This is a Technical Exhibit containing pictorial documentation and descriptions of work scopes for electrical repair services at the NOAA Western Regional Center in Seattle, WA under Request for Quotations (RFQ) solicitation number 1305M326Q0317.

The file outlines six contract line items (CLINs) detailing specific electrical repair and panel work requirements: CLIN 0002 involves removing panels and equipment from the NE Stairwell and Hangar Entry, including removal and refeeding of Panel HH; CLIN 0003 addresses correcting deficiencies in the Center Wind Tunnel; CLIN 0004 requires removing panels and fuses from the SE Stairwell and Hangar Entry and refeeding Panel II on the 2nd Floor, along with replacing CB1 in the location of S-5; CLIN 0005 involves removing panels and fuses from the SW Stairwell and refeeding Panel JJ on the 2nd floor; and CLIN 0006 (Optional) calls for installing a new Manual Transfer Switch for Generator at the NE Stairwell and Hangar Entry Panel FF. The RFQ is for commercial construction services on a firm fixed-price basis with a 6-month period of performance from Notice to Proceed and Net 30 payment terms. Award will be made on an all-or-none basis to a single responsible source.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLIN 0002 NE Stairwell and Hangar Entry – Remove panels and equipment

TECHNICAL EXHIBIT 2 - PICTURES

CLIN 0002 NE Stairwell and Hangar Entry – Remove panels and equipment Panel D used as a pass-thru to Panel HH. Remove and refeed Panel HH.

CLIN 0003 Center Wind Tunnel – Correct noted deficiencies.

CLIN 0004 SE Stairwell and Hangar Entry – Remove panels & fuses and refeed Panel II (2nd Floor)

CLIN 0004 SE Stairwell and Hangar Entry – S5 & CB1

Remove S-5 and replace CB1 in location of S-5 with new panel. Refeed Panel II (2nd Floor and existing panel CB1 circuits)

CLIN 0005 SW Stairwell – Remove Panels & fuses and refeed Panel JJ (2nd floor)

CLIN 0006 (Optional) NE Stairwell and Hangar Entry – Panel FF – Install new Manual Transfer SW for Generator