21-3-General Conditions ag.pdf

PDF 350 KB Posted

Attached to
BID #2026-049A-W/S OCEAN ACRES BOOSTER PUMP REPLACEMENT PHASE 2 AND WELL NO. 5 REDEVELOPMENT
Solicitation number
BID #2026-049A-W/S
Issued by
Ocean County, New Jersey

About this file

This file contains the General Conditions for a contract awarded by Stafford Township, Ocean County, New Jersey, for the Ocean Acres Booster Pump Replacement Phase 2 and Well No. 5 Redevelopment project (Bid #2026-049A-W/S). The work involves furnishing all labor, materials, equipment, tools, and supervision required to rehabilitate existing Well No. 5 and replace two existing high service booster pumps with associated motor rehabilitation. The high service pumps are located at 327 Golfview Drive, Manahawkin, New Jersey, and Well No. 5 is located at 181 Stafford Avenue, Manahawkin, New Jersey. All well rehabilitation work must be performed under the direct supervision of a New Jersey Licensed Master Well Driller in accordance with New Jersey Department of Environmental Protection requirements. The contract time limit is ninety (90) days from the date of the Engineer's Notice to Proceed. The Engineer for this project is Remington & Vernick Engineers, located at 9 Allen Street, Toms River, New Jersey 08753.

The General Conditions establish liquidated damages for delay, with penalties escalating from $500 per calendar day for days one through fifteen beyond the contract time limit, to $1,000 per calendar day for days sixteen through thirty, and $2,000 per calendar day for delays exceeding thirty days. The contractor must provide proof of insurance including General Liability, Automobile Liability, Excess Liability, and Worker's Compensation coverage, with the Owner and Engineer named as additional insureds. Payment procedures include retainage of 10 percent on contracts of $100,000 or less, while contracts exceeding $100,000 are subject to the Local Public Contracts Law with a 2 percent retainage requirement. The contractor must comply with the New Jersey Prevailing Wage Act and submit certified payroll reports within ten days of wage payment. The contractor is responsible for all surveys, material testing costs, and maintaining a competent superintendent continually present on the project site. Final payment is contingent upon submission of a Full Release and Waiver of Liens and a Prevailing Wage Payment Certification.

View the file

Other files

Show all 25

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Revised 09/22 GC, Table of Contents

TABLE OF CONTENTS

GENERAL CONDITIONS

PAGE NO.

1.0 GENERAL PROVISIONS

1.01 Definitions GC-1

1.02 Special Notice GC-2

1.03 Representation of Contractor GC-2

1.04 Subletting or Assigning of Contract GC-2

1.05 Construing the Specifications GC-2

1.06 Necessary to Complete GC-2

1.07 Drawings and Specifications GC-2

1.08 Right-Of-Way GC-3

1.09 Time Limits GC-3

1.10 Liquidated Damages GC-3

1.11 Owner's Right to Stop Work or Terminate Contract GC-4

1.12 Reference to the Standard Specifications GC-5

2.0 INSURANCE

2.01 State Law and Regulations and Insurance GC-5

2.02 Contractor's Insurance GC-5

2.03 Suit or Claims GC-6

2.04 Damages to Persons and Property GC-6

3.0 CONDUCT OF THE WORK

3.01 Role of the Engineer GC-6

3.02 Surveys GC-6

3.03 Preservation of Stakes GC-7

3.04 Uses of Premises and Removal of Debris GC-7

3.05 Injury to Existing Structures GC-7

3.06 Correction of Work GC-7

3.07 Public Utilities GC-8

3.08 Protection of Work and Property GC-8

3.09 Contractor to Act in an Emergency GC-8

PAGE NO.

3.10 Extra Work GC-8

3.11 Dispute Resolution GC-9

4.0 CONTRACTOR'S PERSONNEL

4.01 Personal Attention GC-9

4.02 Contractor's Superintendent GC-9

4.03 Labor Laws GC-10

4.04 Contractor's Employees GC-10

4.05 Eight Hour Day: Prevailing Wage Rate GC-11

4.06 Payment of Employees GC-11

4.07 Safety and Health Regulations GC-11

4.08 Accident Prevention GC-11

5.0 MATERIALS

5.01 Contractor's Title to Materials GC-11

5.02 Royalties and Payments GC-11

5.03 Use of Domestic Material GC-11

5.04 Ordering Materials GC-12

5.05 Samples GC-12

5.06 Shop or Setting Drawings GC-12

5.07 Additional Instructions and Detail Drawings GC-12

5.08 Or Equal Clauses GC-13

5.09 Substitutions GC-13

5.10 Material Safety Data GC-13

6.0 INSPECTION AND TESTING

6.01 Inspection GC-14

6.02 Daily Reports GC-14

6.03 Inspectors GC-14

6.04 Access to the Work GC-15

6.05 Covering Uninspected Work GC-15

6.06 Testing Materials GC-15

PAGE NO.

7.0 PAYMENTS

7.01 Construction Schedule and Periodic Estimates GC-15

7.02 Payments GC-16

7.03 Retainage GC-17

7.04 Acceptance of Final Payment as Release GC-17

7.05 Owner's Right to Withhold Payments GC-18

7.06 Costs of Engineering and Inspection GC-18

7.07 Liens GC-18

7.08 Prevailing Wage Payment Certificate GC-18

7.09 Certified Payroll Reports GC-19

8.0 VALUE ENGINEERING CONSTRUCTION CHANGE ORDERS

8.01 Implementation of Value Engineering GC-19

8.02 Statutory Provisions GC-19

8.03 Procedures GC-20

9.0 DIFFERING SITE CONDITIONS PROVISIONS GC-23

Prevailing Wage Payment Certification Form GC-27

Form GC-6.02S - Certificate of Site Safety Conditions GC-28

Full Release and Waiver of Liens GC-29

Revised 09/22 GC-1

GENERAL CONDITIONS

1.0 GENERAL

1.01 DEFINITIONS

The following words and expressions used in the contract documents shall be construed as follows:

Owner Stafford Township

260 East Bay Avenue, Manahawkin, NJ 08050 Engineer Remington &Vernick Engineers

9 Allen Street Toms River, New Jersey 08753

Contractor Party, firm, corporation with whom or which the contract is made, or authorized agent thereof.

Day Calendar day Legal Holiday Days which the owner does not conduct regular business hours. The

Contractor is responsible to contact the Owner for a listing of these days Substantial Completion The work will not reach Substantial Completion until all project systems included in the work are operational as designed and scheduled, all designated or required inspections, certifications, permits, approvals, licenses and other documents from any governmental authority having jurisdiction thereof necessary for the beneficial use and occupancy of the work are received, designated instruction of Owner’s personnel has been completed, and all final finishes within the Contract are in place.

Any remaining work shall be minor in nature, so that the Owner can occupy the building on that date and the completion of the remaining work by the Contractor would not materially interfere or hamper the Owner’s (or those claiming by, through or under the Owner) normal operations. Contractor recognizes that normal operations require the use and occupancy of the work area without interruption and that any punchlist or corrective work shall be done at times when the work area is not so occupied. As a further condition of reaching Substantial Completion, the Contractor shall certify that all remaining work will be completed within thirty (30) consecutive calendar days or as so agreed upon following the date of Substantial Completion. Site related projects and/or projects including facilities with site improvements shall not reach Substantial Completion until such time as all site amenities (i.e.

lighting, top paving, striping, fencing, stormwater compliance, etc..) are placed into service leaving only minor improvements that will not hamper access or use to complete the project.”

Final Completion All warranties and guarantees required pursuant to the Contract Documents shall be assembled and delivered by the Contractor to the Owner as part of the final application for payment. The final Certificate for Payment will not be issued by the Engineer until all warranties and guarantees have been received and accepted by the Owner.

Revised 09/22 GC-2

1.02 SPECIAL NOTICE

The "Information for Bidders", the "General Conditions", the "Notice to Bidders", and "Proposal Section" shall be held equally binding with and are to be considered a part of the specifications and contract and the party of the second part, the Contractor, will be held responsible for neglect in attending to any part, paragraph or item therein.

1.03 REPRESENTATION OF CONTRACTOR

The Contractor represents and warrants:

(a) That he is financially solvent and that he is experienced in and competent to perform the type of work to furnish the labor, plant, materials and supplies or equipment to be so performed or furnished by him and

(b) That he is familiar with all Federal, State, County, Municipal and Department Laws, Ordinances and

Regulations, which may in any way affect the work or those employed therein, including, but not limited to, any special Acts relating to the work or to the project of which it is a part, and

(c) That such temporary and permanent work required by the contract documents and is to be done by him can be satisfactorily constructed and used for the purpose for which it is intended, and that such construction will not injure any persons or damage any property, and

(d) That he has carefully examined the drawings, specifications, and the site of the work, and that from his own investigations he has satisfied himself as to the nature and location of the work, the character, quality and quantity of surface and subsurface materials likely to be encountered, the character of equipment and other facilities needed for the performance of the work, the general and local conditions and all other items which may in any way affect the work or its performance.

1.04 SUBLETTING OR ASSIGNING OF CONTRACT

The Contractor shall not assign, sell or transfer or otherwise dispose of the contract or any portion thereof or of the work provided therein or his right, title or interest therein, to any persons, firm or corporation, without prior written consent of the Owner.

1.05 CONSTRUING THE SPECIFICATIONS

To avoid disputes and litigation, it must be distinctly understood by the Bidder/Contractor that the Engineer shall construe or interpret the specifications and explain any ambiguity therein and shall have the right to decide as to their purpose and intent and his decision upon any such ambiguity shall be final, conclusive and binding.

1.06 NECESSARY TO COMPLETE

If any work or materials are required which are obviously necessary to carry out the full intent and meaning of the said specifications although the same may not be either directly or indirectly in the specifications, the Contractor is hereby bound to furnish the same without charge or claim.

1.07 DRAWINGS AND SPECIFICATIONS

The Contractor shall keep at the site of the work one copy of the drawings and specifications signed and identified by the Engineer and shall at all times give the Engineer and other representatives of the Owner access thereto.

Anything shown on the drawings and not mentioned in the specifications or mentioned in the specifications and not shown on the drawings, shall have the same effect as if shown or mentioned respectively in both.

In case of any conflict within the construction documents, the Engineer shall determine which of the requirements shall govern based upon the most stringent of the requirements, and the Contractor shall perform the work at no

Revised 09/22 GC-3 additional cost or time to the owner. Any ambiguity or discrepancy between drawings and specifications shall be submitted by the Contractor to the Engineer whose decision shall be conclusive.

The general arrangement and location of equipment, the various pipe, duct, and conduit runs, etc. are shown on the drawings. All dimensions or the scales of the drawings shall be considered as approximate and shall be checked by each bidder to his own satisfaction prior to bid. The exact location of all parts of the work shall be governed by existing conditions, and the Contractor shall coordinate and locate all work at the time of installation.

Any changes in location, etc. from that shown on the drawings, necessary by existing conditions, shall be made by the Contractor at no increase of the contract sum.

1.08 RIGHT-OF-WAY

All right-of-ways through private property required shall be secured by the Owner. Contractor shall not start construction in right-of-ways until directed by the Engineer. No claim shall be made by the Contractor for damage due to delay in securing right-of-ways.

1.09 TIME LIMITS

The Contractor agrees to start the work herein contracted for within ten (10) days from the date of the Engineer's Notice to Proceed to the Contractor directing him to proceed with the work. The time to complete the work contracted for, from the date of the Proceed Order, shall be limited to the following:

90 (NINETY) DAYS

No extension of time will be allowed for delay from any cause whatsoever, including normal weather conditions unless the Contractor shall have notified the Engineer in writing of such delay and his intention to claim an extension of time within two (2) days after the beginning of such delay. Such notice shall give complete information concerning the nature, extent and cause of the delay. If, in the opinion of the Owner, an extension of time is warranted the Owner or Owner’s representative, will issue a written extension, setting a new time limit for the completion of the work.

1.10 LIQUIDATED DAMAGES

In case the Contractor fails to complete the work contracted for, satisfactory to and acceptable to the Owner within the stipulated time limit, or violates any terms or conditions of said contract or the terms and conditions of P.L.

1971, c. 198 (C.40A:11-1 et seq.,, Local Publics Contract Law), then the Contractor shall and will pay to the Owner for each and every calendar day determined to be in default, the following sums, which are agreed upon, fixed and determined by the parties hereto to be liquidated damages.

One (1) to Fifteen (15) Days beyond Contract Time Limits………Five Hundred ($500.00) dollars per calendar day.

Sixteen (16) to Thirty (30) Days beyond Contract Time Limits…..One Thousand ($1,000.00) dollars per calendar day

Greater than Thirty (30) Days beyond Contract Time Limits ……..Two Thousand ($2,000.00) dollars per calendar day

The Owner shall recover said damages by deducting the amount thereof out of any money which may be due or become due the Contractor, or by an action of law against the Contractor, his surety or by either or both of these methods.

Revised 09/22 GC-4

In case the Contractor shall be delayed due to the failure on the part of the Owner to furnish anything on its part to be furnished or for any other cause beyond the control of the Contractor, he shall be entitled to such an extension of time for the delivery of equipment, materials, work and supplies as in the judgement of the Owner or Owner’s representative to be fair and just.

1.11 OWNER'S RIGHT TO STOP WORK OR TERMINATE CONTRACT

The Owner has the right to stop work or terminate the contract, if:

(a) The Contractor has violated the provisions of P.L. 1971 c. 198 (C:40A:11-1 et seq., Local Public

Contracts Law),or any other Federal, State or Local law, or

(b) The Contractor shall be adjudged bankrupt or make an assignment for the benefit of creditors, or

(c) A receiver or liquidator shall be appointed for the Contractor or for any of his property and shall not be dismissed within 20 days after such appointment or the proceedings in connection therewith shall not be stayed on appeal within the said 20 days, or

(d) The Contractor shall refuse or fail, after notice or warning from the Engineer, to supply enough properly skilled workmen or proper materials, or

(e) The Contractor shall refuse or fail to prosecute to work or any part thereof with such diligence as will ensure its completion within the period herein specified (or any duly authorized extension thereof) or shall fail to complete the work within said period, or

(f) The Contractor shall fail to make prompt payment to persons supplying labor or materials for the work, or

(g) The Contractor shall fail or refuse to regard laws, ordinances or regulations or otherwise to be guilty of a violation of any provisions of the contract or the Scope of Work therein, then and in such event, the Owner, without prejudice or any rights or remedy it may have, may give seven (7) days notice to the Contractor to terminate the employment of the Contractor and his right to proceed, either as to the entire work or at the option of the Owner as to any portion thereof as to which delay shall have occurred, and may take possession of the work and complete the work by the Contractor or otherwise, as the Owner may deem expedient. In such case, the Contractor shall not be entitled to receive any further payment until the work is finished. If the unpaid balance of the compensation to be paid the Contractor hereunder shall exceed the expense of so completing the work, including compensation for additional managerial, administrative and inspection services and any damages for delay, such excess shall be paid to the Contractor. If such expense shall exceed such unpaid balance, the Contractor and his sureties shall be liable to the Owner for such expenses. If the right of the Contractor to proceed with the work is terminated, the Owner may take possession of and utilize in completing the work such materials, appliances, supplies, drawings, and equipment, as may be on the site of the work and necessary therefore.

If the Owner does not terminate the right of the Contractor to proceed, the Contractor shall continue the work.

If the work shall be stopped by order of the Court or any other public authority, for a period of three (3) months without act or fault of the Contractor or of any of his agents, servants, employees, or Subcontractor, the Contractor may, upon ten (10) days notice to the Owner, discontinue his performance of the work and/or terminate the contract, in which event the liability of the Owner to the Contractor shall be determined as provided in the paragraphs immediately preceding, except that the Contractor shall not be obligated to pay to the Owner any excess of the expense of completing the work over the unpaid balance of the compensation to be paid by the Contractor hereunder.

Revised 09/22 GC-5

1.12 REFERENCE TO THE STANDARD SPECIFICATIONS

(a) All applicable portions of the work performed under this contract shall comply with the requirements of the current New Jersey Department of Transportation Standard Specifications for Road and Bridge Construction, as amended or supplemented and whose specifications are made part of these specifications.

The New Jersey Department of Transportation Standard Construction Details shall govern except insofar as same are expressly modified, amended or changed in detail drawings prepared specifically for this particular project.

(b) The Standard Specifications are made part of these specifications by this reference as if were set forth in full. It is the responsibility of the prospective bidder to be familiar with these Standard Specifications.

Copies may be examined in the Engineer's office or may be purchased from the New Jersey Department of Transportation.

2.0 INSURANCE

2.01 STATE LAW AND REGULATIONS AND INSURANCE

The Contractor must assume all risks connected with his work. He shall comply with all State Laws and Regulations concerning Workmen's Compensation and shall maintain such insurance as will protect him against all claims for damages for personal injury, including death which may arise during prosecution of the contract, either by himself or by any Subcontractor or anyone directly or indirectly employed by either of them.

2.02 CONTRACTOR'S INSURANCE

The Contractor shall not commence work under this contract, until he has obtained all insurance required under this paragraph and such insurance has been approved by the Owner, nor shall the Contractor allow any Subcontractor to commence work, in his subcontract until all similar insurance required of the Subcontractor has been so obtained and approved.

Insurance coverage shall remain in effect until the project is accepted by the Owner, and at all times thereafter when the Contractor may be removing or replacing defective work.

The Contractor shall furnish the Owner with proof of insurance by execution of the Certificate of Insurance, of which a copy is included herein. The Owner, Remington & Vernick Engineers and the Solicitor shall be a named additional insured.

The Certificate of Insurance shall give the Owner and Engineer 30 days written notice of any material change in, cancellation of, or expiration of the policies.

The following types of insurance are required:

a. General Liability

b. Automobile Liability

c. Excess Liability

d. Worker's Compensation and Employer's Liability

The amounts for property damage and bodily injury for each type of insurance are as shown on the Certificate of Insurance herein.

The Contractor's insurance shall apply to and provide coverage for all Subcontractors and/or suppliers unless the Contractor forwards to the Owner and Engineer the Certificate of Insurance for the Subcontractor and/or supplier.

Revised 09/22 GC-6

Any insurance company providing coverage must be licensed, admitted and authorized to do business in the State of New Jersey.

2.03 SUIT OR CLAIMS

The Contractor agrees to indemnify and save harmless the Owner and the Engineer and all their agents and employees from actions and suits of every kind and description brought against them, or on account of the use of patented rights, and from any damages or injuries received or sustained by any party, or parties, arising out of any act or omission of the Contractor, his workmen or agents in performance of the work under this agreement, including the furnishing of equipment, materials and supplies at the site of the proposed work.

2.04 DAMAGES TO PERSONS AND PROPERTY

Contractor shall fully and completely indemnify and same harmless the Owner from damages or injury to persons or property resulting from the performance of the work, or through negligence to the contract, or through the use of any improper or defective machinery implements or appliances or through any act of omission of the Contractor, or his agents, or his employees.

3.0 CONDUCT OF THE WORK

3.01 ROLE OF THE ENGINEER

The Engineer may verify, by observation and/or required tests, the amount, quality, acceptability and fitness of the materials, equipment and supplies furnished; and shall interpret any ambiguities in the drawings and specifications, contract documents, and any extra work order. Upon request, the Engineer shall confirm in writing any oral direction, requirement or determination.

All work of refilling sunken ditches, repaving over trenches and keeping the streets and sidewalks in passable condition shall be satisfactorily performed by the Contractor during the construction of the work as well as during the maintenance period. If any work is not done within 48 hours after written notice given by the Engineer, the work may be done by the Owner and charged to the Contractor.

3.02 SURVEYS

Unless otherwise expressly provided for in the specifications, the Contractor will furnish all surveys necessary for the execution of the work. The Owner will furnish a base line and datum bench marks as required.

The Contractor shall measure and lay out his work and be responsible for the accuracy thereof from bench marks and base lines established by the Engineer which shall constitute the surveys hereinbefore referred to. The contractor shall submit cut sheets for curb, sidewalk and roadway construction projects unless specifically waived in writing by the Engineer.

3.03 PRESERVATION OF STAKES

The Contractor shall carefully preserve bench marks, reference points and stakes, and in case of willful or careless destruction, he will be charged with the resulting expense and shall be responsible, for any mistakes that may be caused by their unnecessary loss or disturbance.

3.04 USES OF PREMISES AND REMOVAL OF DEBRIS

The Contractor expressly undertakes at his own expense:

Revised 09/22 GC-7

(a) To take every precaution against injuries to persons or damage to property.

(b) To store his apparatus, materials, supplies and equipment in such orderly fashion at the site of the work as will not unduly interfere with the progress of his work or the administration of Owner's affairs.

(c) To place upon the work any part thereof only such loads as are consistent with the safety of that portion of the work.

(d) To frequently clean up all refuse, scrap material and debris caused by his operations and at all times the site of the work shall present a neat, orderly condition.

(e) Before final payment to remove all surplus material, false work, temporary structures, including foundations thereof, plant of any description and debris of every nature resulting from his operations and to put the site in a neat orderly condition.

(f) To affect all cutting, fitting, or patching of his work required to make the same conform to the drawings and specifications, and except with the consent of the Engineer, not to cut or otherwise alter the work.

3.05 INJURY TO EXISTING STRUCTURES

The Contractor shall be responsible for all injury to existing structures met within the prosecution of the work, including the delivery to the site of the proposed improvements of materials and supplies. In case of accident to existing structures met within the prosecution of the work, the Contractor will be required to immediately notify the proper authorities and as soon as possible thereafter also notify the Engineer.

3.06 CORRECTION OF WORK

The Contractor expressly warrants that his work shall be free from any defects in materials or workmanship and agrees to correct any such defects which may appear in such materials or workmanship within two years or the term of the maintenance bond, whichever is longer, following the final acceptance of the work by the Owner, such final acceptance to be evidenced by an appropriate resolution of the governing body in the case of municipal corporation, quasi municipal corporation, municipal board, municipal commission or other municipal authority or by the issuance of final payment in the case of any Owner other than a municipal corporation, quasi municipal corporation, municipal board, municipal commission or other municipal authority.

Neither the acceptance of the completed work nor payment therefore shall operate to release the Contractor or his surety or sureties from any obligation or obligations under this contract or the bonds required under these Contract Documents.

3.07 PUBLIC UTILITIES

The contract drawings indicate the approximate location of known overhead and subsurface utilities in the vicinity of the work. The bidder is advised to investigate and ascertain for himself all the facts concerning the actual location of these utilities.

The Contractor shall cooperate with the utility Owners in the adjustment of their facilities and shall notify the utility Owners not less than ten (10) days in advance of the time he proposes to perform any work that will endanger or affect their facilities.

The Contractor shall permit the Owners of utilities, or their agents, access to the site of the work at all times in order to relocate, construct or protect their lines and he shall cooperate with them in performing this work.

Separate payments will not be made for the following:

Revised 09/22 GC-8

1. Coordination and cooperation of the Contractor with the utility companies, nor for the protection or replacement of utilities as specified hereinbefore.

2. Damages for delay caused by conflicts with utilities outside the jurisdiction of the Owner (ex: gas mains, telephone or electric lines, county storm sewer, water mains, etc.).

The bidder shall include all such costs in the prices bid for the various scheduled items in the Bid form.

3.08 PROTECTION OF WORK AND PROPERTY

The Contractor shall continuously maintain adequate protection of his work and shall protect Owner's property from injury or loss arising in connection with his work. He shall also protect all adjacent property as provided by law, and shall be responsible for all injury to property and existing structures sustained during the prosecution of his work, including delivery to the site of the equipment, materials and supplies. He shall repair and replace any such damage, injury or loss equal or better than the condition of the item prior to the Contractor's action.

All passageways, guard fences, light and other facilities required for protection by local authorities or local conditions must be provided and maintained.

3.09 CONTRACTOR TO ACT IN AN EMERGENCY

In case of any emergency which threatens loss or injury of property, and/or safety of life, the Contractor is required to act as he sees fit. He shall notify the Engineer thereof immediately thereafter.

3.10 EXTRA WORK

The Contractor further agrees that the Engineer, in consultation with the Township Administrator, may make such alterations as he may see fit in the form, dimensions, plans for materials of the work, materials and supplies bid upon or any part thereof, either before or after work. If such alterations diminish the quantity of the equipment, materials and supplies to be furnished and delivered to the site or work to be executed, they shall not constitute a claim for damages for anticipated profits on the work that may be dispensed with. If the extra work, change or alteration increases the amount of work to be performed or equipment, they shall be paid for at the price bid. If prices for such extra work are not included in the lump sum prices or unit prices bid, the Contractor hereby agrees to furnish the necessary materials and perform such labor as extra work, and agrees to accept in full payment therefore a price which shall be fixed by the Engineer previous to its commencement. The basis of such estimated cost will be the actual cost of materials, labor, equipment, and a maximum 10 % overhead plus a maximum ten percent (10%) profit. Contractor shall furnish breakdown estimate for such extra work. Payment for markup on subcontracted work shall be at a maximum rate of 5% of the total amount for all costs on the subcontracted work.

Change Orders and Open End Contracts will be in accordance with N.J.A.C. 5:30-11 et seq.

The Contractor shall not be entitled to receive payment for any extra work unless the same is certified in writing by the Engineer.

3.11 DISPUTE RESOLUTION

For construction contracts, the Owner and Contractor agree that in the event of a dispute arising under this contract, it shall be submitted to a process of resolution pursuant to alternative dispute resolution practices, such as mediation, binding arbitration or non-binding arbitration pursuant to industry standards, prior to being submitted to a Court for adjudication. Nothing in this section shall prevent the contracting unit from seeking injunctive or declaratory relief in court at any time. The alternative dispute resolution practices shall not apply to disputes concerning the bid solicitation or award process, or to the formation of contracts or subcontracts to be entered to pursuant to P.L. 1971, c. 198 ( C. 40A:11-1 et seq., Local Public Contracts Law).

Revised 09/22 GC-9

Notwithstanding industry rules or any provision of law to the contrary, whenever a dispute concerns more than one contract, such as when a dispute in a contract involving design, architecture, engineering or management, upon demand of a contracting party, other interested parties to the dispute shall be joined unless the arbitrator or person appointed to resolve the dispute determines that such a joinder is inappropriate. Notwithstanding industry rules or any provision of law to the contrary, whenever more than one dispute of a similar nature arises under a construction contract, or related construction contracts, upon demand of a contracting party, the disputes shall be joined unless the arbitrator of person appointed to resolve the dispute determines that the disputes are inappropriate for joinder.

4.0 CONTRACTOR'S PERSONNEL

4.01 PERSONAL ATTENTION

The Contractor shall give his personal supervision to the prosecution of the work, or have a competent representative on the work who shall have written authority to carry out the requirements of the Contract Documents. He shall also supply all manpower, materials and equipment as they may be required in the furnishing and delivery to the site of the proposed work, the equipment, materials and supplies bid upon.

4.02 CONTRACTOR'S SUPERINTENDENT

The Contractor shall attend to the work personally or through a competent, English-speaking superintendent, who shall be continually present on the project site whenever work is in progress. Such a superintendent shall be satisfactory to the Owner and Engineer and shall not be removed or replaced without due notice being given the Owner and Engineer. The Superintendent shall have full authority to act for the Contractor without the need to consult any higher level of authority.

4.03 LABOR LAWS

The Contractor and any Subcontractors shall comply with all the requirements of the Labor Laws of the State of New Jersey applicable to contracts on behalf of this Owner for construction, alteration or repair of any building or public work, including particularly, but without limitation of the foregoing, the provisions of New Jersey Administrative Codes and related statues including N.J.S.A. 10:2-1 to 10:2-4, inclusive and N.J.S.A. 34:11-56.25 et seq., New Jersey Prevailing Wage Act.

The Contractor hereby agrees to comply in all respect with the New Jersey Prevailing Wage Act, N.J.S.A. 34:11-

56.25 et seq. as amended. A copy of the prevailing wage rates pertaining to the work and issued by the New Jersey Department of Labor entitled, "Prevailing Wage Rate Determination" is on file in the Engineer's office and is included herein. Pursuant to N.J.S.A. 34:11-56.25 et seq. – New Jersey Prevailing Wage Act, no public works contract may be awarded to any contractor and subcontractor or to any firm, corporation or partnership in which they have an interest on the attached disbarred bidders list located at the end of this specification, until expiration date given. Workmen shall be paid not less than such prevailing wage rate.

In accordance with N.J.A.C. 12:60-9.1, if the Contractor who makes the lowest bid for the contract is 10% or more under the amount of the next lowest bid, they must, prior to the award, certify to the Owner via the “Lowest Bidder Prevailing Wage Certification” that the prevailing wage rates required by the Prevailing Wage Act shall be paid in performing the work under the contract. If the Contractor does not provide the Certification required prior to the award of the contract, the Owner shall award the contract to the next lowest responsible and responsive bidder.

Before final payment is made by or on behalf of the Owner of any sum or sums due to the work, the Contractor or Subcontractor shall file with the treasurer of the Owner, written statements in form satisfactory to the Commissioner of Labor certifying to the amounts then due and owing from such contractor or subcontractor filing

Revised 09/22 GC-10 such statement to any and all workmen for wages due on account of the work, setting forth therein the names of the persons whose wages are unpaid and the amount due to each respectively which statement shall be certified by the oath of the Contractor or Subcontractor as the case may be in accordance with the said New Jersey Prevailing Wage Act

The prevailing wage rate shall be determined by the Commissioner of Labor or his duly authorized representative.

Contractors or Subcontractors performing public work of a public body subject to the provisions of this act shall post the prevailing wage rates for each craft and classification involved as determined by the Commissioners of Labor including the effective date of any changes thereof, in prominent and easily accessible places at the site of the work or at such place or places as are used by them to pay workmen their wages.

In the event it is found that any workmen, employed by the Contractor or any Subcontractor, on this project, has been paid a rate of wages less than the prevailing wage required, the Department of Labor along with the Owner may terminate the Contractor's or Subcontractor's right to proceed with the work or such part of the work as to which there has been a failure to pay required wages and to prosecute the work to completion or otherwise, the Contractor and his surety(ies) shall be liable to the Department of Labor along with the Owner for any excess costs occasioned thereby.

Prior to final payment, the Contractor shall be required to execute and deliver an Affidavit of Compliance in a form provided by the Engineer, as required by the Act.

4.04 CONTRACTOR'S EMPLOYEES

All workmen must be competent and fully qualified in the type of work to be performed. Any employee of the Contractor, who is found by the Engineer to be incompetent, or who is performing his work in an unsightly manner or contrary to the specifications or the Engineer's instructions, or who is disorderly, shall be removed from the project and shall not again be employed on the project without the Engineer's consent.

4.05 EIGHT HOUR DAY: PREVAILING WAGE RATE

All mechanics, workers, laborers, employed or engaged in the work hereunder shall work no more than eight (8) hours in any one day. In case of necessity for the protection of property or human life, mechanics, workmen and laborers may be employed for longer periods than eight hours per calendar day, if paid extra compensation on the basis of eight hours constituting a days work, in accordance with the Prevailing Wage Act, N.J.S.A. 34:11-56-25 et seq., and all State and Federal laws.

4.06 PAYMENT OF EMPLOYEES

The Contractor and each of his Subcontractors shall pay each of his employees engaged in work on the project under this contract in full (less deductions made mandatory by law) in legal tender and not less often than once each month.

4.07 SAFETY AND HEALTH REGULATIONS

The Contractor shall comply with the Department of Labor, Safety and Health Regulations for construction promulgated under the Occupational Safety and Health Act of 1970 (P.L.91-596) and under Section 107 of the Contract Work Hours and Safety Standards for Construction (P.L.91-54).

4.08 ACCIDENT PREVENTION

Precautions shall be exercised at all times for the protection of persons (incl. employees) and property. The safety provisions of applicable laws, buildings and construction codes shall be observed. Machinery, equipment, and all

Revised 09/22 GC-11 hazards shall be guarded or eliminated in accordance with the safety provisions of the Manual of Accident Prevention in Construction published by the Association General Contractors in America and Part VI "Temporary Traffic Control" of the U.S. Dept. of Transportation. Federal Highway Administration "Manual on Uniform Traffic Control Devices”, latest edition, whichever is more stringent to the extent that such provisions are not in contravention of applicable law. Contractor alone shall be responsible for the safety, efficiency, and adequacy of his plant, appliances and methods and for any damage which may result from their failure for their improper construction, maintenance or operation. The cost of "Accident Prevention" shall be included in the lump sum or unit price bid whichever is applicable.

5.0 MATERIALS

5.01 CONTRACTOR'S TITLE TO MATERIALS

No materials or supplies for the work shall be purchased by the Contractor or by Subcontractor that are subject to any chattel mortgage or under a conditional sale or other agreement by which an interest is retained by the seller.

The Contractor warrants that he has good title to all materials and supplies used by him in the work.

5.02 ROYALTIES AND PAYMENTS

The Contractor shall pay all royalties and license fees. He shall defend all suits or claims for infringements of any patent rights and shall save the Owner harmless from loss or account thereof.

5.03 USE OF DOMESTIC MATERIAL

In the performance of the work, the Contractor and all Subcontractors shall use only manufactured materials and farm products of the United States of America, wherever available.

All Contractors and Subcontractors shall comply with the provisions of N.J.S.A. 40A:11-18, which relate to the use of domestic materials.

5.04 ORDERING MATERIALS

Before ordering materials, the Contractor shall obtain the Engineer's approval of their conformity to the specifications. In the case of concrete aggregate, and similar materials, samples must accompany the request for approval. The Contractor must forward to the Engineer copies of all shipping lists, invoices or delivery slips accompanying such deliveries.

5.05 SAMPLES

The Contractor shall submit to the Engineer any samples of materials before or during the progress of the work that may be required by the Contract Documents and all materials and workmanship must be equal in every respect to the samples submitted and approved.

5.06 SHOP OR SETTING DRAWINGS

(a) The Contractor shall submit promptly eight copies, of which two will be returned to the contractor, of each shop or setting drawings prepared in accordance with the schedule predetermined under the provisions of the preceding paragraph hereof with the Contractor's approval stamp and date thereon. After examination of such drawings by the Engineer, and the return thereof, the Contractor shall make such corrections to the drawings as have been indicated and shall furnish the Engineer with eight corrected copies. If requested by the Engineer, the Contractor must furnish additional copies, regardless of corrections made in or approval given to such drawings by the Engineer. The Contractor will nevertheless be responsible for the accuracy of such drawings and for their

Revised 09/22 GC-12 conformity to the drawings and specifications unless he notified the Engineer in writing of any deviations, at the time he furnished such drawings. Shop drawing requirements as detailed within the technical specifications and scope of work shall govern should they be in conflict with the General Conditions.

(b) The Contractor shall likewise submit, in writing, the type, kind and name of the manufacturer of all materials to be used in the work for the written approval of the Engineer prior to the installation of same.

(c) Any equipment or materials installed without this written approval of the Engineer will be required to be removed by the Contractor at his own expense and replaced with equipment and materials as approved.

5.07 ADDITIONAL INSTRUCTIONS AND DETAIL DRAWINGS

The Contractor will be furnished additional instructions and detail drawings to carry out the work included in the contract as required. The additional drawings and instructions thus supplied to the Contractor, will coordinate with the contract documents and will be so prepared that they can be reasonably interpreted as a part thereof. The Contractor shall carry out the work in accordance with the additional detail drawings and instructions.

The Contractor and the Engineer will prepare, jointly (a) a schedule fixing the date at which special drawings will be required and by whom they will be made, such drawings, if any, to be furnished by the Engineer in accordance with said schedule, and (b) a schedule fixing the respective dates for the submission of shop or setting drawings;

the beginning of manufacture, testing and installation of materials, supplies and equipment and the completion of the various parts of the work, each such schedule to be subject to change from time to time in accordance with the progress of the work.

5.08 OR EQUAL CLAUSES

Wherever in these contract documents a particular brand, make of materials, device or equipment is shown or specified, such brand, make of material, device or equipment should be regarded merely as a standard.

When a bidder submits an equivalent, it shall be the responsibility of the bidder to document the equivalence claim.

Failure to submit such documentation shall be grounds for rejection of the claim of equivalence.

If two or more brands, makes of material, devices or equipment are shown or specified, each should be regarded as the equal of the other. Any other brand, make of material, devices or equipment, which in the opinion of the Engineer is the recognized equal of that specified, considering quality, workmanship and economy of operation, and is suitable for the purpose intended, will be accepted. All material and workmanship shall, in every respect be in accordance with what, in the opinion of the Engineer is in conformity with approved modern practice.

Whenever the drawings, specifications or other contract documents or the direction of the Owner or its authorized agent admit of doubt as to what is permissible, and/or fail to note the quality of any work, that interpretation will be made by the Engineer which is in accordance with approved modern practice to meet the particular requirement of the contract.

In all cases, new materials shall be used unless this provision is waived by notice from the Engineer.

5.09 SUBSTITUTIONS

After the execution of the contract, substitution of equipment or materials of makes other than those named in the contract will be considered for one reason only. That the equipment proposed for substitution is superior or equal in construction and/or efficiency to that named in the contract.

Revised 09/22 GC-13

Complete data, to include: shop drawings, specifications, performance curves, test results, list of similar installation with years of service, operating and maintenance instruction, a statement that the Contractor agrees to pay all costs that will result directly or indirectly from acceptance of the substitute, and all other necessary information; shall be submitted in triplicate to enable the Engineer to evaluate the proposed substitution equipment or material. The determination as to whether or not such changes will be permitted rests solely with the Engineer.

The Contractor shall take and assume full responsibility and bear any extra expense or cost incurred by changes advocated by him. Those costs include, but are not limited to, review time by the Engineer or the Engineer’s Consultants, costs of redesign, and claims of other contractors affected by the resulting change. It will be assumed that the cost to the Contractor of the equipment or materials proposed to be substituted is less than the equipment or materials named in the contract, and if the substitution is approved, the contract price shall be reduced by an amount equal to the savings.

5.10 MATERIAL SAFETY DATA

In accordance with the requirements of N.J.S.A. 34:5A-1 et seq., “Workers and Community Right to Know Act”, the State Department of Health has adopted a Workplace Hazardous Substance List (N.J.A.C. 8:59-9) which includes substances that pose a threat to the health and safety of employees. Therefore, under the provisions of N.J.A.C. 8:59-7, the contractor must furnish the Owner a “Material Safety Data Sheet” for each product which is supplied to the Owner which contains a substance listed on the Hazardous Substance List (N.J.A.C. 8:59-9). The Owner reserves the right to request a copy of the applicable Material Safety Data Sheet be forwarded with the delivery of each product. Furthermore, under the provisions of N.J.A.C. 8:59-5, each product shall have a label affixed or stenciled onto any container that contains any substance listed on the Hazardous Substance List (N.J.A.C. 8:59-9).

6.0 INSPECTION AND TESTING

6.01 INSPECTION

The Contractor shall afford every facility for inspection of the equipment, materials and supplies at all times by the Engineer prior to the delivery of same to the site of the work. All equipment, supplies and materials shall be tested in the presence of the Engineer, if so desired.

Any equipment, materials, supplies or workmanship deemed of inferior quality, or not in accordance with the finally approved specifications, brought to or incorporated in the work may be rejected by the Engineer. The equipment, materials and supplies and workmanship may be re-inspected at any time, prior to delivery to the site of the proposed improvements. The Contractor shall bear all the expense of testing materials.

When construction is not continuous through the normal work week, (Monday through Friday), Contractor must notify the Engineer at least 24 hours in advance of any stopping or starting of the work. Notification may be by writing, telephone, facsimile, telegraph or personal visit to the Engineer’s listed office.

Contractor shall notify Engineer at least forty-eight (48) hours in advance to any work on Saturdays. There will be no work permitted on Sundays or holidays. If the project receives inspection by the Engineer, the normal working hours for the Engineers inspector are from 7:30 a.m. to 4:00 p.m., Monday through Friday. Any overtime inspection costs for the Engineers inspector which are avoidable shall be reimbursed by the Contractor.

Should the contractor have an emergency or need to cancel scheduled work, notification of the cancelled work must be received by the Engineer’s inspector no later than 6:00 am the morning of the cancellation. Failure of the contractor to provide the required notification will require the contractor to pay for eight (8) hours of inspection

Revised 09/22 GC-14 at the rate of the Engineer’s local inspector. The costs for cancellation of inspection without the required notification will be deducted from the contractor’s payment application.

As the Owner is only paying for the contract time in the Contract Documents, the Contractor shall be responsible for all costs of inspection and contract management beyond the contract time limits, unless a written extension of time has been granted by the Owner. These costs are in addition to any liquidated damages that may be charged to the Contractor.

6.02 DAILY REPORTS

On a daily basis, the Contractor shall have his Authorized Representative complete, sign and present the Engineer with a Certificate of Site Safety Conditions, attached hereto as Form GC-6.02S.

At the Engineers discretion, the Contractor may be directed to furnish a daily report, on a form, which will include the date, the weather, a general description of the work performed, line item quantities involved, number and skill type of workers, equipment utilized, location of work, and any pertinent remarks affecting the work.

6.03 INSPECTORS

The work shall be conducted under the general observation of the Engineer through such Inspectors as the Engineer employs. Inspectors are stationed on the site of the work to represent the Engineer and to report to him concerning the observation of progress of the work and the workmanship and materials being furnished. Such Inspectors shall inform the Engineer and the Contractor when they observe that work being performed and/or the materials being furnished do not conform to the requirements of the Contract Documents. Such observation, if and when provided, shall not relieve the Contractor of any responsibility to furnish materials and perform work in complete accordance with the requirements of the Contract Documents, nor does such observation create any duty or obligation to any employee or invitee of Contractor, any Subcontractor, or to any third party.

The Inspector is not authorized to revoke, alter, enlarge, relax or release any requirements of the Contract Documents or to issue instructions contrary to the Contract Documents.

6.04 ACCESS TO THE WORK

The Contractor shall furnish the Engineer with every reasonable facility for observing the work as performed. The Engineer shall have the right to inspect all work done and all materials furnished either in the field or at the point of manufacture. The Contractor shall furnish or cause to be furnished safe access at all times to the places where preparation, fabrication or manufacture of materials and/or construction of the work is in progress.

When the Engineer or his representative are in or about the premises mentioned above in the course of their duties, they shall be deemed conclusively to be an invitee of the Contractor. If the Contractor is not the Owner of the premises mentioned above, the Owner thereof shall be deemed an agent of the Contractor with respect to the obligation assumed hereby. The Contractor or his agent, as described above, shall be liable for the payment of claims for injuries, damages, etc, for death of the Owner or his representative due to the negligence on the part of the Contractor or his agent.

6.05 COVERING UNINSPECTED WORK

If any work be buried, covered or otherwise concealed prior to observation by Engineer or contrary to the orders and direction of the…

This is the start of the file's text. The full file is on GovTribe.