This is a Schedule of Values document for the Pinellas County, Florida Solid Waste Administration Building HVAC Renovation project (ITB-C #26-0394-ITB-C). The project encompasses a complete replacement of the building's HVAC systems, including demolition of existing units and installation of two 15-ton VAV DX split systems, one 1500 CFM decoupled 100% outside air DX split system, VAV terminal units for zone control, a new DDC control system, ductwork modifications, new exhaust fans, and all associated electrical, controls, and piping work. The project includes a non-mandatory pre-bid conference and site visit scheduled for April 9, 2026 at 1:30 p.m., with Step One qualification submissions due April 21, 2026 at 3:00 p.m. and Step Two sealed bids due May 5, 2026 at 3:00 p.m. The contract term is 365 consecutive calendar days from the Notice to Proceed.

The total Guaranteed Maximum Price (GMP) is $686,580.00, with major cost allocations including overhead and profit at $103,000.00 (15.0%), electrical panel and equipment at $100,000.00 (14.6%), electrical wiring and conduit at $65,000.00 (9.5%), ductwork supports and insulation at $50,500.00 (7.4%), DX split systems condensing units and AHUs at $47,600.00 (6.9%), contingency reserves at $40,000.00 (5.8%), and VAV boxes at $31,200.00 (4.5%). The schedule of values includes 29 line items detailing mobilization, general conditions, selective demolition, HVAC equipment and components, electrical work, controls, testing and commissioning, permits, and contingencies. Liquidated damages are assessed at $1,200 per calendar day for delays beyond the contract completion date, and the County will retain 5% of monthly progress payments until final completion and acceptance.

View the file

Other files

File Type Posted
Panel_PP-1_Interior2.pdf PDF
MDP.pdf PDF
Panel_PP-1_Outer_Casing.pdf PDF
SOLID_WASTE_ADMINISTRATION_BUILDING_HVAC_RENOVATION.pdf PDF
Pricing_Proposal_26-0394_(reference_only).pdf PDF
QUALIFICATION_SUBMITTAL_FORM_8-25.pdf PDF
QUALIFICATION_SUBMITTAL_FORM_8-25.pdf PDF
Sample_Agreement-26-0394.pdf PDF
Common_Carrier_Attestation_02.05.2025.pdf PDF
Foreign_Countries_of_Concern_Affidavit_02.05.2025_(1).pdf PDF
Common_Carrier_Attestation_02.05.2025.pdf PDF
Foreign_Countries_of_Concern_Affidavit_02.05.2025_(1).pdf PDF
Human_Trafficking_Affidavit_02.05.2025_(3).pdf PDF
Human_Trafficking_Affidavit_02.05.2025_(3).pdf PDF
Human_Trafficking_Affidavit_02.05.2025_(3).pdf PDF
2022-Pinellas-County-Division-27.pdf PDF
2022-Pinellas-County-Division-27.pdf PDF
Pinellas_County_Solid_Waste_100%_CD_DS01202026.pdf PDF
Pinellas_County_Solid_Waste_100%_CD_DS01202026.pdf PDF
Pinellas_County_Solid_Waste_100%_CD_DS01202026.pdf PDF
Pinellas_County_Solid_Waste_HVAC_Renovation_100%_CD_Review_-_Specifications_-_DS01.20.2026.pdf PDF
Pinellas_County_Solid_Waste_HVAC_Renovation_100%_CD_Review_-_Specifications_-_DS01.20.2026.pdf PDF
Pinellas_County_Solid_Waste_HVAC_Renovation_100%_CD_Review_-_Specifications_-_DS01.20.2026.pdf PDF
Affdavit_of_Release_and_Guarantee.pdf PDF
Performance_and_Payment_Bonds.pdf PDF
RE__For_Review__Draft_CIP_HVAC_Replacement_Construction_RFB.pdf PDF
Sample_Application_for_Payment.pdf PDF
25002_PCSW_HVAC_Renovation_Schedule_of_Values.pdf PDF
Bid_Submittal_Form-JOC.pdf PDF
E-Verify_Affidavit.pdf PDF
Sample_Change_Order.pdf PDF
Airport_Security_Program.pdf PDF
Bid_Submittal_Form-JOC.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
Performance_and_Payment_Bonds.pdf PDF
RE__For_Review__Draft_CIP_HVAC_Replacement_Construction_RFB.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
Non-Competitive_Oversight_Committee_Justification_Form.docx DOCX document
Sample_Change_Order.pdf PDF
Florida_Trench_Safety_Form.pdf PDF
RE__For_Review__Draft_CIP_HVAC_Replacement_Construction_RFB.pdf PDF
Sample_Application_for_Payment.pdf PDF
Non-Competitive_Oversight_Committee_Justification_Form.docx DOCX document
Sample_Change_Order.pdf PDF
Airport_Security_Program.pdf PDF
E-Verify_Affidavit.pdf PDF
OpenGov_Fillable-_Final.pdf PDF
Non-Competitive_Oversight_Committee_Justification_Form.docx DOCX document
OpenGov_Fillable-_Final.pdf PDF
Performance_and_Payment_Bonds.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

A B C D C

ITEM

NO.

DESCRIPTION OF WORK

SCHEDULED

VALUE

% OF

TOTAL

NOTES

1 BOND PREMIUM $10,000.00 1.5%

2 MOBILIZATION $15,000.00 2.2%

3 GENERAL CONDITIONS $20,500.00 3.0%

4 SELECTIVE DEMOLITION $12,500.00 1.8% REMOVE EXISTING HVAC SYSTEMS AND DISPOSAL

5 CONCRETE $4,500.00 0.7% HOUSEKEEPING PADS FOR NEW CUS

6 FENCING $2,500.00 0.4% FENCED ENCLOSURE FOR NEW CUS / MECH YARD

7 DRYWALL $5,000.00 0.7% AS REQUIRED FOR HVAC RENOVATIONS

8 CEILINGS, OTHER $7,500.00 1.1% AS REQUIRED FOR HVAC RENOVATIONS

9 PAINT AND WALL COVERINGS $2,500.00 0.4% AS REQUIRED FOR HVAC RENOVATIONS

10 INSULATION - MINOR REPAIRS $6,000.00 0.9% AS REQUIRED FOR HVAC RENOVATIONS

11 GENERAL HVAC REQUIREMENTS $12,500.00 1.8% BASIC MECHANICAL REQUIREMENTS, SUPPORTS, ANCHORS, ETC.

12 DX SPLIT SYSTEMS - CONDENSING UNITS, AHUS $47,600.00 6.9% QTY. 2 - 15 TON VAV DX SPLIT SYSTEMS

13 VAV BOXES $31,200.00 4.5% QTY. AS SCHEDULED ON PLANS, WITH ELECTRIC HEAT

14 100% OA DX SPLIT SYSTEM $27,840.00 4.1% 1500 CFM DOAS DX SPLIT SYSTEM

15 REFRIGERANT PIPING, SUPPORTS, AND INSULATION $6,300.00 0.9% NEW REFRIGERANT LINES

16 DUCTWORK, SUPPORTS, AND INSULATION $50,500.00 7.4% NEW SHEET METAL DUCTWORK, SUPPORTS AND INSULATION

17 AIR DEVICES, GRILLES, REGISTERS $22,640.00 3.3% NEW AIR DEVICES

18 HVAC CONTROLS $22,500.00 3.3% NEW HVAC CONTROLS

19 HVAC TEST AND BALANCE (T&B) $6,500.00 0.9% AABC OR NEBB CERTIFIED T&B OF ALL HVAC SYSTEMS

20 SYSTEM COMMISIONING (CxA) $3,500.00 0.5% CxA OF NEW HVAC SYSTEMS BY APPROVED COMMISIONING AGENT

21 ELECTRICAL PANEL AND EQUIPMENT $100,000.00 14.6%

22 ELECTRICAL WIRING AND CONDUIT $65,000.00 9.5%

23 ELECTRICAL DEMOLITION - VARIOUS $25,000.00 3.6%

24 ELECTRICAL LIGHTING/CONFERENCE ROOM $10,000.00 1.5%

25 CONDUIT FOR MECHANICAL CONTROLS $5,000.00 0.7%

26 COMMUNICATIONS - FIRE ALARM $20,000.00 2.9%

27 CONTINGENCY, OTHER $40,000.00 5.8%

28 PERMITS, FEES, OTHER $1,500.00 0.2%

29 OVERHEAD AND PROFIT (OH&P) $103,000.00 15.0%

TOTAL GMP = $686,580.00