20260223_Sanitary_Sewer_Bypass_Specification.pdf
PDF 10 KB Posted
- Attached to
- Asset Protection - Electrical
- Solicitation number
- 914-0213-26
- Issued by
- Tehama County, California
About this file
This specification document outlines the sanitary sewer bypass requirements for the Solano County Justice Campus Asset Protection project, prepared by project manager KSN, Inc. and project engineer Baumbach & Piazza, Inc. The contractor must furnish all labor, materials, equipment, and services necessary to install, operate, and maintain a temporary sewer bypass system as detailed on plan sheet SS-1. The scope includes installing and operating bypass pumping systems and pipelines, with complete restoration of the site including backfilling, grassing, sodding, and routine site restoration upon completion. All work must conform to Fairfield-Suisun Sewer District Standards and applicable City, District, County, State, and Federal regulations and environmental codes.
Compensation for the sewer bypass work will be provided as a lump sum payment covering all labor, materials, tools, transportation, disposal, supplies, equipment, and incidentals necessary for complete sewer bypass installation and operation. The contractor must submit work in accordance with Sanitary Sewer Bypass Provisions detailed on plan sheet SS-1 and comply with all District standards and regulatory requirements. Any site restoration items not specifically covered in the Bid Schedule are to be included in the cost for other bid items. This specification is one component of the larger Asset Protection Project, which involves multiple trades and protection measures across several County-owned properties.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOLANO COUNTY
JUSTICE CAMPUS ASSET PROTECTION
SANITARY SEWER BYPASS SPECIFICATION
FEBRUARY 23, 2026
Project Manager KSN, Inc.
1550 Harbor Blvd.
West Sacramento, CA 95691
Project Engineer Baumbach & Piazza, Inc.
323 W. Elm St.
Lodi, CA 95240
Solano County Sanitary Sewer Bypass Justice Campus Asset Protection 02 01 40-1
SECTION 02 01 40
SANITARY SEWER BYPASS
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. The Contractor shall furnish all labor, materials, equipment, and incidentals to place and maintain operation of a temporary sewer bypass system as shown on plan sheet SS-1.
1.02 MEASUREMENT AND PAYMENT
A. Full compensation for conforming to the requirements of this Section shall be paid by lump sum price. The lump sum price includes installing and operating bypass pumping (if used) and pipelines, and including furnishing all labor, materials, tools, transportation, disposal, supplies, equipment, appurtenances, and incidentals and for doing all the work involved in sewer bypass, complete as shown on plan sheet SS-1.
1.03 REFERENCES
A. Perform Work in accordance with the Fairfield-Suisun Sewer District (District) Standards, and the Sanitary Sewer Bypass Provisions as shown on plan sheet SS-1.
1.04 REGULATORY REQUIREMENTS
A. Conform to applicable City, District, County, State and Federal regulations and/or codes for environmental requirements.
1.05 SUBMITTALS
A. Refer to Sanitary Sewer Bypass Provisions as shown on plan sheet SS-1.
PART 2 - PRODUCTS – NOT USED
PART 3 - EXECUTION
3.01 PREPARATION
A. Refer to Sanitary Sewer Bypass Provisions as shown on plan sheet SS-1.
3.02 GENERAL
A. Refer to Sanitary Sewer Bypass Provisions as shown on plan sheet SS-1.
B. Provide complete restoration including, but not limited to, all backfilling, grassing and sodding, and routine site restoration. Items not covered in the Bid Schedule shall be included in the cost for other items.
END OF SECTION 02 01 40