Summary of ITB 23-122: Taylor Road Left-Turn Lane Project

This is an Invitation to Bid (ITB) issued by the City of Johns Creek, Georgia, for construction of roadway improvements on Taylor Road from Mortons Crossing to Starfire Lane. The project encompasses asphalt pavement, storm drainage, concrete sidewalks, curb and gutter, thermoplastic pavement markings, and associated site work. A pre-bid conference was held on April 13, 2023, at 10:00 AM ET via Zoom with required pre-registration. Prospective bidders could submit questions electronically through BidNet until April 25, 2023, at 5:00 PM ET. Sealed bids were due May 2, 2023, at 2:00 PM ET through the Georgia Purchasing Group's BidNet system. The anticipated Notice to Proceed was scheduled for May 31, 2023, with a project completion deadline of July 31, 2023—a 60-calendar-day timeline from mobilization to substantial completion. The City anticipated reviewing bids at a work session on May 9, 2023, and presenting the award recommendation to City Council on May 23, 2023.

Bidders must provide three references demonstrating experience with similar projects and submit unit price proposals directly through BidNet. Required bonds include a 5% bid bond and 100% performance and payment bonds based on the contract value. Insurance requirements mandate workers' compensation at statutory limits and commercial general liability coverage of $1,000,000 per person and $2,000,000 per occurrence for bodily injury, plus $500,000 per occurrence for property damage. The contractor is responsible for all labor, materials, equipment, permits, licenses, utility coordination, traffic control, erosion control, and site restoration. The City will retain 10% of monthly invoices as retainage until final project acceptance. Liquidated damages of $150 per calendar day apply for work not completed by the deadline. Work hours are restricted to 8:00 AM to 5:00 PM Monday through Friday, with no work permitted during specified peak traffic hours (6:00-9:00 AM and 4:00-7:00 PM weekdays). All work must comply with GDOT specifications, OSHA regulations, and applicable federal civil rights requirements.

Text of this file

INVITATION TO BID (ITB)

TAYLOR ROAD LEFT-TURN LANE

(MORTONS CROSSING TO STARFIRE LANE)

BID # ITB 23-122

RECOMMENDED PRE-BID CONFERENCE

April 13, 2023 @ 10:00AM ET

Interested firms/individuals must preregister for the teleconference by emailing the City Purchasing Division with bid number 23-122, firm name, contact name, email address to purchasing@johnscreekga.gov in advance of meeting day

Release of Bid April 6, 2023

BID DUE DATE

May 2, 2023 @ 2:00 PM ET

Questions must be asked electronically via BidNet:

Deadline for Questions

April 25, 2023 5:00PM ET

Quotes, bids, and RFPs are electronically managed through the Georgia Purchasing Group by BidNet, our online bidding/vendor registration system, on the City website:

https://www.johnscreekga.gov/Residents/Purchasing. To access the RFP document you must register with BidNet. Go to the City website above and click the link “register and view quote/bid/RFP opportunities”.

EXHIBIT A - Bid Specifications

PURPOSE, INTENT AND PROJECT DESCRIPTION

The Contractor will construct asphalt pavement, storm drainage, concrete sidewalk, and all other miscellaneous items necessary for completion of the work within the City of Johns Creek (City), Georgia.

This work includes the following project:

TAYLOR ROAD LEFT-TURN LANE (MORTONS CROSSING TO STARFIRE LANE)

All work shall be constructed according to the Construction Plans and are made part of the contract by reference.

SCOPE OF WORK

The Contractor shall construct the project per:

Georgia Department of Transportation (GDOT) Specifications, Standards, and Details;

The Contract Documents including but not limited to the scope of work and specifications;

The Plans - drawings/details/notes;

Purchase Order;

Approved Schedule;

City of Johns Creek ordinances and regulations;

OSHA standards and guidelines;

Any other applicable codes, laws and regulations including but not limited to Section 45-10-20 through 45-10-28 of the Official Code of Georgia Annotated, Title VI of the Civil Rights Act, Drug-Free Workplace Act, and all applicable requirements of the Americans with Disabilities Act of 1990

The contractor will be responsible for providing all labor, materials, and equipment necessary to perform the work. The contractor will be responsible for constructing all improvements shown on the plans unless specifically noted otherwise in the specifications/plans.

The contractor is responsible for inspecting the jobsite prior to submitting a bid. No change orders will be issued for differing site conditions. In case of discrepancies between the plans and specifications, the most stringent prevails.

The successful bidder must have verifiable experience at construction of similar projects in accordance with these specifications. Bidder shall submit (3) references demonstrating experience completing projects of similar scope (please include contact email please).

The City will inspect the work as it progresses.

Retainage in the amount of 10% of the total amount due on each monthly invoice will be held by the City until project completion and acceptance.

BID QUESTIONS:

All questions related to the project and documents must be asked electronically through BidNet. A response will be made within 72 hours electronically via BidNet. Contact with City staff during the solicitation period is forbidden. Offerors may contact the procurement officer for any clarification on schedule and bid submissions at purchasing@johnscreekga.gov .

PROCUREMENT SCHEDULE:

Bid Release April 6, 2023 Virtual Zoom Pre-Bid Meeting April 13, 2023, 10:00 AM ET

Interested firms/individuals must preregister for the teleconference by emailing the City Purchasing Division with bid number 23-122, firm name, contact name, email address to purchasing@johnscreekga.gov in advance of meeting day

Deadline to Submit Questions April 25, 2023 5:00 PM ET Deadline to Submit Bid May 2, 2023 2:00 PM ET Anticipated Work Session May 9, 2023 Anticipated Council Meeting May 23, 2023 Anticipated NTP May 31, 2023 Completion Date July 31, 2023

SPECIAL PROVISIONS

All materials and workmanship associated with this contract shall meet current GDOT Specifications and Standards for construction materials, methods and procedures. Please refer to the GDOT website for the most current versions of the Specifications and Special Provisions.

The following are special provisions prepared specifically for this contract and may be in conflict with parts of the standard specifications. If conflicts are evident the special provisions shall take precedence over the standard specifications.

PROSECUTION AND PROGRESS

The Contractor will have Sixty (60) calendar days from issuance of Notice to Proceed to be substantially complete with the project. The Contractor will be considered substantially complete when all contract work except for punch list work has been completed and accepted.

The Contractor will mobilize with sufficient forces such that all construction identified as part of this contract shall be substantially completed by the completion date indicated above. Upon Notice of Award the Contractor will be required to submit a Progress Schedule. The Contractor shall be assessed liquidated damages in the amount of $150.00 per calendar day for any work not completed by the deadline. Liquidated damages shall be deducted from the 10% retainage held by the City.

Normal workday for this project shall be 8:00 AM to 5:00 PM and the normal work week shall be Monday through Friday. The City will consider extended workdays or work weeks upon written request. No work will be allowed on City holidays (a complete list can be found on the City website).

The Contractor shall not install lane closures or perform work or move equipment or materials on the traveled way that interferes with traffic flow between the hours of 6:00 am to 9:00 am and 4:00 pm to 7:00 pm (Monday through Friday), and 9:00 am to 1:00 pm on Sundays.

The work will require bidder to provide all labor, administrative forces, equipment, materials and other incidental items to complete all required work. The City shall perform a Final Inspection upon notification from the contractor that all work is complete. A Punch List of found deficiencies will be submitted to the contractor upon completion of the Final Inspection. All repairs shall be completed by the Contractor at his expense prior to issuance of Final Acceptance. 10% retainage will be held from the total amount due the Contractor until Final Acceptance of work is issued by the City.

The City will retain 10% of the fee due the Contractor. The retainage will be paid as the final invoice after the project has been completed and accepted. All punch-list work must be complete before release of any retainage.

PERMITS AND LICENSES

The Contractor shall procure all permits and licenses, pay all charges, taxes and fees, and give all notices necessary and incidental to the due and lawful prosecution of the work.

MATERIALS

Contractor will be responsible for quality control testing of materials incorporated into the project. All materials will meet appropriate GDOT specifications. Materials quality control test types will meet GDOT specifications at a frequency equal to or exceeding that set by those specifications.

Contractor will be responsible for replacing any work performed with material from rejected sample lot at no cost to the City.

INVOICING

The Contractor shall invoice monthly for work satisfactorily completed. Invoices need to be sent to the City’s Project Manager for approval.

EXISTING CONDITIONS / DEVIATION OF QUANTITIES

The City reserves the right to add, modify, or delete quantities. Contractor will be paid for actual in-place quantities completed and accepted for pay items listed in the Bid Schedule. Contractor will not be entitled to an adjustment of unit price on an item which increased or decreased from the original plan quantity.

All other work required by this ITB, plans, specs, standards, etc. but not specifically listed in the Bid Schedule shall be considered “incidental work”. The bidder shall include the cost for all incidental work in the “Grading Complete” bid item. Contractor will notify the City in writing if quantities of contract items will exceed plan. At no time will contractor proceed with work outside the prescribed scope of services for which additional payment will be requested without the written authorization of the City.

All information given concerning existing conditions is for information purposes only. It is the Contractors responsibility to inspect the project site to verify existing conditions prior to submitting their bid.

No adjustment will be made to the bid based on missing or inaccurate information on the plans.

UTILITIES

Contractor shall be responsible for protecting all utilities and for coordinating any utility relocation necessary for the completion of the work.

Contractor shall be responsible for the adjusting to grade of existing utility structures that are incorporated into the work including but not limited to water valves and sewer cleanouts.

All known utility facilities are shown schematically on highway plans, and are not necessarily accurate in location as to plan or elevation. Utility facilities such as service lines or unknown facilities not shown on plans will not relieve the contractor of their responsibility under this requirement. "Existing utility facilities" means any utility that exists on the project in its original, relocated or newly installed position.

TRAFFIC CONTROL

The Contractor shall, at all times, conduct his work as to assure the least possible obstruction to the citizens.

Work staging and operations shall be conducted in a manner to minimize interference with traffic flow thru existing parking areas. The safety and convenience of the general public and the protection of persons and property shall be provided for by the Contractor as specified in the State of Georgia, Department of Transportation Standard Specifications Sections 104.05, 107.09 and 150.

The Contractor shall furnish, install and maintain all necessary and required barricades, signs and other traffic control devices in accordance with MUTCD and DOT specifications. Contractor shall take all necessary precautions for the protection of the workers and safety of the public.

All existing signs, markers and other traffic control devices removed or damaged during construction operations will be reinstalled or replaced at the Contractors expense. At no time will Contractor remove regulatory signing which may cause a hazard to the public. The Contractor shall, within 24 hours place temporary pavement markings (paint or removable tape) to match existing pavement markings. No additional payment will be made for this work.

The ingress and egress includes entrances and exits via driveways at various properties, and access to the intersecting roads and streets. The Contractor shall maintain sufficient personnel and equipment (including flaggers and traffic control signing) on the project at all times, particularly during inclement weather, to insure that ingress and egress are safely provided when and where needed.

Two way traffic shall be maintained at all times, utilizing certified flaggers as necessary, unless otherwise specified or approved by the City. In the event of an emergency situation, the Contractor shall provide access to emergency vehicles and/or emergency personnel through or around the construction area.

All personnel, equipment, and materials required for installing and maintaining traffic control shall be the responsibility of the contractor.

Mandatory: Contractor shall furnish copies of traffic control certifications and a headshot photo of all personnel providing traffic control services during project. This requirement shall be furnished to the City at the project kick-off meeting.

PROTECTION AND RESTORATION OF PROPERTY AND LANDSCAPE

The Contractor shall be responsible for the preservation of all public and private property, crops, fish ponds, trees, monuments, highway signs and markers, fences, grassed and sodded areas, etc. along and adjacent to the highway, road or street, and shall use every precaution necessary to prevent damage or injury thereto, unless the removal, alteration, or destruction of such property is provided for under the contract.

When or where any direct or indirect damage or injury is done to public or private property by or on account of any act, omission, neglect or misconduct in the execution of the work, or in consequence of the non-execution thereof by the Contractor, he shall restore, at his/her own expense, such property to a condition similar or equal to that existing before such damage or injury was done, by repairing, rebuilding or otherwise restoring as may be directed, or she/he shall make good such damage or injury in an acceptable manner. The Contractor shall correct all disturbed areas before retainage will be released.

SURVEY

The Contractor will be responsible for all staking necessary to complete construction activities. All survey equipment, stakes and other materials needed will be considered incidental to construction operations and no additional compensation will be provided.

RIGHTS AND USE OF MATERIAL

Materials excavated within the project limits become the property of the Contractor. The Contractor, at his/her discretion, may elect to incorporate any of the excavated material into his/her work provided and that it is suitable for the intended use. Materials identified to be removed and are unsuitable for the project will be removed from the site by the Contractor. All excavation, placement, hauling and grading of on-site material will be the Contractors responsibility.

GRADING COMPLETE

The Contractor shall be responsible for all grading work including all clearing, grubbing, hauling, grading, excavation, backfilling, and compaction tasks associated with the work. In addition to the above listed tasks, any costs associated with providing borrow material from a location not within the project limits will be the responsibility of the Contractor. Sub-grade excavation to required elevations, removal of excavated material if necessary, sub-grade compaction, fine grading, and back-filling excavated area with suitable material will be the responsibility of the Contractor. Also included in this work will be the removal and hauling off of existing construction materials, trees and any other items necessary to complete the work.

Finished grade of disturbed areas will match and blend with adjacent areas not disturbed by construction operations. The Contractor is also responsible for all ditch grading required to maintain drainage.

Tree save fence shall be installed and maintained by the contractor as indicated on the plans.

EROSION/SEDIMENT CONTROL

It is the responsibility of the Contractor to follow all Federal, State and Local erosion and sediment control laws and specifications. This includes meeting all NPDES guidelines.

Erosion/Sediment Control measures shall be installed and maintained by the Contractor throughout the duration of the project. The Contractor is responsible for the removal and disposal, off project site, all installed temporary erosion/sediment control measures when affected areas have been restored to a level where vegetative coverings will minimize erosion.

Contractor shall install and maintain erosion control BMP’s per the plans.

GRASSING COMPLETE

Contractor will be responsible for temporary and permanent grassing all disturbed areas. This work shall consist of ground preparation, furnishing and planting, seeding (including the cost of the seed), fertilizing, sprigging, mulching and watering of all areas disturbed due to construction operations. This work will comply with GDOT Section 700 – “Grassing.” Finished grade of disturbed areas will match and blend with adjacent areas not disturbed by construction operations. In the event that areas are damaged prior to final project acceptance, the Contractor will repair or replace as necessary. Please refer to the seeding schedule in the plans for species and spreading rates.

COORDINATION

The Contractor shall keep the City updated on the construction schedule, daily work plans and any challenges, setbacks in a timely manner.

PREPARATION OF SUBGRADE

This work shall consist of constructing the sub-grade such that the finished line and grade will conform to the line and grade as shown on the plan or as directed by City staff. The subgrade will be compacted to a degree such that no noticeable deflection is apparent. Removal of unsuitable material and replacement with suitable material is the responsibility of the Contractor. The City staff will verify line, grade, and compaction prior to placement of any materials. Contractor will not proceed with placement of materials without authorization by City staff.

CONCRETE SIDEWALK

The Contractor shall construct 4” and/or 6” depth Portland Cement Concrete sidewalks as stated in the plans, in accordance with the typical section.

Where space does not allow for a two-foot setback or where immovable objects restrict the width or location of the sidewalk, the contractor shall seek approval by the City prior to making adjustments in regard to the sidewalk width and/or location. Curb cut ramps shall be located at all intersections and driveways in accordance with GDOT and ADA requirements.

In addition, ADA compliant detectable warning surfaces shall be used at the toe of the ramps. Curb cut ramps and detectable warning surfaces are incidental to the cost for the Portland cement concrete sidewalks.

The detectable warning surfaces shall be the yellow fiberglass insert type and shall be at a minimum 2’ x 4’ in size. The detectable warning surfaces shall be considered incidental and no separate payment will be made. Also, the proposed sidewalk shall tie to the existing driveways in accordance with GDOT and ADA requirements. ADA ramps will be paid for at the contract unit price per SDY for sidewalk.

This work shall consist of supplying, transporting, forming, placing, finishing, and curing Portland Cement Concrete as sidewalks at locations specified in this ITB. Concrete shall conform to the minimum requirements for Class “B” as specified by GDOT. Concrete shall be placed only when the air temperature is 40 degrees Fahrenheit and rising. Concrete will be protected from freezing for the first 24 hours.

Appropriate levels of care will be employed by contractor to restrict public access to uncured concrete.

Concrete will be broom finished, edged, and jointed.

Concrete sidewalk construction will be performed in accordance with current GDOT specifications.

CONCRETE CURB AND GUTTER

The Contractor shall saw cut the existing edge of pavement at locations where curb is to be installed to provide a straight and uniform tie-in. This work is incidental and no separate payment will be made. The curb and gutter shall be installed in a manner to provide a uniform curb section.

ASPHALT CONCRETE PAVEMENT

The plant mix materials from which the asphaltic pavement is manufactured and the plant at which it is manufactured shall meet the requirements of the State of Georgia Department of Transportation (GDOT), Standard specifications, Articles 820; 802; 883; 831; 828; and 882.

Load tickets that meet Georgia Department of Transportation Specifications must accompany all delivered materials. The Contractor must supply copies of all asphalt tickets to the City.

Refer to plan sheet 5-002 for asphalt depths.

THERMOPLASTIC/PREFORMED PLASTIC PAVEMENT MARKINGS

This work shall consist of placement of Thermoplastic Pavement Markings on the asphalt pavement sections and Preformed Plastic Markings with black contrast on the bridge. Final (thermoplastic and preformed plastic) pavement markings shall be placed at least 20 calendar days but no more than 60 calendar days after placement of final asphalt lift. Final pedestrian crosswalk markings shall adhere to the latest standards. Pavement marking materials shall meet GDOT standard specifications and be on the qualified products list.

The Contractor shall install temporary paint pavement markings prior to re-opening the roadway. This work will be considered incidental and should be included in the lump sum bid for Traffic Control.

The 20-day wait period for installing final thermoplastic striping will not count against the available calendar days as long as all other work is complete, including temporary centerline striping, and the road has been re-opened.

Existing striping shall be removed by a City approved method. Depending on field conditions, methods may include:

1. Blasting for temporary and painted striping

2. Grinding for thermoplastic striping. The Contractor shall use a surface treatment for eradication by grinding to ensure and even look and feel to the roadway, if needed.

SAFETY

Beginning with mobilization and ending with acceptance of work, the Contractor shall be responsible for providing a clean and safe work environment at the project site. The Contractor shall comply with all OSHA regulations as they pertain to this project.

CLEANUP

All restoration and clean-up work shall be performed daily. Operations shall be suspended if the Contractor fails to accomplish restoration and clean-up within an acceptable period of time. Failure to perform clean-up activities may result in suspension of the work.

ADDITIONAL SPECIAL PROVISIONS (if any)

Contractor shall name the owners of Parcels 1 (listed below) as additionally insured and provide certificates of insurance to a representative of each parcel.

5230 Taylor Road: Fulton County Board of Education (Parcel 1)

REQUIRED BONDS

5% Bid Bond (Contract value).

100% Payment Bond (Contract value).

100% Performance Bond (Contract value)

INSURANCE REQUIREMENTS

The Contractor shall, at its own cost and expense, obtain and maintain worker’s compensation and commercial general liability insurance coverage covering the period of this Agreement, such insurance to be obtained from a responsible insurance company legally licensed and authorized to transact business in the State of Georgia. The minimum limit for Worker’s Compensation Insurance shall be the statutory limit for such insurance. The minimum limits for commercial general liability insurance, which must include personal liability coverage will be $1,000,000 per person and $2,000,000 per occurrence for bodily injury and $500,000 per occurrence for property damage

EXHIBIT B.

COST PROPOSAL

Offeror’s shall enter their firm’s unit price cost proposal directly into BidNet at the time of your bid submission. Offeror’s may copy and pace line items from bid document page into an excel sheet in order to create a worksheet. No worksheet shall accompany a firm’s bid submission.

EXHIBIT C.

REQUIRED FORMS AND DOCUMENTS

Offeror(s) will list N/A-Not Applicable to the fields below, if applies:

employees

BID BOND

KNOW ALL MEN BY THESE PRESENTS, THAT ______________

(Name of Contractor)_________________ (Address of Contractor) at __________________________________

(Corporation, Partnership and or Individual) hereinafter called Principal, and ________________

(Name of Surety)

(Address of Surety

A corporation of the State of _________________, and a surety authorized by law to do business in the State of Georgia, hereinafter called Surety, are held and firmly bound unto

City of Johns Creek Georgia (Name of Obligee) 10700 Abbotts Bridge Rd., Suite 190, Johns Creek, Georgia 30097 (Address of Obligee)

Hereinafter referred to as Obligee, in the penal sum of___________________________________ Dollars ($ _______________) in lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents.

WHEREAS, the Principal is about to submit, or has submitted, to the City of Johns Creek, Georgia, a proposal for furnishing materials, labor and equipment for:

TITLE

WHEREAS, the Principal desires to file this Bond in accordance with law in lieu of a certified Bidder’s check otherwise required to accompany this Proposal.

NOW, THEREFORE, the conditions of this obligation are such that if the bid is accepted, the Principal shall within ten days after receipt of notification of the acceptance execute a Contract in accordance with the Bid and upon the terms, conditions, and prices set forth in the form and manner required by the City of Johns Creek, Georgia, and execute a sufficient and satisfactory Performance Bond and Payment Bond payable to the City of Johns Creek, Georgia, each in an amount of 100% of the total Contract Price, in form and with security satisfactory to said the City of Johns Creek, Georgia, and otherwise, to be and remain in full force and virtue in law; and the Surety shall, upon failure of the Principal to comply with any or all of the foregoing requirements within the time specified above, immediately pay to the City of Johns Creek, Georgia, upon demand, the amount hereof in good and lawful money of the United States of America, not as a penalty, but as liquidated damages.

PROVIDED, FURTHER, that Principal and Surety agree and represent that this bond is executed pursuant, to and in accordance with the applicable provisions of the Official Code of Georgia Annotated, as Amended, including, but not limited to, O.C.G.A. SS 13-10-1, et. Seg. And SS 36- 86-101, et. Seg. And is intended to be and shall be constructed as a bond in compliance with the requirements thereof.

Signed, sealed, and dated this __________ day of ________________________________A.D., 20____

ATTEST:

(Principal Secretary) (Principal)

(SEAL) BY: _________________________________

(Witness to Principal) (Address)

(Address) (Surety)

ATTEST

BY: _______________________________

(Attorney-in-Fact) and Resident Agent (Attorney-in-Fact)

(Seal) _________________________________ (Address) (Witness as to Surety) (Address)

Form W-9 (Rev. October 2018) Department of the Treasury Internal Revenue Service

Request for Taxpayer Identification Number and Certification

Go to www.irs.gov/FormW9 for instructions and the latest information.

Give Form to the requester. Do not send to the IRS.

P ri n t o r ty p e

S ee

S p e c if ic

I n s tr u c ti o n s o n p ag e

3.

1 Name (as shown on your income tax return). Name is required on this line; do not leave this line blank.

2 Business name/disregarded entity name, if different from above

3 Check appropriate box for federal tax classification of the person whose name is entered on line 1. Check only one of the following seven boxes.

Individual/sole proprietor or single-member LLC

C Corporation S Corporation Partnership Trust/estate

Limited liability company. Enter the tax classification (C=C corporation, S=S corporation, P=Partnership)

Note: Check the appropriate box in the line above for the tax classification of the single-member owner. Do not check LLC if the LLC is classified as a single-member LLC that is disregarded from the owner unless the owner of the LLC is another LLC that is not disregarded from the owner for U.S. federal tax purposes. Otherwise, a single-member LLC that is disregarded from the owner should check the appropriate box for the tax classification of its owner.

Other (see instructions)

4 Exemptions (codes apply only to certain entities, not individuals; see instructions on page 3):

Exempt payee code (if any)

Exemption from FATCA reporting code (if any)

(Applies to accounts maintained outside the U.S.)

5 Address (number, street, and apt. or suite no.) See instructions.

6 City, state, and ZIP code

Requester’s name and address (optional)

7 List account number(s) here (optional)

Part I Taxpayer Identification Number (TIN)

Enter your TIN in the appropriate box. The TIN provided must match the name given on line 1 to avoid backup withholding. For individuals, this is generally your social security number (SSN). However, for a resident alien, sole proprietor, or disregarded entity, see the instructions for Part I, later. For other entities, it is your employer identification number (EIN). If you do not have a number, see How to get a TIN, later.

Note: If the account is in more than one name, see the instructions for line 1. Also see What Name and Number To Give the Requester for guidelines on whose number to enter.

Social security number or Employer identification number

Part II Certification

Under penalties of perjury, I certify that:

1. The number shown on this form is my correct taxpayer identification number (or I am waiting for a number to be issued to me); and

2. I am not subject to backup withholding because: (a) I am exempt from backup withholding, or (b) I have not been notified by the Internal Revenue

Service (IRS) that I am subject to backup withholding as a result of a failure to report all interest or dividends, or (c) the IRS has notified me that I am no longer subject to backup withholding; and

3. I am a U.S. citizen or other U.S. person (defined below); and

4. The FATCA code(s) entered on this form (if any) indicating that I am exempt from FATCA reporting is correct.

Certification instructions. You must cross out item 2 above if you have been notified by the IRS that you are currently subject to backup withholding because you have failed to report all interest and dividends on your tax return. For real estate transactions, item 2 does not apply. For mortgage interest paid, acquisition or abandonment of secured property, cancellation of debt, contributions to an individual retirement arrangement (IRA), and generally, payments other than interest and dividends, you are not required to sign the certification, but you must provide your correct TIN. See the instructions for Part II, later.

Sign Here

Signature of

U.S. person Date

General Instructions Section references are to the Internal Revenue Code unless otherwise noted.

Future developments. For the latest information about developments related to Form W-9 and its instructions, such as legislation enacted after they were published, go to www.irs.gov/FormW9.

Purpose of Form An individual or entity (Form W-9 requester) who is required to file an information return with the IRS must obtain your correct taxpayer identification number (TIN) which may be your social security number (SSN), individual taxpayer identification number (ITIN), adoption taxpayer identification number (ATIN), or employer identification number (EIN), to report on an information return the amount paid to you, or other amount reportable on an information return. Examples of information returns include, but are not limited to, the following.

• Form 1099-INT (interest earned or paid)

• Form 1099-DIV (dividends, including those from stocks or mutual funds)

• Form 1099-MISC (various types of income, prizes, awards, or gross proceeds)

• Form 1099-B (stock or mutual fund sales and certain other transactions by brokers)

• Form 1099-S (proceeds from real estate transactions)

• Form 1099-K (merchant card and third party network transactions)

• Form 1098 (home mortgage interest), 1098-E (student loan interest), 1098-T (tuition)

• Form 1099-C (canceled debt)

• Form 1099-A (acquisition or abandonment of secured property)

Use Form W-9 only if you are a U.S. person (including a resident alien), to provide your correct TIN.

If you do not return Form W-9 to the requester with a TIN, you might be subject to backup withholding. See What is backup withholding, later.

Cat. No. 10231X Form W-9 (Rev. 10-2018)

REFERENCES

REFERENCES: Please provide the City with three (3) clients of similar size and scope of work. You may submit your standard list of references as opposed to using this form, but you still need to complete and sign at the bottom.

REFERENCE # 1

Name of Entity/Firm:

Mailing Address:

City/State/Zip Code:

Contact Person Name: _____________________________________________________

Contact Phone Number and Email:

Date When Work Performed:

Description of Work Performed _

REFERENCE # 2

Contact Person Name: ____________________________________________________

Description of Work Performed

REFERENCE # 3

Contact Person Name: ____________________________________________________

Description of Work Performed

EXHIBIT D.

LOCATION MAP

Other files

File Type Posted
Plans —
Specifications —
Award Information —
Bid Form —
23-122 Wall Plan —
23-122 Addendum #1 Handrail —
23-122 NOIA —
23-122 Plans —
Award Information —
Addendum 1 Arborist —
23-122 addendum #1 —
23-122 Bids —
23-122 Sidewalk Plan —
23-122 revised plans —
23-122 Sample Contract —
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .