Adams County, Asotin County, Benton County, Chelan County, Clallam County, Clark County, Columbia County, Cowlitz County, Douglas County, Ferry County, Franklin County, Garfield County, Grant County, Grays Harbor County, Island County, Jefferson County, King County, Kitsap County, Kittitas County, Klickitat County, Lewis County, Lincoln County, Mason County, Okanogan County, Pacific County, Pend Oreille County, Pierce County, San Juan County, Skagit County, Skamania County, Snohomish County, Spokane County, Stevens County, Thurston County, Wahkiakum County, Walla Walla County, Whatcom County, Whitman County, Yakima County, Asotin City, Clarkston City, Clarkston Heights-Vineland CDP, West Clarkston-Highland CDP, Benton City, Chelan City, Chelan Falls CDP, Clallam Bay CDP, Lewisville CDP, Rock Island City, Pacific Beach CDP, Whidbey Island Station CDP, Mercer Island City, Pacific City, Bainbridge Island City, Kingston CDP, Kitsap Lake CDP, Kittitas City, Klickitat CDP, Okanogan City, Anderson Island CDP, Fort Lewis CDP, Fox Island CDP, Herron Island CDP, Ketron Island CDP, North Fort Lewis CDP, Raft Island CDP, Stevenson City, Hat Island CDP, Lake Stevens City, Snohomish City, Spokane City, Spokane Valley City, Puget Island CDP, Garfield Town, Yakima City, Washington

About this file

This document is an electrical details sheet from the Washington State Parks and Recreation Commission for the Tolmie State Park Wastewater Lift Station Retrofit project located in Thurston County. The sheet (E-12) provides technical specifications for electrical connections, including detailed diagrams for timber pole base, conduit trenching, wet well, dry well, and float power connections. The design is a 100% review plan set that includes specific technical details for infrastructure improvements at the lift station.

The electrical details sheet includes comprehensive technical specifications such as a panel schedule, power load calculations, and precise installation requirements for electrical components. Key elements include a 2" diameter corrugated metal pipe, 4" minimum rock base, concrete specifications, and detailed mounting instructions for mechanical and electrical equipment. The document is part of a larger set of engineering plans prepared by Cross Engineers, Inc., and is specifically focused on the electrical infrastructure aspects of the wastewater lift station retrofit project at Tolmie State Park.

View the file

Other files

Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

22 24

Sheets and Views
E-12 ELECTRICAL DETAILS