24-8265_Exhibit_L-9_-_UWS_FPL_Distribution_Signed.pdf

PDF 437 KB Posted

Attached to
16th Street NE Bridge Project (LAP) GRANT FUNDED
Solicitation number
24-8265
Issued by
Collier County, Florida

About this file

This is a Utility Work Schedule document prepared by the Florida Department of Transportation (FDOT) in coordination with Florida Power & Light Company (FPL), the utility agency owner, for the 16th Street NE Bridge Project (Financial Project ID: 451283-1-58-01) located in Collier County, Florida. The schedule addresses the relocation and adjustment of FPL's overhead and buried electric distribution facilities within the project limits, spanning from station 1025+22 to station 1174+13. The utility work is estimated to require 90 consecutive calendar days during FDOT project construction, with no preparatory work required prior to construction commencement. FPL's designated project representative and field representative is Michael Martinez, Relocation Coordinator, reachable at 239-353-6047 or michael.martinez@fpl.com. The utility work schedule was submitted by FPL on September 22, 2023, and approved by FDOT's Roadway Engineer of Record and Utility Coordinator, Jesse E. Gill, P.E., on March 15, 2024, in accordance with the 2017 Utility Accommodation Manual.

The work activities include the installation and removal of overhead electric facilities (Activity 1) requiring 30 days during construction, with commencement dependent on completion of clearing and grubbing, right-of-way staking, and silt fence installation activities, and buried electric facilities (Activity 2) requiring 60 days during construction, dependent on completion of Activity 1. FPL has identified two special conditions: line crew availability may be limited due to emergency response requirements depending on severity, and all phase-to-phase voltage for FPL distribution facilities within project limits is below 50 kilovolt. The utility work schedule is based on FDOT plans dated August 10, 2023, and any deviation from these plans by FDOT or its contractor may void the schedule, with renegotiation available upon notification of plan changes.

View the file

Other files

File Type Posted
24-8265_-_Exhibit_I_-_Enviornmental_Supplemental.pdf PDF
24-8265_Solicitation_R2.pdf PDF
24-8265_–_Gopher_Tortoise_Burrow_Map.pdf PDF
24-8265_Pre-Bid_Meeting_Sign-In_sheets.pdf PDF
24-8265_Exhibit_M-5_-_Structures_Plans_S&S.pdf PDF
24-8265_Exhibit_M-5_-_Structures_Plans_S&S.pdf PDF
24-8265_Exhibit_M-5_-_Structures_Plans_S&S.pdf PDF
Construction_Bid_Instructions_Version_1.pdf PDF
24-8265_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
Construction_Services_LAP_Agreement_2025_version_1.pdf PDF
24-8265_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
24-8265_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
24-8265_Federal_Provisions_Package.pdf PDF
24-8265_Federal_Provisions_Package.pdf PDF
24-8265_Federal_Provisions_Package.pdf PDF
24-8265_-_Bid_Schedule.xlsx XLSX spreadsheet
24-8265_-_Bid_Schedule.xlsx XLSX spreadsheet
24-8265_-_Bid_Schedule.xlsx XLSX spreadsheet
24-8265_Exhibit_L-16_-_Utilities_Clear_16th_St_Ne_Bridge_dm.pdf PDF
24-8265_Exhibit_L-18_-_Structure_Geotech_Report_3.19.25.pdf PDF
24-8265_Exhibit_M-3_-_Signalization_Plans_S&S.pdf PDF
24-8265_Exhibit_L-17_-_TECO_UWS_Signed.pdf PDF
24-8265_Exhibit_L-19_-_Roadway_Geotechnical_Report_Signed.pdf PDF
24-8265_Exhibit_L-18_-_Structure_Geotech_Report_3.19.25.pdf PDF
24-8265_Exhibit_L-19_-_Roadway_Geotechnical_Report_Signed.pdf PDF
24-8265_Exhibit_L-15_-_CCWSD_No_Conflict.pdf PDF
24-8265_Exhibit_L-14_-_City_of_Naples_No_Conflict.pdf PDF
24-8265_Exhibit_M-2_-_Roadway_Plans_S&S.pdf PDF
24-8265_Exhibit_L-18_-_Structure_Geotech_Report_3.19.25.pdf PDF
24-8265_Exhibit_M-4_-_Signing_&_Pavement_Marking_Plans_S&S.pdf PDF
24-8265_Exhibit_M-3_-_Signalization_Plans_S&S.pdf PDF
24-8265_Exhibit_M-3_-_Signalization_Plans_S&S.pdf PDF
24-8265_Exhibit_L-17_-_TECO_UWS_Signed.pdf PDF
24-8265_Exhibit_L-14_-_City_of_Naples_No_Conflict.pdf PDF
24-8265_Exhibit_M-2_-_Roadway_Plans_S&S.pdf PDF
24-8265_Exhibit_L-19_-_Roadway_Geotechnical_Report_Signed.pdf PDF
24-8265_Exhibit_M-2_-_Roadway_Plans_S&S.pdf PDF
24-8265_Exhibit_L-15_-_CCWSD_No_Conflict.pdf PDF
24-8265_Exhibit_L-20_-_Railroad_Clear_16th_st_ne_bridge_dm.pdf PDF
24-8265_Exhibit_M-1_-_LightingPlans_S&S.pdf PDF
24-8265_Exhibit_M-1_-_LightingPlans_S&S.pdf PDF
24-8265_Exhibit_M-1_-_LightingPlans_S&S.pdf PDF
24-8265_Exhibit_L-20_-_Railroad_Clear_16th_st_ne_bridge_dm.pdf PDF
24-8265_Exhibit_M-4_-_Signing_&_Pavement_Marking_Plans_S&S.pdf PDF
24-8265_Exhibit_L-14_-_City_of_Naples_No_Conflict.pdf PDF
24-8265_Exhibit_L-16_-_Utilities_Clear_16th_St_Ne_Bridge_dm.pdf PDF
24-8265_Exhibit_L-17_-_TECO_UWS_Signed.pdf PDF
24-8265_Exhibit_L-15_-_CCWSD_No_Conflict.pdf PDF
24-8265_Exhibit_L-16_-_Utilities_Clear_16th_St_Ne_Bridge_dm.pdf PDF
24-8265_Exhibit_L-20_-_Railroad_Clear_16th_st_ne_bridge_dm.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rule 14-46.001 F.A.C

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.

FDOT PROJECT INFORMATION

Financial Project ID: 451283-1-58-01 Federal Project ID:

State Road Number: County: Collier FDOT Plans Dated: 8/10/2023 District Document No.: 710-010-05

UTILITY AGENCY/OWNER (UAO)

Utility Company: Florida Power & Light Company UAO Project Rep: Michael Martinez Phone: 239-353-6047 E-mail: michael.martinez@fpl.com UAO Field Rep: Michael Martinez Phone: 239-353-6047 E-mail: michael.martinez@fpl.com

UTILITY SIGNATURE

I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.

UAO Rep. Date 9 / 22 / 2023 Name Michael Martinez Title Relocation Coordinator

ENGINEER OF RECORD SIGNATURE

I attest this utility work schedule is compatible with the FDOT plans referenced above.

EOR. Date / / Name Title

APPROVAL BY DISTRICT UTILITIES

This utility work schedule is complete and acceptable to FDOT.

FDOT Rep. Date / / Name Title

SECTION A: SUMMARY OF UTILITY WORK

The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.

Days prior to FDOT project construction: 0 Days during FDOT project construction: 90 jgill Text Box Jesse E. Gill, P.E.

jgill Text Box Roadway EOR / Utility Coordinator jgill Text Box 03 15 2024

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Financial Project ID: 451283-1-58-01 Utility Company: Florida Power & Light Company FDOT Plans Dated: 8/10/2023

SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS

1- FPL line crew availability may be affected or limited due to required response to emergency conditions. This limitation will be dependant upon the severity of the emergency.

2- The phase-to-phase voltage for all FPL Distribution facilities within the project limits is below 50KV.

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Financial Project ID: 451283-1-58-01 Utility Company: Florida Power & Light Company FDOT Plans Dated: 8/10/2023

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility (type, size, material, status)

From Station/Offset

To Station/Offset

Utility Work Activity

Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

1 Overhead Electric (O.E) 1025+22, 28' LT/RT

CL CONST.

1174+13, 30' LT/RT

CL CONST.

To be Installed/Removed

Clearing and Grubbing

ROW Staking Silt Fence Instl.

0 30

2 Buried Electric (B.E) 1025+26, 28' LT/RT

CL CONST.

1026+06, 29' LT/RT

CL CONST.

To be Installed/Removed Act. No. 1 0 60

2024-03-15T13:34:35-0400
Jesse E Gill

File details come from the government source that posted it. Updated .