This document is a technical specification section for demonstrations and tests required for boiler plant equipment and systems under Department of Veterans Affairs (VA) federal construction contracts.

The specification establishes mandatory procedures for onsite demonstration, testing, and training of boiler plant equipment prior to Government acceptance for beneficial use. Contractor responsibilities include conducting start-up activities (initial inspection, cleaning, lubrication, and adjustment), pre-tests to verify system readiness, and final tests witnessed by the Contracting Officer's Representative (COR) or designated representative. All safety devices must pass 100 percent inspection before acceptance. Equipment requiring demonstration and testing includes boilers and economizers, burners, control systems, and instrumentation. Experienced technical service personnel representing equipment manufacturers must conduct all demonstrations, instructions, and tests. The contractor must deliver maintenance and operating manuals four weeks prior to instruction, arrange for all test personnel to be continuously present during testing, furnish special tools, and correct any detected defects at no additional cost. Demonstrations and training must occur no more than four weeks prior to Government acceptance and include at least eight total instructor hours covering operation, maintenance, troubleshooting, and lockout/tagout procedures using contractor-provided written standard operating procedures. Contractors must submit certification of completed pre-testing, preliminary test schedules two weeks in advance, and final reports within three weeks of satisfactory completion, including test data and calculations. If final tests fail and require retesting, the Government receives full credit for all independent testing organization or consultant expenses incurred for re-inspections.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

04-01-20

23 08 11 - 1

SECTION 23 08 11

DEMONSTRATIONS AND TESTS FOR BOILER PLANT

PART 1 - GENERAL

1.1 DESCRIPTION

A. Procedures for onsite demonstration and testing of equipment and systems, including temporary facilities.

B. Instruction of Government operating personnel.

C. All demonstrations, instructions, access platforms, and testing must be completed prior to Government acceptance for beneficial use. All safety devices shall pass 100 percent before the boiler plant can be accepted for beneficial use.

D. Plumbing and emergency power systems are not included.

E. Definitions:

1. Start-Up: Initial inspection, cleaning, lubrication, adjustment, and operation of equipment and systems by the contractor with the assistance of the representatives of the equipment manufacturers.

2. Pre-Tests: The final stage of the start-up procedure. This occurs after all adjustments have been made except for minor fine-tuning that can be done during the pre-test. Serves as verification that the systems are ready for the final test. Witnessing of pre-test by

COR is not required.

3. Final Tests: Tests, witnessed by the COR or designated representative, which demonstrate that all equipment and systems are in compliance with requirements. At VA expense, VA may utilize the services of an independent testing organization or consultant to witness the tests. If any portion of the final test fail and must be retested the Government shall receive a full credit for any expenses incurred for services from independent testing organizations or consultant services for all re-inspections or tests.

F. A complete listing of common acronyms and abbreviations are included in Section 23 05 10, COMMON WORK RESULTS FOR BOILER PLANT AND STEAM

GENERATION.

1.2 RELATED WORK

A. Section 23 05 10, COMMON WORK RESULTS FOR BOILER PLANT AND STEAM

GENERATION.

B. Section 23 09 11, INSTRUMENTATION AND CONTROL FOR BOILER PLANT.

C. Section 23 52 33, WATER-TUBE BOILERS.

23 08 11 - 2

1.3 APPLICABLE PUBLICATIONS

A. The publications listed below form a part of this specification to the extent referenced. The publications are referenced in the text by the basic designation only. Where conflicts occur these specifications and the VHA standard will govern.

B. Department of Veterans Affairs (VA):

2008....................VHA Boiler Plant Safety Devices Testing Manual, Third Edition

PG-18-10-2015...........Physical Security and Resiliency Design Manual

1.4 SUBMITTALS

A. Submittals, including number of required copies, shall be submitted in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND

SAMPLES.

B. Information and material submitted under this section shall be marked

“SUBMITTED UNDER SECTION 23 08 11, DEMONSTRATIONS AND TESTS FOR BOILER

PLANT”, with applicable paragraph identification.

C. Names and qualifications of personnel performing demonstrations, instructions and tests.

D. Certification that pre-testing is complete. Copies of boiler-burner and feedwater deaerator pre-test data as specified. Copies of the VHA

Boiler Plant Safety Devices Testing Manual completely filled out with notes.

E. Preliminary schedule of all demonstrations, instructions and final tests two weeks prior to proposed dates.

F. Provide reports within three weeks after satisfactory completion of demonstrations, instructions, and tests. List date, type of work, persons participating, amount of time, test results, calculations of test results, test data.

1.5 QUALITY ASSURANCE

A. Experienced, trained technical service personnel who are representatives of the equipment manufacturers and system designers shall demonstrate, provide instructions, pre-test and final test, as specified, the following equipment:

1. Boilers and economizers

2. Burners

3. Control systems

4. Instrumentation

23 08 11 - 3

B. The COR, upon request, will provide a list of personnel to receive instructions and will coordinate their attendance at agreed upon times.

C. All safety devices shall comply with the VHA Boiler Plant Safety

Devices Testing Manual.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 PREPARATION FOR FINAL TESTS, DEMONSTRATIONS, AND INSTRUCTIONS

A. Verify that equipment and systems are fully operational. Complete all start-up and pre-test activities for all equipment and systems.

Complete all construction and finish work.

B. Arrange for all test personnel for all equipment to be continuously present during one period of time so that all equipment and systems can be tested in their interrelated functions.

C. Deliver maintenance and operating manuals four weeks prior to instruction period.

D. Furnish all special tools.

3.2 FINAL TESTS

A. Demonstrate proper operation of each equipment and system to include demonstration and testing of all safety devices.

B. Provide tests on equipment as specified in the individual specification sections.

3.3 START-UP AND TESTING

A. When any defects are detected, correct defects and repeat test at no additional cost or time to the Government.

3.4 DEMONSTRATIONS AND TRAINING

A. Demonstrate operation and maintenance of equipment and systems to

Government personnel no more than four weeks prior to Government acceptance of the replacement equipment.

B. Use operation and maintenance manuals, as-built drawings, and single line drawings as basis of instruction. Review contents of manuals and drawings with personnel in detail to explain all aspects of operation and maintenance.

C. Demonstrate start-up, operation, control, adjustment, trouble-shooting, servicing, maintenance, and shut-down of each item of equipment. Allow

Government personnel to practice operating the equipment under supervision of instructors.

1. All demonstrations shall follow a contractor provided written step by step standard operating procedure.

23 08 11 - 4

2. Demonstrate lockout/tagout locations for all equipment and hazards using a written procedure that clearly identifies lockout points

(breakers, disconnects, valves, etc.) for each piece of equipment.

Valves are to be identified by a valve tag number, breakers are by number located in breaker box number, disconnect location and number etc.

3. Demonstrate the as-built drawings are correct and provide single line drawings for each system.

D. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instructions.

3.5 TIME ALLOCATED FOR DEMONSTRATIONS AND INSTRUCTIONS

A. At least 8 total instructor hours to include boilers, economizers, burners, burner controls, combustion controls, instrumentation.

- - - E N D - - -

SECTION 23 08 11
DEMONSTRATIONS AND TESTS FOR BOILER PLANT
PART 1 - GENERAL
1.1 DESCRIPTION
1.2 RELATED WORK
1.3 APPLICABLE PUBLICATIONS
1.4 SUBMITTALS
1.5 QUALITY ASSURANCE
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION
3.1 PREPARATION FOR FINAL TESTS, DEMONSTRATIONS, AND INSTRUCTIONS
3.2 FINAL TESTS
3.3 START-UP AND TESTING
3.4 DEMONSTRATIONS AND TRAINING
3.5 TIME ALLOCATED FOR DEMONSTRATIONS AND INSTRUCTIONS