26 08 00.pdf

PDF 13 KB Posted

Attached to
TINKER AFB MAC BOA WWYK200323 REPAIR HVAC DIFFUSER AND DUCTWORK B3001
Solicitation number
WWYK200323-P
Issued by

About this file

This document is a technical specification for Section 26 08 00 - Apparatus Inspection and Testing related to a federal contract opportunity at Tinker AFB in Oklahoma. The key details are:

The technical specification outlines the requirements for acceptance testing and inspection of electrical equipment and systems, including diesel generators, medium voltage cables, grounding systems, automatic transfer switches, and low-voltage switchgear. It requires the contractor to engage a qualified independent testing organization with a minimum of 5 years' experience to perform the required inspections and tests per NETA standards. The contractor must submit qualifications of the testing organization and lead technician, as well as test plans and reports for government approval. Final system acceptance is contingent on satisfactory completion of the acceptance tests and inspections.

The related federal contract opportunity is a repair project for HVAC diffuser and ductwork at Tinker AFB, which is only open to Tinker AFB MAC BOA holders. The estimated price range is between $1,000,000 and $5,000,000, and it is set aside for small businesses. A mandatory site visit is required for MAC BOA prime contractors to be considered responsive.

View the file

Other files

File Type Posted
Attachment 1 EAL List - BLANK to Contractor_WWYK200323 .xlsx XLSX spreadsheet
32 13 11.pdf PDF
23 82 01.pdf PDF
07 72 20.pdf PDF
08 11 13.pdf PDF
23 08 01.00 20.pdf PDF
08 33 23.pdf PDF
23 05 48.00 40.pdf PDF
10 44 16.pdf PDF
26 05 48.00 10.pdf PDF
01 33 16.00 10.pdf PDF
06 61 16.pdf PDF
23 25 00.pdf PDF
Tinker General Req Specs Nov22ChLog.pdf PDF
23 64 26.pdf PDF
07 41 13.pdf PDF
03 30 00.pdf PDF
26 28 01.00 10.pdf PDF
40 17 26.00 20.pdf PDF
06 20 00.pdf PDF
07 31 13.pdf PDF
23 05 15.pdf PDF
09 29 00.pdf PDF
21 13 13.pdf PDF
07 52 00.pdf PDF
07 62 13.pdf PDF
000 TABLE OF CONTENTS.pdf PDF
200323_Submittal Register.pdf PDF
23 82 43.00 40.pdf PDF
00 70 00.pdf PDF
32 01 17.pdf PDF
03 11 13.00 10.pdf PDF
03 20 00.00 10.pdf PDF
31 23 06.pdf PDF
09 72 00.pdf PDF
13 48 00.pdf PDF
04 20 00.pdf PDF
23 31 13.00 40.pdf PDF
08 52 00.pdf PDF
08 51 13.pdf PDF
32 92 23.pdf PDF
10 28 13.pdf PDF
23 81 23.pdf PDF
32 11 23.pdf PDF
01 45 00.00 10.pdf PDF
05 40 00.pdf PDF
07 53 23.pdf PDF
10 26 00.pdf PDF
23 11 25.pdf PDF
23 57 10.pdf PDF
Show 40 more

Latest 50 of 183 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ti nker AFB, OK TAFB Techni cal Spr ci f i cat i ons 2019

SECTI ON 26 08 00

APPARATUS I NSPECTI ON AND TESTI NG

04/17

PART 1 GENERAL

1. 1 REFERENCES

The publ i cat i ons l i s t ed bel ow f or m a par t of t hi s speci f i cat i on t o t he ext ent r ef er enced. The publ i cat i ons ar e r ef er r ed t o wi t hi n t he t ext by t he basi c desi gnat i on onl y.

I NTERNATI ONAL ELECTRI CAL TESTI NG ASSOCI ATI ON ( NETA)

NETA ATS ( 2013) St andar d f or Accept ance Test i ng Speci f i cat i ons f or El ect r i cal Power Equi pment and Syst ems

1. 2 RELATED REQUI REMENTS

Sect i on 26 00 00. 00 20 BASI C ELECTRI CAL MATERI ALS AND METHODS appl i es t o t hi s sect i on wi t h addi t i ons and modi f i cat i ons speci f i ed her ei n.

1. 3 SUBMITTALS

Gover nment appr oval i s r equi r ed al l submi t t al s. Submi t t he f ol l owi ng i n accor dance wi t h Sect i on 01 33 00 SUBMI TTAL PROCEDURES:

SD- 06 Test Repor t s

Accept ance t est s and i nspect i ons

SD- 07 Cer t i f i cat es

Qual i f i cat i ons of or gani zat i on, and l ead engi neer i ng t echni c i an

Accept ance t est and i nspect i ons pr ocedur e

1. 4 QUALI TY ASSURANCE

1. 4. 1 Qualifications

Cont r act or shal l engage t he ser vi ces of a qual i f i ed t est i ng or gani zat i on t o pr ovi de i nspect i on, t est i ng, cal i br at i on, and adj ust ment of t he el ect r i cal di st r i but i on syst em and gener at i on equi pment l i s t ed i n par agr aph ent i t l ed " Accept ance Test s and I nspect i ons" her ei n.

Or gani zat i on shal l be i ndependent of t he suppl i er , manuf act ur er , and i nst al l er of t he equi pment . The or gani zat i on shal l be a f i r st t i er subcont r act or . No wor k r equi r ed by t hi s sect i on of t he speci f i cat i on shal l be per f or med by a second t i er subcont r act or .

a. Submi t name and qual i f i cat i ons of or gani zat i on. Or gani zat i on shal l have been r egul ar l y engaged i n t he t est i ng of el ect r i cal mat er i al s, devi ces, i nst al l at i ons, and syst ems f or a mi ni mum of 5 year s. The or gani zat i on shal l have a cal i br at i on pr ogr am, and t est i nst r ument s used shal l be cal i br at ed i n accor dance wi t h NETA ATS.

Apr i l 2019 Page 1 SECTI ON 26 08 00

b. Submi t name and qual i f i cat i ons of t he l ead engi neer i ng t echni c i an per f or mi ng t he r equi r ed t est i ng ser vi ces. I ncl ude a l i s t of t hr ee compar abl e j obs per f or med by t he t echni c i an wi t h speci f i c names and t el ephone number s f or r ef er ence. Test i ng, i nspect i on, cal i br at i on, and adj ust ment s shal l be per f or med by an engi neer i ng t echni c i an, cer t i f i ed by NETA or t he Nat i onal I nst i t ut e f or Cer t i f i cat i on i n Engi neer i ng Technol ogi es ( NI CET) wi t h a mi ni mum of 5 year s ' exper i ence i nspect i ng, t est i ng, and cal i br at i ng el ect r i cal di st r i but i on and gener at i on equi pment , syst ems, and devi ces.

1. 4. 2 Accept ance Test s and I nspect i ons Repor t s

Submi t cer t i f i ed copi es of i nspect i on r epor t s and t est r epor t s. Repor t s shal l i ncl ude cer t i f i cat i on of compl i ance wi t h speci f i ed r equi r ement s, i dent i f y def i c i enci es, and r ecommend cor r ect i ve act i on when appr opr i at e.

Type and neat l y bi nd t est r epor t s t o f or m a par t of t he f i nal r ecor d.

Submi t t est r epor t s document i ng t he r esul t s of each t est not mor e t han 10 days af t er t est i s compl et ed.

1. 4. 3 Accept ance Test and I nspect i ons Pr ocedur e

Submi t t est pr ocedur e r epor t s f or each i t em of equi pment t o be f i el d t est ed at l east 45 days pr i or t o pl anned t est i ng dat e. Do not per f or m t est i ng unt i l af t er t est pr ocedur e has been appr oved.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTI ON

3. 1 ACCEPTANCE TESTS AND I NSPECTI ONS

Test i ng or gani zat i on shal l per f or m accept ance t est s and i nspect i ons. Test met hods, pr ocedur es, and t est val ues shal l be per f or med and eval uat ed i n accor dance wi t h NETA ATS, t he manuf act ur er ' s r ecommendat i ons, and par agr aph ent i t l ed " Fi el d Qual i t y Cont r ol " of each appl i cabl e speci f i cat i on sect i on. Test s i dent i f i ed as opt i onal i n NETA ATS ar e not r equi r ed unl ess ot her wi se speci f i ed. Equi pment shal l be pl aced i n ser vi ce onl y af t er compl et i on of r equi r ed t est s and eval uat i on of t he t est r esul t s have been compl et ed. Cont r act or shal l suppl y t o t he t est i ng or gani zat i on compl et e set s of shop dr awi ngs, set t i ngs of adj ust abl e devi ces, and ot her i nf or mat i on necessar y f or an accur at e t est and i nspect i on of t he syst em pr i or t o t he per f or mance of any f i nal t est i ng. Cont r act i ng Of f i cer shal l be not i f i ed at l east 14 days i n advance of when t est s wi l l be conduct ed by t he t est i ng or gani zat i on. Per f or m accept ance t est s and i nspect i ons on appl i cabl e equi pment and syst ems speci f i ed i n t he f ol l owi ng sect i ons:

a. Sect i on 26 32 14. 00 10 DI ESEL- GENERATOR SET, STATI ONARY 15- 300 KW, STANDBY APPLI CATI ONS. Funct i onal engi ne shut down t est s, v i br at i on base- l i ne t est , and l oad bank t est shal l not be per f or med by t he t est i ng or gani zat i on. These t est s shal l be per f or med by t he st ar t - up engineer.

b. Sect i on 33 71 02 UNDERGROUND ELECTRI CAL DI STRI BUTI ON. Medi um vol t age cabl es and gr oundi ng syst ems onl y.

Apr i l 2019 Page 2 SECTI ON 26 08 00

c. Sect i on 26 36 00. 00 10 AUTOMATI C TRANSFER SWI TCHES

d. Sect i on 26 23 00 LOW VOLTAGE SWI TCHGEAR

3. 2 SYSTEM ACCEPTANCE

Fi nal accept ance of t he syst em i s cont i ngent upon sat i sf act or y compl et i on of accept ance t est s and i nspect i ons.

3. 3 PLACI NG EQUI PMENT I N SERVI CE

A r epr esent at i ve of t he appr oved t est i ng or gani zat i on shal l be pr esent when equi pment t est ed by t he or gani zat i on i s i ni t i al l y ener gi zed and pl aced i n ser vi ce.

- - End of Sect i on - -