2025_55140_Exhibit_A_PlanSet_Part4.pdf

PDF 3 MB Posted

Attached to
2025-55140 Tolmie Lift Station Improvements
Solicitation number
2025-55140
Issued by
Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Douglas County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington

About this file

This document is a technical design plan sheet (G-06) for the Tolmie State Park Wastewater Lift Station Retrofit project, prepared by the Washington State Parks and Recreation Commission. The sheet provides detailed technical specifications for pipe installation, polypigging testing procedures, shackle (threaded rod) restraints, mechanical notes, and test and inspection requirements for a wastewater lift station infrastructure improvement project. The plan set is marked as a 100% design plan set for review, focusing on specific technical guidelines for pipe installation, testing, and quality control measures.

The document includes comprehensive technical specifications for pipe materials, installation methods, testing protocols, and component requirements. Key technical details cover polypigging procedures, pipe restraint methods, valve testing protocols, and hydrostatic pressure testing guidelines. The specifications emphasize precise installation techniques, material compatibility, corrosion resistance, and stringent quality control measures, with specific instructions for handling different pipe sizes, materials, and installation environments. The technical notes provide detailed guidance for contractors on everything from pipe joining and thrust blocking to valve operation and pressure testing, ensuring a comprehensive and precise approach to the lift station retrofit project.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PIPE NOTES

G-06

NO SCALE

40525-070_G-04_GENERAL NOTES

PARKS FILE#

SCALE

PARKS

STATE

RECREATION

WASHINGTON

COMMISSION

AND

R E V I S I O

N S

CHECKED (HDQTS.)

REGISTERED STAMP

DESIGNED

CHECKED (FIELD)

DRAWN

ACTION BY

DATE

N O

CAD NO.

A P P

I N

T

D A T E

04/21/23JP/CS

04/21/23PCB

TOLMIE

STATE PARK

WASTEWATER

LIFT STATION

RETROFIT

AE 123-168

100% DESIGN PLAN SET (REVIEW ONLY)

SHEET OF 24

PRELIMINARY

POLYPIG TESTING NOTES

1. POLYPIGGING SHALL BE PERFORMED ON ALL PIPING AS SHOWN ON THE PLANS AND SPECIFIED HEREIN:

1.1. POLYPIGGING LOCATIONS:

1.1.1. FORCE MAIN FROM NEW MECHANICAL VAULT TO SEPTIC LEACHFIELD.

2.MATERIALS

2.1. THE PIG SHALL BE OF POLYURETHANE MATERIAL WITHOUT ABRASIVE COATINGS OR STRIPS THAT

MIGHT DAMAGE THE INSIDE LINING OF THE PIPE. THE PIG DIAMETER SELECTED SHALL BE

APPROPRIATE FOR THE INSIDE DIAMETER OF THE PIPE AND SHALL BE OF A MATERIAL, SIZE, AND

CONFIGURATION RECOMMENDED BY THE PIG MANUFACTURER FOR USE IN CLEANING AND

REMOVING ALL LOOSE DEBRIS FROM INSIDE THE PIPE. A DOUBLE DISH SHAPED PIG SHALL BE USED

UNLESS PREVIOUSLY APPROVED IN WRITING BY THE OWNER. THE MATERIAL, DENSITY, AND SIZE OF

THE PIG SHALL BE SUCH THAT IT WILL NOT DAMAGE THE INTERIOR LINING OF THE PIPE. THE EXACT

INSIDE DIAMETER OF THE PROPOSED PIPE SHALL BE MEASURED TO THE NEAREST 0.10 INCH AND

REPORTED TO THE PIG MANUFACTURER FOR MANUFACTURING TO EXACT PIPE TOLERANCES.

2.2. THE PIG MUST BE CAPABLE OF SUCCESSFULLY PASSING THROUGH THE PIPE WITH DEFLECTIONS OF

90 DEGREES OR LESS, TEES AND OPEN VALVES WITHOUT DAMAGE TO THE PIPE OR PIPE LINING.

3. EXECUTION

3.1. RUN THE PIG FROM THE INSERTION POINT TO THE REMOVAL POINT AS RECOMMENDED BY THE PIG

MANUFACTURER. DURING THE PIGGING PROCESS, WATER USAGE, AND PRESSURE FLUCTUATIONS IN

THE SYSTEM SHALL BE MEASURED. AT A MINIMUM, FLOW AND PRESSURE READINGS MUST BE

RECORDED AT 30 SECOND INTERVALS. ALL OTHER PRESSURE FLUCTUATIONS OR JUMPS SHALL BE

RECORDED AND NOTED ON A RECORD SHEET. PRESSURE INCREASES MAY INDICATE THE PRESENCE

OF A BLOCKAGE. THE CONTRACTOR SHALL BE RESPONSIBLE FOR ENSURING PRESSURE SURGES DO

NOT EXCEED THE RATED WORKING PRESSURE OF THE PIPING, FITTINGS, AND APPURTENANCES. ANY

DAMAGES TO THE MAIN FROM PRESSURE SURGES DURING POLYPIGGING SHALL BE PAID FOR AND

REPAIRED BY THE CONTRACTOR.

3.2. THE TIME AND PRESSURE LOG SHALL BE SUBMITTED TO THE OWNER FOLLOWING THE POLYPIGGING

PROCESS FOR THEIR MAINTENANCE RECORDS INCLUDING; 1) THE NUMBER OF PIG PASSES AND

NUMBER OF PIGS USED; 2) OBJECTS FOUND DURING FLUSHING AND THEIR APPROXIMATE

LOCATIONS IN THE WATER MAIN; 3) APPROXIMATE PIG VELOCITY AND LOCATION; 4) PRESSURE

ZONE OF SYSTEM; 5) FLUSHING TIME BEFORE WATER APPEARED CLEAR; AND 6) DATE.

4.CLEANING

4.1. THE PIG SHALL BE INSPECTED UPON REMOVAL TO DETERMINE WHETHER OR NOT IT HAS BEEN

DAMAGED FROM PASSING OVER OR AROUND A LARGE OBJECT THAT IS WEDGED INSIDE THE PIPE.

IF THE PIG IS DAMAGED, THE LOCATION OF THE BLOCKAGE THAT CAUSED THE DAMAGE SHALL BE

IDENTIFIED USING THE PRESSURE LOG. THE BLOCKAGE SHALL THEN BE REMOVED AND THE PIPELINE

INSPECTED AND REPAIRED TO A LIKE NEW CONDITION. AFTER THE BLOCKAGE(S) HAS BEEN

REMOVED AND THE PIPELINE REPAIRED, A SECOND PIG SHALL RUN THROUGH THE LINE USING THE

SAME PROCESS AND PROCEDURES IDENTIFIED IN THE PREVIOUS PARAGRAPHS.

4.2. DO NOT ALLOW THE SWABBED DEBRIS TO REENTER THE PIPE FOLLOWING A POLYPIG PASS. PIPE

ENDS SHALL BE CAPPED OR FITTINGS REPLACED TO PREVENT DEBRIS FROM ENTERING THE CLEANED

PIPE. ANY FITTINGS OR VALVES NOT CAPABLE OF PASSING A POLYPIG SHALL BE FLUSHED OR SWEPT

CLEAN. AFTER THE PIG HAS BEEN REMOVED, WATER SHALL BE FLUSHED THROUGH THE PIPING

SYSTEM UNTIL THE WATER IS CLEAR AND APPROVED IN WRITING BY THE OWNER.

PIPE INSTALL NOTES

1. USE MATERIALS AND INSTALLATION METHODS IN ACCORDANCE WITH THE LATEST EDITION OF THE

UNIFORM PLUMBING CODE AND LOCAL CODES AND REGULATIONS THAT ARE APPLICABLE.

2. INSTALLATION AND CONSTRUCTION

2.1. INSTALL PIPES IN ACCORDANCE WITH THE MANUFACTURER'S RECOMMENDATIONS. USE TYPES AND

SIZES OF PIPES AS SPECIFIED HEREIN AND/OR AS SHOWN ON THE PLANS.

2.2. WHERE SMALL PIPE SIZES ARE OMITTED FROM THE PLANS AND NOT MENTIONED IN THE

SPECIFICATIONS, USE SIZES CORRESPONDING TO CODE REQUIREMENTS AND AS REQUIRED BY

EQUIPMENT AND PLUMBING FIXTURES AND APPURTENANCES.

2.3. PROPERLY SIZE ANY UNDESIGNATED PIPE SIZES FOR THE FUNCTIONS TO BE PERFORMED.

2.4. LAY PIPE AND SUPPORTS AT PROPER LINES AND GRADES. FOLLOW THE PIPING RUNS SHOWN ON THE

PLANS AS CLOSELY AS POSSIBLE, EXCEPT FOR MINOR ADJUSTMENTS TO AVOID ARCHITECTURAL AND

STRUCTURAL FEATURES. MAKE MAJOR RELOCATIONS, IF REQUIRED, IN A MANNER ACCEPTABLE TO THE

OWNER.

2.5. KEEP OPENINGS IN PIPES CLOSED DURING PROGRESS OF WORK.

2.6. FORM THRUST BLOCKING SO THAT BOLTS, JOINTS, GASKETS, AND FLANGES OF ADJACENT JOINTS ARE

CLEAR OF CONCRETE ALLOWING BOLTS AND JOINTS TO BE DISMANTLED WITHOUT REMOVING

CONCRETE. ALL CONCRETE BLOCKING SHALL HAVE A MINIMUM COMPRESSIVE STRENGTH OF 4,000 PSI

UNLESS IDENTIFIED OTHERWISE IN DIVISION 3 OR ON THE PLANS.

2.7. PIPE PASSING THROUGH CONCRETE WALLS OR SLABS SHALL BE MADE WATERTIGHT.

2.8. BEDDING SHALL BE MECHANICALLY COMPACTED IN LIFTS NO GREATER THAN 8-INCHES FROM BASE TO

SPRINGLINE AND FROM SPRINGLINE TO TOP OF PIPE USING A JUMPING JACK OR SHEEPSFOOT.

2.9. HOE-PACKS, SHEEPSFOOTS, AND VIBRATORY ROLLERS SHALL NOT BE USED WITHIN 12-INCHES DIRECTLY

ABOVE THE PIPE. COMPACT TRENCH BACKFILL IN LIFTS NOT EXCEEDING 18-INCHES LOOSE-THICKNESS.

2.10.FLANGED JOINT ASSEMBLY

2.10.1. BOLT HOLES OF FLANGES SHALL STRADDLE THE HORIZONTAL AND VERTICAL CENTERLINES OF THE

PIPE. CLEAN FLANGES BY WIRE BRUSHING BEFORE ASSEMBLING. CLEAN FLANGE BOLTS AND NUTS

BY WIRE BRUSHING; LUBRICATE BOLTS WITH GRAPHITE OR OIL.

2.10.2. INSERT THE NUTS AND BOLTS (OR STUDS), FINGER TIGHTEN, AND PROGRESSIVELY TIGHTEN

DIAMETRICALLY OPPOSITE BOLTS UNIFORMLY AROUND THE FLANGE TO THE PROPER TENSION.

BOLTS SHALL HAVE MINIMUM OF TWO THREADS SHOWING BEYOND THE NUT.

2.10.3. TIGHTEN JOINTS CAREFULLY TO PREVENT STRAIN UPON VALVES, PUMPS, AND OTHER EQUIPMENT.

2.10.4. IF FLANGES LEAK UNDER PRESSURE TESTING, LOOSEN OR REMOVE THE NUTS AND BOLTS, RESET

OR REPLACE THE GASKET, REINSTALL OR RE-TIGHTEN THE BOLTS AND NUTS, AND RETEST THE

JOINTS. REPLACE THE GASKET IF DAMAGED.

2.10.5. VERIFY THE SIZE, MATERIAL, AND LOCATION OF THE EXISTING MAIN AT THE CONNECTION POINT

PRIOR TO INSTALLING THE NEW SEWER FORCE MAIN.

3.PREPARATION

3.1. PROVIDE ALL REQUIRED PERSONNEL AND EQUIPMENT AND COMPLETE ALL TESTS REQUIRED TO

DEMONSTRATE THE INTEGRITY OF THE FINISHED INSTALLATION FOR THE APPROVAL OF THE OWNER

AND ALL AGENCIES HAVING JURISDICTION.

3.2. BACKFILL THE PIPELINE TRENCH SUFFICIENTLY TO PREVENT MOVEMENT OF THE PIPE UNDER PRESSURE.

ALL THRUST BLOCKS SHALL BE IN PLACE AND SUFFICIENTLY CURED TO REACH DESIGN STRENGTH

BEFORE TESTING. FURNISH, INSTALL, AND REMOVE TEMPORARY BLOCKING WHERE PERMANENT

BLOCKING IS NOT REQUIRED AND REMOVE IT AFTER TESTING.

3.3. ALL PUMPS, GAUGES, PLUGS, SADDLES, CORPORATION STOPS, MISCELLANEOUS HOSE AND PIPING, AND

OTHER EQUIPMENT NECESSARY FOR PERFORMING THE TEST SHALL BE FURNISHED AND OPERATED BY

THE CONTRACTOR. GAUGES USED IN THE TEST MAY BE REQUIRED TO BE CERTIFIED FOR ACCURACY AT

A LABORATORY BY THE OWNER. GAUGE RANGE SHALL NOT EXCEED 200-PERCENT OF THE TEST

PRESSURE.

SHACKLE (THREADED ROD) RESTRAINTS

1. DEFINITIONS

1.1. ANCHOR FASTENER: THE ITEM WHICH CONNECTS TO THE FITTING AND WHICH THE

SHACKLE ROD PASSES THROUGH. SUCH AS A 90° EYE BOLT OR SHACKLE PLATE.

1.2. WEATHERING STEEL: STEEL ALLOY DESIGNED TO RESIST CORROSION. OFTEN REFERRED TO

USING THE GENERICIZED TRADE NAME COR-TEN.

2.DESIGN CRITERIA

2.1. UNLESS SHOWN OTHERWISE ON THE PLANS, USE THE FOLLOWING SHACKLE ROD SIZES

FOR 250 PSI TEST PRESSURE. MINIMUM NUMBER (#) AND DIAMETER OF RODS:

UNDOCUMENTED STEEL

OR STAINLESS STEEL SS COLD DRAWNWEATHERING STEEL

PIPE SIZE(30 KSI MIN YIELD) (35 KSI MIN YIELD)(45 KSI MIN YIELD)

4” (2) AT ½” (2) AT ½” (2) AT ½”

6” (2) AT ¾” (2) AT ¾” (2) AT ¾”

8” (3) AT ¾” OR (3) AT ¾” OR (2) AT ¾” OR

(2) AT 1” (2) AT 1” (2) AT 1”

10” (5) AT ¾” OR (4) AT ¾” OR (3) AT ¾” OR

(3) AT 1” (2) AT 1” (2) AT 1”

12” (7) AT ¾” OR (6) AT ¾” OR (4) AT ¾” OR

(4) AT 1” (3) AT 1” (3) AT 1”

CONTACT ENGINEER FOR OTHER SIZES OR PRESSURE.

3. SUBMITTALS

3.1. PROVIDE SUBMITTAL FOR ANCHOR FASTENER WHICH INCLUDES STRENGTH RATING IN

POUNDS. FOR SHACKLE PLATES, INCLUDE DIMENSIONAL DRAWING.

3.2. FOR HIGH STRENGTH RODS (COLD DRAWN OR WEATHERING STEEL), PROVIDE

SUBMITTALS SHOWING ROD MATERIAL AND YIELD STRENGTH.

4.COMPONENTS

4.1. ANCHOR FASTENERS MUST BE A STEEL ALLOY. DUCTILE IRON, CAST IRON, OR ANY

MATERIAL DEEMED BRITTLE IN THE OPINION OF THE OWNER ARE NOT ALLOWED.

SHACKLE (THREADED ROD) RESTRAINTS CONTINUED

4.COMPONENTS (CONTINUED)

4.1. VERIFY ANCHOR FASTENER IS APPROPRIATE FOR ANCHOR LOCATION.

4.2. ALL BURIED SHACKLED THRUST RESTRAINT SYSTEMS SHALL BE STAINLESS STEEL OR WEATHERING STEEL. EXPOSED

SHACKLES, SUCH AS IN A VAULT OR MECHANICAL ROOM, MAY BE NON-WEATHERING STEEL BUT IF SO, MUST BE

COATED WITH EPOXY PAINT SYSTEM. CLEAN RUST PRIOR TO PAINTING.

MATERIAL (* = WEATHERING STEEL)YIELD STRENGTH CORROSION RESISTANT

TYPE 304/316 SS LOW (30 KSI) YES

ASTM A36 LOW (36 KSI) NO

ASTM A588 * MED (45 KSI) YES

ASTM A709 GR 50W * MED (50 KSI) YES

ASTM A242 * MED (50 KSI) YES

ASTM A307 HIGH (60 KSI) NO

ASTM F3125 A325 TYPE 1 HIGH (90 KSI) NO

ASTM F3125 A325 TYPE 3 * HIGH (90 KSI) YES

4.3. ALL COMPONENTS OF ANY STAINLESS STEEL OR WEATHERING STEEL SYSTEM SHALL INCLUDE ONLY STAINLESS STEEL

OR WEATHERING STEEL COMPONENTS. BOLTS, NUTS, WASHERS, RODS, AND OTHER COMPONENTS SHALL BE ONE

MATERIAL AND NOT INTERMIXED.

4.4. SHACKLE SYSTEMS MUST PROVIDE A MECHANISM TO PREVENT UNTHREADING. EXPOSED SHACKLES SHALL USE DOUBLE

NUTS. BURIED SHACKLE SYSTEMS MAY USE DOUBLE NUTS, SINGLE NUT WITH TACK WELD, OR SINGLE NUT WITH

CENTER PUNCH ON OUTSIDE ROD THREAD.

4.5. PROVIDED WASHERS AT ANCHOR FASTENERS. INSTALL ANCHOR FASTENERS ON THE OPPOSITE SIDE OF THE FLANGE OR

MECHANICAL JOINT FROM THE ROD.

5. INSTALLATION

5.1. FOR STANDARD ELONGATION RESTRAINT, SPACE SHACKLES ROUGHLY EQUALLY AROUND THE PIPE.

5.2. WHEN RESTRAINT IS INTENDED TO ALLOW DEFLECTION MOVEMENT WITHOUT EXPANSION, SUCH AS AT A PUMP OR

TANK CONNECTION, CONCENTRATE RODS ALONG THE NEUTRAL AXIS OF DEFLECTION. IN OTHER WORDS, IF VERTICAL

DEFLECTION IS ALLOWED, PLACE RODS ALONG HORIZONTAL AXIS. CONFIRM PROPER ORIENTATION WITH OWNER.

5.3. NUTS SHALL BE FINGER TIGHTENED TO SNUG, THEN TIGHTENED BY WRENCH ONE FULL TURN. DO NOT OVERTIGHTEN.

MECHANICAL NOTES:

1. PROVIDE THE NECESSARY PIPING, PLUMBING, FITTINGS, AND APPURTENANCES TO MAKE ALL PIPING SYSTEMS COMPLETE, TESTED, AND READY FOR OPERATION AS SPECIFIED HEREIN AND AS SHOWN ON THE PLANS.

1.1. SOME FITTINGS THAT ARE NECESSARY FOR THE COMPLETE PIPING SYSTEM INSTALLATION AND OPERATION MAY NOT

HAVE BEEN SHOWN.

1.2. PROVIDE FITTINGS, PIPE, AND APPURTENANCES NECESSARY, WHETHER SHOWN ON THE PLANS OR NOT, TO MAKE ALL

PIPING SYSTEMS COMPLETE, TESTED, AND READY FOR OPERATION.

2. SOME PIPE SUPPORTS, THRUST BLOCKING, AND TIE RODS ARE NOT SHOWN ON THE PLANS.

2.1. PROVIDE PIPE SUPPORTS, THRUST BLOCKING, AND TIE RODS FOR PIPES AS REQUIRED BY ACCEPTED DESIGN CRITERIA

TO SUPPORT AND RESTRAIN THE LOADS ENCOUNTERED.

3.MATERIALS

3.1. ALL VALVES, METERS, HYDRANTS, SPECIALTIES, APPURTENANCES, AND OTHER SUCH MECHANICAL AND PLUMBING

COMPONENTS THAT ARE OF SIMILAR PURPOSE SHALL BE OF A SINGLE MANUFACTURER AND MODEL LINE.

3.2. DO NOT “MIX AND MATCH” UNLESS SPECIFICALLY STATED OTHERWISE OR ALLOWED BY THE ENGINEER.

3.3. THE INTENTION OF THIS REQUIREMENT IS TO MAINTAIN CONSISTENCY ACROSS ALL COMPONENTS INSTALLED ON THE

PROJECT FOR FUNCTION, MAINTENANCE, AESTHETICS, AND DETAILS OF INSTALLATION.

4.COMPONENTS

4.1. UNDER NO CIRCUMSTANCE SHALL THE FASTENERS BE OF LESSER STRENGTH OR HIGHER CORROSIVE POTENTIAL THAN

THE MATERIALS BEING CONNECTED.

4.1.1. IF DISSIMILAR METALS ARE ADJACENT (FOR EXAMPLE: STAINLESS STEEL FLANGE CONNECTING TO DUCTILE IRON

FLANGE) A DIELECTRIC INSULATION KIT SHALL BE USED.

4.2. FASTENERS FOR PIPE AND FITTINGS: PER AWWA STANDARDS UNLESS OTHERWISE SPECIFIED. ALL RELEVANT

SUBSECTIONS OF AWWA C100, C200, AND C500.

4.2.1. ALL BOLTS AND STUDS SHALL BE LONG ENOUGH SO THAT NO LESS THAN TWO THREADS EXTEND BEYOND THE

FACE OF THE NUT.

4.2.2. NON-SUBMERGED FLANGE BOLTS TO BE ASTM A307 GRADE A, ZINC PLATED.

4.3. FOR SUBMERGED CONDITIONS, CONNECTION BOLTS SHALL BE NITRONIC 60 STEEL.

4.3.1. NUTS AND WASHERS SHALL BE STAINLESS STEEL, MINIMUM GRADE 304 IN RAW DOMESTIC OR TREATED

DOMESTIC WATER AND MINIMUM GRADE 316 IN TREATMENT PROCESSES AND SEWAGE APPLICATIONS.

4.3.2. MINIMUM GRADE 317 FOR ACIDIC TRANSPORT.

4.3.3. BOLTS AND NUTS SHALL MEET ASTM F593 AND F594. STAINLESS STEEL SHALL NOT BE USED WHERE IN CONTACT

WITH CHLORINE OR CHLORINE SOLUTIONS.

4.3.4. STAINLESS STEEL BOLTS MAY BE USED IN LIEU OF NITRONIC BUT MUST BE ASSEMBLED USING APPROPRIATE

LUBRICANT OR TAPE.

4.3.5. FOR INSTALLATIONS IN DOMESTIC WATER, LUBRICANT, OR TAPE MUST BE APPROVED FOR DOMESTIC WATER

SERVICE. COBAS STAINLESS STEEL THREAD SEALING TAPE OR APPROVED EQUAL.

5. FINISHES

5.1. FOR CONDITIONS OTHER THAN SUBMERGED, ALL NUTS AND BOLTS SHALL BE ZINC PLATED, AND SUITABLE FOR

ABOVE AND BELOW GRADE LOCATIONS AS REQUIRED.

5.2. WHERE ABOVE GRADE/EXPOSED PIPING IS SPECIALLY COATED, THE CONNECTING NUTS AND BOLTS SHALL BE COATED

USING THE SAME SYSTEM UNLESS DIRECTED OTHERWISE BY THE OWNER.

6. CONSTRUCTION

6.1. ALL PIPING AND RELATED EQUIPMENT TO BE JOINED SHALL BE CONNECTED AS SHOWN ON THE PLANS, SPECIFICATIONS, AS RECOMMENDED BY THE MANUFACTURER OR AS REQUIRED BY STANDARD INDUSTRY PRACTICES IF

NOT OTHERWISE SPECIFIED.

6.2. STEEL AND STAINLESS STEEL THREADS SHALL BE PROTECTED AGAINST GALLING USING STEEL THREAD SEALING TAPE

EQUAL TO COBAS STEEL THREAD SEALING TAPE. TAPE SHALL BE SPECIFIC TO THE STEEL TYPE USED.

7.FIELD QUALITY CONTROL

7.1. PRESSURE GAUGES USED FOR TESTING AND COMMISSIONING SHALL BE IN GOOD WORKING ORDER AND SCALED

APPROPRIATELY FOR THE TEST.

7.2. SCALE RANGE SHALL NOT EXCEED 200% OF THE TEST PRESSURE. FOR EXAMPLE, FOR A 250 PSI TEST, THE GAUGE

SCALE SHALL NOT EXCEED 500 PSI. THE OWNER HAS THE RIGHT TO REJECT ANY GAUGES THAT ARE SUSPECT IN THEIR

ACCURACY.

7.3. IF ANY COMPONENTS THAT HAVE BEEN APPROVED BY THE OWNER ARE NOT RATED FOR THE SPECIFIED SYSTEM TEST

PRESSURE, REMOVE OR ISOLATE THOSE COMPONENTS DURING PRESSURE TESTING IN A METHOD ACCEPTABLE TO THE

OWNER. SAID COMPONENTS MUST STILL BE PRESSURE TESTED IN THEIR PERMANENT CONFIGURATION AT THEIR

INDIVIDUAL TEST PRESSURE RATING.

TEST AND INSPECTION NOTES

1. TESTS AND INSPECTION

1.1. HYDROSTATIC PRESSURE TESTING

1.1.1. COVER ANY EXPOSED PRESSURIZED PVC OR HDPE PIPE TO PROTECT FROM DIRECT SUNLIGHT

IF THE AIR TEMPERATURE IS ABOVE 70°F.

1.1.2. TEST ALL PIPELINES AND APPURTENANCES UNDER A HYDROSTATIC TEST PRESSURE EQUAL

TO THAT SPECIFIED UNDER DIVISION 1.81.40 OF THESE SPECIFICATIONS. IF NOT STATED, THE

HYDROSTATIC TESTING PRESSURE SHALL BE 150 PSI OVER WORKING PRESSURE OR 250 PSI,

WHICHEVER IS GREATER, MEASURED AT THE LOW POINT OF THE TEST SECTION. THE OWNER

HAS THE RIGHT TO REQUIRE MORE STRINGENT TEST CRITERIA THAN STATED IN THIS

SPECIFICATION OR IN THE PRESSURE RATING SECTION IF IT IS DETERMINED THAT FIELD

CONDITIONS WARRANT SUCH MEASURES.

1.2. THE OWNER WILL FURNISH THE WATER NECESSARY TO FILL THE PIPELINES AND FOR TESTING AT

A TIME OF DAY WHEN SUFFICIENT QUANTITIES OF WATER ARE AVAILABLE FOR NORMAL SYSTEM

OPERATION.

1.3. FILL THE PIPELINES WITH WATER AND ALLOW TO STAND UNDER PRESSURE FOR A MINIMUM OF

24 HOURS TO ALLOW AIR TO ESCAPE AND ALLOW THE LINING OF THE PIPE TO ABSORB WATER.

THE CONTRACTOR IS RESPONSIBLE FOR THE PROPER DISPOSAL OF ANY WASTE, INCLUDING

WATER.

1.3.1. FITTINGS AND SECTIONS OF PIPE THAT CANNOT BE PRESSURE TESTED, SUCH AS

CONNECTIONS TO THE EXISTING SYSTEM, SHALL BE LEFT EXPOSED FOR A VISUAL

INSPECTION UNDER SYSTEM PRESSURE. ANY VISIBLE LEAKAGE SHALL BE CORRECTED BY THE

CONTRACTOR TO THE SATISFACTION OF THE OWNER REGARDLESS OF THE ALLOWABLE

LEAKAGE SPECIFIED HEREIN. SHOULD THE TEST SECTION FAIL TO MEET THE SPECIFIED

PRESSURE TEST SUCCESSFULLY, THE CONTRACTOR SHALL LOCATE AND REPAIR THE DEFECTS

AND THEN RETEST THE PIPELINE AT THEIR EXPENSE.

1.3.2. PRIOR TO CALLING OUT THE OWNER TO WITNESS THE PRESSURE TEST, THE EQUIPMENT

SHALL BE COMPLETELY SET UP, READY FOR OPERATION, AND HAVE SUCCESSFULLY

PERFORMED THE TEST TO ASSURE THAT THE PIPE IS IN A SATISFACTORY CONDITION. THE

OWNER SHALL WITNESS THE TEST; IF THE TEST DOES NOT PASS INSPECTION FOR ANY

REASON, ADDITIONAL TRIPS REQUIRED TO WITNESS ANOTHER TEST SHALL BE DONE AT THE

CONTRACTOR'S EXPENSE.

1.3.3. BEFORE APPLYING THE SPECIFIED TEST PRESSURE, AIR SHALL BE EXPELLED COMPLETELY FROM

THE PIPE, VALVES, AND APPURTENANCES.

1.3.4. THE TEST SHALL BE ACCOMPLISHED BY PUMPING THE MAIN UP TO THE REQUIRED

PRESSURE; STOP THE PUMP FOR A MINIMUM OF 15 MINUTES UP TO A MAXIMUM OF 60

MINUTES AS DIRECTED BY THE ENGINEER, AND THEN PUMP THE MAIN UP TO THE TEST

PRESSURE AGAIN. DURING THE TEST, THE SECTION BEING TESTED SHALL BE OBSERVED FOR

VISIBLE LEAKAGE. A CLEAN CONTAINER SHALL BE USED FOR HOLDING WATER FOR PUMPING

PRESSURE ON THE MAIN BEING TESTED. THIS MAKEUP WATER SHALL BE STERILIZED BY THE

ADDITION OF CHLORINE TO A CONCENTRATION OF 50 MG/L (PPM).

1.3.5. SECTIONS TO BE TESTED SHALL NORMALLY BE LIMITED TO 1,500 FEET. THE OWNER MAY

REQUIRE THAT THE FIRST SECTION OF PIPE, NOT LESS THAN 1,000 FEET IN LENGTH,

INSTALLED BY EACH OF THE CONTRACTOR'S CREWS BE TESTED IN ORDER TO QUALIFY THE

CREW AND/OR THE MATERIAL. PIPE LAYING SHALL NOT CONTINUE MORE THAN AN

ADDITIONAL 1,000 FEET UNTIL THE FIRST SECTION HAS BEEN TESTED SUCCESSFULLY.

1.3.6. SECTIONS TO BE TESTED SHALL BE ISOLATED AND PUMPED TO TEST PRESSURE. TEST

PRESSURE SHALL BE SUSTAINED FOR A MINIMUM OF 60 MINUTES WITH LESS THAN

2-PERCENT (5 PSI) LOSS IN PRESSURE THROUGHOUT THE TEST DURATION WITH OWNER

PRESENT AND ON SITE THROUGHOUT TEST DURATION. IF TEST RESULTS DO NOT COMPLY,

CONTRACTOR SHALL REPAIR LEAKS AND RETEST UNTIL TESTING IS PASSED IN PRESENCE OF

OWNER. OWNER MAY BLEED OFF PRESSURE FROM PUMP TO PIPING CONNECTION ONCE

TEST IS PASSED TO VERIFY SYSTEM PIPING WAS TESTED.

2. VALVE TESTING

2.1. ALL VALVES SHALL BE PRESSURE TESTED. DO NOT EXCEED THE RATED WORKING PRESSURE OF

THE VALVE WHEN OPERATING THE VALVE. BLEED OFF TEST PRESSURE PRIOR TO OPERATING.

CHECK ALL VALVE BONNET FASTENERS FOR TIGHTNESS.

2.2. PRE-INSTALLATION

2.2.1. ALL BURIED VALVES SHALL BE PRESSURE TESTED OUTSIDE THE TRENCH. GATE VALVES SHALL

BE TESTED ON ONE SIDE OF THE CLOSED SEAT. BUTTERFLY AND ECCENTRIC VALVES MUST

BE TESTED ON BOTH SIDES OF THE CLOSED SEAT.

2.3. POST-INSTALLATION

2.3.1. TEST ALL VALVES FOR WATER TIGHTNESS UNDER DIFFERENTIAL WORKING PRESSURE. TO

PERFORM THIS TEST, PRESSURIZE PIPE SECTION WITH VALVE IN PLACE, CLOSE VALVE AND

RELIEVE PRESSURE ON SEAT SIDE OF THE VALVE. THE VALVE SHALL NOT PASS WATER

DURING A 5-MINUTE TEST PERIOD.

2.3.2. OPERATE ALL VALVES AT LEAST ONCE FROM CLOSED-TO-OPEN-TO-CLOSED POSITIONS WHILE

VALVE IS UNDER WORKING (NOT TEST) PRESSURE.

Sheets and Views
G-06 PIPE NOTES