A00003 - Time Extension and RFI Responses.pdf

PDF 401 KB Posted

Attached to
127EAW26R0001 - Brush Creek Work Center Construction
Solicitation number
127EAW26R0001
Issued by

About this file

This is a Standard Form 30 Amendment of Solicitation/Modification of Contract issued by the USDA Forest Service, Procurement & Property Services (PPS), Contract Service Area (CSA) 6 – Construction, located in McClellan Park, California. The amendment extends the proposal due date for solicitation 127EAW26R0001 (Brush Creek Work Center Construction) from March 26, 2026 to April 2, 2026 at 1:00 PM Pacific Time. The amendment is effective as of March 11, 2026, and is identified as Amendment A00003.

The amendment incorporates three revised documents and supporting materials into the solicitation: (1) 127EAW26R0001 - Brush Creek Work Center Construction, Revision 001 with updates marked in red; (2) Schedule of Items, Revision 001 with updates marked in red; and (3) 127EAW26R0001 - RFI Log dated 3.11.2026, which provides responses to Requests for Information received, with unanswered RFIs to be addressed in forthcoming Amendment A00004. A zip folder containing four attachments is also provided, including a Brush Creek Geotechnical Report, Pre-Demolition Asbestos and Lead Paint Survey, example site signage, and a roofing substitution request. All other terms and conditions of the original solicitation remain unchanged. Offerors must acknowledge receipt of this amendment prior to the extended proposal due date to avoid rejection.

View the file

Other files

Show all 21

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

A00003

GREGORY L. CUNNINGHAM

See attached continuation page.

USDA FOREST SERVICE

PROCUREMENT & PROPERTY SERVICES (PPS)

CONTRACT SERVICE AREA (CSA) 6 – CONSTRUCTION

3237 PEACEKEEPER WAY, SUITE 101

MCCLELLAN PARK, CA 95652

ALL INTERESTED VENDORS 127EAW26R0001

1 2

03/11/2026

01/27/2026

AMENDMENT OF SOLICITAITON/MODIFICATION OF CONTRACT PAGE NO. 2

CONTINUATION PAGE

SOLICITATION NO:

127EAW26R0001

ORDER NO:

AMENDMENT NO:

A00003

14. DESCRIPTION OF AMENDMENT/MODIFICATION (CONTINUED)

STANDARD FORM 30 (CONTINUATION)

1) The purpose of this amendment is to extend the proposal due date, post RFI responses, and other applicable documentation. The following information is provided:

a) Proposal due is hereby extended FROM March 26th, 2026, TO April 2nd, 2026 at 1:00 PM Pacific Time.

b) The following documents are provided with instructions and hereby incorporated into any subsequent award:

i) 127EAW26R0001 - Brush Creek Work Center Construction, REVISION 001: All updates to this document are made in red. All other information remains the same.

ii) 2. Schedule of Items, REVISION 001: All updates to this document are made in red. All other information remains the same.

iii) 127EAW26R0001 - RFI Log, 3.11.2026: This document is provided in response to RFI’s received.

Unaswered RFIs will be responded to within forthcoming Amendment A00004.

iv) A00003 Attachments: Zip folder is provided with documents associated with RFI responses.

(1) 2024.04.12_Brush Creek Geotech Rpt_Kleinfelder

(2) 2024.05_Brush Creek PreDemo Asbestos Lead Paint Survey_P&P

(3) Example Site Sign

(4) RFI 78 - Roofing Substitution Request_Redacted

G. All other terms and conditions remain unchanged.