This is a Submittal Register form used to track contractor submissions throughout the duration of a construction contract. The form serves as a master checklist documenting all required submittals, their specifications paragraph references, approval requirements, and processing timelines.

The register encompasses submittals across multiple categories: SD-01 Preconstruction Submittals (including Schedule of Prices, List of Contact Personnel, Construction Schedule, Accident Prevention Plan, Activity Hazard Analysis, Crane Work Plans and Critical Lift Plans, Equipment Delivery Schedule, Traffic Control Plan, Environmental Protection Plan, Preconstruction Survey, MSDS for Class I ODS Waivered Products, Permit for Storm Water Discharge, and Notice of Intent); SD-03 Product Data (Backflow Preventers); SD-06 Test Reports (Reports, Accident Reports, Monthly Exposure Reports, Backflow Preventer Tests, and Crane Reports); SD-07 Certificates (Confined Space Entry Permits, Backflow Tester Certification, Backflow Preventers Certificates, Certificate of Compliance, and Third Party Certification of Barge-Mounted Mobile Cranes); and SD-11 Closeout Submittals (Interim DD1354 Transfer & Acceptance, Submittal Register, Complete Submittal Package, and Quality Control Plan). The form provides columns for tracking submission dates, approval authority, contractor action dates, material needed dates, reviewer communications, and remarks, enabling systematic management of all contract documentation throughout the project lifecycle.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTRACT NO.

CONTRACTOR

SUBMIT

APPROVAL

NEEDED

BY

MATERIAL

NEEDED

BY

A C T I O N

C O D E

DATE

OF

ACTION

DATE FWD

TO APPR

AUTH/

DATE RCD

FROM

CONTR

DATE FWD

TO OTHER

REVIEWER

DATE RCD

FROM OTH

REVIEWER

A C T I O N

C O D E

DATE

OF

ACTION

MAILED

TO

CONTR/

DATE RCD

FRM APPR

AUTH REMARKS

(a) (b) (c) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)

01 20 00

1.3

01 30 00

1.4.1

01 31 50

1.2

01 32 16

1.2

1.3

01 33 00

1.4.1

1.6.1

01 35 29

1.9

1.10

1.9.1

1.9.1

1.7.1.4

1.14

1.14.1

1.14.3

1.14.4

1.14.5

1.11

Crane Reports

SD-07 CERTIFICATES

Confined Space Entry Permit

Approving AuthorityContractor Schedule Dates

SD-11 CLOSEOUT SUBMITTALS

Interim DD1354, Transfer & Acceptance

SD-11 CLOSEOUT SUBMITTALS

Submittal Register

Complete Submittal Package

TITLE AND LOCATION

(Enter Contract Title and Locaiton Here)

Schedule of Prices

List of Contact Personnel

Construction Schedule of Military Real Property (If Applicable)

A C T I V I T Y

N O

T R A N S M I T T A L

N O

(d)

Contractor Action

DESCRIPTION

ITEM SUBMITTED

(Enter Contractor Name Here)

Crane Work Plan (If Applicable)

Activity Hazard Analysis (AHA)

SD-06 TEST REPORTS

SD-01 PRECONSTRUCTION SUBMITTALS

(Enter Contract No. Here)

SD-01 PRECONSTRUCTION SUBMITTALS

Accident Prevention Plan (APP)

SD-01 PRECONSTRUCTION SUBMITTALS

Equipment Delivery Schedule

SD-01 PRECONSTRUCTION SUBMITTALS

SUBMITTAL REGISTER

P A R A G R A P H

N O

S P E C

S E C T

C L A S S I F I C A T I O N

G O V T

O R

A E

R E V W R

Crane Critical Lift Plan (If Applicable)

Crane Operators (If Applicable)

Reports

Accident Reports

Monthly Exposure Reports

Regulatory Citations and Violations

1.14.6

1.14.7

01 45 10

1.6

01 50 00

1.6.2.1

2.1

3.1

1.3

01 57 19

1.6.1

1.6.4

1.7.2

1.7

1.7

PAGE 1 OF _

Third Party Certification of Barge-

Mounted Movile Cranes

SD-11 CLOSEOUT SUBMITTALS

Qaulity Control Plan (QC Plan)

Certificate of Compliance

Backflow Tester Certification (If Applicable)

Backflow Preventer Tests (If Applicable)

SD-01 PRECONSTRUCTION SUBMITTALS

Traffic Control Plan (If Applicable)

SUBMITTAL FORM, JAN 96 PREVIOUS EDITION OBSOLETE

MSDS for Class I ODS Waivered Product

SD-01 PRECONSTRUCTION SUBMITTALS

Permit for Storm Water Discharge (If applicab

Environmental Protection Plan

Preconstruction Survey

Notice of Intent (If applicable)

SD-03 PRODUCT DATA

Backflow Preventers (If Applicable)

Backflow Preventers Certificate (If Applicable)

SD-06 TEST REPORTS

SD-07 CERTIFICATES