24-8265_Exhibit_L-9_-_UWS_FPL_Distribution_Signed.pdf

PDF 437 KB Posted

Attached to
16th Street NE Bridge Project (LAP) GRANT FUNDED
Solicitation number
24-8265
Issued by
Collier County, Florida

About this file

This is a Utility Work Schedule prepared by the Florida Department of Transportation (FDOT) for the 16th Street NE Bridge Project in Collier County, Florida. The document outlines the coordination and timing requirements for Florida Power & Light Company (FPL) to relocate and adjust its electrical utilities within the project area as part of the overall infrastructure improvement initiative. The utility work includes the removal and installation of overhead electric lines spanning from station 1025+22 to 1174+13 and buried electric lines from station 1025+26 to 1026+06. FPL's primary project representative is Michael Martinez, Relocation Coordinator, and the work is coordinated with the project's Engineer of Record, Jesse E. Gill, P.E. The utility relocation work is scheduled to occur during the 520-day FDOT project construction period, with the overhead electric work requiring 30 consecutive calendar days and the buried electric work requiring 60 consecutive calendar days, totaling 90 days of utility work during construction.

The utility work schedule is based on FDOT plans dated August 10, 2023, and was submitted on September 22, 2023, with final approval by the Engineer of Record on March 15, 2024. FPL's line crew availability may be limited due to required response to emergency conditions, with the severity of the emergency dictating the extent of limitations. The electrical facilities within the project limits operate at phase-to-phase voltages below 50 kilovolts. All utility work must comply with the 2017 Utility Accommodation Manual and requires FPL to obtain a utility permit. FPL is not responsible for events beyond its control that could not be reasonably anticipated and could not be avoided with the exercise of due diligence at the time of occurrence. Prior written notification to FDOT and the contractor is required before starting, stopping, resuming, and completing work under this utility work schedule.

View the file

Other files

File Type Posted
24-8265_-_Exhibit_I_-_Enviornmental_Supplemental.pdf PDF
24-8265_Solicitation_R2.pdf PDF
24-8265_–_Gopher_Tortoise_Burrow_Map.pdf PDF
24-8265_Pre-Bid_Meeting_Sign-In_sheets.pdf PDF
24-8265_Exhibit_M-5_-_Structures_Plans_S&S.pdf PDF
24-8265_Exhibit_M-5_-_Structures_Plans_S&S.pdf PDF
24-8265_Exhibit_M-5_-_Structures_Plans_S&S.pdf PDF
Construction_Bid_Instructions_Version_1.pdf PDF
24-8265_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
Construction_Services_LAP_Agreement_2025_version_1.pdf PDF
24-8265_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
24-8265_Exhibit_N_-_EHS_Contractor_Requirements_Master_2021_rev.pdf PDF
24-8265_Federal_Provisions_Package.pdf PDF
24-8265_Federal_Provisions_Package.pdf PDF
24-8265_Federal_Provisions_Package.pdf PDF
24-8265_-_Bid_Schedule.xlsx XLSX spreadsheet
24-8265_-_Bid_Schedule.xlsx XLSX spreadsheet
24-8265_-_Bid_Schedule.xlsx XLSX spreadsheet
24-8265_Exhibit_L-16_-_Utilities_Clear_16th_St_Ne_Bridge_dm.pdf PDF
24-8265_Exhibit_L-18_-_Structure_Geotech_Report_3.19.25.pdf PDF
24-8265_Exhibit_M-3_-_Signalization_Plans_S&S.pdf PDF
24-8265_Exhibit_L-17_-_TECO_UWS_Signed.pdf PDF
24-8265_Exhibit_L-19_-_Roadway_Geotechnical_Report_Signed.pdf PDF
24-8265_Exhibit_L-18_-_Structure_Geotech_Report_3.19.25.pdf PDF
24-8265_Exhibit_L-19_-_Roadway_Geotechnical_Report_Signed.pdf PDF
24-8265_Exhibit_L-15_-_CCWSD_No_Conflict.pdf PDF
24-8265_Exhibit_L-14_-_City_of_Naples_No_Conflict.pdf PDF
24-8265_Exhibit_M-2_-_Roadway_Plans_S&S.pdf PDF
24-8265_Exhibit_L-18_-_Structure_Geotech_Report_3.19.25.pdf PDF
24-8265_Exhibit_M-4_-_Signing_&_Pavement_Marking_Plans_S&S.pdf PDF
24-8265_Exhibit_M-3_-_Signalization_Plans_S&S.pdf PDF
24-8265_Exhibit_M-3_-_Signalization_Plans_S&S.pdf PDF
24-8265_Exhibit_L-17_-_TECO_UWS_Signed.pdf PDF
24-8265_Exhibit_L-14_-_City_of_Naples_No_Conflict.pdf PDF
24-8265_Exhibit_M-2_-_Roadway_Plans_S&S.pdf PDF
24-8265_Exhibit_L-19_-_Roadway_Geotechnical_Report_Signed.pdf PDF
24-8265_Exhibit_M-2_-_Roadway_Plans_S&S.pdf PDF
24-8265_Exhibit_L-15_-_CCWSD_No_Conflict.pdf PDF
24-8265_Exhibit_L-20_-_Railroad_Clear_16th_st_ne_bridge_dm.pdf PDF
24-8265_Exhibit_M-1_-_LightingPlans_S&S.pdf PDF
24-8265_Exhibit_M-1_-_LightingPlans_S&S.pdf PDF
24-8265_Exhibit_M-1_-_LightingPlans_S&S.pdf PDF
24-8265_Exhibit_L-20_-_Railroad_Clear_16th_st_ne_bridge_dm.pdf PDF
24-8265_Exhibit_M-4_-_Signing_&_Pavement_Marking_Plans_S&S.pdf PDF
24-8265_Exhibit_L-14_-_City_of_Naples_No_Conflict.pdf PDF
24-8265_Exhibit_L-16_-_Utilities_Clear_16th_St_Ne_Bridge_dm.pdf PDF
24-8265_Exhibit_L-17_-_TECO_UWS_Signed.pdf PDF
24-8265_Exhibit_L-15_-_CCWSD_No_Conflict.pdf PDF
24-8265_Exhibit_L-16_-_Utilities_Clear_16th_St_Ne_Bridge_dm.pdf PDF
24-8265_Exhibit_L-20_-_Railroad_Clear_16th_st_ne_bridge_dm.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rule 14-46.001 F.A.C

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Pursuant to Section 337.403 F.S., the UAO and FDOT agree to the UAO’s need for relocation or adjustment to its utilities and FDOT’s need for a schedule for the UAO to effect the relocation or adjustment. This utility work schedule is based on FDOT plans dated in the project information box below. Any deviation by FDOT or its contractor from these plans, may void this utility work schedule. Upon notification by FDOT of a change to these plans, the UAO may negotiate a new utility work schedule. The UAO agrees to notify FDOT and the contractor in writing prior to starting, stopping, resuming, and completing work in accordance with this utility work schedule. The UAO shall obtain a utility permit and comply with requirements of the 2017 Utility Accommodation Manual (UAM) for all work done under this utility work schedule. The UAO is not responsible for events beyond the control of the UAO that could not be reasonably anticipated by the UAO and which could not be avoided by the UAO with exercise of due diligence at the time of the occurrence.

FDOT PROJECT INFORMATION

Financial Project ID: 451283-1-58-01 Federal Project ID:

State Road Number: County: Collier FDOT Plans Dated: 8/10/2023 District Document No.: 710-010-05

UTILITY AGENCY/OWNER (UAO)

Utility Company: Florida Power & Light Company UAO Project Rep: Michael Martinez Phone: 239-353-6047 E-mail: michael.martinez@fpl.com UAO Field Rep: Michael Martinez Phone: 239-353-6047 E-mail: michael.martinez@fpl.com

UTILITY SIGNATURE

I have reviewed the FDOT plans referenced above and submit this utility work schedule in compliance with UAM Section 5 and agree to be bound by the terms of this utility work schedule.

UAO Rep. Date 9 / 22 / 2023 Name Michael Martinez Title Relocation Coordinator

ENGINEER OF RECORD SIGNATURE

I attest this utility work schedule is compatible with the FDOT plans referenced above.

EOR. Date / / Name Title

APPROVAL BY DISTRICT UTILITIES

This utility work schedule is complete and acceptable to FDOT.

FDOT Rep. Date / / Name Title

SECTION A: SUMMARY OF UTILITY WORK

The below days are the total numbers of days shown for all activities in Section C of this utility work schedule. The breakdown of how these days are to be incorporated into the FDOT project and the dependence of these days upon the completion of other activities by the UAO or others is shown in Section C.

Days prior to FDOT project construction: 0 Days during FDOT project construction: 90 jgill Text Box Jesse E. Gill, P.E.

jgill Text Box Roadway EOR / Utility Coordinator jgill Text Box 03 15 2024

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Financial Project ID: 451283-1-58-01 Utility Company: Florida Power & Light Company FDOT Plans Dated: 8/10/2023

SECTION B: UAO SPECIAL CONDITIONS/CONSTRAINTS

1- FPL line crew availability may be affected or limited due to required response to emergency conditions. This limitation will be dependant upon the severity of the emergency.

2- The phase-to-phase voltage for all FPL Distribution facilities within the project limits is below 50KV.

FLORIDA DEPARTMENT OF TRANSPORTATION

UTILITY WORK SCHEDULE

December 14, 2016

Financial Project ID: 451283-1-58-01 Utility Company: Florida Power & Light Company FDOT Plans Dated: 8/10/2023

SECTION C: UAO’s WORK ACTIVITIES

Act.

No.

Utility Facility (type, size, material, status)

From Station/Offset

To Station/Offset

Utility Work Activity

Description

Dependent Activity TCP Phase

Consecutive Calendar Days

Prior to During Const. Const.

1 Overhead Electric (O.E) 1025+22, 28' LT/RT

CL CONST.

1174+13, 30' LT/RT

CL CONST.

To be Installed/Removed

Clearing and Grubbing

ROW Staking Silt Fence Instl.

0 30

2 Buried Electric (B.E) 1025+26, 28' LT/RT

CL CONST.

1026+06, 29' LT/RT

CL CONST.

To be Installed/Removed Act. No. 1 0 60

2024-03-15T13:34:35-0400
Jesse E Gill

File details come from the government source that posted it. Updated .