24-0005 QA1.docx

DOCX document 65 KB Posted

Attached to
Facility Technology Modernization
Solicitation number
24-0005
Issued by
Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Douglas County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington

About this file

This document is a Question and Answer (Q&A) related to a state of Washington Department of Enterprise Services (DES) competitive solicitation for Facility Technology Modernization (Solicitation #24-0005). The solicitation is seeking a comprehensive software technology solution that supports Asset Management, Work Order Management, and Capital Project Management. DES manages and provides services to 42 state agencies, and maintains the 144-acre state Capitol Campus in Olympia. The Q&A document captures and responds to questions received during the procurement process, including topics such as system requirements, data migration, user roles, implementation approach, and proposal requirements. The solicitation has been updated based on the Q&A, and the deadline for submitting additional questions is October 8, 2024. No solicitation questions received after that date will be addressed.

The Q&A document provides details on the expected system users, including approximately 6-12 system administrators, 10 primary users, 20 executive users, 200 technicians, and 250 tenant users. DES does not currently have an existing facility management system, and is conducting this competitive procurement to purchase and implement a new solution. Bidders are permitted to utilize third-party software to meet the system requirements, and must identify any such solutions in their proposal. Bidders are also required to provide at least one reference for each of three different contracts for similar services.

View the file

Other files

File Type Posted
24-0005 Exhibit B1 Performance Requirements.xlsx XLSX spreadsheet
24-0005 PreBid Slides.pdf PDF
24-0005Exhibit-B1PerformanceRequirementsREV1.xlsx XLSX spreadsheet
24-0005 QA2.docx DOCX document
24-0005 Exhibit B2 Implementation Plan.docx DOCX document
24-0005 Exhibit D Contract.docx DOCX document
24-0005 Exhibit E -InclusionPlan-Subcontract.docx DOCX document
24-0005 ExhibitA-1-Bidder'sCertification.docx DOCX document
24-0005 ExhibitA-2-Bidder'sProfile.docx DOCX document
24-0005 Facility Tech Modernization CompSol.docx DOCX document
24-0005 Exhibit C Bid Price.xlsx XLSX spreadsheet
24-0005 Amd1.docx DOCX document
Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question & Answer #1 Facility Technology Modernization – 24-0005

This document is posted to capture the questions received during the question & answer period for 24-0005 Facility Technology Modernization. This document is the official response to the questions received.

Questions or responses included in this document require changes to the solicitation documents. The solicitation has been updated in Exhibit B-1 – Performance Requirements on WEBS as Exhibit B-1 – Performance RequirementsRev1 and all changes are detailed below, and summarized as follows:

· The Exhibit B-1 – Performance RequirementsRev1 document has been updated on WEBS to include dropdown menus for all required cells. See also 24-0005 Amd1.

Any additional questions regarding this solicitation must be directed to the Procurement Coordinator listed below. As a reminder, all questions must be received by Tuesday October 8, 2024. No solicitation questions received after October 8, 2024 will be addressed.

Name:
Terry Cooper
Telephone:
360-407-7950
Email:
descprminternal@des.wa.gov
Question #
Question
Response
Did this change the solicitation?
1.
Is DES able/willing to sign an NDA in order to receive SOC 1 and SOC 2 vendor reports? If not, will WA DES accept a SOC 3 report, and/or only the auditor letter portion of the SOC 2 Type II report?
This response references: Exhibit B-1 Performance Requirements. Requirement IDs 242, 243 and 247.

DES ETS Security Staff will sign a vendor’s NDA in order to receive the vendor’s SOC 1 type II and SOC 2 type II reports. DES acknowledges the need for confidentiality. DES is also prepared to sign annual NDAs if required, requested or needed. The vendor should provide the required details and instructions in the bidder’s written response in requirement IDs 242, 243 and 247.

No

2.
Is there any dependency for implementing these systems or can they be implemented in parallel?
DES’s preference is to move forward with Asset Management and Work Order Management in parallel. Capital Project Management will then be implemented in a subsequent phase.
No
3.
How many administrators and editors will be using the system?
We will have approximately six (6) to twelve (12) system admins and approximately two hundred fifty (250) editors using the system.
No
4.
What is DES’ current FM system?
DES does not currently have a system.
No
5.
Is DES committed to replacing their current system?
DES does not currently have a system. DES intends to conduct a competitive procurement to award a Contract for DES to purchase a software solution to implement Facility Technology Modernization.
No
6.
What is the motivation for replacing the current system?
DES does not currently have a system.
No
7.
Is there a desired “Go-Live” date?
No.
No
8.
What is the form and format of existing asset data to be migrated into the new platform (Work Order information, photos, related data)?
The current system being used is primarily Microsoft Excel.
No
9.
Are there existing workflows that define business processes related to the maintenance of various asset types?
There are no existing workflows that define the business processes.
No
10.
What are the asset types (vertical and/or linear) managed in the current system?
The asset types reflect all aspects of the built environment, including buildings, roads, sidewalks, monuments, and infrastructure.
No
11.
What is the size of the total portfolio of the DES owned assets to be managed?
The size of the portfolio includes thirty-five (35) Buildings, approximately five (5) million square feet, on approximately one hundred seventy (170) acres.
No
12.
a. Does DES have an existing library of PM procedures to be loaded into the system?

b. Are they available for all asset classes?

a. Yes –DES does have an existing library of PM procedures to be loaded into the system.

b. Yes—they are available for all asset classes.

No

13.
What is the expected (existing) volume of ad-hoc and PM work orders?
The expected (existing) volume of ad-hoc and PM work orders is approximately seven-thousand (7000) qty.
No
14.
Can you provide the expected number of the users by User Roles?

a. System Administrators – Users responsible for System Administration including System configuration, Audits, access control, User ID and Authorizations etc.

b. Primary Named users - with Read / Write privileges to access the entire system, exercise all functional capabilities, retrieve and update data, and generate reports and analysis.

c. Executive users – focused on performance information access, Key performance indicators, dashboards, reports, and analysis.

d. Technicians - with Read / Write privileges to access the system, exercise functional capabilities for managing, executing, and closing Work Orders, and retrieve and update relevant data.

e. Contractor – They can only access specific data.

f. Tenant – They can only submit work orders and track their requests.

The expected number of users by roles is detailed as follows:

a. System Administrators – approximately six (6) to twelve (12) qty.

b. Primary Named users – approximately ten (10) qty.

c. Executive users – approximately twenty (20) qty.

d. Technicians – approximately two hundred (200) qty.

e. Contractor - None

f. Tenant – approximately two hundred fifty (250) qty; we intend to have a customer facing portal.

No

15.
Many requirements in this worksheet have no dropdown for “How bidder meets Requirement” and “Response Code”. Please advise how to respond to these. Should the Bidder add the dropdowns for these requirements?
The Exhibit B-1 – Performance Requirements document has been updated to include dropdown menus for all required cells. Please see Amendment No. 1 and Exhibit B-1 – Performance RequirementsRev1.
Yes
16.
During the pre-bid conference, it was stated that all mandatory items must be met and if any cannot be met then a Bidder should not respond to the RFP. Is "Partially Meet" considered meeting a requirement and would "Partially Meet" be acceptable to DES?
If Bidder answer is “Partially Meets” bidder is required to provide a written response which provides a brief explanation on what component of the requirement is not being met. The DES evaluation team will evaluate the merits of the bidder response in accordance with the requirement and then determine Pass/Fail and/or whether clarifying questions are required. If a bidder’s response to a Mandatory Requirement is determined to be a ‘fail’, the bidder will be disqualified from further consideration.
No
17.
The requirement is “Provide at least one (1) reference for each of three (3) different contracts for which bidder has provided/performed goods and/or services similar in scope to the goods/services described in the above-referenced Competitive Solicitation.”. Please confirm that this is one reference for an Asset Management Software System, one reference for a Capital Project Management System, and one reference for s system that will support Enterprise Services’ Buildings and Grounds.
The DES requirement is to provide at least one (1) reference for each of three (3) different contracts for which bidder has provided/performed goods and/or services similar in scope to the goods/services described in the above-referenced Competitive Solicitation (i.e., 24-0005). There is no further refined requirement that states bidder should specify one reference for each of the system solutions defined in the solicitation (i.e., Asset Management, Work Order Management, Capital Project Management.) However, if a bidder chooses to respond with one reference per system solution type, that is the bidder’s decision.
No
18.
Some requirements say, “Bidder must provide…” or "Bidder will provide…” It is not clear which of these are asking for things to be provided with the proposal, or which are to be provided by the awarded Bidder. Can DES specify which of these require something to be provided with the proposal?
In the instructions worksheet of Exhibit B-1 Performance Requirements it is stated: “Please note that, if bidder is awarded a contract, bidder’s responses will be incorporated into the resulting contract.

Accordingly, bidder is cautioned to state only commitments that bidder can meet throughout the term of the contract. An awarded bidder (i.e., contractor) who is not able to meet such commitments throughout the contract term, will be subject to contract termination for breach of contract and damages."

In the Exhibit B-1 – Performance Requirements document the use of “must” is a mandatory obligation. The contractor is required to perform the specified action. Failing to comply with a “must” clause may constitute a breach of contract. For example, Requirement ID 244, Bidder must have an incident response process that follows NIST standards and includes breach detection, breach notification and breach response. The process must include notification to DES as defined in the contract. If bidder’s response to this requirement is “Fully Meets”, contractor must comply with this requirement throughout the duration of the contract.

The use of “will” is used to indicate a future action or commitment by the contractor. For example, Requirement ID 214, Bidder will provide printable/downloadable electronic training manuals. This use of “will” identifies a future commitment by the contractor to provide electronic training manuals. If bidder’s response to this requirement is “Fully Meets”, contractor will provide the electronic training manuals after the contract is awarded during the implementation phase of the contract.

If any document(s) is required to be included as part of the bidder’s proposal, DES will specify and identify such document(s) in the solicitation document and/or accompanying Exhibit(s).

No

19.
The Exhibit B-1 – Performance Requirements requirement ID #253 states “Bidder shall perform its duties as prime contractor which includes devices, all peripheral hardware, software and overall solution.” Can the Prime Contractor (Bidder) offer software provided by a Subcontractor? Also, please confirm that the Bidder is not responsible for providing end user devices such as personal computers and mobile devices.
In the instructions worksheet in the Exhibit B-1 – Performance Requirements document there is a “Response Code” defined as “Third Party”: The bidder can meet this requirement by utilizing a third party solution. The third party solution must be included in the bid. If selecting this option, in Column G: Written Response column, indicate if the third party functionality is already live with any other customers, what additional customization, or effort would be needed to deploy this third party solution, and any applicable limitations or restrictions related to the third party solution. Additionally, if the Prime Contractor (Bidder) intends to use Subcontractors, the Bidder must complete and submit Exhibit E – Bidder’s Diverse Business Inclusion Plan – Subcontractors.

This document is a required bid submittal IF bidder intends to utilize subcontractors if awarded a Contract. If so, bidder must complete Exhibit E – Bidder’s Diverse Business Inclusion Plan – Subcontractors as instructed therein and submit it with the bid to Enterprise Services.

Bidder is not required to provide DES with end user devices such as personal computers and mobile devices as part of its bid submission.