This is a Schedule of Items document for a fixed-price construction contract solicitation (127EAW26R0001) for the Brush Creek Work Center, issued by the Department of Agriculture Forest Service. The contract is a Total Small Business Set Aside with an estimated magnitude exceeding $10,000,000.
The base construction scope includes thirteen line items valued on a lump-sum basis: General Conditions & General Requirements, Demolition, Engine Garage Construction, Barracks Construction, Warehouse Construction, Storage Container Construction, Seeding Cooler & Canopy Construction, Hazmat Storage Construction, Pump House and Trash Enclosure Construction, Site Water and Sewer Utilities, Site Electrical Utilities, Site Improvements, and Landscaping. The solicitation includes five optional removal line items: removal of a Landing Zone Hydrant and associated infrastructure (Option 1), removal of canopies adjacent to seedling coolers (Option 2), removal of a trash enclosure (Option 3), removal of a hazmat storage container unit (Option 4), and removal of a seedling cooler unit (Option 5). Contractors must submit pricing for all base and optional items, with one award to be made from the solicitation. The schedule notes indicate that quantities are estimated and contractors must field-verify all requirements against the drawings, Statement of Work, and specifications. An organized site visit is scheduled for Wednesday, February 18th, 2026 at 1:00 PM PST, with RSVP required to gregory.cunningham@usda.gov. Requests for Information must be submitted to Contracting Officer Greg Cunningham by 1300 hours PST on February 27th, 2026. Bond premium payments shall not be in addition to the contract price, per FAR Clause 52.232-5.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART I—THE SCHEDULE
SECTION B-- SCHEDULE OF ITEMS
B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)
| Item |
| Construction Items |
| Qty |
| UNIT |
| Total Price |
| 0001 |
| General Conditions & General Requirements |
| 1 |
| LS |
| $_____________________ |
| 0002 |
| Demolition |
| 1 |
| LS |
| $_____________________ |
| 0003 |
| Engine Garage Construction |
| 1 |
| LS |
| $_____________________ |
| 0004 |
| Barracks Construction |
| 1 |
| LS |
| $_____________________ |
| 0005 |
| Warehouse Construction |
| 1 |
| LS |
| $_____________________ |
| 0006 |
| Storage Container Construction |
| 1 |
| LS |
| $_____________________ |
| 0007 |
| Seeding Cooler & Canopy Construction |
| 1 |
| LS |
| $_____________________ |
| 0008 |
| Hazmat Storage Construction |
| 1 |
| LS |
| $_____________________ |
| 0009 |
| Pump House and Trash Enclosure Construction |
| 1 |
| LS |
| $_____________________ |
| 0010 |
| Utilities - Site Water and Sewer |
| 1 |
| LS |
| $_____________________ |
| 0011 |
| Utilities - Site Electrical |
| 1 |
| LS |
| $_____________________ |
| 0012 |
| Site Improvements |
| 1 |
| LS |
| $_____________________ |
| 0013 |
| Landscaping |
| 1 |
| LS |
| $_____________________ |
| BASE CONSTRUCTION TOTAL: |
| $_____________________ |
B.2 SCHEDULE OF ITEMS - (OPTION 1)
| Item |
| Construction Items |
| Qty |
| UNIT |
| Total Price |
| 0001 |
| Remove Landing Zone Hydrant and Associated Infrastructure |
| 1 |
| LS |
| $_____________________ |
B.2 SCHEDULE OF ITEMS - (OPTION 2)
| Item |
| Construction Items |
| Qty |
| UNIT |
| Total Price |
| 0001 |
| Remove Canopies adjacent to Seedling Coolers |
| 1 |
| LS |
| $_____________________ |
B.2 SCHEDULE OF ITEMS - (OPTION 3)
| Item |
| Construction Items |
| Qty |
| UNIT |
| Total Price |
| 0001 |
| Remove Trash Enclosure |
| 1 |
| LS |
| $___________ |
B.2 SCHEDULE OF ITEMS - (OPTION 4)
| Item |
| Construction Items |
| Qty |
| UNIT |
| Total Price |
| 0001 |
| Remove Hazmat Storage Container Unit |
| 1 |
| LS |
| $___________ |
B.2 SCHEDULE OF ITEMS - (OPTION 5)
| Item |
| Construction Items |
| Qty |
| UNIT |
| Total Price |
| 0001 |
| Remove (1) Seedling Cooler Unit |
| 1 |
| LS |
| $___________ |
| OPTION 1 – 5 COMBINED TOTAL: |
| $___________________ |
B.2 SCHEDULE NOTES
* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.
* One award will be made from this solicitation, contractors must submit pricing for all items.
NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.