2025.06.13_Construction_Cost_Estimate.pdf

PDF 88 KB Posted

Attached to
North & South ARFF Stations Mechanical, Electrical & Plumbing (MEP) Modifications & Tank Installation
Solicitation number
25-069-ITB
Issued by
Kenton County, Kentucky

About this file

This is a Construction Cost Estimate document for the Kenton County Airport Board's North & South Aircraft Rescue and Firefighting (ARFF) Stations Mechanical, Electrical & Plumbing (MEP) Modifications & Tank Installation project dated June 13, 2025. The project involves comprehensive renovations at both ARFF facilities to transition from Aqueous Film Forming Foam (AFFF) to Fluorine Free Foam (F3). The North ARFF station renovation encompasses 1,270 square feet in the truck bay and 116 square feet in the mezzanine tank area, while the South ARFF station includes 1,350 square feet in the truck bay and 274 square feet in the mezzanine tank area. Primary deliverables include demolition of existing systems, installation of new 2000-gallon polyethylene foam storage tanks, centrifugal chemical processing pumps, distribution piping, electrical modifications including wiring and conduit installation, and associated infrastructure upgrades. The mandatory pre-bid meeting and site visit is scheduled for November 6, 2025, at 10:00 am at ARFF South Station, with bidder questions due by November 20, 2025, at 11:59 pm and final bid submission deadline of December 4, 2025, at 2:00 pm. The contractor must commence work within 10 calendar days of receiving the Notice to Proceed, with design and construction completion targeted for July 2026.

The total estimated project cost is $229,915, with the North ARFF station estimated at $127,937 ($92 per square foot) and the South ARFF station at $101,977 ($63 per square foot). Direct costs total $154,851 across both locations, with Division 21 Fire Protection comprising the largest expense category at $120,000, followed by Division 5 Metals at $11,800 and Division 26 Electrical at $11,951. The estimate includes General Conditions at 12 percent, General Contractor Overhead and Profit at 18 percent, and a 15 percent contingency. The project is funded through CAPEX with a total approved budget of $660,000, which includes the $229,915 construction estimate plus $109,000 contingency reserve. A proposal bond of at least 5 percent of the total bid amount is required from all bidders. Known project risks include potential reduced fire suppression effectiveness, higher costs due to foam product availability constraints, required firefighter retraining, and specialized storage and disposal requirements for the new foam system.

View the file

Other files

File Type Posted
25-069-ITB_Pre-Bid_Sign-In_Sheets.pdf PDF
25-069-ITB_Pre-Bid_Meeting_Agenda.pdf PDF
North_&_South_ARFF_Stations_Mechanical,_Electrical_&_Plumbing_(MEP)_Modifications_&_Tank_Installation.pdf PDF
25-069-ITB_N_&_S_ARFF_MEP_&_Tank_Installation_-_Ad.pdf PDF
25-069-ITB_N_&_S_ARFF_MEP_&_Tank_Installation_-_Exhibit_B-Contract_&_Bonds.pdf PDF
25-069-ITB_Bidders_List_2025.xlsx XLSX spreadsheet
25-069-ITB_N_&_S_ARFF_MEP_&_Tank_Installation_-_Exhibit_A-Proposal_Forms.pdf PDF
25-069-ITB_South_ARFF-AFFF_-_Full_Set_Drawings.pdf PDF
25-069-ITB_North_ARFF-AFFF_-_Full_Set_Drawings.pdf PDF
25-069-ITB_N_&_S_ARFF_-_AFFF_-_Technical_Specifications.pdf PDF
5035-05-CVG_-_South_ARFF-AFFF-Full_Set_ITB.pdf PDF
5035-05-CVG_-_North_ARFF-AFFF-Full_Set_ITB.pdf PDF
5035-05-CVG-ARFF-AFFF-ITB_Specifications.pdf PDF
2025.10.16_APPROVED_ADDITION_Q4_2025_-_Business_Case_-_ARFF_AFFF_Transition_-_New_Construction_-_signed.pdf PDF
2025.06.13_Construction_Cost_Estimate.pdf PDF
Buy_American_Certification-Construction_Projects.docx DOCX document
EEO_Certification.docx DOCX document
Affirmative_Action_Certification.docx DOCX document
Non_Debarment_or_Suspension_Certification.docx DOCX document
Buy_American_Certification-Equipment-Building_Projects.docx DOCX document
NonSegregated_Facilities_Certification.docx DOCX document
Certification_of_Offeror-Bidder_Regarding_Tax_Delinquency_and_Felony_Convictions.docx DOCX document
Disclosure_of_Lobbying_Activities_Certification.docx DOCX document
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project No. 5035-05

Date: 6/13/2025

100% Docs

ARFF North Truck Bay 1270

ARFF North Mezzanine Tank Area 116

ARFF South Truck Bay 1350

ARFF South Mezzanine Tank Area 274

Total Renovation 1740 North South

Division 2 - Demolition 5,000 2,500

Division 4 - Masonry 1,200 0

Division 5 - Metals 8,050 3,750

Division 6 - Wood, Plastic, and Composites 0 0

Division 8 - Openings 0 0

Division 9 - Finishes 1,775 625

Division 21 - Fire Protection 62,500 57,500

Division 22 - Plumbing 0 0

Division 23 - HVAC 0 0

Division 26 - Electrical 8,413 3,538

Division 27 - Communications 0 0

Division 28 - Fire Alarm 0 0

Total Direct Cost $86,938 $67,913

Division 1 General Conditions 12.00% 10,433 8,150

Total Direct Costs & General Conditions 97,370 76,062

GC O&P 18.00% 17,527 13,691

Contingency 15.00% 13,041 12,224

Allowance - Geotech / Survey / Hazardous Materials Survey 0 0

North South Combined

Total Project $127,937 $101,977 $229,915

North cost per SF 1386 $92

South cost per SF 1624 $63

CVG ARFF AFFF Build Back, Erlanger KY

Estimate of Probable Cost

SUMMARY

Total

Cost

General Builing Area SF

Description

Total

Cost

GRW 1 of 7

Project No. 5035-05 Level: 100% Docs

Date: 6/13/2025 Dwg. No. NA

Estimator: Staff Type: Unit Price

Division 1 - General Requirements

Construct. documentation, Temp. Fac., Waste Manage., O/M Man. See summary page

Division 1 Subtotal 0

Division 2 - Existing Conditions, Demolition:

Demo CMU wall 57 SF sawcut, remove, disposal 1 LF 5,000.00 5,000

Division 2 Subtotal 5,000

Division 4- Masonry:

Grout perimeter of new CMU wall opening 1 LF 1,200.00 1,200

Division 4 Subtotal 1,200

Division 5 - Metals

Steel channel C10x15.3 A36 welded and bolted in place 23 LF 23 LF 350.00 8,050

Steel plate 5/8"x1'4"x8'8" bolted in place 9 LF 250.00 2,250

Steel pipe railing 9 LF 250.00 2,250

Division 5 Subtotal 8,050

Division 6 - Wood, Plastic, and Composites :

Division 6 Subtotal 0

Division 7 - Thermal and Moisture Protection :

Division 7 Subtotal 0

Division 8 - Openings

Division 8 Subtotal 0

CVG ARFF AFFF Build Back, Erlanger KY

Estimate of Probable Cost

NORTH BREAKDOWN

Units of

Measure

Unit

Cost

Total

CostDescription

Number of

Units

GRW 2 of 7

Units of

Measure

Unit

Cost

Total

CostDescription

Number of

Units

Division 9 - Finishes

Paint CMU at perimeter of demo openning 23 LF 25.00 575

Paint steel channel, railing, and mounting plate 1 LS 1,200.00 1,200

Division 9 Subtotal 1,775

Division 10 - Specialties:

Division 10 Subtotal 0

Division 11 - Equipment

Division 11 Subtotal 0

Division 12 - Furnishings

Division 12 Subtotal 0

Division 21 - Fire Protection

2000 gallon tank - material and installation 1 EA 15,000.00 15,000

Foam Pump - material and installation 1 EA 7,500.00 7,500

Piping - material and installation 1 LUMP 40,000.00 40,000

Division 21 Subtotal 62,500

Division 22 - Plumbing

Division 22 Subtotal 0

Division 23 - HVAC:

Division 23 Subtotal 0

Division 26 - Electrical:

Wiring, Copper 225 LF 12.50 2,813

Conduit, EMT 225 LF 20.00 4,500

Disconnect Switch, Heavy Duty 1 EA 850.00 850

Circuit Breaker, Bolt-On 1 EA 250.00 250

Division 26 Subtotal 8,413

Division 27 - Communications:

Division 27 Subtotal 0

GRW 3 of 7

Units of

Measure

Unit

Cost

Total

CostDescription

Number of

Units

Division 28 - Fire Alarm:

Division 28 Subtotal 0

Division 31 - Earthwork

Division 31 Subtotal 0

Division 32 - Exterior Improvements

Division 32 Subtotal 0

Division 33 - Utilities

Division 33 Subtotal 0

TOTAL 86,938

GRW 4 of 7

Project No. 5035-05 Level: 100% Docs

Date: 6/13/2025 Dwg. No. NA

Estimator: Staff Type: Unit Price

Division 1 - General Requirements

Construct. documentation, Temp. Fac., Waste Manage., O/M Man. See summary page

Division 1 Subtotal 0

Division 2 - Existing Conditions, Demolition:

Remove steel railing 25 LF 100.00 2,500

Division 2 Subtotal 2,500

Division 4- Masonry:

Division 4 Subtotal 0

Division 5 - Metals

Reinstall steel railing 25 LF 150.00 3,750

Division 5 Subtotal 3,750

Division 6 - Wood, Plastic, and Composites :

Division 6 Subtotal 0

Division 7 - Thermal and Moisture Protection :

Division 7 Subtotal 0

Division 8 - Openings

Division 8 Subtotal 0

Description

Number of

Units

Units of

Measure

Unit

Cost

Total

Cost

CVG ARFF AFFF Build Back, Erlanger KY

Estimate of Probable Cost

SOUTH BREAKDOWN

GRW 5 of 7

Description

Number of

Units

Units of

Measure

Unit

Cost

Total

Cost

Division 9 - Finishes

Paint reinstalled steel railing 25 LF 25.00 625

Division 9 Subtotal 625

Division 10 - Specialties:

Division 10 Subtotal 0

Division 11 - Equipment

Division 11 Subtotal 0

Division 12 - Furnishings

Division 12 Subtotal 0

Division 21 - Fire Protection

2000 gallon tank - material and installation 1 EA 10,000.00 10,000

Foam Pump - material and installation 1 EA 7,500.00 7,500

Piping - material and installation 1 LUMP 40,000.00 40,000

Division 21 Subtotal 57,500

Division 22 - Plumbing

Division 22 Subtotal 0

Division 23 - HVAC:

Division 23 Subtotal 0

Division 26 - Electrical:

Wiring, Copper 75 LF 12.50 938

Conduit, EMT 75 LF 20.00 1,500

Disconnect Switch, Heavy Duty 1 EA 850.00 850

Circuit Breaker, Bolt-On 1 EA 250.00 250

Division 26 Subtotal 3,538

Division 27 - Communications:

Division 27 Subtotal 0

GRW 6 of 7

Description

Number of

Units

Units of

Measure

Unit

Cost

Total

Cost

Division 28 - Fire Alarm:

Division 28 Subtotal 0

Division 31 - Earthwork

Division 31 Subtotal 0

Division 32 - Exterior Improvements

Division 32 Subtotal 0

Division 33 - Utilities

Division 33 Subtotal 0

TOTAL 67,913

GRW 7 of 7