127EAW26R0001 - Brush Creek Work Center Construction.pdf

PDF 692 KB Posted

Attached to
127EAW26R0001 - Brush Creek Work Center Construction
Solicitation number
127EAW26R0001
Issued by

About this file

This is a negotiated Request for Proposal (RFP) for construction services issued by the USDA Forest Service, Procurement & Property Services, Contract Service Area 6. Solicitation number 127EAW26R0001 is for the Brush Creek Work Center construction project located at 12815 Oro Quincy Highway, Berry Creek, California 95916. The project magnitude exceeds $10,000,000 and is a Total Small Business Set Aside. Proposals are due by 1300 PST on March 26, 2026, with a mandatory organized site visit scheduled for February 18, 2026, at 1:00 PM PST. The contractor must begin performance within 10 calendar days of receiving the Notice to Proceed and complete all work within 650 calendar days. Performance bonds and payment bonds equal to 100% are required, with a bid guarantee of 20% of the bid price or $1,000,000, whichever is less, due within 10 calendar days of award.

The base construction scope includes General Conditions & General Requirements, Demolition, Engine Garage Construction, Barracks Construction, Warehouse Construction, Storage Container Construction, Seeding Cooler & Canopy Construction, Hazmat Storage Construction, Pump House and Trash Enclosure Construction, Utilities (Site Water and Sewer), Utilities (Site Electrical), Site Improvements, and Landscaping. Five optional items are also included for separate pricing: removal of a landing zone hydrant, removal of canopies adjacent to seedling coolers, removal of trash enclosure, removal of hazmat storage container, and removal of a seedling cooler unit. All construction activity must occur between May 1st and October 15th, with any incomplete ground-disturbing work requiring winterization at the contractor's expense. Proposals must be submitted via email to Gregory.Cunningham@usda.gov as five separate documents including: completed SF1442, price proposal with Schedule of Items, Project Schedule of Values, technical proposal addressing past performance (5 pages maximum), work plan/capability (10 pages maximum), key personnel (3 pages maximum), and performance schedule (3 pages maximum), plus scanned bid guarantee documentation. Award will be made using a tradeoff source selection method based on technical evaluation factors (past performance, work plan/technical approach, key personnel, performance schedule) and price, with evaluation criteria approximately equal in weight.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(See ).

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

9. FOR INFORMATION

CALL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".

SOLICITATION

1. SOLICITATION NUMBER

5. REQUISITION/PURCHASE REQUEST NUMBER

CODE

6. PROJECT NUMBER

8. ADDRESS OFFER TO

4. CONTRACT NUMBER

7. ISSUED BY

11. The contractor shall begin performance within

12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES", indicate within how many calendar days after award in Item 12b.)

13. ADDITIONAL SOLICITATION REQUIREMENTS:

a. Sealed offers in original and

b. An offer guarantee

c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

d. Offers providing less than

STANDARD FORM 1442 (REV. 8/2014)

Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.

is, is not required.

local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.

calendar days and complete it within calendar days after receiving

a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)

12b. CALENDAR DAYS

2. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

3. DATE ISSUED PAGE OF PAGES

127EAW26R0001

USDA FOREST SERVICE

PROCUREMENT & PROPERTY SERVICES (PPS)

CONTRACT SERVICE AREA (CSA) 6 – CONSTRUCTION

333 BROADWAY BLVD SE

ALBUQUERQUE NM 87102-3498

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)

127EAW26R0001 - Brush Creek Work Center

Disclosure of Magnitude of the Construction Project: More than $10,000,000

Set Aside: Total Small Business Set Aside

IMPORTANT NOTES:

See Section L, Paragraph L.3 for the Documents to Submit with Your Proposal

All Requests for Information (RFI's) shall be submitted to the Contracting Officer, Greg Cunningham, on the attached RFI form not later than 1300 hours PST, February 27th, 2026.

An organized site visit will be held on Wednesday Feb 18th, 2026, 1:00 PM PST. See page attachment "1. Statement of Work" for full details. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

PLEASE RSVP TO THE SITE VISIT BY EMAILING: GREGORY.CUNNINGHAM@USDA.GOV

GREGORY.CUNNINGHAM@USDA.GOV

1156272

GREGORY CUNNINGHAM

1 OF 2201/27/2026

03/26/2026

1300 PST

10 Calender days

17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)

OFFER (Must be fully completed by offeror)

AMOUNTS

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT

NUMBER

DATE.

AWARD (To be completed by Government)

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)

CODE FACILITY CODE

15. TELEPHONE NUMBER (Include area code)

16. REMITTANCE ADDRESS (Include only if different than Item 14.)

20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)

21. ITEMS ACCEPTED:

22. AMOUNT

26. ADMINISTERED BY

30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)

31c. DATE

STANDARD FORM 1442 (REV. 8/2014) BACK

31b. UNITED STATES OF AMERICA

BY

31a. NAME OF CONTRACTING OFFICER (Type or print)

29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.

30b. SIGNATURE 30c. DATE

28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.

copies to issuing office.) Contractor agrees to furnish

24. SUBMIT INVOICES TO ADDRESS SHOWN IN

(4 copies unless otherwise specified)

23. ACCOUNTING AND APPROPRIATION DATA

ITEM 25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

27. PAYMENT WILL BE MADE BY

10 U.S.C. 2304(c) ( ) 41 U.S.C. 3304(a) ( )

20b. SIGNATURE 20c. OFFER DATE

E-mail:________________ UEI #:________________

7EAW

USDA FOREST SERVICE

PROCUREMENT & PROPERTY SERVICES (PPS)

CONTRACT SERVICE AREA (CSA) 6 – CONSTRUCTION

Invoice Processing Platform, www.ipp.gov

GREGORY CUNNINGHAM

Solicitation No: 127EAW26R0001 Project Name: Brush Creek Work Center Construction

Table of Contents

PART I—THE SCHEDULE

SECTION B-- SCHEDULE OF ITEMS

B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)

B.2 SCHEDULE OF ITEMS - (OPTION 1)

B.2 SCHEDULE OF ITEMS - (OPTION 2)

B.2 SCHEDULE OF ITEMS - (OPTION 3)

B.2 SCHEDULE OF ITEMS - (OPTION 4)

B.2 SCHEDULE OF ITEMS - (OPTION 5)

B.2 SCHEDULE NOTES

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

C.2 PROJECT LOCATON

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

C.4 TECHNICAL SPECIFICATIONS

SECTION D--PACKAGING AND MARKING

D-1 PACKING AND MARKING

D-2 PROJECT LABELING FOR OFFICIAL COORESPONDENCE

SECTION E--INSPECTION AND ACCEPTANCE

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 INVOICES & PAYMENTS

G.2 CONTRACT ADMINISTRATION DATA

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 SPECIAL REQUIREMENTS

H.2 SPECIAL REQUIREMENTS

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND

OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

K.1 PROVISIONS

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO OFFERORS OR RESPONDENTS

L.1 PROVISIONS

L.2 GENERAL INSTRUCTIONS

L.3 SUBMISSION OF PROPOSAL DOCUMENTS:

L.4 TECHNICAL PROPOSAL INSTRUCTIONS

SECTION M--EVALUATION FACTORS FOR AWARD

M.1 PROVISIONS

M.2 PROPOSAL EVALUATION

M.3 TECHNICAL EVALUATION FACTORS

M.4 EVALUATION RATINGS

M.5 AWARD DETERMINATION

PART I—THE SCHEDULE

SECTION B-- SCHEDULE OF ITEMS

B.1 SCHEDULE OF ITEMS - (BASE CONSTRUCTION)

Item Construction Items Qty UNIT Total Price

0001 General Conditions & General Requirements 1 LS

0002 Demolition 1 LS $_____________________

0003 Engine Garage Construction 1 LS

0004 Barracks Construction 1 LS

0005 Warehouse Construction 1 LS

0006 Storage Container Construction 1 LS

0007 Seeding Cooler & Canopy Construction 1 LS

0008 Hazmat Storage Construction 1 LS

0009 Pump House and Trash Enclosure Construction 1 LS

0010 Utilities - Site Water and Sewer 1 LS

0011 Utilities - Site Electrical 1 LS

0012 Site Improvements 1 LS

0013 Landscaping 1 LS

BASE CONSTRUCTION TOTAL:

B.2 SCHEDULE OF ITEMS - (OPTION 1)

0001 Remove Landing Zone Hydrant and Associated Infrastructure 1 LS

B.2 SCHEDULE OF ITEMS - (OPTION 2)

0001 Remove Canopies adjacent to Seedling Coolers 1 LS

B.2 SCHEDULE OF ITEMS - (OPTION 3)

0001 Remove Trash Enclosure 1 LS

B.2 SCHEDULE OF ITEMS - (OPTION 4)

0001 Remove Hazmat Storage Container Unit 1 LS

B.2 SCHEDULE OF ITEMS - (OPTION 5)

0001 Remove (1) Seedling Cooler Unit 1 LS

OPTION 1 – 5 COMBINED TOTAL:

B.2 SCHEDULE NOTES

* QUANITIES ARE ESTIMATED, CONTRACTOR SHALL FIELD VERIFY TO SATISFY ALL REQUIREMENTS OF THE

DRAWINGS, STATEMENT OF WORK, AND SPECIFICATIONS.

* One award will be made from this solicitation, contractors must submit pricing for all items.

NOTE: Payment for bond premiums in accordance with Clause 52.232-5, Payments under Fixed-Price Construction Contracts, shall not be in addition to the contract price.

Company Name: POC & Title:

Email: Phone Number:

UEI Number: Tax ID:

SECTION C--DESCRIPTION/SPECIFICATIONS/STATEMENT OF WORK

C.1 SCOPE OF CONTRACT

The scope of this project entails, but is not limited to, decommissioning specified exiting Plumas National Forest facilities at the Brush Creek Work Center and construct a new work center including utility infrastructure. Further information is included in solicitation attachments.

The Contractor shall be responsible for providing all labor, tools, material, and equipment necessary to perform all work in strict accordance with the specifications, drawings and industry standards. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for the items shown.

C.2 PROJECT LOCATON

12815 Oro Quincy Highway, Berry Creek, CA 95916 Lat/Long: 39.691407, -121.340275

See project drawings for a map of each location.

C.3 MAGNITUDE OF CONSTRUCTION PROJECT

Disclosure of Magnitude of the Construction Project:

• More than $10,000,000

C.4 TECHNICAL SPECIFICATIONS

Technical Specifications: See Section J for Statement of Work and other pertinent information.

Section J of this contract contains Supplemental and Special Project Specifications that supplement and/or modify the Standard Specifications. The Standard, Supplemental, and Special Project Specifications shall all be used in conjunction with each other to properly determine the correct specification for each Pay Item in the Schedule of Items.

SECTION D--PACKAGING AND MARKING

D-1 PACKING AND MARKING

All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.

D-2 PROJECT LABELING FOR OFFICIAL COORESPONDENCE

The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.

SECTION E--INSPECTION AND ACCEPTANCE

E.1 CLAUSES

52.246-12 Inspection of Construction (AUG 1996)

SECTION F--DELIVERIES OR PERFORMANCE

F.1 CLAUSES

52.242-14 Suspension of Work (APR 1984)

SECTION G--CONTRACT ADMINISTRATION DATA

G.1 INVOICES & PAYMENTS

All invoices are to be submitted via the electronic Invoice Processing Platform (IPP) System. The "Submit Invoice-to" address for USDA orders is the Department of Treasury's Invoice Processing Platform (IPP). The contractor must follow the instructions on how to register and submit invoices via IPP as prescribed in previous communications from USDA and Treasury.

This is a mandatory requirement initiated by the U.S. Department of Treasury and you can find more information at this website https://www.ipp.gov/index.htm. Ensure your company has registered at https://www.ipp.gov/vendors/enrollment-vendors.htm to establish your account. Offeror must have an established account prior to commencement of work.

Invoice Processing Platform (IPP) does not allow for the contractor to change the description of the line items being invoiced against and therefore an itemized invoice must be uploaded as an attachment(s).

Itemized invoice shall include at a minimum:

Contractor Name & Address Contract, Task Order or Purchase Order numbers Invoice Number Description of Services or work completed Date of services or completion.

G.2 CONTRACT ADMINISTRATION DATA

1. Contract Award. A written award or acceptance of offer mailed or otherwise furnished to the Contractor shall result in a binding contract without further action by either party.

2. Notice to Proceed. The Contractor shall commence work upon receipt of a properly executed Notice to Proceed.

3. Changes. The Contracting Officer is the only person authorized to approve changes in any of the requirements under this contract and notwithstanding any provisions contained elsewhere in this contract the said authority remains solely with the Contracting Officer. In the event the Contractor effects any such change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in costs incurred as a result thereof.

4. Unauthorized Instructions from Government or Other Personnel. The Contractor shall not accept instructions issued by any person employed by the U.S. Government or otherwise other than the Contracting Officer, or the authorized representative of the Contracting Officer acting within the limits of his/her authority.

5. Designation of Contracting Officer’s Representative (COR). Designation will be made upon contract award and a copy of the designation letters will be furnished to the Contractor. Limits https://www.ipp.gov/index.htm https://www.ipp.gov/vendors/enrollment-vendors.htm of authority are described in each designation letter.

6. Designation of Authorized Representative of the Contractor. The Contractor shall assign a member or employee who will act as Project Manager during the course of this contract or during the course of this project. The official shall be responsible for affording liaison between the contract forces and the contracting offices. This designation shall be in writing and a copy furnished to the Contracting Officer.

SECTION H--SPECIAL CONTRACT REQUIREMENTS

H.1 SPECIAL REQUIREMENTS

Key Personnel

(a) The Contractor shall assign to this contract the following key personnel:

i. Project Manager

ii. Project Superintendent

iii. Quality Control Manager

iv. Project Safety Manager

v. After-Hours Emergency Contact

vi. Signature Authority for Contract Mod

(b) During the first ninety (90) days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.

(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.

H.2 SPECIAL REQUIREMENTS

Emergencies Fire Plan

[ X ]See Section J, Fire Plan [ ]Not applicable; however, Contractors are required to comply with State law during fire season.

Area of Responsibility for Fire. Unless otherwise noted elsewhere in the contract, the following define the limits of a contractor's area of responsibility for fire under the terms of the Fire Plan (Section J):

[ ](a) Trail Construction - 100 meters on either side of the centerline [ X ](b) Construction of Structures - 100 meters around the perimeter of the project [ ](c) Road Construction - 400 meters on either side of the centerline [ ](d) Special for this project:

Utility Services The contractor is responsible for water, electricity, and restrooms.

Superintendence by Contractor In addition to Clause 52.236-6, the following applies: The name and the specific authorities of the foreman or superintendent must be designated in writing to the Contracting Officer. The Contractor may use his/her own prepared letterhead stationery or a "Designation of Contractor's Representative" form available from the Contracting Officer. If the Contractor or the designee is not present when work is being performed on the contract, a Suspend Work Order may be issued with contract time continuing to run. The Contractor shall have a person on-site that is fully conversant in the English language.

Loss, Damage or Destruction Equipment Furnished with Operator. The Government shall not be liable for loss, damage, or destruction of equipment furnished under this contract except for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) while acting within the scope of their employment.

Other. Even though this contract may provide for performing services at the direction of Government personnel, the contract is not for personal services, and neither the Contractor nor their personnel are Government employees. The Government assumes no liability for injury occurring to Contractor personnel or to third parties, or for loss, damage, or destruction involving third parties' property as a result of the Contractor's operation. Except that the Government is liable for such loss, damage, or destruction resulting from the negligent or wrongful act(s) of Government employee(s) acting within the scope of their employment.

Archaeological and Historic Sites Location of known archaeological, historic, or pre-historic materials--such as Amerind artifacts and/or historic mining, logging, or fur trapping remains protected by the American Antiquities Act (l6 USC 433)--will be identified for the contractor before work commences.

Spill Plan If the total oil or oil products storage exceeds 1,320 gallons or if any single container exceeds a capacity of 660 gallons, the Contractor shall prepare and implement a Spill Prevention and Countermeasures (SPCC) Plan. Such plan shall meet applicable EPA requirements (40 CFR 112), including certification by a registered professional engineer. The Contractor under the direction of the Contracting Officer, or in the absence of said officer, acting independently, shall immediately take action to contain and clean up, without expense to the Government, all petroleum products spills on or in the vicinity of the project which are caused by the Contractor's employees directly or indirectly as a result of contract operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation deemed necessary by the Government for the containment and clean up of petroleum products spills caused by Contractor's employees or resulting from contract operations. The Contractor shall immediately report all petroleum products spills to the Contracting Officer.

Equipment Cleaning All off-road equipment used on this project shall be washed before moving into the project area so that the equipment is free of soil, seeds, vegetative material, or other debris that could contain or hold seeds of noxious weeds. “Off-road equipment” includes all logging and construction equipment and such brushing equipment as brush hogs, masticators, and chippers; it does not include log trucks, chip vans, service vehicles, water trucks, pickup trucks, and similar vehicles not intended for off-road use.

Equipment will be considered clean when visual inspection does not reveal soil, seeds, plant material, or other such debris. Disassembly of equipment components or specialized inspection equipment is not required. Contractor shall notify the Contracting Officer at least five days in advance of moving equipment in so that arrangements can be made for inspection.

If the project area is known to contain noxious weeds, the equipment shall be cleaned before moving to other Forest Service system lands which do not contain noxious weeds.

Work Limit Items All construction activity shall be performed during the period between May 1st and Oct 15th.

Any ground disturbing work not completed by Oct 15th shall be winterized. Ground disturbing work may resume on May 1st of the following year. Winterization shall consist of placing wood chips on all disturbed areas at the direction of the COR, aggregate material (if asphalt work is not complete), covering of stockpiles, leaving the site in a safe condition and allowing for use of the site by the Forest Service or its assignees. Winterization shall be at the contractor’s expense if the work is not completed by October 15th.

Work may continue past Oct 15th if the foundation and any other ground disturbing work have been completed. Materials may only be staged from hardened surfaces such as pavement or concrete.

PART II--CONTRACT CLAUSES

SECTION I--CONTRACT CLAUSES

I.1 CLAUSES

52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses: https://www.acquisition.gov/far-overhaul (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:

https://www.acquisition.gov/agar (AGAR clauses begin with 452) Deviations to clauses may be viewed at:

https://www.dm.usda.gov/procurement/policy/FARClassDeviations.htm

52.203-3 Gratuities (APR 1984) 52.203-5 Covenant against Contingent Fees (MAY 2014) 52.203-6 Restrictions on Subcontractor Sales to the Government (JUN 2020) 52.203-7 Anti-Kickback Procedures (JUN 2020) 52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity (MAY 2014) 52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (MAY 2014) 52.203-12 Limitation on Payments to Influence Certain Federal Transactions (JUN 2020) 52.203-13 Contractor Code of Business Ethics and Conduct (NOV 2021) 52.203-19 Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN

2017) 52.204-10 Reporting Executive Compensation and First-Tier Subcontract Awards (NOV 2025) 52.204-13 System for Award Management Maintenance (NOV 2025) 52.204-19 Incorporation by Reference of Representations and Certifications (DEC 2014) 52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (SEP 2026) 52.209-10 Prohibition on Contracting with Inverted Domestic Corporations (SEP 2026) 52.211-13 Time Extensions (SEP 2000) 52.215-2 Audit and Records -- Negotiation (NOV 2025) https://www.acquisition.gov/far-overhaul https://www.acquisition.gov/agar

52.215-8 Order of Precedence—Uniform Contract Format (NOV 2025) 52.215-23 Limitations on Pass-Through Charges (JUN 2020) 52.219-6 Notice of Total Small Business Set-Aside (NOV 2025) 52.219-8 Utilization of Small Business Concerns (NOV 2025) 52.222-3 Convict Labor (NOV 2025) 52.222-4 Contract Work Hours and Safety Standards -- Overtime Compensation (NOV 2025) 52.222-6 Construction Wage Rate Requirement (NOV 2025) 52.222-7 Withholding of Funds (NOV 2025) 52.222-8 Payrolls and Basic Records (NOV 2025) 52.222-9 Apprentices and Trainees (NOV 2025) 52.222-10 Compliance with Copeland Act Requirements (NOV 2025) 52.222-11 Subcontracts (Labor Standards) (NOV 2025) 52.222-12 Contract Termination - Debarment (MAY 2014) 52.222-13 Compliance with Construction Wage Rate Requirements and Related Regulations (MAY

2014) 52.222-14 Disputes Concerning Labor Standards (NOV 2025) 52.222-15 Certification of Eligibility (MAY 2014) 52.222-50 Combating Trafficking in Persons (OCT 2025) 52.222-55 Minimum Wages for Contractor Workers Under Executive Order 14026 (JAN 2022) 52.222-62 Paid Sick Leave under Executive Order 13706 (NOV 2025) 52.223-2 Affirmative Procurement of Biobased Products under Service and Construction Contracts

(NOV 2025)

52.223-5 Pollution Prevention and Right-to-Know Information (MAY 2024) 52.223-11 Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons

(NOV 2025)

52.225-11 Buy American—Construction Materials under Trade Agreements (NOV 2023) 52.226-8 Encouraging Contractor Policies to Ban Text Messaging While Driving (MAY 2024) 52.227-1 Authorization and Consent (JUN 2020) 52.227-2 Notice and Assistance Regarding Patent and Copyright Infringement (JUN 2020) 52.227-4 Patent Indemnity -- Construction Contracts (DEC 2007) 52.228-2 Additional Bond Security (OCT 1997) 52.228-5 Insurance – Work on a Government Installation (JAN 1997) 52.228-11 Individual Surety - Pledge of Assets (FEB 2021) 52.228-12 Prospective Subcontractor Requests for Bonds (DEC 2022) 52.228-14 Irrevocable Letter of Credit (NOV 2014) 52.228-15 Performance and Payment Bonds -- Construction (JUN 2020) 52.229-3 Federal, State, and Local Taxes (FEB 2013) 52.232-5 Payments under Fixed-Price Construction Contracts (MAY 2014) 52.232-17 Interest (MAY 2014) 52.232-23 Assignment of Claims (MAY 2014) 52.232-27 Prompt Payment for Construction Contracts (JAN 2017) 52.232-33 Payment by Electronic Funds Transfer – System for Award Management (OCT 2018) 52.232-39 Unenforceability of Unauthorized Obligations (JUN 2013) 52.232-40 Providing Accelerated Payments to Small Business Subcontractors (MAR 2023) 52.233-1 Disputes (SEP 2025) Alt 1 (SEP 2025) 52.233-3 Protest after Award (SEP 2025) 52.233-4 Applicable Law for Breach of Contract Claim (SEP 2025) 52.236-2 Differing Site Conditions (JULY 2025) 52.236-3 Site Investigation and Conditions Affecting the Work (JULY 2025) 52.236-5 Material and Workmanship (JULY 2025) 52.236-6 Superintendence by the Contractor (JULY 2025) 52.236-7 Permits and Responsibilities (JULY 2025)

52.236-8 Other Contracts (JULY 2025) 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements

(JULY 2025)

52.236-10 Operations and Storage Areas (JULY 2025) 52.236-11 Use and Possession Prior to Completion (JULY 2025) 52.236-12 Cleaning Up (JULY 2025) 52.236-13 Accident Prevention (JULY 2025) 52.236-14 Availability and Use of Utility Services (JULY 2025) 52.236-15 Schedules for Construction Contracts (JULY 2025) 52.236-16 Quantity Surveys (JULY 2025) 52.236-17 Layout of Work (JULY 2025) 52.236-21 Specifications and Drawings for Construction (JULY 2025)

Alternate I (APR 1984) 52.242-13 Bankruptcy (JUL 1995) 52.243-4 Changes (JUN 2025) 52.244-6 Subcontracts for Commercial Products and Commercial Services (NOV 2025) 52.246-21 Warranty of Construction (NOV 2025)

Alternate I (MAR 1994) 52.248-3 Value Engineering – Construction (OCT 2025) 52.249-2 Termination for Convenience of the Government (Fixed-Price) (APR 2012) Alternate I (SEP

1996) 52.249-10 Default (Fixed-Price Construction) (APR 1984) 52.253-1 Computer Generated Forms (NOV 2025) 452.204-70 Modification for Contract Closeout 452.204-71 Personal Identity Verification of Contractor Employees 452.236-70 Emergency Response, Fire Suppression, and Liability

52.211-12 Liquidated Damages-Construction. (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $1,137.77 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor’s right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

52.252-6 Authorized Deviations in Clauses (NOV 2020)

(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the date of the clause.

(b) The use in this solicitation or contract of any Agriculture Acquisition Regulation (48 CFR __4___) clause with an authorized deviation is indicated by the addition of “(DEVIATION)” after the name of the regulation.

PART III--LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

SECTION J--LIST OF ATTACHMENTS

J.1 ATTACHMENTS

Attachment Number

Attachment Title

Number of Pages

01 Statement of Work 6

02 Schedule of Items 2

03 USFS_BCWC_Final Submittal DWGS 2025 07 03 R1 237

04 USFS_BCWC_Final Submittal SPECS 2025 07 03 R1 839

05 Fire Plan 9

06 Davis-Bacon Act WD # CA20260007 44

07 RFI Form 2

PART IV--REPRESENTATIONS AND INSTRUCTIONS

SECTION K--REPRESENTATIONS, CERTIFICATIONS, AND

OTHER STATEMENTS OF OFFERORS OR RESPONDENTS

K.1 PROVISIONS

52.203-11 Certification and Disclosure Regarding Payments to Influence Certain Federal Transactions

(SEP 2024)

52.209-2 Prohibition on Contracting with Inverted Domestic Corporations—Representation (SEP

2025) 52.209-5 Certification Regarding Responsibility Matters (SEP 2025) 52.209-7 Information Regarding Responsibility Matters (SEP 2025) 52.209-11 Representation by Corporations Regarding Delinquent Tax Liability or a Felony Conviction under any Federal Law (SEP 2025) 52.209-13 Violation of Arms Control Treaties or Agreements—Certification (SEP 2025) 52.223-1 Biobased Product Certification (NOV 2025) 52.223-4 Recovered Material Certification (May 2008) 52.240-90 Security Prohibitions and Exclusions Representations and Certifications (NOV 2025) 52.240-91 Security Prohibitions and Exclusions (NOV 2025)

SECTION L--INSTRUCTIONS, CONDITIONS, AND NOTICES TO

OFFERORS OR RESPONDENTS

L.1 PROVISIONS

52.252-1 Solicitation Provisions Incorporated by Reference (FEB 1998)

This solicitation incorporates one or more solicitation provisions by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. The offeror is cautioned that the listed provisions may include blocks that must be completed by the offeror and submitted with its quotation or offer. In lieu of submitting the full text of those provisions, the offeror may identify the provision by paragraph identifier and provide the appropriate information with its quotation or offer. Also, the full text of a solicitation provision may be accessed electronically at this/these address(es):

Federal Acquisition Regulation (FAR) Clauses: https://www.acquisition.gov/browse/index/far (FAR clauses begin with 52) Department of Agriculture Acquisition Regulation (AGAR) Clauses:

https://www.acquisition.gov/agar (AGAR clauses begin with 452) Deviations to provisions may be viewed at:

52.204-7 System for Award Management (NOV 2025) 52.215-1 Instructions to Offerors--Competitive Acquisition (NOV 2025) 52.215-22 Limitations on Pass-Through Charges—Identification of Subcontract Effort (NOV 2025) 52.222-5 Construction Wage Rate Requirements—Secondary Site of the Work (NOV 2025) 52.225-10 Notice of Buy American Act Requirement—Construction Materials (MAY 2014) https://www.acquisition.gov/browse/index/far https://www.acquisition.gov/agar

52.216-1 Type of Contract (APR 1984)

The Government contemplates award of a Firm-Fixed Priced contract resulting from this solicitation.

52.228-1 Bid Guarantee (SEP 1996)

(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.

(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds –

(1) To unsuccessful bidders as soon as practicable after the opening of bids, and (2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.

(c) The amount of the bid guarantee shall be Twenty (20) percent of the bid price or $1,000,000.00 whichever is less.

(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.

(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.

52.233-2 Service of Protest (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from:

Greg Cunningham, Contracting Officer

3237 Peacekeeper Way McClellan Park, CA 95652

THRESHOLDS REQUIRED BONDING REQUIRED BONDING

Individual Project amounts less than $35,000.00 No bid guarantee is required.

No bonding is required.

Individual Project amounts between $35,000.00 and $150,000.00 Refer to FAR 52.228-13

No bid guarantee is required.

Alternate Payment Protection is required:

100% Payment Bond or 100% Deposit [authorized check/MO]

Individual Project amounts greater than $150,000.00 Refer to FAR 52.228-1 Refer to FAR 52.228-15

20% bid guarantee is required.

100% Payment Bond is required.

-AND

100% Performance Bond is required.

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

L.2 GENERAL INSTRUCTIONS

The Government must receive your proposal no later than the time and date specified in the SF 1442, request for proposal. Any deviations to the terms and conditions within this solicitation will result in a nonresponsive proposal. Proposals submitted in response to this solicitation shall be furnished in the following format with the numbers of copies as specified below:

L.3 SUBMISSION OF PROPOSAL DOCUMENTS:

Proposal must be submitted by Email ONLY to Gregory.Cunningham@usda.gov. No other forms of submission will be accepted. Contractor is responsible for verifying receipt of proposal by the Contracting Officer.

Each of the parts shall be submitted as five (5) separate attachments/documents (so evaluation of one document may be accomplished independently from the others).

ONLY RETURN DOCUMENTS REQUESTED – DO NOT RETURN ENTIRE THE SOLICITATION OR

UNREQUESTED PAGES

1. Completed, Signed Offer SF1442 (Section A.) complete blocks 10 Fill-ins, 14, 15, 16, 17, 20a, b, and c on the SF 1442. If amendment(s) are issued acknowledge amendments or complete blocks 19, 20a, 20b & 20c. Signed by authorized person to bind firm.

2. Price Proposal Section B, Schedule of Items. This solicitation requires submission of a proposal on ALL items. Include unit pricing and totals for all bid items. Failure to do so may result in the proposal being rejected without further consideration. All pricing shall be rounded to the nearest cent and not more than two decimal places. Unit prices will govern any total errors unless otherwise determined by the Contracting Officer. Complete fill ins Company Name, POC, E-mail, UEI #, TAX ID #, POC Name, POC E-mail.

3. Project Schedule of Values (SOV). Document pricing in an organized way with a sufficient level of detail for Government to review proposal and effectively administer the contract. At a minimum the schedule of values should be organized by project phases as described by section B and specification section.

4. Technical Proposal – Emailed electronic copy only (see para. L.4 for technical requirements)

5. Bid Guarantees – See FAR 52.228-1, Scanned copy of fully executed Bid Guarantee (Standard Form 24 and Power of Attorney). In addition, ONLY WHEN REQUESTED the original Bid Guarantee shall be hardcopy mailed to:

Greg Cunningham, Contracting Officer 3237 Peacekeeper Way McClellan Park, CA 95652

L.4 TECHNICAL PROPOSAL INSTRUCTIONS

The technical proposal will be used to make an evaluation and arrive at a determination as to whether the proposal will meet the requirements of the Government. Therefore, the technical proposal must present sufficient information to reflect a thorough understanding of the requirements and a detailed description of the techniques, procedures, and program for achieving the objectives of the specifications/statement of work. Proposals which merely paraphrase the requirements of the Government's specifications/statement of work or use such phrases as "will comply" or "standard techniques will be employed" will be considered mailto:Gregory.Cunningham@usda.gov unacceptable and will not be considered further. Offerors are strictly advised to comply with all instructions within this solicitation to ensure submission of a complete Prime Contractor Offer. Failure to furnish a complete offer per the instructions in this solicitation, at the required time and on the required date, may result in the Offeror’s proposal being determined ineligible.

• Submission Instructions One (1) electronic copy via (email shall be less than 10MB) of the technical and price proposals are to be sent to arrive on or before the due date/time to the following email address:

Gregory.Cunningham@usda.gov

As a minimum, the proposal must clearly provide the following:

A. Factor 1 - Relevant Past Performance (NTE 5 pages): Furnish a list of three (3) projects of similar magnitude completed by the firm within the last three (3) years. The list should include work similar in nature and complexity to that required by this solicitation. Include contracts with the Federal Government, agencies of state, local governments, and commercial customers. For each project cited, provide the following:

• Name and location of the project;

• Project Point of Contact’s name, phone, email address, and fax numbers; Total cost of the project;

• A brief narrative of the project (include size, i.e. acres, square feet; date of start, and completion or anticipated completion date).

• Provide CPARS evaluation report or past performance questionnaires for applicable projects. (Note* CPARS will not count against 5-page limit for past performance factor).

• The Government reserves the right to contact reference for verification or additional information. The Government’s inability to contact any of the Offeror’s reference or the unwillingness to provide the information requested may affect the Government’s evaluation of this factor.

The Government may or may not contact any or all references listed. For any projects listed that may report less than positive performance, you are encouraged to provide a description of the problems and efforts made to correct and prevent future occurrences.

B. Factor 2 - Work Plan / Capability of the Offeror (NTE 10 pages): The offeror shall compose a narrative detailing a response to the below questions / statements.

1. Provide a brief explanation of your capability to accomplish this work, include a description of the work you plan to subcontract out

2. Any information that indicates the extent to which the site for this project was visited.

3. The results concluded from the site visit.

4. Provide your planned sequencing of all work.

5. The resources (personnel and equipment) planned for use on the project and their availability.

a. Document any given concurrent obligations.

b. Include any subcontractors and their experience and capabilities.

6. Site-specific safety plan.

7. Plan of work to include the major tasks and timelines.

8. Where applicable, estimated production rates.

C. Factor 3 - Key Personnel (NTE 3 pages): The offeror shall provide a detailed summary of experience with work similar to the type of work required under this project as well as a letter of intent for mailto:Gregory.Cunningham@usda.gov assignment to this project. Provide a list of personnel with job titles and years of experience, number of crews, number of personnel in each crew (experience, and background), to be assigned to meet the 650 day period of performance.

D. Factor 4 - Performance Schedule (NTE 3 pages): The performance schedule shall be presented in the form of a time scaled Network Diagram, CPM Schedule, or a Gantt chart, clearly showing the critical path, indicating commencement and completion of the entire project within the required contract period of performance. The schedule shall be in sufficient detail to clearly show each portion of work and its planned commencement and completion dates. Performance period shall be provided in calendar days. The period shall include all time aspects of the work, including advance ordering of long lead items.

PAGE LIMITATIONS: Pages that exceed limitation will not be evaluated. DO NOT provide pictures, blank or cover pages. A page is defined as one side of a sheet of paper. Do not use less than 10pt font. Pages will be evaluated in order received, any pages beyond the stated maximum will not be evaluated.

• Relevant Past Performance (A): one page per project for a maximum of five (5) pages.

• Work Plan / Capability of the Offeror (B): do not exceed five (10) pages.

• Key Personnel (C): do not exceed three (3) pages.

• Performance Schedule (D): do not exceed two (3) pages.

Offerors are Cautioned that sufficient and detailed information must be provided to enable the Government to evaluate their proposals fully in accordance with the evaluation and award criteria contained herein. The Government is not obligated to ask for additional information and in the absence of appropriate information; the proposal will be rated deficient. The Government will evaluate proposals in accordance with the evaluation criteria as set forth herein.

SECTION M--EVALUATION FACTORS FOR AWARD

M.1 PROVISIONS

52.217-5 Evaluation of Options (JULY 1990)

M.2 PROPOSAL EVALUATION

This contract will be awarded with a Tradeoff process source selection method conducted in accordance with Federal Acquisition Regulation (FAR) Part 15, Contracting by Negotiation and may be awarded without discussion. This contract will be awarded in accordance with FAR Part 15 -- 15.101-1 Tradeoff process.

M.3 TECHNICAL EVALUATION FACTORS

Factor 1. Past Performance

Past performance is a measure of the degree to which the offeror (including major subcontracts) has satisfied previous customers and complied with Federal, State and Local laws and regulations.

The Government will contact references to assess the quality of the contractor’s work, timely completion, project management, and compliance with regulatory requirements. The Government will consider the currency and relevance of the information, source of the information, context of the data and general trends in contractor performance.

The past performance evaluation will characterize the level of the Government’s confidence that the offeror will successfully complete the work, in compliance with all contract requirements, based on its record of successful performance on recent and relevant similar projects.

In the past performance evaluation, the Government may use information from sources other than the offeror’s proposal. Other sources of information, may include, but are not limited to:

Federal, State and Local government agencies, better business bureaus, published media and electronic databases such as the Contractor Performance Assessment Reporting System (CPARS).

Where there is little or no information available regarding the offeror’s past performance history because the offeror is new to the marketplace, the past performance evaluation may take into account information regarding predecessor companies, key personnel who have relevant experience, or subcontractors that will perform major or critical aspects of the work. When no information is available, the offeror will not be evaluated favorably or unfavorably on past performance.

Factor 2. Work Plan / Technical Approach to Performing the Work

The Government will evaluate the overall approach and rational means & methods to complete the project in a successful, safe, and efficient manner. When evaluating the Technical Approach to Performing the Work, the government will assess the reasonableness of the contractor’s proposed approach to performing the work

Factor 3. Key Personnel

The offeror will be evaluated by relevant experience on the basis of its extent and depth as well as scaled amounts of personnel when compared to the size / complexity of the project.

Factor 4. Performance Schedule

The firm will be evaluated for a schedule within the mandatory period of performance with logical work progression to meet the requirements of the statement of work and specification requirements.

Factor 5. Price

The proposed price will be evaluated for reasonableness in accordance with FAR 15.404-1(b). The government expects to make an award without discussions, however reserves the right to conduct discussion if necessary. In the event that discussion are conducted, the competitive range may be limited for purposes of efficiency. Offerors schedule of values is clearly organized with a sufficient level of detail to allow for the Government to effectively administer the contract.

M.4 EVALUATION RATINGS

Since an offeror's proposal(s) must be compliant in order for it to be eligible for award, compliance of the offer is a mandatory solicitation requirement. Each proposal will be evaluated strictly on its content and will not assume that performance will include anything not specified in the proposal. The evaluation will be conducted in accordance with the procedures established herein. The Evaluation Panel will assign to each evaluation criterion a final adjective consensus rating.

1. Award will be made to that offeror whose proposal is technically beneficial and whose technical benefit to price relationship is the most advantageous to the Government.

2. Evaluation criteria, when combined, are approximately equal to price. The critical factor in making any tradeoff between technical performance and price is the importance of the difference in the technical rating and not the spread between the technical scores.

3. The Government reserves the right to make price/technical trade-offs that are in the best interest and most advantageous to the Government.

4. The Government may reject any or all offers if such action is determined to be in the best interest of the Government.

5. The Government will use an adjectival rating system as detailed below.

Adjectival Rating Definition Exceptional Quote/Offer contains no deficiencies and fully addresses all aspects of the criteria and demonstrates an excellent approach/solution and understanding of the requirements. Many strengths exist, far outweighing any weaknesses. The highest quality of contract performance is anticipated with very low risk.

Very Good Quote/Offer contains no deficiencies; fully addresses all aspects of the criteria and demonstrates a very effective approach/solution and understanding of the requirements. Some weaknesses may exist; however, the weaknesses, if any, are outweighed by strengths. A high quality of contract performance is anticipated with low risk.

Satisfactory Quote/Offer contains no deficiencies; addresses all aspects of the criteria and demonstrates an adequate approach/solution and understanding of the requirements. Strengths and weaknesses are offsetting or will have little or no impact on contract performance. A quality contract performance is anticipated with an acceptable amount of risk.

Marginal Quote/Offer may contain deficiencies; fails to address all of the criteria and does not demonstrate an adequate approach/solution or understanding of the requirements. One or more weaknesses exist which are not offset by strengths.

Contract performance is anticipated with high risk.

Unsatisfactory Quote/Offer contains many deficiencies and does not address all aspects of the criteria and/or does not present evidence demonstrating an adequate approach/solution and understanding of the requirements. Many weaknesses and/or omissions exist creating an unacceptable risk.

M.5 AWARD DETERMINATION

The contract resulting from this solicitation will be awarded to that responsible offeror whose offer

Past Performance Rating Description

Substantial Confidence Based on the offeror’s performance record, the government has a high expectation that the offeror will successfully perform the required effort.

Satisfactory Confidence Based on the offeror’s performance record, the government has an expectation that the offeror will successfully perform the required effort.

Limited Confidence Based on the offeror’s performance record, the government has a low expectation that the offeror will successfully perform the required effort.

No Confidence Based on the offeror’s performance record, the government has no expectation that the offeror will be able to successfully perform the required effort.

Unknown Confidence No performance record is identifiable, or the offeror’s performance record is so sparse that no confidence assessment rating can be reasonably assigned.

conforming to the solicitation is determined to be best valued and acceptable proposal. The offeror’s proposal shall be in the format prescribed and shall contain a response to each of the areas identified which affects the evaluation factors for award.

Award may be made without further discussions/clarifications. Initial offers should be submitted with the most favorable terms, from a price and technical standpoint.

This is the start of the file's text. The full file is on GovTribe.