21-Attachment KK - Performance Standards References Tables.pdf

PDF 447 KB Posted

Attached to
RFP - Emergency Debris Removal and Management Services for Harris County (Grant Funded)
Solicitation number
26/0066
Issued by
Harris County, Texas

About this file

This document is a performance standards reference table attachment for Harris County's Emergency Debris Removal and Management Services contract, establishing quantitative operational requirements for debris removal contractors. The attachment specifies three disaster classifications with corresponding first-pass completion deadlines: Standard Events (debris less than 3 million cubic yards) require completion within 45 calendar days for all zones; Major Events (3-8 million cubic yards) require 45 days for priority zones and 60 days for secondary zones; and Catastrophic Events (debris exceeding 8 million cubic yards) require negotiated timelines established within 7 days of Notice to Proceed. Priority zones are designated by the County Debris Manager based on life-safety corridors, critical infrastructure, high-density residential areas, and Commissioner Precinct priorities, with first-pass completion requiring clearance of all county-pinned debris locations, monitor verification with timestamped photography, and formal County acceptance.

Contractors must maintain minimum operational capacity including 150 debris hauling units with 20+ cubic yard capacity, 40 small trucks deployable within 72 hours, and 20 self-loading units or loader/truck combinations, with additional debris reduction and support equipment as specified in operational plans. Daily operational readiness must meet an 80% standard, calculated as trucks working divided by total trucks deployed, assessed through County monitor records and GPS tracking data with 5-minute ping intervals, with consequences including work reallocation or liquidated damages assessment if readiness falls below 80% for more than two consecutive days. Contractors must also establish and maintain a minimum of 15 Debris Management Sites distributed across all four Commissioner Precincts with at least 3 sites per precinct, each site requiring 5 acres minimum size, location outside FEMA floodways and 100-year floodplains, executed lease agreements during activation, and 80% daily operational readiness, with the first 8 sites operational within 7 days and all 15 sites operational within 14 days of County authorization.

View the file

Other files

File Type Posted
20-Attachment II – FEMA Disaster Questionnaire.pdf PDF
26-Federal RFP General Requirements and Specifications.pdf PDF
13-Attachment K - Certification of Compliance with Federal Standards Requirements.pdf PDF
4-Attachment X – Non-HUB MWBE Utilization Plan Commitment Form.pdf PDF
6-Attachment B - Pricing Form.pdf PDF
8-Attachment CC - Harris County Minimum Wage Policy and Certification and FAQs.pdf PDF
2-Attachment G - Contractor Profile.pdf PDF
17-Attachment JJ - Federal Highway Administration (FHWA).pdf PDF
9-Attachment D - Statement of Offeror Qualifications.pdf PDF
18-Attachment HH - Stump Conversion Table.pdf PDF
15-Attachment GG - CPI-W Based Price Adjustment Calculations.pdf PDF
27-Attachment EE - Bid Bond and Bid Check Authorization Form.pdf PDF
12-Attachment J - Payment Bond.pdf PDF
25-Attachment N - Required Contract Provisions.pdf PDF
1-Attachment AA - Policy for Payment.pdf PDF
23-Attachment LL - Prevailing Wage Rates and Payroll Submittal Instructions.pdf PDF
10-Attachment F - References.pdf PDF
14-Attachment DD - Vendor Disclosure Form.pdf PDF
7-Attachment C - Certification Regarding Lobbying.pdf PDF
3-Attachment A - RFP and Addenda Acknowledgement.pdf PDF
16-Attachment FF - Heat Protection Safety Requirements.pdf PDF
5-Attachment Y – Non-HUB MWBE Goal Participation Information Packet.pdf PDF
22-Attachment L - Harris County Minimum Insurance Requirements (Construction).pdf PDF
19-Attachment Z – MWBE Trucking Procedure Compliance Packet.pdf PDF
11-Attachment H - Performance Bond for Public Works over 100,000.pdf PDF
24-Attachment M - Workers Compensation Insurance Coverage Rule 110.110.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT KK

Performance Standards Reference Tables

This Appendix contains the quantitative performance standards referenced throughout the solicitation.

These tables are operative contract requirements if this document is used as a standalone solicitation. If issued as part of a larger contract package, the executed contract documents and any issued addenda govern. Where a conflict exists, the more stringent requirement applies.

Table A-1: First Pass Completion Deadlines by Disaster Classification

The County establishes First Pass completion deadlines based on estimated total debris volume. Zone priority designations are determined by the County Debris Manager at time of NTP.

Disaster Classification Zone Type First Pass Completion Deadline

Standard Event (Total debris <

3M CY)

All zones 45 calendar days from zone assignment

Major Event (Total debris 3M–

8M CY)

Priority zones 45 calendar days from zone assignment

Major Event (continued) Secondary zones 60 calendar days from zone assignment

Catastrophic Event (Total debris > 8M CY)

All zones Negotiated timeline established within 7 days of NTP in collaboration with the County

Priority Zone criteria: life-safety corridors (hospitals, emergency routes); critical infrastructure (fire stations, power grid); high-density residential areas; Commissioner Precinct priorities. First Pass is not complete until all County-pinned debris locations are cleared, monitors have verified every county road in the zone as clean with timestamped photography, and the County has formally accepted zone completion.

Table A-2: Operational Capacity Minimums and Readiness Formula

The following capacity standards apply during all active debris removal operations. Failure to maintain minimum operational readiness may result in LD assessment or work reallocation at the County’s discretion.

A. Minimum Fleet Requirements for Award Eligibility

Equipment Type Minimum Count

Notes

Debris hauling units (20+ CY capacity)

150 units Owned, leased, rented, or broker-committed

Small trucks (10–15 CY capacity) 40 units Must be deployable within 72 hours of NTP

Self-loading units or loader/truck combinations

20 units For right-of-way push and collection

Debris reduction equipment As proposed Grinders, chippers, compactors per operational plan

Equipment Type Minimum Count

Notes

Support equipment As proposed Excavators, dozers, water trucks per operational plan

B. Daily Operational Readiness Standard

Metric Standard / Definition

Minimum Daily Readiness 80% of deployed equipment must be operational each day

Readiness Formula (Trucks Working ÷ Total Trucks Deployed) × 100% ≥ 80%

Operational Definition Mechanically functional; properly certified; qualified and licensed driver present; compliant with all applicable safety and DOT requirements

Measurement Period Assessed daily based on County monitor records and GPS tracking data (5-minute ping intervals minimum)

Consequence of Failure If readiness falls below 80% for more than two (2) consecutive days, the County may reallocate work to other qualified pool contractors or assess liquidated damages

C. Debris Management Site (DMS) Minimum Requirements

Requirement Standard

Minimum total sites 15 sites distributed across all four Commissioner Precincts

Minimum sites per Precinct 3 sites per Precinct

Minimum site size 5 acres each

Flood zone restriction All sites outside FEMA floodway and 100-year floodplain

Lease status Executed lease agreements required during activation; letters of intent to lease updated annually; current site list provided to County within 30 days of each contract anniversary

Activation timeline – first 8 sites Operational within 7 days of County authorization

Activation timeline – all 15 sites Operational within 14 days of County authorization

Operational hours Accept debris 24/7 when operational

Daily readiness standard 80% of DMS site equipment operational daily (same formula as field equipment)