16 Att 01 Statement of Work ZDV CTRB Raised Floor.pdf
PDF 1 MB Posted
- Attached to
- ZDV CTRB Raised Floor
- Solicitation number
- 6973GH-26-R-00024
About this file
This Statement of Work (SOW) details a renovation project for the FAA Air Route Traffic Control Center (ARTCC) in Denver, Colorado, located at 2211 17th Ave., Longmont. The project involves installing an 18-inch raised access floor system (approximately 2,982 square feet) and Static Reference Ground (SRG) in the Control Wing Basement. Key scope elements include constructing (2) ADA-compliant ramps and stairs, building a 9'-6" partition to enclose the raised floor, and replacing the existing east door with a new 2-hour rated door alcove.
The project requires comprehensive electrical, communications, and safety modifications, including relocating power outlets, light switches, light fixtures, fire extinguishers, and exit signs. Specific technical requirements include installing static dissipative rubber and carpet tiles, providing wall and floor-mounted handrails, implementing fire stopping measures, and establishing a grounding system with copper mats and perimeter grounding wire. Contractors must comply with EPA, OSHA, Fire Marshal, NFPA regulations, and FAA standards, and all personnel must be vetted for facility access with proper identification. The work demands strict coordination with FAA personnel, weekly progress meetings, and continuous facility protection throughout the construction process.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
ZDV ARTCC (Denver) | JCN: 21002189
Install SRG and Raised Floor in Control Wing Basement (B120A)
2211 17th Ave., Longmont, CO 80501
1 SCOPE OF WORK
The overall scope of this project is to provide a new 18” high raised access floor system (+/- 2,982 SF) and SRG in the
Control Wing Basement at ZDV. (2) new ADA compliant ramps and stairs will be provided to access the new raised access floor. A new 9’-6” partition will be constructed to enclose the new raised access floor system. The existing non-conforming east door will be removed, and a new door will be provided within a new 2-hour rated alcove.
The contractor shall provide all necessary labor, materials, and equipment to complete the following work. Also review the attached drawings and specifications.
1.1 DIVISION 01 GENERAL CONDITIONS:
Area cleanup throughout project duration
Final clean at the end of project.
1.2 DIVISION 02 EXISTING CONDITIONS:
1.2.1 Selective Demolition
o 1.2.1.1 Demolish existing ramps and stairs and stair skirting.
o 1.2.1.2 Electrical Demolition
Remove electrical outlets to be relocated
Remove light switches to be relocated
Remove light fixtures to be removed
Remove light fixtures to be relocated
Remove existing to be relocated exit sign at east door o 1.2.1.3 Remove central vacuum drops o 1.2.1.4 Remove fire alarm/strobes to be relocated o 1.2.1.5 Remove existing east door and door frame, patch, repair and paint where removed.
o 1.2.1.6 Remove portions of existing partition to prepare for new door alcove and door.
1.3 DIVISION 05 METALS:
1.3.1 Provide wall mounted handrail at new stairs and ramps.
1.3.2 Provide floor mounted handrail at new stairs and ramps.
1.4 DIVISION 07 THERMAL AND MOISTURE PROTECTION:
1.4.1 Provide fire stopping for penetrations at fire rated partitions.
1.5 DIVISION 08 OPENINGS:
1.5.1 Provide new east door and door frame.
1.5.2 Provide new door hardware at new east door.
1.6 DIVISION 09 FINISHES:
1.6.1 Construct 9’-6” high 1-hour rated partition enclosing new raised floor area.
1.6.2 Construct 2-hour rated alcove at new east door.
1.6.3 New rubber wall base at new partitions and perimeter of new raised floor.
1.6.4 New complete raised access floor system, including floor panels, pedestals and stringers. Part of the new raised floor will have static dissipative rubber tiles as a floor covering, the rest will have static dissipative carpet tiles.
o 1.6.4.1 Raised floor system with static dissipative rubber tiles.
o 1.6.4.2 Raised floor system with static dissipative carpet tiles.
o 1.6.4.3 (2) ADA compliant ramps with rubber flooring.
o 1.6.4.4 (1) ADA compliant steps with rubber flooring.
1.6.5 Painting at existing columns and new partitions, paint touch-ups at existing walls where damaged or scuffed.
1.7 DIVISION 10 SPECIALTIES:
1.7.1 Relocate (2) existing fire extinguishers to code compliant height.
1.7.2 Relocate AED to code compliant height.
1.8 DIVISION 26 ELECTRICAL:
1.8.1 Relocate (3) power outlets
1.8.2 Relocate (2) light switches
1.8.3 Light Fixtures
o 1.8.3.1 Relocate (4) light fixtures o 1.8.3.2 Provide (2) wall mounted light fixtures at new partition.
1.8.4 Exit Signs
o 1.8.4.1 Relocate illuminated exit sign at east door.
o 1.8.4.2 Provide new illuminated exit sign.
1.9 DIVISION 27 COMMUNICATIONS:
1.9.1 Provide SRG under new raised access floor, all components to be welded using smokeless exothermic welds.
o 1.9.1.1 Provide SRG copper mats with 2’ centers.
o 1.9.1.2 Provide perimeter grounding wire around SRG.
o 1.9.1.3 Ground SRG to raised floor pedestals.
o 1.9.1.4 Ground SRG to building.
1.10 DIVISION 28 ELECTRONIC SAFETY & SECURITY:
1.10.1 Provide (1) new fire detection alarm and strobe connected to existing fire detection and alarm system.
1.10.2 Disconnect and reconnect key card reader and system at new east door.
2 PRE-CONSTRUCTION REQUIREMENTS
Stakeholder Coordination: Attend construction coordination meetings post contract award.
Compliance: Adhere to the requirements of JO3900.57A for planning, design, and safety during pre and post construction activities.
Work Request Review (WRR): Submit a Work Request Review (WRR) form and obtain approval before work begins. WRR completed by COR/SSC – EOSH approval prior to construction start.
Coordination and Scheduling: Submit a phased workplan for approval prior to NTP.
Submittals: Submit, for review and approval, cut sheets for all proposed materials/supplies/equipment.
System Component Verification: Ensure all system components meet the specified project requirements.
Pre-construction meeting.
3 PREPARATION
Personnel Vetting: All contractor personnel must be vetted and screened for FAA facility access. All personnel must present a REAL ID-compliant driver’s license or alternative identification that is accepted by DHS.
FAA Notification: Notify the FAA at least 24 hours prior to personnel arrival for security clearance.
Material Compliance: All materials (e.g., paints, adhesives) must be low VOC/odor and FAA-approved.
Equipment Outages: Discuss any potential concerns with the System Support Centers (SSCs), although no outages are expected.
4 CONSTRUCTION
Delivery and Equipment Handling: Coordinate, with the COR, proper delivery, handling, and storage of materials, ensuring no damage to existing facilities.
Weekly Progress Meetings: Conduct weekly meetings with stakeholders to review progress and adjust schedules as necessary.
Operational Impact: Ensure construction activities do not impact ARTCC operations, taking necessary precautions.
FAA Personnel Coordination: FAA personnel must operate all circuit breakers, switches, and valves, coordinated through the COR.
Unauthorized Work: Any work performed without FAA authorization may be subject to removal or inspection and will not be paid for.
Power Supply: Construction power is available; contractors must provide their own tools, materials, and safety equipment.
FAA Escort Requirements: Contractor personnel must be escorted by FAA representatives at all times.
4.1 PROTECTING GOVERNMENT PROPERTY
Facility Protection: Take all precautions to protect existing facilities, equipment, and structures during construction activities.
Repair of Damaged Property: Any damage caused by the contractor or subcontractors must be repaired at the contractor's expense and must match the original finish.
4.2 DISPOSITION OF WASTE AND CLEANUP
Maintain a clean area during construction.
Perform a final cleanup at the end of the project
ACM Disposal: Dispose of any asbestos-containing materials (ACM) per state and Environmental Occupational, Safety, and Health (EOSH) procedures.
Waste Management: Provide a dumpster on-site for waste collection and removal as needed throughout the project.
Lead or Materials Containing Lead: Dispose of lead or any lead-containing materials (ACM) per state and
Environmental Occupational, Safety, and Health (EOSH) procedures.
5 REQUIREMENTS AND COMPLIANCE
Regulatory Compliance: The contractor must comply with EPA, OSHA, Fire Marshal, and NFPA regulations, FAA standards, Industry Codes, and all other applicable local codes.
Building and Electrical Codes: The contractor must adhere to the latest building codes, National Electrical Code
(NEC), ADA, and FAA specifications, including FAA-STD-019x and FAA-C-1217H standards.
6 PROJECT PHOTOS
6.1 ESU VIEW
6.2 COMM WING VIEW
6.3 AUTO WING VIEW
Back wall view