA as outlined above for Contracting Officer- initiated changes. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Proposal Request Form: Sample Change Request Submitted by Contractor [DOCX -
19 KB]
4. Materials and Equipment: Materials incorporated in Work at Contractor's actual invoice cost, including freight but excluding sales tax. Indicate rates and units required.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting
1/13/2026 CONTRACT MODIFICATION PROCEDURES 012600 Page 22 of 316 https://sites.google.com/gsa.gov/project-management-pm-hub/sop-and-tools-library/resources-tools/pm-guide/change-order-management https://sites.google.com/gsa.gov/project-management-pm-hub/sop-and-tools-library/resources-tools/pm-guide/change-order-management an extension of the Contract Time.
6. Comply with requirements in SECTION 01 25 00 SUBSTITUTION PROCEDURES if the proposed change requires substitution of one product or system for product or system specified.
7. Overhead and Profit: The DBC and Subcontractors will be allowed up to 20 percent of the net change in cost for work performed by their own forces to account for both overhead and profit. The allowance for the overhead includes, but is not limited to, costs for: estimating; field supervision above the foreman level, general foreman, superintendents, assistant superintendents, engineers, accountants, timekeepers, schedulers, office managers, and others on staff;
office supplies; drinking water; temporary heat, temporary cooling, light and power; field toilets; small tools; dumpsters; record documents; home office costs;
and other materials and/or equipment unless specifically allowed by the change order scope of work.
a) DBC Overhead and Profit on First Tier Subcontractors and Suppliers: The DBC will be allowed up to 10 percent of the net cost of change order work provided by first tier Subcontractors.
b) First Tier Subcontractor Overhead and Profit on Second Tier Subcontractors and Suppliers: First tier subcontractors will be allowed up to 10 percent of the net cost of change order work provided by second tier Subcontractors and suppliers.
c) Second Tier Subcontractor Overhead and Profit on Third Tier Subcontractors and Suppliers: No allowance for overhead and profit on subcontracted work will be made for subcontractors and suppliers below the second tier.
d) Example: In the case of work provided by a third (or lower) tier subcontractor, the subcontractor providing the work will be allowed up to 20 percent of the net change in cost for work performed by its own forces to account for both overhead and profit. The DBC and the first tier subcontractor would each be allowed up to 10 percent of the net cost of the change order work. The total markup for overhead and allowance paid by the Government would not exceed 40%.
1.7 ADMINISTRATIVE CHANGE ORDERS
A. Allowance Adjustment: Refer to SECTION 01 21 00 - ALLOWANCES for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances.
B. Unit-Price Adjustment: Refer to SECTION 01 27 00 UNIT PRICES for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect measured scope of unit-price work.
1.8 CONTRACT MODIFICATION PROCEDURES
A. On Contracting Officer's approval of a Proposal Request, the CMa will issue a Contract modification (Change Order) for signatures of Contracting Officer and the Contractor on
1/13/2026 CONTRACT MODIFICATION PROCEDURES 012600 Page 23 of 316
CO Template [XLSX - 84 KB] SF30.
1. If the change order is on a T&M basis or is directed by GSA at a not to exceed amount. The contractor must submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract upon completion of the work.
B. A Copy of fully executed contract modification will be maintained by CMa and record copies will be distributed by the CMa to the A/E, Contracting Officer (original), and DBC.
1.9 SUPPLEMENTAL AGREEMENT (BILATERAL)
A. In a Supplemental Agreement, the SF30 must be signed by both contractual parties; an authorized representative of the DBC and the CO. Sufficient lead time is needed to execute a supplemental agreement for negotiations and funding of the change order.
1.10 CHANGE ORDER WITH PRICE-TO-BE-DETERMINED-LATER PDL (UNILATERAL)
A. A PDL is used when the SOW has been established and a proposal obtained from the DBC, but the necessity to proceed with the change does not permit time to negotiate the proposal and/or reach agreement on cost and time. Issuance of this type of change order requires preparation of an SF30 that describes the SOW, indicates the change is being made on a PDL basis, and states the not-to-exceed amount. The change document requires only the signature of the CO. CONSTRUCTION CHANGE DIRECTIVE
A. Once a contract is awarded, its requirements can only be adjusted by issuing a contract modification, signed by the CO. It is important that the contract modification process be understood by all project management personnel. Although FAR clauses associated with modifications may be periodically updated, the current construction contract on each project governs the modification process for that project.
B. Construction Change Directive contains a complete description of change in the Work. It also designates the method to be followed to determine change in the Contract Sum or the Contract Time.
C. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.
D. After completion of change, the contractor shall submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
1.11 CHANGE ORDER-- UNILATERAL DIRECTION
E. The construction contract clause, GSAM 552.243-71, Equitable Adjustments, allows the CO to determine the price of a change order if agreement is not reached with the GC.
F. In a unilateral change order, the government sets the cost and time adjustments for an
SOW.
G. Once issued, a unilateral change is subject to the provisions of the construction contract clause FAR 52.233-1, Disputes, and the GC can pursue final settlement. In this process, the GC is required by contract to perform the changed work pending resolution.
H. Payment of a unilateral change order amount is made as the related work is performed.
1/13/2026 CONTRACT MODIFICATION PROCEDURES 012600 Page 24 of 316 https://sites.google.com/gsa.gov/project-management-pm-hub/sop-and-tools-library/resources-tools/pm-guide/change-order-management
1.12 ADMINISTRATIVE CHANGE (UNILATERAL)
This type of change is used to amend the contract provisions when the modification does not alter the specified contract work, the contract time, or the performance cost.
1.13 PENDING CHANGE LOG PCL
When a pending change issue arises, the Project Team shall assign a tracking number, referred to as CE (Cost Event or Change Event) numbers. Pending change issues include:
A. A Request for Proposal (RFP) issuance
B. A claim is received from the Contractor
C. An action occurs that may require modification of the contract The pending change numbers should be used to identify all further correspondence and documents pertaining to the issue. Proposal requests and the status of the corresponding issues can be tracked in the Project Management Information System by the Project Team, or a Proposal Record SF1520 can be used.
1.14 TRACK CONTRACT MODIFICATIONS
The CO must ensure the contract modification is established in accordance with the General Services Administration Acquisition Manual (GSAM) 504.7001-4.
PART 2 PRODUCTS (Not Used)
END OF SECTION 01 26 00
1/13/2026 CONTRACT MODIFICATION PROCEDURES 012600 Page 25 of 316
SECTION 01 27 00 UNIT PRICES
A. Unit price is defined in the Agreement. Unit prices shall be specified, in both words and figures, for each item for which a quantity is provided. Unit prices, without exception, shall be net bid and contracted for, unless otherwise noted or specified, and shall include full compensation for all materials, transportation, fees, equipment, tools, labor, incidental work, overhead and profit necessary to complete the item to the satisfaction of the Government.
1.1 PROCEDURES
A. Measurement: Method of measurement for each unit price is specified in the section applicable to the work.
B. Verification: The Government reserves the right to reject the Contractor's measurement of work in place that involves use of an established unit price, and to have this work measured at the Government's expense by an independent surveyor.
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 UNIT PRICE ITEM SCHEDULE
A. Unit Price Item No. 1:
N/A
1. Description:
N/A
END OF SECTION 01 27 00
1/13/2026 UNIT PRICES 012700 Page 26 of 316
SECTION 01 29 00 - PAYMENT PROCEDURES
1.1 SUMMARY
A. This Section specifies administrative and procedural requirements necessary to prepare and to process Requests for Payment.
1.2 DEFINITIONS
A. Schedule of Values: A detailed written statement (masterformat/uniformat) furnished by the Contractor outlining the portions of the contract sum, which allocates values (price & percentage) for the various parts of the work and used as the basis for payment application and reviewing progress payments. The Agreement provides further details.
B. Request for Payment: A contractor’s invoice and request for progress payment with substantiating information consistent with approved schedule of values.
1.3 SCHEDULE OF VALUES
A. This contract requires the use of a cost-loaded Critical Path Method (CPM) Schedule. The information required for the Schedule of Values (SOV) shall be entered as an integral part of the schedule. Within 30 calendar days of notice to proceed, prepare and deliver to the Contracting Officer a SOV reflecting a detailed breakdown of the contract price, giving quantities for each of the various kinds of work, unit prices, and extended prices. Costs must be summarized, and totals provided for each construction category.
B. Coordination: Submit a complete Schedule of Values integral with the Contractor’s CPM Schedule. Reference additional information in Section 013110 – Critical Path Method (CPM) Scheduling.
This is the start of the file's text. The full file is on GovTribe.