22-Attachment Z - Policy for Payment.pdf

PDF 57 KB Posted

Attached to
ITB – Drainage Improvements in the Barwood Subdivision (2018) for Harris County Precinct 3 (CDBG-MIT / GLO)
Solicitation number
25/0227
Issued by
Harris County, Texas

About this file

This document is a policy for payment of material on hand issued by the Harris County Engineering Department in Texas, dated December 6, 2005. The policy outlines the procedures for requesting compensation for nonperishable materials that have been delivered to a work location but not yet used, with specific guidelines for what materials are eligible for payment. Eligible materials include those that have been sampled, tested, approved, or certified, and are ready for incorporation into the work, such as concrete traffic barriers, precast concrete box culverts, beams, reinforced concrete pipe, steel girders, and other items deemed reasonable by the Engineer.

The policy establishes that payment for material on hand will only be made for materials authorized for purchase by work order or with written approval from the Engineer, and will not exceed the actual cost as established by invoice. The total value for associated reasonable placement costs is also considered. Contractors must submit monthly material on hand forms until the total value reaches zero, and by submitting a request, they authorize Harris County Engineering Department to audit records and review the record-keeping system. The document emphasizes that payment does not constitute acceptance of materials, and materials not used within 60 days will be ineligible for payment and removed from the summary.

View the file

Other files

File Type Posted
34-BidOpeningSummaryReport 2025-08-04.pdf PDF
11-Attachment W - GLO Compliance Package.pdf PDF
1-Attachment A - Bid Addenda Acknowledgement.pdf PDF
15-Attachment G - Contractor Profile.pdf PDF
21-Attachment V - Project Signs and Plaques.pdf PDF
13-Attachment CC – MWBE Utilization Plan Commitment Form.pdf PDF
9-Attachment N - Workers Compensation Insurance Coverage Rule 110.110.pdf PDF
17-Attachment L - Certification of Compliance with Federal Standards Requirements.pdf PDF
10-Attachment H - Bid Bond Confirmation and Bid Check Authorization Form.pdf PDF
33-25 0227 - Bid Submissions.zip ZIP file
2-Attachment B - Bid Schedule - Pricing Form.pdf PDF
32-Addendum No. 1 - General Notices, Notes and Information.pdf PDF
16-Attachment Q - Section 3 Bid Requirements.pdf PDF
18-Attachment P - Required Contract Provisions.pdf PDF
30-Addendum No. 1 - Plans and Drawings (Index Sheet).pdf PDF
27-Attachment S - Plans and Drawings.pdf PDF
19-Attachment T - General Conditions.pdf PDF
12-Attachment FF - Heat Protection Safety Requirements.pdf PDF
23-Attachment AA - Report File.pdf PDF
7-Attachment K - Payment Bond.pdf PDF
3-Attachment C - Certification Regarding Lobbying.pdf PDF
29-Addendum No. 1 - 250227.pdf PDF
20-Attachment U - General Notices, Notes and Information.pdf PDF
24-Attachment BB - MWBE Goal Participation Information Packet.pdf PDF
35-25-5445 Award Job No. 250227 - C.E. Barker, Ltd.pdf PDF
31-Addendum No. 1 - Plans and Drawings (Proposed Typical Sections).pdf PDF
8-Attachment M - Minimum Insurance Requirements for Harris County.pdf PDF
25-Federal IFB General Conditions and Specifications - Construction.docx DOCX document
5-Attachment F - References.pdf PDF
28-Pre Bid Sign-in Sheet 250227.pdf PDF
14-Attachment DD – MWBE Trucking Procedure Compliance Packet.pdf PDF
4-Attachment D - Statement of Bidder Qualifications.pdf PDF
26-Attachment O - Davis Bacon Wage Decision.pdf PDF
6-Attachment I - Performance Bond for Public Works over 100,000.pdf PDF
Show all 34

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .