This document comprises combined architectural and engineering drawings, specifications, and general requirements for the Palm Bay City Hall Building "E" Third Floor Modifications project, a full-service design for the interior build-out of 12,149 square feet on the third floor of the new City Hall Annex located at 120 Malabar Road, Palm Bay, Florida 32907. The Owner is the City of Palm Bay, Parks and Facilities Department, represented by Greg Minor, Parks and Facilities Director. The Architect is Gregory Tsark, AIA of Tsark Architecture, LLC, with mechanical engineering services provided by Jim Mullen, PE at TLC Engineering Solutions, and electrical engineering services provided by Stephen Cotton, PE at TLC Engineering Solutions. The project scope includes comprehensive architectural, mechanical, plumbing, fire protection, and electrical systems for Public Works office space. Construction documents include reflected ceiling plans, interior elevations, door schedules, life safety plans, floor plans with partial demolition areas, partition types and details, finish schedules, mechanical demolition and floor plans with details, plumbing plans for gravity and pressure systems with risers, fire protection plans, electrical riser diagrams, schedules, and details. The project must comply with the 2023 Florida Building Code, 8th Edition, including accessibility, mechanical, plumbing, energy conservation, fuel gas, and test protocols standards, as well as NFPA codes including standards for portable fire extinguishers, sprinkler systems, and the National Electrical Code. Four submittal phases are scheduled: 30 percent Schematic Design on March 31, 2026; 60 percent Design Development on April 21, 2026; 90 percent Construction Documents on May 21, 2026; and 100 percent Issued for Permit on June 16, 2026, with two revisions submitted on July 7, 2026 and July 29, 2026.
The specifications define comprehensive requirements for construction materials, installation standards, and quality assurance across multiple divisions including metals, wood and composites, thermal and moisture protection, doors and windows, finishes, and furnishings. Contractors must be licensed to operate in Brevard County, Florida, and comply with all environmental protection regulations and permit requirements prior to construction. The project requires full-time construction representation during all operating hours, weekly coordination meetings with the owner's representative and architect, weekly progress reports detailing project status and current issues, a linear bar chart construction schedule updated monthly, and daily jobsite reports. The General Contractor must provide a construction access and staging area plan for owner approval, establish safety barriers to prevent public interaction with the jobsite, maintain the building in a dried-in condition, and coordinate all materials testing through a qualified testing agency. All subcontractors must complete City of Palm Bay background checks prior to work commencement. The contractor is responsible for final cleaning and closeout documentation, including digital copies of record drawings, operation and maintenance data binders in digital format, material safety data sheets for hazardous products, digitally recorded training videos, and copies of warranties for all installed products and systems.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Palm Bay City Hall Building "E" 3rd Floor Modifications
PROJECT SCOPE
FULL-SERVICE DESIGN FOR THE INTERIOR BUILD-OUT OF THE 12,149 SQ. FT. 3RD FLOOR
OF THE NEW CITY HALL ANNEX (BUILDING E) FOR PUBLIC WORKS.
PROJECT ADDRESS
120 MALABAR ROAD,
PALM BAY, FLORIDA 32907
OWNER
CITY OF PALM BAY - PARKS AND FACILITIES
GREG MINOR - PARKS AND FACILITIES DIRECTOR
1150 DEGROODT RD. SW,
PALM BAY, FLORIDA 32908
321-725-2778 Greg.Minor@PalmBayFlorida.org
ARCHITECT
GREGORY TSARK, AIA
TSARK ARCHITECTURE, LLC
1600 SARNO RD., SUITE 212
MELBOURNE, FL 32935
321-241-6378 Greg@Tsarkarchitecture.com
MECHANICAL ENGINEER
JIM MULLEN, PE
TLC ENGINEERING SOLUTIONS
7370 CABOT COURT
MELBOURNE, FLORIDA 32940
321-636-0274
JIM.MULLEN@TLC-ENG.COM
ELECTRICAL ENGINEER
STEPHEN COTTON, PE
TLC ENGINEERING SOLUTIONS
7370 CABOT COURT,
MELBOURNE, FLORIDA 32940
321-636-0274
STEPHEN.COTTON@TLC-ENG.COM
APPLICABLE CODES
FBC (2023) 8TH EDITION FLORIDA BUILDING CODE: BUILDING
FBC-EB (2023) 8TH EDITION FLORIDA BUILDING CODE: EXISTING BUILDING
FBC-A (2023) FLORIDA BUILDING CODE 8TH EDITION: ACCESSIBILITY
FBC-M (2023) FLORIDA BUILDING CODE 8TH EDITION: MECHANICAL
FBC-P (2023) FLORIDA BUILDING CODE 8TH EDITION: PLUMBING
FBC-ECC (2023) FLORIDA BUILDING CODE 8TH EDITION: ENERGY CONSERVATION
FBC-FG (2023) FLORIDA BUILDING CODE 8TH EDITION: FUEL GAS
FBC-TP (2023) FLORIDA BUILDING CODE 8TH EDITION: TEST PROTOCOLS HVHZ
FFPC (2021) FLORIDA FIRE PREVENTION CODE 8TH EDITION (W/ NFPA 101)
NFPA 10 (2018) STANDARD FOR PORTABLE FIRE EXTINGUISHERS
NFPA 13 (2019) STANDARD FOR THE INSTALLATION OF SPRINKLER SYSTEMS
NFPA 70 (2020) NATIONAL ELECTRICAL CODE
COMPLIANCE STATEMENT
REVIEW AND APPROVAL BY THE AUTHORITY HAVING JURISDICTION SHALL NOT RELIEVE
THE APPLICANT OF THE RESPONSIBILITY OF COMPLIANCE WITH THE APPLICABLE MINIMUM
CODES AND STANDARDS.
TO THE BEST OF OUR KNOWLEDGE, THESE DOCUMENTS COMPLY WITH THE APPLICABLE
MINIMUM CODES AND STANDARDS AS SET FORTH BY THE FLORIDA BUILDING CODE AND
GOVERNING FLORIDA STATUTES.
ACCESSIBILITY NOTES
ALTERNATES
100% PERMIT SET
N
PROJECT LOCATION
KEY NOTE DESIGNATION
B1
101A
DOOR NUMBER
ROOM NUMBER
ROOM NAME
ON WHICH ELEVATION IS SHOWN
ELEVATION NUMBER/SHEET NUMBER
SHEET ON WHICH SECTION IS SHOWN
SECTION NUMBER
DRAWING NUMBER
A
P1
WINDOW DESIGNATION
ACCESSORY DESIGNATION
PARTITION TYPE DESIGNATION
WHICH DETAIL IS SHOWN
SURFACE SHOWN IN ELEVATION
DIRECTION OF CUTTING PLANE
EXTENT OF DETAIL
SHEET ON WHICH DRAWING IS SHOWN
ROOM
NAME
A101
DETAIL NUMBER/SHEET NUMBER ON
A/C AIR CONDITIONING
ADMIN ADMINISTRATION
AFF ABOVE FINISHED FLOOR
ALT ALTERNATE, ALTERNATIVE
ALUM ALUMINUM
APPROX APPROXIMATE(LY)
ARCH ARCHITECT(URAL)
AV AUDIOVISUAL
BLDG BUILDING
BO BOTTOM OF
CLG CEILING
CLG HT CEILING HEIGHT
CLO CLOSET
CLR CLEAR(ANCE)
CMU CONCRETE MASONRY UNIT
COL COLUMN
CONC CONCRETE
CONF CONFERENCE
CONT CONTINUE, CONTINUOUS
CORR CORRIDOR
DEMO DEMOLISH
DET DETAIL
DIA DIAMETER
DIAG DIAGONAL
DIV DIVISION
E EAST
EA EACH
EL ELEVATION
ELEC ELECTRIC(AL)
ELEV ELEVATOR
EQ EQUAL
EQUIP EQUIPMENT
EWC ELECTRIC WATER COOLER
EXIST EXISTING
EXT EXTERIOR
FE FIRE EXTINGUISHER
FEC FIRE EXTINGUISHER CABINET
FIN FLR FINISHED FLOOR
FLR FLOOR
FT FOOT, FEET
FURN FURNITURE
GA GAUGE
GALV GALVANIZED
GC GENERAL CONTRACTOR
GWB GYPSUM BOARD
HC HANDICAP
HDWD HARDWOOD
HDWR HARDWARE
HM HOLLOW METAL
HORIZ HORIZONTAL
HT HEIGHT
HVAC HEATING, VENTILATION & AIR
CONDITIONING
INCL INCLUDE(D), (ING)
INFO INFORMATION
INSUL INSULATION
INT INTERIOR
KIT KITCHEN
LAB LABOATORY
LAV LAVATORY
LF LINEAR FEET
MAINT MAINTENANCE
MATL MATERIAL
MAX MAXIMUM
MECH MECHANICAL
MEZZ MEZZANINE
MFG MANUFACTURING
MFR MANUFACTURER
MIN MINUMUM
MISC MISCELLANEOUS
MR MOISTURE RESISTANT
MTG MOUNTING
N NORTH
NIC NOT IN CONTRACT
NOM NOMINAL
NTS NOT TO SCALE
OC ON CENTER
OPT OPTION(AL)
PLAM PLASTIC LAMINATE
PLF POUNDS PER LINEAR FEET
PLYWD PLYWOOD
PR PAIR
PREFAB PREFABRICATED
PREFIN PREFINISH
PSF POUNDS PER SQUARE FOOT
PSI POUNDS PER SQUARE INCH
QTY QUANTITY
RCP REFLECTED CEILING PLAN
RD ROOF DRAIN
REF REFRIGERATOR, REFERENCE
REQD REQUIRED
RM ROOM
RO ROUGH OPENING
S SOUTH
SC SOLID CORE
SD STORM DRAIN
SECT SECTION
SF SQUARE FEET
SIM SIMILAR
SPEC SPECIFICATION
SQ SQUARE
SS STAINLESS STEEL
STD STANDARD
STOR STORAGE
SUSP SUSPENDED
SYS SYSTEM
TEL TELEPHONE
TEMP TEMPORARY
THRU THROUGH
TO TOP OF
TRTD TREATED
TV TELEVISION
TYP TYPICAL
UNO UNLESS NOTED OTHERWISE
VERT VERTICAL
VEST VESTIBULE
VIF VERIFY IN FIELD
W WEST, WIDE
W/ WITH
W/O WITHOUT
WC WATER CLOSET
WD WOOD
WT WEIGHT
GRAPHIC SYMBOLS
ABBREVIATIONS
PROJECT INFORMATION
SERIES OF DOORS
DRINKING FOUNTAIN
ADA GUIDELINES
LOCATION MAP
ALL WORK SHALL COMPLY WITH THE AMERICANS WITH DISABILITIES ACT (2010), THE CURRENT
VERSION OF FLORIDA BUILDING CODE -- ACCESSIBILITY, AND LOCAL ACCESSIBILITY
REGULATIONS TO INCLUDE BUT NOT LIMITED TO THE FOLLOWING:
1. THE INTERNATIONAL SYMBOL FOR ACCESSIBILITY SHALL BE LOCATED ALONGSIDE THE
DOOR AT THE LATCH SIDE OF ALL ACCESSIBLE RESTROOM FACILITIES.
2. WATER CLOSETS SHALL BE POSITIONED WITH A WALL OR PARTITION TO THE REAR AND
ONE SIDE. THE CENTERLINE OF THE WATER CLOSET SHALL BE 16 INCHES MINIMUM TO
18 INCHES MAXIMUM FROM THE SIDE WALL OR PARTITION. THE SEAT HEIGHT OF A
WATER CLOSET ABOVE THE FINISH FLOOR SHALL BE 17 INCHES MINIMUM AND 19 INCHES
MAXIMUM MEASURED FROM THE TOP OF THE SEAT. SEATS SHALL NOT BE SPRUNG TO
RETURN TO A LIFTED POSITION.
3. ACCESSIBLE URINALS SHALL BE THE STALL-TYPE OR THE WALL-HUNG TYPE WITH THE
RIM 17 INCHES MAXIMUM ABOVE THE FINISH FLOOR OR GROUND. URINALS SHALL BE
13-1/2 INCHES DEEP MINIMUM MEASURED FROM THE OUTER FACE OF THE URINAL RIM
TO THE BACK OF THE FIXTURE. PROVIDE A CLEAR FLOOR SPACE 30" X 48" IN FRONT OF
THE ACCESSIBLE URINAL.
4. LAVATORIES SHALL BE INSTALLED WITH THE FRONT OF THE HIGHER OF THE RIM OR
COUNTER SURFACE 34 INCHES MAXIMUM ABOVE THE FINISH FLOOR WITH A CLEARANCE
OF 29" FROM THE FLOOR TO THE BOTTOM OF THE APRON. SPACE UNDER A LAVATORY
BETWEEN 9 INCHES AND 27 INCHES ABOVE THE FINISH FLOOR OR GROUND SHALL BE
CONSIDERED KNEE CLEARANCE. KNEE CLEARANCE SHALL EXTEND 25 INCHES
MAXIMUM UNDER AN ELEMENT AT 9 INCHES ABOVE THE FINISH FLOOR AND 8 INCHES
DEEP MINIMUM AT 27 INCHES ABOVE THE FINISH FLOOR. SPACE UNDER A LAVATORY
BETWEEN THE FINISH FLOOR OR GROUND AND 9 INCHES ABOVE THE FINISH FLOOR OR
GROUND SHALL BE CONSIDERED TOE CLEARANCE. TO CLEARANCE SHALL EXTEND 25
INCHES MAXIMUM AND 17 INCHES MINIMUM UNDER A LAVATORY. KNEE CLEARANCE
SHALL BE 30 INCHES WIDE MINIMUM.
5. WATER SUPPLY AND DRAIN PIPES UNDER LAVATORIES AND SINKS SHALL BE INSULATED
OR OTHERWISE CONFIGURED TO PROTECT AGAINST CONTACT. THERE SHALL BE NO
SHARP OR ABRASIVE SURFACES UNDER LAVATORIES AND SINKS.
6. CONTROLS FOR FAUCETS SHALL BE OPERABLE WITH ONE HAND AND SHALL NOT
REQUIRE TIGHT GRASPING, PINCHING, OR TWISTING OF THE WRIST. THE FORCE
REQUIRED TO ACTIVATE OPERABLE PARTS SHALL BE 5 POUNDS MAXIMUM.
HAND-OPERATED METERING FAUCETS SHALL REMAIN OPEN FOR 10 SECONDS MINIMUM.
7. MIRRORS LOCATED ABOVE LAVATORIES OR COUNTERTOPS SHALL BE INSTALLED WITH
THE BOTTOM EDGE OF THE REFLECTING SURFACE 40 INCHES MAXIMUM ABOVE THE
FINISH FLOOR OR GROUND. MIRRORS NOT LOCATED ABOVE LAVATORIES OR
COUNTERTOPS SHALL BE INSTALLED WITH THE BOTTOM EDGE OF THE REFLECTING
SURFACE 35 INCHES MAXIMUM ABOVE THE FINISH FLOOR OR GROUND.
8. DOORS SHALL NOT SWING INTO THE CLEAR FLOOR SPACE OR CLEARANCE REQUIRED
FOR ANY FIXTURE. DOORS SHALL BE PERMITTED TO SWING INTO THE REQUIRED
TURNING SPACE.
9. GRAB BARS SHALL BE INSTALL IN A HORIZONTAL POSITION, 33 INCHES MINIMUM AND 36
INCHES MAXIMUM ABOVE THE FINISH FLOOR MEASURED TO THE TOP OF THE GRIPPING
SURFACE. GRAB BARS AND ANY WALL OR OTHER SURFACES ADJACENT TO GRAB BARS
SHALL BE FREE OF SHARP OR ABRASIVE ELEMENTS AND SHALL HAVE ROUNDED EDGES.
GRAB BARS SHALL NOTE ROTATE WITHIN THEIR FITTINGS. ALLOWABLE STRESSES
SHALL NOT BE EXCEEDED FOR MATERIALS USED WHEN A VERTICAL OR HORIZONTAL
FORCE OF 250 POUNDS IS APPLIED AT ANY POINT ON THE GRAB BAR, FASTENER,
MOUNTING DEVICE, OR SUPPORTING STRUCTURE.
10. DRINKING FOUNTAINS SHALL BE PROVIDED WITH SPOUT OUTLETS AT 36 INCHES
MAXIMUM ABOVE THE FINISH FLOOR AND 38 INCHES MINIMUM AND 43 INCHES MAXIMUM
ABOVE THE FINISH FLOOR OR GROUND. THE SPOUT SHALL BE LOCATED 15 INCHES
MINIMUM FROM THE VERTICAL SUPPORT AND 5 INCHES MAXIMUM FROM THE FRONT
EDGE OF THE UNIT, INCLUDING BUMPERS. THE SPOUT SHALL PROVIDE A FLOW OF
WATER 4 INCHES HIGH MINIMUM AND SHALL BE LOCATED 5 INCHES MAXIMUM FROM THE
FRONT OF THE UNIT. THE ANGLE OF THE WATER STREAM SHALL BE MEASURED
HORIZONTALLY RELATIVE TO THE FRONT FACE OF THE UNIT. WHERE SPOUTS ARE
LOCATED LESS THAN 3 INCHES OF THE FRONT OF THE UNIT, THE ANGLE OF THE WATER
STREAM SHALL BE 30 DEGREES MAXIMUM. WHERE SPOUTS ARE LOCATED BETWEEN 3
INCHES AND 5 INCHES MAXIMUM FROM THE FRONT OF THE UNIT, THE ANGLE OF THE
WATER STREAM SHALL BE 15 DEGREES MAXIMUM.
11. DOOR CLOSERS SHALL BE ADJUSTED SO THAT FROM AN OPEN POSITION OF 90
DEGREES, THE TIME REQUIRED TO MOVE THE DOOR TO A POSITION OF 12 DEGREES
FROM THE LATCH IS 5 SECONDS MINIMUM.
12. FIRE DOORS SHALL HAVE A MINIMUM OPENING FORCE ALLOWABLE BY THE
APPROPRIATE ADMINISTRATIVE AUTHORITY. THE FORCE FOR PUSHING OR PULLING
OPEN A DOOR OR GATE OTHER THAN FIRE DOORS SHALL BE 5 POUNDS MAXIMUM.
THESE FORCES DO NOT APPLY TO THE FORCE REQUIRED TO RETRACT LATCH BOLTS
OR DISENGAGE OTHER DEVICES THAT HOLD THE DOOR OR GATE IN A CLOSED
POSITION.
13. FIRE ALARM SYSTEMS SHALL HAVE PERMANENTLY INSTALLED AUDIBLE AND VISIBLE
ALARMS COMPLYING WITH NFPA 72 AND ANSI A117.1, EXCEPT THAT THE MAXIMUM
ALLOWABLE SOUND LEVEL OF AUDIBLE NOTIFICATION APPLIANCES COMPLYING WITH
SECTION 4-3.2.1 OF NFPA 72 (1999 EDITION) SHALL HAVE A SOUND LEVEL NO MORE THAN
110 DB AT THE MINIMUM HEARING DISTANCE FROM THE AUDIBLE APPLIANCE.
14. FLOOR AND GROUND SURFACES SHALL BE STABLE, FIRM, AND SLIP RESISTANT.
CHANGES IN LEVEL OF 1/4 INCH HIGH MAXIMUM SHALL BE PERMITTED TO BE VERTICAL.
CHANGES IN LEVEL BETWEEN 1/4 INCH HIGH MINIMUM AND 1/2 INCH HIGH MAXIMUM
SHALL BE BEVELED WITH A SLOPE NOT STEEPER THAN 1:2.
15. CHANGES IN LEVEL AT FLOOR OR GROUND SURFACE WITHIN REQUIRED MANEUVERING
CLEARANCES AND AT DOORS ARE NOT PERMITTED, WITH THE FOLLOWING EXCEPTIONS:
A. SLOPES NOT STEEPER THAN 1:48 SHALL BE PERMITTED.
B. CHANGES IN LEVEL AT THRESHOLDS OF DOORS SHALL BE 1/2 INCH HIGH MAXIMUM.
THE ARCHITECT HAS IDENTIFIED THE FOLLOWING ALTERNATES FOR ADDITIONAL PROJECT
VALUE. CONTRACTOR TO PROVIDE A SEPARATE PRICE FOR THE WORK DESCRIBED.
1. N/A
SHEET DESCRIPTION REVISION #
ARCHITECTURAL
G101 COVER SHEET
G102
INDEX OF DRAWINGS
A301 REFLECTED CEILING PLAN - LEVEL 3
A702 INTERIOR ELEVATIONS AND ENLARGED FLOOR PLANS
A901 DOOR SCHEDULE AND DETAILS
ID201 FLOOR PATTERN PLAN AND SIGNAGE
MECHANICAL
M001 MECHANCIAL LEGEND, SYMBOLS, AND NOTES
PLUMBING
PLUMBING LEGEND, SYMBOLS AND NOTESP001
PLUMBING PLAN - GRAVITY DEMO
PLUMBING PLAN - GRAVITY PERSONAL RR
FP001 FIRE PROTECTION SYMBOLS, SPECS AND NOTES
FIRE PROTECTION
FP002 FIRE PROTECTION PLAN
E001 ELECTRICAL SYMBOLS, LEGEND, AND ABBREVIATIONS
ELECTRICAL
ELECTRICAL GENERAL NOTES
ELECTRICAL DEMOLITION PLAN
ELECTRICAL LIGHTING PLAN
LIGHTING PHOTOMETRIC PLAN - NORMAL
LIGHTING PHOTOMETRIC PLAN - EMERGENCY
ELECTRICAL POWER & SYSTEMS PLAN
G103
G104
G105
GENERAL REQUIREMENTS
ARCHITECTURAL SPECIFICATIONS
ARCHITECTURAL SPECIFICATIONS
ARCHITECTURAL SPECIFICATIONS
A101 LIFE SAFETY PLAN
A201 FLOOR PLAN - LEVEL 3, PARTIAL DEMOLITION PLAN - LEVEL 2
A202 PARTITION TYPES AND DETAILS
PARTIAL REFLECTED CEILING PLAN - LEVEL 2
A701 FINISH SCHEDULE AND DETAILS
A703 INTERIOR ELEVATIONS AND DETAILS
M101
M201
M301
MECHANCIAL DEMOLITION PLAN
MECHANCIAL FLOOR PLAN
MECHANCIAL DETAILS
P200
P201
P202
P203
P302
P303
PLUMBING PLAN - GRAVITY GROUP RR
PLUMBING PLAN - PRESSURE
PLUMBING RISERS - GRAVITY
PLUMBING RISERS - PRESSURE
E002
E101
E201
E202
E203
E301
E401
E402
E501
E502
ELECTRICAL RISER DIAGRAMS
ELECTRICAL SCHEDULES
ELECTRICAL DETAILS
ELECTRICAL DETAILS
HI-LO DRINKING FOUNTAIN
(SURFACE MOUNTED)
42" SPOUT
HEIGHT
36" SPOUT
HEIGHT
G101
LL
Cover Sheet
REVISION:
DRAWN BY:
DATE:
SHEET TITLE:
ãCOPYRIGHT 2026 by Tsark Architecture, LLC All rights reserved. No part of this work covered by the copyright hereon may be reproduced or used in any form or by any means - graphic, electronic or mechanical, including photocopying, recording, taping or information storage and retrieval systems - without written permission of the copyright holder.
06/16/2026
Tsark Architecture, LLC 1600 Sarno Rd., Suite 212 Melbourne, Florida 32935 tel: (321) 241-6378 License Number: AA26003779
P al m B ay C it y
H al l
M al ab ar R o ad
P al m
B ay
F lo ri d a
P ro je ct
N o
A
SUBMITTALS
1 03/31/26 30% SD SUBMITTAL
2 60% DD SUBMITTAL
B u ild in g
"E
M o d if ic at io n s
3 90% CD SUBMITTAL
4 100% IFP SUBMITTAL
04/21/26
05/21/26
06/16/26
10" MAX.
" M
AX
" M
AX
" M
AX
" M
AX
> 10"-24" MAX. 10" MAX.
" M
AX
" M
IN
" M
AX
" M
AX
>20"-25" MAX.20" MAX.
" M
IN
" M
AX
OBSTRUCTED HIGH SIDE REACH UNOBSTRUCTED
SIDE REACH
UNOBSTRUCTED
FORWARD REACH
OBSTRUCTED HIGH FORWARD REACH
A B
A B
C
C
REFERENCE 904.3.2 FBC AND 904.4.1 FBC - COUNTER AND PARALLEL
APPROACH FOR FURTHER INFORMATION.
HOT WATER SUPPLY & DRAIN LINES SHALL BE FULLY
INSULATED OR COVERED W/ A REMOVABLE,
NON-METALLIC BAFFLE WHEN HOT WATER TEMP.
6" 8"
17" MIN.
48" MIN. CLEAR
SHADED AREA DENOTES KNEE & TOE
SPACE REQ'D. @ ACCESSIBLE LAV.
DIRECTION OF TRAVEL
FLOOR LINE
DASHED LINE DENOTES MAX. SIZE OF
MOUNTING BRACKETS FROM REMOVABLE
PROTECTION & APPEARANCCE PANEL
MIRROR
9" M
IN
" M
IN
" M
IN
" M
AX
" M
AX
EXCEEDS 120° F.
48" MIN.
48" MIN.
48" MIN.
(B)
T-SHAPED SPACE FOR 180° TURNS
60" MIN.
(A)
60 INCH
DIAMETER
SPACE
12" MIN. 36" MIN.
" M
IN
" M
IN
" M
IN
REVISION 1 - 07/07/26
REVISION 1 - 07/07/26
REVISION 1 - 07/07/26
REVISION 1 - 07/07/26
REVISION 1 - 07/07/26
REVISION 1 - 07/07/26
1 07/07/2026 OWNER CHANGES
REVISION 1 - 07/07/26
2 07/29/2026 COMMENT RESPONSES
REVISION 2 - 07/29/26
REVISION 2 - 07/29/26
GENERAL REQUIREMENTS SUBMITTAL PROCEDURES
1. THE ARCHITECT HAS PREPARED THIS SET OF CONTRACT DOCUMENTS BASED ON VISUAL
INSPECTION OF THE EXISTING PREMISES AND ON INFORMATION PROVIDED BY THE
OWNER.
2. IN THE EVENT OF A DISCREPANCY IN THE CONSTRUCTION DOCUMENTS, THE PREVAILING
ORDER SHALL BE:
A. CONTRACT FOR CONSTRUCTION AGREEMENT
B. GENERAL REQUIREMENTS
C. SPECIAL REQUIREMENTS
D. OWNER'S PUBLISHED DESIGN STANDARDS, IF APPLICABLE
E. SPECIFICATIONS
F. DETAILS ON DRAWINGS
G. PLAN DRAWINGS
3. ALL DIMENSIONS GOVERNED BY EXISTING CONDITIONS ARE APPROXIMATE. ALL SUCH
DIMENSIONS AND CONDITIONS SHALL BE FIELD VERIFIED BY THE GENERAL CONTRACTOR
PRIOR TO PROCEEDING WITH ANY WORK. SHOULD CONDITIONS OR DIMENSIONS VARY
FROM THOSE SHOWN, THE CONTRACTOR SHALL NOTIFY THE ARCHITECT BEFORE
PROCEEDING. USE FIGURED DIMENSIONS. DO NOT SCALE DRAWINGS. WHERE
DIMENSIONS ARE SHOWN WITH A "±", ADJUSTMENTS MAY BE MADE TO SUIT FIELD
CONDITIONS.
4. TO ESTABLISH THE COMPREHENSIVE SCOPE OF WORK AND TO ASSURE COORDINATION
WITH OTHER TRADES, EACH SUBCONTRACTOR SHALL COMPLETELY REVIEW THE PLANS,
NOT ONLY FOR HIS OR HER RESPECTIVE TRADE, BUT FOR THE WORK OF OTHER TRADES AS
WELL. THE DOCUMENTS ARE INTERDEPENDENT. ONCE THE CONTRACTOR OR
SUBCONTRACTOR HAS COMMENCED WITH HIS WORK, IT SHALL BE ASSUMED THAT HE
HAS ACCEPTED THE CONDITIONS IN THE FIELD TO BE CORRECT AND RIGHT FOR THE
INSTALLATION OF HIS WORK.
5. ALL WORK SHALL BE ACCOMPLISHED IN ACCORDANCE WITH THE ENVIRONMENTAL
PROTECTION AGENCY, STATE AND LOCAL ENVIRONMENTAL LAWS AND REGULATIONS.
THE CONTRACTOR SHALL OBTAIN ALL REQUIRED PERMITS PRIOR TO CONSTRUCTION.
PERMITS SHALL BE POSTED AT THE JOBSITE.
6. CONSTRUCTION SHALL COMPLY WITH THE CURRENT EDITION OF THE FLORIDA BUILDING
CODE.
7. ALL WORK SHALL BE OF BEST PRACTICE OF EACH TRADE.
8. THE CONTRACTOR SHALL PROVIDE ALL LABOR AND MATERIAL NECESSARY TO MEET THE
STANDARD OF CARE FOR A COMPLETE JOB INCLUDING EQUIPMENT AND TOOLS.
9. NO ASBESTOS CONTAINING BUILDING MATERIALS MAY BE USED DURING CONSTRUCTION.
10. ALL SUBCONTRACTORS SHALL BE LICENSED TO OPERATE IN BREVARD COUNTY, FLORIDA.
11. OWNER SHALL RETAIN ALL SALVAGE RIGHTS UNTIL THE RIGHTS ARE RELEASED BY THE
OWNER.
12. PROVIDE PRODUCTS HAVING "ENERGY STAR" CERTIFICATIONS WHEN AVAILABLE.
13. CONTRACTOR SHALL PROVIDE A CONSTRUCTION ACCESS AND STAGING AREA PLAN FOR
OWNER'S APPROVAL.
14. THE PROJECT SHALL HAVE FULL TIME, CONSTRUCTION REPRESENTATION DURING ALL
HOURS OF OPERATION. THIS REPRESENTATION CAN BE IN THE FORM OF A PROJECT
MANAGER OR SUPERINTENDENT.
15. CONTRACTOR SHALL PROVIDE A SAFETY BARRIER TO PREVENT INTERACTIONS BETWEEN
THE PUBLIC AND THE JOBSITE.
16. WORKING HOURS SHALL BE COORDINATED WITH, AND APPROVED BY, THE OWNER.
17. PROGRESS PAYMENTS ARE TO BE SUBMITTED MONTHLY.
18. A SCHEDULE OF VALUES SHALL BE SUBMITTED AND APPROVED PRIOR TO THE INITIAL PAY
REQUEST.
19. A DAILY REPORT IS TO BE KEPT BY THE CONTRACTOR AND A WEEKLY REPORT IS TO BE
SUBMITTED TO THE OWNER'S REPRESENTATIVE SHOWING THE CURRENT PROJECT
STATUS, TWO WEEK LOOK-AHEAD, ISSUES AND PROBLEMS, PERMIT STATUS AND PERCENT
COMPLETE.
20. THE CONTRACTOR'S CONSTRUCTION SCHEDULE SHALL BE IN THE FORM OF A LINEAR BAR
CHART SCHEDULE.
21. CONTRACTOR IS TO PROVIDE A COMPLETE SUBMITTAL REQUIREMENT MATRIX FOR EACH
PRODUCT LISTING ALL ANTICIPATED SUBMITTALS CROSS REFERENCED WITH THE SECTION
NUMBER.
22. THE QUANTITY OF SUBMITTALS THAT WILL BE REQUIRED FOR THE PROJECT INCLUDING
THE NUMBER OF SAMPLES, PRODUCT DATA AND SHOP DRAWINGS REQUIRED TO BE
DETERMINED.
23. CONTRACTOR IS TO HOLD WEEKLY COORDINATION MEETINGS, INVITING BOTH THE
OWNER'S REPRESENTATIVE AND THE ARCHITECT.
24. COORDINATION MEETINGS SHALL HAVE AN AGENDA PREPARED BY AND MEETING
MINUTES TAKEN BY THE CONTRACTOR.
25. THE CONSTRUCTION SCHEDULE WILL BE UPDATED MONTHLY AT EACH PAY REQUEST AND
BE REVIEWED AT THAT TIME AS A CONDITION OF THE PAY APPLICATION.
26. THROUGHOUT THE DURATION OF CONSTRUCTION, THE CONTRACTOR SHALL MAKE EVERY
EFFORT TO ENSURE THE BUILDING REMAIN IN DRIED-IN CONDITION AND PREVENT
UNLAWFUL ENTRY INTO THE CONSTRUCTION SITE.
27. THE CONTRACTOR SHALL BE RESPONSIBLE FOR CONTRACTING WITH AND COORDINATION
OF MATERIALS TESTING AS PART OF QUALITY ASSURANCE. THE TESTING AGENCY IS TO
COPY THE OWNER AND THE ARCHITECT ON ALL REPORTS.
28. THE CONTRACTOR IS RESPONSIBLE FOR PROVIDING LADDERS OR OTHER MEANS OF
ACCESS TO THE AUTHORITY HAVING JURISDICTION (AHJ), ARCHITECT, ENGINEER, AND
OWNER FOR REQUIRED OBSERVATIONS AND INSPECTIONS.
29. ALL EXITS SHALL COMPLY WITH FLORIDA ACCESSIBILITY CODE FOR LEVEL ENTRY; SEE FBC, ACCESSIBILITY, SECTION 303; CHANGES IN LEVEL.
30. CONTRACTORS SHALL INCLUDE DIGITAL COPIES OF THE RECORD DRAWINGS ALONG WITH
ONE ELECTRONIC COPY WITH CLOSE-OUT DOCUMENTATION.
31. FINAL SUBMITTAL SHALL INCLUDE COPIES OF THE OPERATION AND MAINTENANCE DATA
BINDERS FOR THE OWNER'S USE THAT NOTES CONTRACTOR LISTINGS, PRODUCTS, AND
WARRANTY INFORMATION IN DIGITAL FORMAT.
32. ALL MATERIAL SAFETY DATA SHEETS ON ANY HAZARDOUS PRODUCT SHALL BE KEPT ON
FILE AT JOBSITE, AND INCLUDED IN CLOSE-OUT DOCUMENTATION.
33. ALL TRAINING VIDEOS SHALL BE DIGITALLY RECORDED AND SUBMITTED TO THE OWNER.
34. THE CONTRACTOR IS TO PROVIDE FINAL CLEANING. THE OWNER RESERVES THE RIGHT TO
PROVIDE CLEANING SERVICES WHEN CLEAN-UP HAS NOT BEEN PROVIDED TO THE
SATISFACTION OF THE OWNER. ASSOCIATED COSTS WILL BE DEDUCTED FROM THE
CONTRACTOR'S FINAL PAYMENT.
35. CONSTRUCTION OF WORK INDICATED ON THE DRAWINGS AS (N.I.C.) IS NOT IN CONTRACT.
36. WHERE GYPSUM BOARD LAYERS DIFFER BETWEEN TWO ADJOINING WALLS, ALIGN
SURFACES TO MAINTAIN A CONTINUOUS FINISH OF WALL.
37. ELECTROLYTIC PROTECTION SHALL BE PROVIDED BETWEEN DISSIMILAR METALS
WHENEVER THE TWO ARE IN CONTACT.
38. DETAILS NOT SHOWN ARE SIMILAR IN NATURE TO THOSE DETAILED. WHERE SPECIFIC
DIMENSIONS, DETAILS OR DESIGN INTENT CANNOT BE DETERMINED, CONSULT
ARCHITECT BEFORE PROCEEDING WITH THE WORK. TYPICAL DETAILS APPLY AT ALL
SIMILAR CONDITIONS WHETHER CROSS REFERENCED OR NOT.
39. PROVIDE PROPER ANCHORAGE OF ESSENTIAL EQUIPMENT IN ACCORDANCE WITH
APPLICABLE CODES. WOOD BLOCKING IN CONTACT WITH CONCRETE OR MASONRY SHALL
BE PRESSURE TREATED.
40. GLAZING SUBJECT TO HUMAN IMPACT AS IDENTIFIED IN APPLICABLE CODES SHALL BE
SAFETY GLAZING MATERIAL. EACH LIGHT OF LAMINATED OR TEMPERED GLAZING SHALL
BE IDENTIFIED BY A PERMANENT LABEL, WHICH SPECIFIES THE LABELER, OR
MANUFACTURER AND THAT SAFETY GLAZING MATERIAL HAS BEEN UTILIZED.
41. THESE DRAWINGS, SPECIFICATIONS, AND ANY ADDENDA SHALL BE THE BASIS FOR THE
CONTRACT FOR CONSTRUCTION BETWEEN THE GENERAL CONTRACTOR AND THE OWNER.
THE RESPONSIBILITIES OF THE OWNER, ARCHITECT, AND GENERAL CONTRACTOR SHALL BE
AS DESCRIBED IN AIA DOCUMENT A201-2017 - GENERAL CONDITIONS OF THE CONTRACT
FOR CONSTRUCTION.
42. CONTRACTOR AND TEAM MUST COMPLY WITH A CITY OF PALM BAY BACKGROUND CHECK
PRIOR TO THE START OF WORK.
43. STANDARDS OF QUALITY - “OR EQUAL” INTERPRETATION
a. MANUFACTURER'S NAMES, TRADE NAMES, BRAND NAMES, MODEL AND CATALOG
NUMBERS USED IN THESE SPECIFICATIONS ARE FOR THE PURPOSE OF
DESCRIBING AND ESTABLISHING GENERAL QUALITY LEVELS. SUCH REFERENCES
ARE NOT INTENDED TO BE RESTRICTIVE. BIDS WILL BE CONSIDERED FOR
ALTERNATIVE BRANDS THAT MEET OR EXCEED THE QUALITY OF THE
SPECIFICATIONS LISTED FOR ANY ITEM. IT IS THE BIDDER'S RESPONSIBILITY TO
SUBMIT BRAND LITERATURE AND/OR SAMPLES TO DEMONSTRATE THE
EQUIVALENCY OF THE PRODUCT OFFERED.
a.a. WHEREVER THE SPECIFICATIONS INDICATE A PRODUCT OF A PARTICULAR
MANUFACTURER, MODEL OR BRAND, AND IN THE ABSENCE OF ANY
STATEMENT TO THE CONTRARY BY THE VENDOR, THE BID SHALL BE
INTERPRETED AS BEING FOR THE EXACT MANUFACTURER, MODEL, OR BRAND
SPECIFIED, TOGETHER WITH ALL ACCESSORIES, QUALITIES, ETC.,
ENUMERATED IN THE DETAILED SPECIFICATIONS; THEREFORE, THE BIDDER
SHALL FURNISH THE ITEM AS SPECIFIED.
PART 1 - GENERAL
1.1 SUMMARY
A. THIS SECTION INCLUDES ADMINISTRATIVE AND PROCEDURAL REQUIREMENTS FOR
SUBMITTING SHOP DRAWINGS, PRODUCT DATA, SAMPLES, AND OTHER MISCELLANEOUS
SUBMITTALS.
1.2 DEFINITIONS
A. ACTION SUBMITTALS: WRITTEN AND GRAPHIC INFORMATION THAT REQUIRES
ARCHITECT'S/ENGINEER'S RESPONSIVE ACTION.
B. INFORMATIONAL SUBMITTALS: WRITTEN INFORMATION THAT DOES NOT REQUIRE
ARCHITECT'S/ENGINEER'S APPROVAL. SUBMITTALS MAY BE REJECTED FOR NOT COMPLYING
WITH REQUIREMENTS.
1.3 SUBMITTAL PROCEDURES
A. GENERAL: ELECTRONIC COPIES (.PDF ONLY) OF DRAWINGS OF THE CONTRACT DRAWINGS
WILL BE PROVIDED BY ARCHITECT/ENGINEER FOR CONTRACTOR'S USE IN PREPARING
SUBMITTALS.
B. CONTRACTOR SHALL SUBMIT SOFT COPIES OF PRODUCT DATA, SHOP DRAWINGS, AND
PHYSICAL COPIES OF SAMPLES.
C. ALL SUBMITTED SHOP DRAWINGS SHALL HAVE ENHANCEMENT OR ADDITIONAL DETAILS
THAN THAT OF THE ARCHITECT'S/ENGINEER'S, REFLECTING TYPES OF MATERIAL ALREADY
SUBMITTED FOR APPROVAL AND APPROVED BY THE ARCHITECT/ENGINEER AND
REFLECTING ALL NECESSARY EQUIPMENT, IF ANY, OR ELSE THE SUBMITTED SHOP DRAWING
SHALL NOT BE CONSIDERED AS COMPLETE.
D. COORDINATION: COORDINATE PREPARATION AND PROCESSING OF SUBMITTALS WITH
PERFORMANCE OF CONSTRUCTION ACTIVITIES.
E. PROCESSING TIME: ALLOW ENOUGH TIME FOR SUBMITTAL REVIEW, INCLUDING TIME FOR
RESUBMITTALS, AS FOLLOWS. TIME FOR REVIEW SHALL COMMENCE ON
ARCHITECT'S/ENGINEER'S RECEIPT OF SUBMITTAL.
1. INITIAL REVIEW: ALLOW UP TO 14 DAYS FOR INITIAL REVIEW OF EACH SUBMITTAL.
ALLOW ADDITIONAL TIME IF PROCESSING MUST BE DELAYED TO PERMIT
COORDINATION WITH SUBSEQUENT SUBMITTALS. ARCHITECT/ENGINEER WILL ADVISE
CONTRACTOR WHEN A SUBMITTAL BEING PROCESSED MUST BE DELAYED FOR
COORDINATION.
2. CONCURRENT REVIEW: WHERE CONCURRENT REVIEW OF SUBMITTALS BY
ARCHITECT'S/ENGINEER'S CONSULTANTS, OWNER, OR OTHER PARTIES IS REQUIRED,
ALLOW UP TO 10 BUSINESS DAYS FOR INITIAL REVIEW OF EACH SUBMITTAL.
3. NO EXTENSION OF THE CONTRACT TIME WILL BE AUTHORIZED BECAUSE OF FAILURE TO
TRANSMIT SUBMITTALS ENOUGH IN ADVANCE OF THE WORK TO PERMIT PROCESSING.
F. IDENTIFICATION: PLACE A LABEL OR TITLE BLOCK ON EACH SUBMITTAL FOR
IDENTIFICATION.
1. INDICATE NAME OF FIRM OR ENTITY THAT PREPARED EACH SUBMITTAL ON LABEL OR
TITLE BLOCK.
2. PROVIDE A SPACE APPROXIMATELY 4 BY 5 INCHES (100 BY 125 MM) ON LABEL OR
BESIDE TITLE BLOCK TO RECORD CONTRACTOR'S REVIEW AND APPROVAL MARKINGS
AND ACTION TAKEN BY ARCHITECT/ENGINEER.
3. INCLUDE THE FOLLOWING INFORMATION ON LABEL FOR PROCESSING AND RECORDING
ACTION TAKEN:
a. PROJECT NAME.
b. DATE.
c. NAME OF ARCHITECT/ENGINEER.
d. NAME OF CONTRACTOR.
e. NAME OF SUBCONTRACTOR.
f. NAME OF SUPPLIER.
g. NAME OF MANUFACTURER.
h. UNIQUE IDENTIFIER, INCLUDING REVISION NUMBER.
i. NUMBER AND TITLE OF APPROPRIATE SPECIFICATION SECTION.
j. DRAWING NUMBER AND DETAIL REFERENCES, AS APPROPRIATE.
G. DEVIATIONS: HIGHLIGHT, ENCIRCLE, OR OTHERWISE IDENTIFY DEVIATIONS FROM THE
CONTRACT DOCUMENTS ON SUBMITTALS.
H. TRANSMITTAL: ARCHITECT/ENGINEER WILL RETURN SUBMITTALS, WITHOUT REVIEW,
RECEIVED FROM SOURCES OTHER THAN CONTRACTOR.
1. ON AN ATTACHED SEPARATE SHEET, PREPARED ON CONTRACTOR'S LETTERHEAD,
RECORD RELEVANT INFORMATION, REQUESTS FOR DATA, REVISIONS OTHER THAN
THOSE REQUESTED BY ARCHITECT/ENGINEER ON PREVIOUS SUBMITTALS, AND
DEVIATIONS FROM REQUIREMENTS OF THE CONTRACT DOCUMENTS, INCLUDING
MINOR VARIATIONS AND LIMITATIONS. INCLUDE THE SAME LABEL INFORMATION AS
THE RELATED SUBMITTAL.
2. INCLUDE CONTRACTOR'S CERTIFICATION STATING THAT INFORMATION SUBMITTED
COMPLIES WITH REQUIREMENTS OF THE CONTRACT DOCUMENTS.
I. DISTRIBUTION: FURNISH COPIES OF FINAL SUBMITTALS TO MANUFACTURERS,
SUBCONTRACTORS, SUPPLIERS, FABRICATORS, INSTALLERS, AUTHORITIES HAVING
JURISDICTION, AND OTHERS AS NECESSARY FOR PERFORMANCE OF CONSTRUCTION
ACTIVITIES.
J. USE FOR CONSTRUCTION: USE ONLY FINAL SUBMITTALS WITH MARK INDICATING ACTION
TAKEN BY ARCHITECT/ENGINEER IN CONNECTION WITH CONSTRUCTION.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. GENERAL: PREPARE AND SUBMIT ACTION SUBMITTALS REQUIRED BY CONTRACT
DOCUMENTS.
1. NUMBER OF COPIES: SUBMIT COPIES OF EACH SUBMITTAL, AS FOLLOWS, UNLESS
OTHERWISE INDICATED:
a. INITIAL SUBMITTAL: SUBMIT A PRELIMINARY SINGLE COPY OF EACH SUBMITTAL
WHERE SELECTION OF OPTIONS, COLOR, PATTERN, TEXTURE, OR SIMILAR
CHARACTERISTICS IS REQUIRED. ARCHITECT/ENGINEER, WILL RETURN SUBMITTAL
WITH OPTIONS SELECTED.
B. PRODUCT DATA: COLLECT INFORMATION INTO A SINGLE SUBMITTAL FOR EACH ELEMENT
OF CONSTRUCTION AND TYPE OF PRODUCT OR EQUIPMENT. l
1. IF INFORMATION MUST BE SPECIALLY PREPARED FOR SUBMITTAL BECAUSE STANDARD
PRINTED DATA ARE NOT SUITABLE FOR USE, SUBMIT AS SHOP DRAWINGS, NOT AS
PRODUCT DATA.
2. MARK EACH COPY OF EACH SUBMITTAL TO SHOW WHICH PRODUCTS AND OPTIONS
ARE APPLICABLE.
3. INCLUDE THE FOLLOWING INFORMATION, AS APPLICABLE:
a. MANUFACTURER'S WRITTEN RECOMMENDATIONS.
b. MANUFACTURER'S PRODUCT SPECIFICATIONS.
c. MANUFACTURER'S INSTALLATION INSTRUCTIONS.
d. STANDARD COLOR CHARTS.
e. MANUFACTURER'S CATALOG CUTS.
f. WIRING DIAGRAMS SHOWING FACTORY-INSTALLED WIRING.
g. PRINTED PERFORMANCE CURVES.
h. OPERATIONAL RANGE DIAGRAMS.
i. MILL REPORTS.
j. STANDARD PRODUCT OPERATING AND MAINTENANCE MANUALS.
k. COMPLIANCE WITH RECOGNIZED TRADE ASSOCIATION STANDARDS.
l. COMPLIANCE WITH RECOGNIZED TESTING AGENCY STANDARDS.
m. APPLICATION OF TESTING AGENCY LABELS AND SEALS.
n. NOTATION OF COORDINATION REQUIREMENTS.
C. SHOP DRAWINGS: PREPARE PROJECT-SPECIFIC INFORMATION, DRAWN ACCURATELY TO
SCALE. DO NOT BASE SHOP DRAWINGS ON REPRODUCTIONS OF THE CONTRACT
DOCUMENTS OR STANDARD PRINTED DATA.
D. SAMPLES: PREPARE PHYSICAL UNITS OF MATERIALS OR PRODUCTS, INCLUDING THE
FOLLOWING:
1. SAMPLES FOR INITIAL SELECTION: SUBMIT MANUFACTURER'S COLOR CHARTS
CONSISTING OF UNITS OR SECTIONS OF UNITS SHOWING THE FULL RANGE OF COLORS,
TEXTURES, AND PATTERNS AVAILABLE.
2. SAMPLES FOR VERIFICATION: SUBMIT FULL-SIZE UNITS OR SAMPLES OF SIZE
INDICATED, PREPARED FROM THE SAME MATERIAL TO BE USED FOR THE WORK, CURED
AND FINISHED IN MANNER SPECIFIED, AND PHYSICALLY IDENTICAL WITH THE PRODUCT
PROPOSED FOR USE, AND THAT SHOW FULL RANGE OF COLOR AND TEXTURE
VARIATIONS EXPECTED. SAMPLES INCLUDE, BUT ARE NOT LIMITED TO, THE
FOLLOWING: PARTIAL SECTIONS OF MANUFACTURED OR FABRICATED COMPONENTS;
SMALL CUTS OR CONTAINERS OF MATERIALS; COMPLETE UNITS OF REPETITIVELY USED
MATERIALS; SWATCHES SHOWING COLOR, TEXTURE, AND PATTERN; COLOR RANGE
SETS; AND COMPONENTS USED FOR INDEPENDENT TESTING AND INSPECTION.
3. PREPARATION: MOUNT, DISPLAY, OR PACKAGE SAMPLES IN MANNER SPECIFIED TO
FACILITATE REVIEW OF QUALITIES INDICATED. PREPARE SAMPLES TO MATCH
ARCHITECT'S/ENGINEER'S SAMPLE WHERE SO INDICATED. ATTACH LABEL ON
UNEXPOSED SIDE THAT INCLUDES THE FOLLOWING:
a. GENERIC DESCRIPTION OF SAMPLE.
b. PRODUCT NAME OR NAME OF MANUFACTURER.
c. SAMPLE SOURCE.
4. ADDITIONAL INFORMATION: ON AN ATTACHED SEPARATE SHEET, PREPARED ON
CONTRACTOR'S LETTERHEAD, PROVIDE THE FOLLOWING, AS APPLICABLE:
a. SIZE LIMITATIONS.
b. COMPLIANCE WITH RECOGNIZED STANDARDS.
c. AVAILABILITY.
d. DELIVERY TIME.
5. SUBMIT SAMPLES FOR REVIEW OF KIND, COLOR, PATTERN, AND TEXTURE FOR A FINAL
CHECK OF THESE CHARACTERISTICS WITH OTHER ELEMENTS AND FOR A COMPARISON
OF THESE CHARACTERISTICS BETWEEN FINAL SUBMITTAL AND ACTUAL COMPONENT
AS DELIVERED AND INSTALLED.
6. NUMBER OF SAMPLES FOR INITIAL SELECTION: SUBMIT ONE FULL SET OF AVAILABLE
CHOICES WHERE COLOR, PATTERN, TEXTURE, OR SIMILAR CHARACTERISTICS ARE
REQUIRED TO BE SELECTED FROM MANUFACTURER'S PRODUCT LINE.
ARCHITECT/ENGINEER WILL RETURN SUBMITTAL WITH OPTIONS SELECTED.
7. DISPOSITION: MAINTAIN SETS OF APPROVED SAMPLES AT PROJECT SITE, AVAILABLE
FOR QUALITY- CONTROL COMPARISONS THROUGHOUT THE COURSE OF
CONSTRUCTION ACTIVITY. SAMPLE SETS MAY BE USED TO DETERMINE FINAL
ACCEPTANCE OF CONSTRUCTION ASSOCIATED WITH EACH SET.
2.2 INFORMATIONAL SUBMITTALS
A. GENERAL: PREPARE AND SUBMIT INFORMATIONAL SUBMITTALS REQUIRED BY OTHER
SPECIFICATION SECTIONS.
1. CERTIFICATES AND CERTIFICATIONS: PROVIDE A NOTARIZED STATEMENT THAT
INCLUDES SIGNATURE OF ENTITY RESPONSIBLE FOR PREPARING CERTIFICATION.
CERTIFICATES AND CERTIFICATIONS SHALL BE SIGNED BY AN OFFICER OR OTHER
INDIVIDUAL AUTHORIZED TO SIGN DOCUMENTS ON BEHALF OF THAT ENTITY.
2. TEST AND INSPECTION REPORTS: COMPLY WITH REQUIREMENTS IN CONTRACT
DOCUMENTS
B. CONTRACTOR'S CONSTRUCTION SCHEDULE:
C. MATERIAL TEST REPORTS: PREPARE REPORTS WRITTEN BY A QUALIFIED TESTING AGENCY,
ON TESTING AGENCY'S STANDARD FORM, INDICATING AND INTERPRETING TEST RESULTS
OF MATERIAL FOR COMPLIANCE WITH REQUIREMENTS.
D. MAINTENANCE DATA: PREPARE WRITTEN AND GRAPHIC INSTRUCTIONS AND PROCEDURES
FOR OPERATION AND NORMAL MAINTENANCE OF PRODUCTS AND EQUIPMENT. COMPLY
WITH GENERAL REQUIREMENTS.
E. MANUFACTURER'S INSTRUCTIONS: PREPARE WRITTEN OR PUBLISHED INFORMATION THAT
DOCUMENTS MANUFACTURER'S RECOMMENDATIONS, GUIDELINES, AND PROCEDURES
FOR INSTALLING OR OPERATING A PRODUCT OR EQUIPMENT. INCLUDE NAME OF PRODUCT
AND NAME, ADDRESS, AND TELEPHONE NUMBER OF MANUFACTURER. INCLUDE THE
FOLLOWING, AS APPLICABLE:
1. PREPARATION OF SUBSTRATES.
2. RECOMMENDATIONS FOR CLEANING AND PROTECTION.
F. MANUFACTURER'S FIELD REPORTS: PREPARE WRITTEN INFORMATION DOCUMENTING
FACTORY-AUTHORIZED SERVICE REPRESENTATIVE'S TESTS AND INSPECTIONS. INCLUDE THE
FOLLOWING, AS APPLICABLE:
1. NAME, ADDRESS, AND TELEPHONE NUMBER OF FACTORY-AUTHORIZED SERVICE
REPRESENTATIVE MAKING REPORT.
2. STATEMENT ON CONDITION OF SUBSTRATES AND THEIR ACCEPTABILITY FOR
INSTALLATION OF PRODUCT.
3. STATEMENT THAT PRODUCTS AT PROJECT SITE COMPLY WITH REQUIREMENTS.
4. SUMMARY OF INSTALLATION PROCEDURES BEING FOLLOWED, WHETHER THEY
COMPLY WITH REQUIREMENTS AND, IF NOT, WHAT CORRECTIVE ACTION WAS TAKEN.
5. RESULTS OF OPERATIONAL AND OTHER TESTS AND A STATEMENT OF WHETHER
OBSERVED PERFORMANCE COMPLIES WITH REQUIREMENTS.
6. STATEMENT WHETHER CONDITIONS, PRODUCTS, AND INSTALLATION WILL AFFECT
WARRANTY.
G. MONTHLY PROGRESS MEETINGS: REPORT SHALL INCLUDE THE FOLLOWING:
1. SCHEDULE OF PLANNING WITH UPDATES AND CURRENT SITUATION AT THE DATE OF
REPORT PREPARATION.
2. SUBMITTALS LOG.
3. CONSTRUCTION PROGRESS PHOTOGRAPHS
4. DAILY REPORTS
5. VARIATION ORDERS.
6. PAYMENT CERTIFICATES.
7. LIST OF PROBLEMS FACED ON SITE.
PART 3 - EXECUTION
3.1 CONTRACTOR'S REVIEW
A. REVIEW EACH SUBMITTAL AND CHECK FOR COMPLIANCE WITH THE CONTRACT
DOCUMENTS. NOTE CORRECTIONS AND FIELD DIMENSIONS. MARK WITH APPROVAL STAMP
BEFORE SUBMITTING TO ARCHITECT/ENGINEER.
B. APPROVAL STAMP: STAMP EACH SUBMITTAL WITH A UNIFORM, APPROVAL STAMP.
INCLUDE PROJECT NAME AND LOCATION, SUBMITTAL NUMBER, SPECIFICATION SECTION
TITLE AND NUMBER, NAME OF REVIEWER, DATE OF CONTRACTOR'S APPROVAL, AND
STATEMENT CERTIFYING THAT SUBMITTAL HAS BEEN REVIEWED, CHECKED, AND APPROVED
FOR COMPLIANCE WITH THE CONTRACT DOCUMENTS.
3.2 ARCHITECT'S/ENGINEER'S ACTION
A. GENERAL: ARCHITECT/ENGINEER WILL NOT REVIEW SUBMITTALS THAT DO NOT BEAR
CONTRACTOR'S APPROVAL STAMP AND WILL RETURN THEM WITHOUT ACTION.
B. ACTION SUBMITTALS: ARCHITECT/ENGINEER WILL REVIEW EACH SUBMITTAL, MAKE MARKS
TO INDICATE CORRECTIONS OR MODIFICATIONS REQUIRED, AND RETURN IT.
ARCHITECT/ENGINEER WILL ATTACH A COVER LETTER TO EACH SUBMITTAL INDICATING AN
ACTION TO BE TAKEN, AS FOLLOWS:
1. REVIEWED
2. REVIEWED WITH COMMENTS
3. REVISE AND RESUBMIT
4. REJECTED
5. FOR INFORMATION ONLY
C. INFORMATIONAL SUBMITTALS: ARCHITECT/ENGINEER WILL REVIEW EACH SUBMITTAL AND
WILL NOT RETURN IT, OR WILL REJECT AND RETURN IT IF IT DOES NOT COMPLY WITH
REQUIREMENTS. ARCHITECT/ENGINEER WILL FORWARD EACH SUBMITTAL TO
APPROPRIATE PARTY.
D. SUBMITTALS NOT REQUIRED BY THE CONTRACT DOCUMENTS WILL NOT BE REVIEWED AND
MAY BE DISCARDED.
SUBMITTAL REQUIREMENTS
05 70 00 DECORATIVE AND ARCHITECTURAL METALS
06 10 53 MISCELLANEOUS CARPENTRY
07 21 16 BATT INSULATION
07 92 00 JOINT SEALANTS
08 12 13 HOLLOW METAL FRAMES
08 14 00 SOLID CORE WOOD DOORS
08 71 00 DOOR HARDWARE
08 80 00 GLAZING
09 12 00 ACOUSTICAL CEILING SUSPENSION SYSTEM
09 20 00 GYPSUM BOARD
09 22 16 METAL STUD FRAMING
09 30 00 PORCELAIN TILE
09 51 13 ACOUSTICAL CEILING PANELS
09 54 10 ACOUSTICAL INSULATION
09 65 00 RESILIENT FLOORING
09 65 10 WALL BASE
09 68 00 CARPETING
09 90 00 PAINTING
10 14 00 IDENTIFYING DEVICES
10 21 13 TOILET PARTITIONS
10 28 00 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
12 32 16 ARCHITECTURAL LAMINATE CASEWORK
12 36 61 SOLID SURFACE COUNTERTOPS
G102
LL
General Requirements
REVISION:
DRAWN BY:
DATE:
SHEET TITLE:
ãCOPYRIGHT 2026 by Tsark Architecture, LLC All rights reserved. No part of this work covered by the copyright hereon may be reproduced or used in any form or by any means - graphic, electronic or mechanical, including photocopying, recording, taping or information storage and retrieval systems - without written permission of the copyright holder.
06/16/2026
Tsark Architecture, LLC 1600 Sarno Rd., Suite 212 Melbourne, Florida 32935 tel: (321) 241-6378 License Number: AA26003779
P al m B ay C it y
H al l
M al ab ar R o ad
P al m
B ay
F lo ri d a
P ro je ct
N o
A
SUBMITTALS
1 03/31/26 30% SD SUBMITTAL
2 60% DD SUBMITTAL
B u ild in g
"E
M o d if ic at io n s
3 90% CD SUBMITTAL
4 100% IFP SUBMITTAL
04/21/26
05/21/26
06/16/26
1 07/07/2026 OWNER CHANGES
ARCHITECTURAL SPECIFICATIONS
DIVISION 5 - METALS
05 70 00 DECORATIVE AND ARCHITECTURAL METAL
PART 1 - PRODUCTS
A. GENERAL: PROVIDE ALL ORNAMENTAL METAL ITEMS WITHOUT PITTING, SEAM
MARKS, ROLLER MARKS, STAINS, DISCOLORATIONS, OR OTHER IMPERFECTIONS
WHERE EXPOSED TO VIEW ON FINISHED UNITS. FURNISH SHEET AND STRIP WITH
STRETCHER-LEVELED STANDARD OF FLATNESS. ORNAMENTAL METAL INCLUDES
ALL ARCHITECTURAL ELEMENTS INTENDED TO BE EXPOSED AND VISIBLE.
B. ALUMINUM: ALLOY AND TEMPER RECOMMENDED BY ALUMINUM PRODUCER AND
FINISHER FOR USE AND FINISH INDICATED, AND WITH NOT LESS THAN THE
STRENGTH AND DURABILITY OF ALLOY AND TEMPER DESIGNATED BELOW:
1. EXTRUDED BARS AND SHAPES: ASTM B 221, ALLOY 6063-T6.
2. EXTRUDED PIPE AND TUBES: ASTM B 429, ALLOY 6063-T6.
3. DRAWN SEAMLESS TUBES: ASTM B 483, ALLOY 6063-T832.
4. PLATE AND SHEET: ASTM B 209, ALLOY 6061-T6.
5. DIE AND HAND FORGINGS: ASTM B 247, ALLOY 6061-T6.
6. CASTINGS: ASTM B 26/B 26M, ALLOY A356-T6.
C. ALUMINUM FINISHES: AS INDICATED.
1. BAKED-ENAMEL FINISH: AA-C12C42R1X, WITH THERMOSETTING,
MODIFIED-ACRYLIC ENAMEL PRIMER/TOPCOAT ORGANIC COATING SYSTEM
COMPLYING WITH AAMA 2603 EXCEPT WITH A MINIMUM DRY FILM THICKNESS
OF 1.5 MILS, MEDIUM GLOSS. COLOR AS INDICATED IN FINISH SELECTIONS.
D. POWDER-COATED FINISH: IMMEDIATELY AFTER CLEANING AND PRETREATING,
APPLY THERMOSETTING POLYESTER OR ACRYLIC URETHANE POWDER COATING
WITH CURED-FILM THICKNESS NOT LESS THAN 1.5 COLOR TO MATCH ARCHITECT'S
SAMPLE.
E. WELDING ELECTRODES AND FILLER METAL: TYPE AND ALLOY RECOMMENDED BY
PRODUCER OF METAL TO BE WELDED FOR COLOR MATCH, STRENGTH, AND
COMPATIBILITY IN FABRICATED ITEMS.
F. FASTENERS: SAME BASIC METAL AS FASTENED METAL; CONCEALED, WITH PHILLIPS
FLAT-HEAD SCREWS FOR EXPOSED FASTENERS, UNLESS OTHERWISE INDICATED
G. ANCHORS: TYPE, SIZE, AND MATERIAL RECOMMENDED BY THE MANUFACTURER.
H. FABRICATION: CUSTOM FABRICATE ORNAMENTAL METAL WORK WITH TRUE
CURVES, LINES, AND ANGLES TO THE SIZES, SHAPES, AND PROFILES SHOWN.
PROVIDE NECESSARY REBATES, LUGS, AND BRACKETS TO ASSEMBLE UNITS AND
TO ATTACH TO OTHER WORK. CLEAN AND DRESS EXPOSED WELDED AND BRAZED
JOINTS. MILL JOINTS TO A TIGHT, HAIRLINE FIT; COPE OR MITER CORNERS.
I. APPROVED MANUFACTURER: PERFECTION ARCHITECTURAL SYSTEMS, LLC.
ALTERNATE MANUFACTURER SHALL MEET THE DESIGN CRITERIA AND BE
APPROVED BY THE ARCHITECT PRIOR TO FABRICATION.
PART 2 - EXECUTION
A. PROVIDE ANCHORAGE DEVICES AND FASTENERS WHERE NECESSARY FOR
SECURING TO IN-PLACE CONSTRUCTION. SET PRODUCTS ACCURATELY IN
LOCATION, ALIGNMENT,AND ELEVATION. FIT EXPOSED CONNECTIONS ACCURATELY
TOGETHER WITH HAIRLINE JOINTS OR, WHERE INDICATED, WITH UNIFORM REVEALS
AND SPACES FOR SEALANTS AND JOINT FILLERS.
DIVISION 6 - WOOD, PLASTICS, AND COMPOSITES
SECTION 06 10 53 - MISCELLANEOUS CARPENTRY
PART 1 - GENERAL
A. THIS SECTION INCLUDES BLOCKING AND PANEL PRODUCTS FOR EQUIPMENT
BACKING PANELS.
PART 2 - PRODUCTS
A. LUMBER: DOC PS 20.
1. PROVIDE DRESSED LUMBER, S4S, UNLESS OTHERWISE INDICATED.
2. PROVIDE DRY LUMBER WITH 19 PERCENT MAXIMUM MOISTURE CONTENT AT
TIME OF DRESSING FOR 2-INCH NOMINAL THICKNESS OR LESS, UNLESS
OTHERWISE INDICATED.
B. WOOD STRUCTURAL PANELS: PLYWOOD DOC PS 1 OR DOC PS 2.
C. FIRE-RETARDANT-TREATED MATERIALS:
1. GENERAL: WHERE FIRE-RETARDANT-TREATED MATERIALS ARE INDICATED,
PROVIDE MATERIALS THAT COMPLY WITH PERFORMANCE REQUIREMENTS IN
AWPA C20(LUMBER) AND AWPA C27 (PLYWOOD). IDENTIFY
FIRE-RETARDANT-TREATED WOOD WITH APPROPRIATE CLASSIFICATION
MARKING OF UL, U.S. TESTING, TIMBER PRODUCTS INSPECTION, OR ANOTHER
TESTING AND INSPECTING AGENCY ACCEPTABLE TO AUTHORITIES HAVING
JURISDICTION.
2. USE INTERIOR TYPE A HIGH TEMPERATURE (HT), UNLESS OTHERWISE
INDICATED.
D. MISCELLANEOUS LUMBER FOR BLOCKING: PROVIDE CONSTRUCTION OR NO. 2
GRADE LUMBER WITH 19 PERCENT MAXIMUM MOISTURE CONTENT OF ANY
SPECIES.
E. TELEPHONE AND ELECTRICAL EQUIPMENT BACKING PANELS: DOC PS 1, EXPOSURE
1, C-D PLUGGED, FIRE-RETARDANT TREATED, IN THICKNESS INDICATED OR, IF NOT
INDICATED, NOT LESS THAN 1/2 INCH THICK.
PART 3 - INSTALLATION
A. SET CARPENTRY TO REQUIRED LEVELS AND LINES, WITH MEMBERS PLUMB, TRUE
TO LINE, CUT, AND FIT CARPENTRY TO OTHER CONSTRUCTION; SCRIBE AND COPE
AS NEEDED FOR ACCURATE LOCATE BLOCKING,TO COMPLY WITH REQUIREMENTS
FOR ATTACHING OTHER CONSTRUCTION.
B. SECURELY ATTACH CARPENTRY WORK AS INDICATED AND ACCORDING TO
APPLICABLE CODES AND RECOGNIZED STANDARDS.
C. WOOD STRUCTURAL PANELS: COMPLY WITH APPLICABLE RECOMMENDATIONS
CONTAINED IN APA FORM NO. E30K, APA DESIGN/CONSTRUCTION GUIDE:
RESIDENTIAL & COMMERCIAL," FOR TYPES OF STRUCTURAL-USE PANELS AND
APPLICATIONS INDICATED.
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
07 21 16 BATT INSULATION
A. FURNISH AND INSTALL FIBERGLASS BATT INSULATION TO FILL WALL CAVITIES
WHERE INDICATED ON THE PLANS.
07 90 00 JOINT SEALERS
A. PROVIDE NEW LATEX BASED, LOW VOC, CAULKING AT JOINTS BETWEEN CHANGES
IN MATERIALS (I.E. WALLS AT DOORS, WINDOWS AND FRAMES, BUILT-IN CABINETS,
ETC).
DIVISION 8 - DOORS AND WINDOWS
08 11 13 HOLLOW METAL FRAMES
A. BASIS OF DESIGN ARE PRODUCTS BY MESKER. CURRIES AND STEELCRAFT ARE
APPROVED EQUALS.
B. ALL NEW HOLLOW METAL DOOR FRAMES SHALL 16 GAUGE STEEL A60 GALVANIZED
AND PRIMED FOR FIELD PAINT UNLESS OTHERWISE NOTED.
C. PRIME FRAMES FOR PAINT. FRAMES TO BE SPRAYED NOT BRUSHED.
D. ANCHOR DOOR FRAME TO STEEL IN ACCORDANCE WITH THE MANUFACTURER'S
RECOMMENDATIONS AND TESTS TO MEET CODES.
E. PROVIDE WEATHER STRIPPING AT DOORS BETWEEN CONDITIONED AND
NON-CONDITIONED SPACES.
08 14 00 SOLID CORE WOOD DOORS
PART 1 - PRODUCTS
A. PROVIDE SOLID STRUCTURAL COMPOSITE LUMBER WOOD CORE DOORS FACED
WITH PLASTIC LAMINATE FINISH. FINISH SELECTION TO BE AS INDICATED IN FINISH
SELECTIONS.
B. BASIS OF DESIGN SHALL BE COMMERCIAL PRODUCTS BY MOHAWK OR APPROVED
EQUAL.
C. SIZE FOR FRAME-OPENING SIZES INDICATED. FACTORY MACHINE DOORS FOR
HARDWARE THAT IS NOT SURFACE APPLIED. LOCATE HARDWARE TO COMPLY
WITH DHI-WDHS-3. INCLUDE TOP RAIL BLOCKING AT WOOD DOORS.
D. FIRE-RATED DOOR ASSEMBLIES: COMPLY WITH NFPA 80, LISTED AND LABELED BY
UL OR WARNOCK HERSEY FOR FIRE-PROTECTION RATINGS INDICATED, BASED ON
TESTING ACCORDING TO NFPA 252, 1997 UBC STANDARD 7-2 "FIRE TEST OF DOOR
ASSEMBLIES", AND UL 10C "STANDARD FOR POSITIVE PRESSURE FIRE TESTS OF
DOOR ASSEMBLIES". FIRE CLASSIFICATION LABELS AT ALL DOORS WITH FIRE
RATINGS GREATER THAN 20 MINUTES SHALL INDICATE THE TEMPERATURE RISE
DEVELOPED ON THE UNEXPOSED SURFACE OF
THE DOOR AFTER THE FIRST 30 MINUTES OF FIRE EXPOSURE.
E. TEMPERATURE-RISE RATING: WHERE INDICATED, PROVIDE DOORS THAT HAVE A
TEMPERATURE-RISE RATING OF 450 DEG F MAXIMUM IN 30 MINUTES OF FIRE
EXPOSURE.
F. PROVIDE FIRE RATED DOOR ASSEMBLIES IN COMPLIANCE WITH 1997 UBC
STANDARD 7-2, PART 1 FOR POSITIVE PRESSURE. SIZES AND CONFIGURATIONS AS
SHOWN ON THE DRAWINGS. INSTALLED DOOR ASSEMBLIES SHALL BE IN
ACCORDANCE WITH DOOR MANUFACTURERS CERTIFIED ASSEMBLIES.
G. PROVIDE FIRE RATED DOOR ASSEMBLIES WITH SMOKE AND DRAFT CONTROL
RATING IN COMPLIANCE WITH 1997 UBC STANDARD 7-2 PART 2 AT CORRIDORS,
STAIRWELLS, AND WHERE REQUIRED BY APPLICABLE CODES. SIZES AND
CONFIGURATIONS AS SHOWN ON THE DRAWINGS INSTALLED DOOR ASSEMBLIES
SHALL BE IN ACCORDANCE WITH DOOR MANUFACTURERS CERTIFIED ASSEMBLIES.
1. FINISH: AS INDICATED.
2. GRADE: AS INDICATED.
3. SPECIES AND CUT: AS INDICATED.
4. MATCH BETWEEN VENEER LEAVES: AS INDICATED.
5. ASSEMBLY OF VENEER LEAVES ON DOOR FACES: AS INDICATED.
PART 2 - EXECUTION
A. INSTALL DOORS TO COMPLY WITH MANUFACTURER'S WRITTEN INSTRUCTIONS AND
THE REFERENCED QUALITY STANDARD. INSTALL FIRE, AND SMOKE, RATED DOORS
ACCORDING TO FIRE LABEL REQUIREMENTS. APPLY HARDWARE IN ACCORDANCE
WITH HARDWARE MANUFACTURER'S INSTRUCTIONS. LEAVE WORK IN COMPLETE
AND PROPER OPERATING CONDITION.
B. FACTORY-FINISHED DOORS: RESTORE FINISH BEFORE INSTALLATION IF FITTING OR
MACHINING IS REQUIRED AT PROJECT SITE.
C. FIELD-FINISHED DOORS: REFER TO DIVISION 9 SECTION "PAINTING" FOR FINISHING
REQUIREMENTS.
08 31 00 ACCESS DOORS
A. PROVIDE PREFABRICATED METAL ACCESS DOORS IN DRYWALL WHERE REQUIRED
TO ACCESS MECH, PLUMBING, ELECTRICAL ITEMS, ETC.
08 71 00 DOOR HARDWARE
1.1RELATED DOCUMENTS
A. DRAWINGS AND GENERAL PROVISIONS OF THE CONTRACT, INCLUDING GENERAL
AND SUPPLEMENTARY CONDITIONS AND DIVISION 01 SPECIFICATION SECTIONS,
APPLY TO THIS SECTION.
1.2 SUMMARY
A. SECTION INCLUDES:
1. MECHANICAL AND ELECTRIFIED DOOR HARDWARE FOR:
a. SWINGING DOORS.
B. RELATED SECTIONS:
1. DIVISION 01 SECTION “ALTERNATES” FOR ALTERNATES AFFECTING THIS
SECTION.
2. DIVISION 07 SECTION “JOINT SEALANTS” FOR SEALANT REQUIREMENTS
APPLICABLE TO THRESHOLD INSTALLATION SPECIFIED IN THIS SECTION.
3. DIVISION 09 SECTIONS FOR TOUCHUP FINISHING OR REFINISHING OF EXISTING
OPENINGS MODIFIED BY THIS SECTION.
4. DIVISION 26 SECTIONS FOR CONNECTIONS TO ELECTRICAL POWER SYSTEM
AND FOR LOW-VOLTAGE WIRING.
5. DIVISION 28 SECTIONS FOR COORDINATION WITH OTHER COMPONENTS OF
ELECTRONIC ACCESS CONTROL SYSTEM.
1.3REFERENCES
A. UL - UNDERWRITERS LABORATORIES
1. UL 10B - FIRE TEST OF DOOR ASSEMBLIES
2. UL 10C - POSITIVE PRESSURE TEST OF FIRE DOOR ASSEMBLIES
3. UL 1784 - AIR LEAKAGE TESTS OF DOOR ASSEMBLIES
4. UL 305 - PANIC HARDWARE
B. DHI - DOOR AND HARDWARE INSTITUTE
1. SEQUENCE AND FORMAT FOR THE HARDWARE SCHEDULE
2. RECOMMENDED LOCATIONS FOR BUILDERS HARDWARE
3. KEY SYSTEMS AND NOMENCLATURE
C. ANSI - AMERICAN NATIONAL STANDARDS INSTITUTE
1. ANSI/BHMA A156.1 - A156.29, AND ANSI/BHMA A156.31 - STANDARDS FOR
HARDWARE AND SPECIALTIES.
D. FLORIDA BUILDING CODES.
1.4 SUBMITTALS
A. GENERAL:
1. SUBMIT IN ACCORDANCE WITH CONDITIONS OF CONTRACT AND DIVISION 01
REQUIREMENTS.
2. HIGHLIGHT, ENCIRCLE, OR OTHERWISE SPECIFICALLY IDENTIFY ON
SUBMITTALS DEVIATIONS FROM CONTRACT DOCUMENTS, ISSUES OF
INCOMPATIBILITY OR OTHER ISSUES WHICH MAY DETRIMENTALLY AFFECT THE
WORK.
3. PRIOR TO FORWARDING SUBMITTAL, COMPLY WITH PROCEDURES FOR
VERIFYING EXISTING DOOR AND FRAME COMPATIBILITY FOR NEW HARDWARE,
AS SPECIFIED IN PART 3, “EXAMINATION” ARTICLE, HEREIN.
B. ACTION SUBMITTALS:
1. PRODUCT DATA: PRODUCT DATA INCLUDING MANUFACTURERS' TECHNICAL
PRODUCT DATA FOR EACH ITEM OF DOOR HARDWARE, INSTALLATION
INSTRUCTIONS, MAINTENANCE OF OPERATING PARTS AND FINISH, AND OTHER
INFORMATION NECESSARY TO SHOW COMPLIANCE WITH REQUIREMENTS.
2. RISER AND WIRING DIAGRAMS: AFTER FINAL APPROVAL OF HARDWARE
SCHEDULE, SUBMIT DETAILS OF ELECTRIFIED DOOR HARDWARE, INDICATING:
a. WIRING DIAGRAMS: FOR POWER, SIGNAL, AND CONTROL WIRING AND
INCLUDING:
1) DETAILS OF INTERFACE OF ELECTRIFIED DOOR HARDWARE AND BUILDING
SAFETY AND SECURITY SYSTEMS.
2) SCHEMATIC DIAGRAM OF SYSTEMS THAT INTERFACE WITH ELECTRIFIED
DOOR HARDWARE.
3) POINT-TO-POINT WIRING.
4)RISERS.
3. SAMPLES FOR VERIFICATION: IF REQUESTED BY ARCHITECT, SUBMIT
PRODUCTION SAMPLE OR SAMPLE INSTALLATIONS OF EACH TYPE OF EXPOSED
HARDWARE UNIT IN FINISH INDICATED, AND TAGGED WITH FULL DESCRIPTION
FOR COORDINATION WITH SCHEDULE.
a. SAMPLES WILL BE RETURNED TO SUPPLIER IN LIKE-NEW CONDITION. UNITS
THAT ARE ACCEPTABLE TO ARCHITECT MAY, AFTER FINAL CHECK OF
OPERATIONS, BE INCORPORATED INTO WORK, WITHIN LIMITATIONS OF KEY
COORDINATION REQUIREMENTS.
4. DOOR HARDWARE SCHEDULE: SUBMIT SCHEDULE WITH HARDWARE SETS IN
VERTICAL FORMAT AS ILLUSTRATED BY SEQUENCE OF FORMAT FOR THE
HARDWARE SCHEDULE AS PUBLISHED BY THE DOOR AND HARDWARE
INSTITUTE. INDICATE COMPLETE DESIGNATIONS OF EACH ITEM REQUIRED FOR
EACH DOOR OR OPENING, INCLUDE:
a. DOOR INDEX; INCLUDE DOOR NUMBER, HEADING NUMBER, AND ARCHITECTS
HARDWARE SET NUMBER.
b. OPENING LOCK FUNCTION SPREADSHEET: LIST LOCKING DEVICE AND FUNCTION
FOR EACH OPENING.
c. TYPE, STYLE, FUNCTION, SIZE, AND FINISH OF EACH HARDWARE ITEM.
d. NAME AND MANUFACTURER OF EACH ITEM.
e. FASTENINGS AND OTHER PERTINENT INFORMATION.
f. LOCATION OF EACH HARDWARE SET CROSS-REFERENCED TO INDICATIONS ON
DRAWINGS.
g. EXPLANATION OF ALL ABBREVIATIONS, SYMBOLS, AND CODES CONTAINED IN
SCHEDULE.
h. MOUNTING LOCATIONS FOR HARDWARE.
i. DOOR AND FRAME SIZES AND MATERIALS.
j. NAME AND PHONE NUMBER FOR LOCAL MANUFACTURER'S REPRESENTATIVE
FOR EACH PRODUCT.
k. OPERATIONAL DESCRIPTION OF OPENINGS WITH ANY ELECTRIFIED HARDWARE
(LOCKS, EXITS, ELECTROMAGNETIC LOCKS, ELECTRIC STRIKES, AUTOMATIC
OPERATORS, DOOR POSITION SWITCHES, MAGNETIC HOLDERS OR
CLOSER/HOLDER UNITS, AND ACCESS CONTROL COMPONENTS). OPERATIONAL
DESCRIPTION SHOULD INCLUDE HOW DOOR WILL OPERATE ON EGRESS,
INGRESS, AND FIRE AND SMOKE ALARM CONNECTION.
1) SUBMITTAL SEQUENCE: SUBMIT DOOR HARDWARE SCHEDULE CONCURRENT
WITH SUBMISSIONS OF PRODUCT DATA, SAMPLES, AND SHOP DRAWINGS.
COORDINATE SUBMISSION OF DOOR HARDWARE SCHEDULE WITH
SCHEDULING REQUIREMENTS OF OTHER WORK TO FACILITATE FABRICATION
OF OTHER WORK THAT IS CRITICAL IN PROJECT CONSTRUCTION SCHEDULE.
5. KEY SCHEDULE:
a. AFTER KEYING CONFERENCE, PROVIDE KEYING SCHEDULE LISTING LEVELS OF
KEYING AS WELL AS EXPLANATION OF KEY SYSTEM'S FUNCTION, KEY SYMBOLS
USED AND DOOR NUMBERS CONTROLLED.
b. USE ANSI/BHMA A156.28 “RECOMMENDED PRACTICES FOR KEYING SYSTEMS” AS
GUIDELINE FOR NOMENCLATURE, DEFINITIONS, AND APPROACH FOR
SELECTING OPTIMAL KEYING SYSTEM.
c. PROVIDE 3 COPIES OF KEYING SCHEDULE FOR REVIEW PREPARED AND
DETAILED IN ACCORDANCE WITH REFERENCED DHI PUBLICATION. INCLUDE
SCHEMATIC KEYING DIAGRAM AND INDEX EACH KEY TO UNIQUE DOOR
DESIGNATIONS.
d. INDEX KEYING SCHEDULE BY DOOR NUMBER, KEYSET, HARDWARE HEADING
NUMBER, CROSS KEYING INSTRUCTIONS, AND SPECIAL KEY STAMPING
INSTRUCTIONS.
e. PROVIDE ONE COMPLETE BITTING LIST OF KEY CUTS AND ONE KEY SYSTEM
SCHEMATIC ILLUSTRATING SYSTEM USAGE AND EXPANSION.
1) FORWARD BITTING LIST, KEY CUTS AND KEY SYSTEM SCHEMATIC DIRECTLY
TO OWNER, BY MEANS AS DIRECTED BY OWNER.
f. PREPARE KEY SCHEDULE BY OR UNDER SUPERVISION OF SUPPLIER, DETAILING
OWNER'S FINAL KEYING INSTRUCTIONS FOR LOCKS.
6. TEMPLATES: AFTER FINAL APPROVAL OF HARDWARE SCHEDULE, PROVIDE
TEMPLATES FOR DOORS, FRAMES AND OTHER WORK SPECIFIED TO BE
FACTORY PREPARED FOR DOOR HARDWARE INSTALLATION.
C. INFORMATIONAL SUBMITTALS:
1. QUALIFICATION DATA: FOR SUPPLIER, INSTALLER AND ARCHITECTURAL
HARDWARE CONSULTANT.
2. PRODUCT CERTIFICATES FOR ELECTRIFIED DOOR HARDWARE, SIGNED BY
MANUFACTURER:
a. CERTIFY THAT DOOR HARDWARE APPROVED FOR USE ON TYPES AND SIZES OF
LABELED FIRE-RATED DOORS COMPLIES WITH LISTED FIRE-RATED DOOR
ASSEMBLIES.
3. CERTIFICATES OF COMPLIANCE:
a. CERTIFICATES OF COMPLIANCE FOR FIRE-RATED HARDWARE AND
INSTALLATION INSTRUCTIONS IF REQUESTED BY ARCHITECT OR AUTHORITY
HAVING JURISDICTION.
b. INSTALLER TRAINING MEETING CERTIFICATION: LETTER OF COMPLIANCE, SIGNED BY CONTRACTOR, ATTESTING TO COMPLETION OF INSTALLER TRAINING
MEETING SPECIFIED IN “QUALITY ASSURANCE” ARTICLE, HEREIN.
c. ELECTRIFIED HARDWARE COORDINATION CONFERENCE CERTIFICATION:
LETTER OF COMPLIANCE, SIGNED BY CONTRACTOR, ATTESTING TO
COMPLETION OF ELECTRIFIED HARDWARE COORDINATION CONFERENCE,
SPECIFIED IN “QUALITY ASSURANCE” ARTICLE, HEREIN.
4. PRODUCT TEST REPORTS: FOR COMPLIANCE WITH ACCESSIBILITY
REQUIREMENTS, BASED ON EVALUATION OF COMPREHENSIVE TESTS
PERFORMED BY MANUFACTURER AND WITNESSED BY QUALIFIED TESTING
AGENCY, FOR DOOR HARDWARE ON DOORS LOCATED IN ACCESSIBLE ROUTES.
5. WARRANTY: SPECIAL WARRANTY SPECIFIED IN THIS SECTION.
D. CLOSEOUT SUBMITTALS:
1. OPERATIONS AND MAINTENANCE DATA: PROVIDE IN ACCORDANCE WITH
DIVISION 01 AND INCLUDE:
a. COMPLETE INFORMATION ON CARE, MAINTENANCE, AND ADJUSTMENT; DATA
ON REPAIR AND REPLACEMENT PARTS, AND INFORMATION ON PRESERVATION
OF FINISHES.
b. CATALOG PAGES FOR EACH PRODUCT.
c. NAME, ADDRESS, AND PHONE NUMBER OF LOCAL REPRESENTATIVES FOR EACH
MANUFACTURER.
d. PARTS LIST FOR EACH PRODUCT.
e. FINAL APPROVED HARDWARE SCHEDULE EDITED TO REFLECT CONDITIONS AS
INSTALLED.
f. FINAL KEYING SCHEDULE
g. COPIES OF FLOOR PLANS WITH KEYING NOMENCLATURE
h. AS-INSTALLED WIRING DIAGRAMS FOR EACH OPENING CONNECTED TO POWER, BOTH LOW VOLTAGE AND 110 VOLTS.
i. COPY OF WARRANTIES INCLUDING APPROPRIATE REFERENCE NUMBERS FOR
MANUFACTURERS TO IDENTIFY PROJECT.
1.5 QUALITY ASSURANCE
A. PRODUCT SUBSTITUTIONS: COMPLY WITH PRODUCT REQUIREMENTS STATED IN
DIVISION 01 AND AS SPECIFIED HEREIN.
1. WHERE SPECIFIC MANUFACTURER'S PRODUCT IS NAMED AND ACCOMPANIED
BY “NO SUBSTITUTE,” INCLUDING MAKE OR MODEL NUMBER OR OTHER
DESIGNATION, PROVIDE PRODUCT SPECIFIED. (NOTE: CERTAIN PRODUCTS
HAVE BEEN SELECTED FOR THEIR UNIQUE CHARACTERISTICS AND
PARTICULAR PROJECT SUITABILITY.)
a. WHERE NO ADDITIONAL PRODUCTS OR MANUFACTURERS ARE LISTED IN
PRODUCT CATEGORY, REQUIREMENTS FOR “NO SUBSTITUTE” GOVERN
PRODUCT SELECTION.
B. SUPPLIER QUALIFICATIONS AND RESPONSIBILITIES: RECOGNIZED ARCHITECTURAL
HARDWARE SUPPLIER WITH RECORD OF SUCCESSFUL IN-SERVICE PERFORMANCE
FOR…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .