Questions_and_Answers_11-1.xlsx
XLSX spreadsheet 13 KB Posted
- Attached to
- ULTRAVIOLET BALLAST WATER TREATMENT SYSTEM FOR SURFACE VESSELS Federal contract opportunity
- Solicitation number
- 19-SBO-002
About this file
This document contains a vendor question and answer session and details of a federal contract opportunity for an Ultraviolet Ballast Water Treatment System. The Naval Surface Warfare Center, Carderock Division seeks to procure engineering design, fabrication, testing and installation services for UV Ballast Water Treatment Systems aboard U.S. Navy surface vessels. Vendors are asked to complete a market research questionnaire and conformance checklist by December 3, 2018 at 1400 EST to be considered for the opportunity. Both engineering firms and ballast water treatment system manufacturers are permitted to respond individually or through teaming arrangements. The Naval Sea Systems Command is the contracting agency for this planned pre-solicitation.
Questions and Answers_11-1
View the file
Other files for this federal contract opportunity
Show all 21
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Vendor Q&A
| Date Received | Date C/633 Responded | Vendor Inquiries | NSWCCD Response |
| 10/18/18 | 10/22/18 | I looked at the documents and have a question related to the Excel sheet (Attachment 4: Navy BWTS Conformance Checklist). |
This checklist seems to be intended for manufacturers of BWMS, while engineering companies like ours would typically not be involved in those areas that are: 1) fixed by type approval; and 2) related directly to a chosen BWMS that will be engineered onboard the vessels.
Are you asking to fill out that sheet as an engineering company or this is not required from us?
The RFI is intended for Engineering firms and BWTS manufacturers to meet Government's needs for obtaining both the services and supplies. While the Government does not have preference pertaining to contractor teaming arrangements, vendors are permitted to present a team approach in providing a response. Complete response to the RFI shall consist of the market research Questionnaire and BWTS Conformance Checklist. Partial response to the RFI will not be considered.
File details come from the government source that posted it. Updated .