16-01 Bid Specification - Whitpain Township - School Road Skippack Pike Signed.pdf

PDF 6 MB Posted

Attached to
2026 Milling and Paving of Various Township Roads
Solicitation number
Not on record
Issued by
Montgomery County, Pennsylvania

About this file

This is a bid specification document for Whitpain Township, Montgomery County, Pennsylvania, for the SR 73, SEC. MT2 (MPMS #81892): Skippack Pike (SR 0073) and School Road (SR 2016) Intersection Improvement Project. The scope of work includes roadway widening, drainage system installation, traffic signal installation, stone masonry, traffic control, and signing and pavement marking installation. Specific line items total approximately 3,462 square yards of asphalt tack coat, 2,581 square yards of wearing course asphalt, 881 square yards of subbase, and various drainage components including 315 linear feet of 18-inch reinforced concrete pipe and 235 linear feet of 24-inch reinforced concrete pipe, among numerous other construction items. Questions must be submitted via PennBid by January 22, 2026 at 5:00 PM, and Responsible Contractor Certification forms are due to Eric Traub no later than January 22, 2026 at 11:00 AM. Sealed bids will be accepted electronically via PennBid until 11:00 AM on Thursday, February 5, 2026, with results posted immediately following opening. The three lowest bidders must submit original supporting documentation by Tuesday, February 10, 2026. The successful bidder must complete the work within 270 calendar days from Notice to Proceed, including a 30-day traffic signal testing period. The contract award will be made to the lowest responsible bidder based on the tabulated base bid and any selected add alternates.

All bids must be accompanied by a bid bond or certified check equal to 10 percent of the total bid price, issued by a surety licensed in Pennsylvania. The successful bidder is required to furnish performance, payment, and maintenance bonds as referenced in the bid documents. All bidders and subcontractors must be PennDOT pre-qualified contractors and must comply with the Pennsylvania Prevailing Wage Act, with minimum wage rates established by the Pennsylvania Secretary of Labor. Bidders must demonstrate financial capability by submitting a financial balance statement and operating statement for the most recent fiscal year no earlier than 2023, and must provide evidence of successfully completing similar contracts for at least 75 percent of the proposed contract amount. The project is partially financed through a Pennsylvania Department of Transportation Multimodal Transportation Fund (MTF) grant (Agreement #C920003442) to Whitpain Township. Bidders must comply with Whitpain Township Responsible Contractor Ordinance No. 394 and all applicable federal and state laws, including requirements regarding nondiscrimination, sexual harassment, contractor integrity provisions, and Americans with Disabilities Act compliance. The engineer for this project is Bowman Consulting Group, Ltd., located in Fort Washington, Pennsylvania.

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADVERTISEMENT

INSTRUCTION TO BIDDERS

FORM OF PROPOSAL

FORM OF GUARANTY

GENERAL CONDITIONS

SPECIAL CONDITIONS

CONSTRUCTION SPECIFICATIONS

FORM OF AGREEMENT

CONTRACT BONDS

LIST OF CONTRACT DOCUMENTS

SR 73, SEC. MT2 (MPMS # 81892):

SKIPPACK PIKE (SR 0073) AND SCHOOL ROAD (SR 2016)

INTERSECTION IMPROVEMENT PROJECT

Along

Skippack Pike (SR 0073) and School Road (SR 2016)

Within

Whitpain Township, Montgomery County, PA

“This project is partially financed utilizing a Pennsylvania Department of Transportation Multimodal Transportation Fund (MTF) grant Agreement # C920003442 to Whitpain Township.”

ENGINEER:

BOWMAN CONSULTING GROUP, LTD. (BOWMAN)

425 COMMERCE DRIVE, SUITE 200

FORT WASHINGTON, PA 19034

PHONE: (215) 283-9444

DATE: DECEMBER 18, 2025

Bowman Project No.: 310581-01-001 PA One Call Design Serial Number: 2023622462 PA One Call Final Design Serial Number: 20253081083

Stephanie L. Butler, P.E.

PA PE License Number 54368-E

All documents prepared by Bowman Consulting Group, Ltd. (Bowman) are instruments of service in respect of the project. They are not intended or represented to be suitable for reuse by Owner or others on extensions of the Project or on any other project. Any reuse without written verification or adaptation by Bowman will be at Owner's sole risk and without liability or legal exposure to Bowman; and Owner will indemnify, and hold harmless Bowman from all acts, claims, damages, losses and expenses arising out of or resulting therefrom.

dschantz Image i

TABLE OF CONTENTS PAGE NO.

A - ADVERTISEMENT A-1

B - INSTRUCTIONS TO BIDDERS B-1

1. Bidder’s Responsibility B-1

2. Delivery of Proposals B-1

3. Addendums B-1

4. Proposal Guaranty B-2

5. Method for Submitting Bids B-2

6. Proof of Bidder’s Responsibility B-2

7. Changes While Bidding B-3

8. Bid Opening Procedure B-3

9. Collusive Bids B-3

10. Withdrawal of Bids B-3

11. Award of Contract B-3

12. Execution of Contract B-4

13. Failure to Execute Contract B-4

14. Subletting or Assigning of Contract B-4

15. Rejection of Proposals B-4

16. Sub-Surface Information B-4

C - FORM OF PROPOSAL C-1

1. Schedule of Prices C-2

2. Non-Collusion Affidavit of Prime Bidder C-8

D - FORM OF GUARANTY D-1

1. List of Subcontractors D-2

E - GENERAL CONDITIONS E-1

1. Definitions E-1

2. Other Contracts E-1

3. Sub-Contracts E-2

4. Mutual Responsibility of Contractor E-2

5. Fitting and Coordination of Work E-2

6. Superintendence by Contractor E-2

7. Permits, Licenses and Taxes E-2

8. Provisions Required by Law E-3

9. Protection of Work and Property E-3

10. Temporary Provision for Public Travel E-3

11. Shop Drawings E-3

12. Termination; Delays; Liquidated Damages E-4

13. Inconsistent Specifications and Drawings E-5

14. Use of Premises E-5

15. Possession Prior to Completion E-5

16. Changes in the Work E-5 ii

TABLE OF CONTENTS (Continued) PAGE NO.

E - GENERAL CONDITIONS (Continued)

17. Claims for Extra Cost E-7

18. Disputes E-7

19. Materials and Workmanship E-7

20. Samples, Certificates and Tests E-8

21. Changes in Equipment and/or Materials E-8

22. Patents E-9

23. Warranty of Title E-9

24. The Owner's Right to do Work E-9

25. The Owner's Right to Terminate Contract E-9

26. Damages E-10

27. Engineers Status E-10

28. No Estoppel or Waiver of Legal Rights E-10

29. Safety and Health Regulations (OSHA) E-11

30. Arbitration E-11

31. Notice To Proceed E-11

32. Limitation of Operations E-12

33. Indemnification E-12

34. Verification of Field Conditions E-13

35. Protection of Utilities E-13

36. Progress Meetings E-13

37. Whitpain Township Responsible Contractor Ordinance E-13

F - SPECIAL/SUPPLEMENTAL CONDITIONS F-1

1. Contract Security F-1

2. Contractor's Insurance F-1

3. Special Insurance F-6

4. Progress Schedule F-6

5. Location of Utilities F-6

6. Inspection of Work F-7

7. Use of Explosives F-7

8. Payment to Contractor F-7

9. Correction of Work After Final Payment F-8

10. General Guaranty F-8

11. Office Space (Deleted) F-8

12. Sanitary Facilities F-8

13. Water F-8

14. Electricity F-8

15. Lines, Grades and Construction Surveying F-8

16. Contract Standards Act F-8

17. Requirements under the Pennsylvania Prevailing Wage Act F-9

18. “Steel Products Procurement Act” F-10

19. Act 50 of 2017 F-11

20. Night, Holiday, and Weekend Work F-11 iii

TABLE OF CONTENTS (Continued) PAGE NO.

21. Required Contract Provisions F-11

a. Conformity to All Applicable Federal and State Laws F-11

b. Compliance with Required Commonwealth Provisions F-11

c. PennDOT Multimodal Transportation Fund Agreement #C920003442 F-11

d. MS-999L Project Completion Report F-11

Exhibit G: Nondiscrimination/Sexual Harassment Clause F-13 Exhibit H: Contractor Integrity Provisions F-15 Exhibit I: Provisions Concerning the Americans with Disability Act F-18 Exhibit J: Contractor Responsibility Provisions F-19 Exhibit K: PennDOT MTF Agreement #C920003442 F-20 Exhibit L: MS-999L Project Completion Report F-21

22. Sample Prevailing Wage Division Forms F-22

G - CONSTRUCTION SPECIFICATIONS G-1

1. General Conditions G-1

2. Specifications G-6

3. Non-Standard Item Specifications (Special Provisions) G-18

4. Utilities – The Requirement to List Information G-30

H - FORM OF AGREEMENT H-1

1. Contractor’s Release H-4

2. Statement of Surety Company H-6

3. Contractor’s Qualification Statement Including Subcontractor Certification H-7

4. Accepting Provisions of the Workmen’s Compensation Act H-12

5. Whitpain Township Responsible Contractor Ordinance (RCO) No. 394 H-13

6. Whitpain Township Certification Form H-14

I - CONTRACT BONDS I-1

Form of Performance Bond I-1 Form of Labor and Materialmen's Bond I-1 Form of Maintenance Bond I-1

J - POST AWARD REQUIRED DOCUMENTS J-1

Public Works Verification Form J-1 Worker Protection and Investment Certification Form J-1

K - LIST OF CONTRACT DOCUMENTS K-1

A-1

A. ADVERTISEMENT

PUBLIC NOTICE IS HEREBY GIVEN to all prospective bidders that Whitpain Township shall accept sealed proposals online for the SR 73, SEC. MT2 (MPMS #81892): Skippack Pike (SR 0073) and School Road (SR 2016) Intersection Improvement Project in Whitpain Township, Montgomery County, PA.

Sealed Bids shall be accepted via PennBid (https://pennbid.bonfirehub.com/) until 11:00 AM prevailing time, on Thursday, February 5, 2026, at which time they shall be opened electronically, and the results made available on PennBid immediately following the opening.

Plans and specifications are available online at no charge via PennBid. (https://pennbid.bonfirehub.com/).

Hard copies of all documents may be optionally purchased through PennBid. Estimated cost is $100.00.

The Scope of Work consists of but is not limited to roadway widening, drainage system installation, traffic signal installation, stone masonry, traffic control, and signing and pavement marking installation.

Questions must be submitted via PennBid by January 22, 2026, at 5:00 PM. Submission of a question does not guarantee that such question will be answered.

Responsible Contractor Certification (RCO) Forms must be submitted to the Township no later than January 22, 2026, at 11:00 AM.

All proposals (bids) are to be accompanied by a bid bond or certified check in the amount of 10% of the total bid price. Said check or bond shall be subject to the conditions provided in the Instructions to Bidders. Bonds are required to be issued by a surety licensed to do business in the Commonwealth of Pennsylvania.

The successful bidder is required to furnish all payment, performance, and maintenance bonds as referenced in the bid documents. Bids must be submitted unconditionally. No bid may be withdrawn within sixty (60) days after the opening thereof, during which time the Township may review the bids and investigate bidder qualifications. The Township reserves the right to waive any minor informalities, irregularities or defects in the bid, or to reject any or all of the bids.

The successful Bidder must comply with the Pennsylvania Prevailing Wage Act. Bidders are advised that prevailing minimum wage rates, promulgated by the Pennsylvania Secretary of Labor, must be paid to workmen employed on this project.

This Project is subject to Ordinance No. 394, Whitpain Township Responsible Contractor Ordinance (RCO), including pre-qualification requirements as specified in the Ordinance. The bidder shall complete the Responsible Contractor Certification Form provided, and shall submit the Form to the Township, to the attention of Eric Traub, Manager, via E-mail to etraub@whitpaintownship.org, no later than fourteen (14) days prior to the bid opening date, together with all documentation required by Section 4 of Ordinance 394, a copy of which is provided, in order to be pre-qualified before submitting a bid.

All bidders are required to establish proof of competency and responsibility, in accordance with 67 PA Code Chapter 457, Regulations Governing Pre-qualification of Prospective Bidders and PennDOT Form 408/2020, as supplemented and amended, Section 102. Subcontractors must pre-qualify in the same manner, if listed in the proposal or if they subsequently undertake the partial or total construction of one or more items of Work. All bidders, and sub-contractors, must be PennDOT pre-qualified Contractors.

Eric Traub Whitpain Township https://pennbid.bonfirehub.com/ mailto:etraub@whitpaintownship.org

B-1

B. INSTRUCTIONS TO BIDDERS

1. BIDDER'S RESPONSIBILITY

Each bidder shall familiarize themselves with all of the attached Form of Proposal, Instructions, General Conditions, Specifications, Drawings, etc., as they shall be held responsible to fully comply therewith. Each bidder must visit the site of the Work and acquaint themselves with conditions affecting the Work. It shall be the Contractor’s sole responsibility to estimate quantities for bidding purposes. The Contractor shall bid the project as a line-item bid.

2. DELIVERY OF PROPOSALS

All bids shall be collected electronically via PennBid (https://pennbid.bonfirehub.com/). Sealed bids shall be opened on Thursday, February 5, 2026 at 11:00 AM prevailing time. It is the responsibility of the bidder to submit their bid prior to the time of opening. Any incomplete or partial bid shall be disregarded by Whitpain Township.

The following Documents are required to be completed and submitted via PennBid prior to the time of opening:

• Form of Proposal

• Schedule of Prices (PennBid)

• Non-Collusion Affidavit of Prime Bidder

• Form of Guaranty/Bid Bond

• Contractor’s Qualification Statement

• Whitpain Township Responsible Contractor Certification

• List of Subcontractors

• Subcontractor Certification

Failure to submit any of the required documentation above shall result in bidder’s disqualification.

The three (3) lowest bidders shall have three (3) business days to submit the original bid documents. If delivered by overnight delivery, the supporting documentation may be delivered. The supporting documentation must be delivered by Tuesday, February 10, 2026.

Deliver supporting documentation to:

Attention: Eric Traub Township Manager 960 Wentz Road Blue Bell, PA 19422

3. ADDENDUMS

Bidders shall acknowledge receipt of all addendums that have been issued during period of bidding and agree that said addenda will become part of this contract. Bidders shall list the numbers and issuing dates of the Addenda received and acknowledge the same on the appropriate page provided in the Form of Guaranty section of those specifications.

B-2

4. PROPOSAL GUARANTY

Each Proposal shall be accompanied by either a certified check or Surety Company's Bid Bond as specified herein under "ADVERTISEMENT", in an amount of not less than ten (10) percent of the base bid, which check or bond shall be payable to the Township as payee or obligee, and shall be forfeited as liquidated damages if the bidder fails to execute the Contract in conformity with the Agreement incorporated in the Contract Documents, and furnish bonds as specified, within fifteen

(15) days after receipt of Contract Documents. Such checks or bid bonds shall be returned, to all except the three (3) lowest bidders immediately after the award, and the remaining unsuccessful bidders checks or bid bonds shall be returned when the Contracts executed by both parties bidder are delivered to the successful bidder.

If the successful bidder fails to execute and deliver the Contract Documents and furnish the required contract security within fifteen (15) days after the Notice of Award, the Township shall annul the Notice of Award and the Proposal guaranty of that Bidder shall be forfeited.

5. METHOD FOR SUBMITTING BIDS

All bids shall be submitted electronically via PennBid (https://pennbid.bonfirehub.com/).

If bidder has been incorporated in some state other than Pennsylvania, bidder will state whether the corporation is registered to do business in Pennsylvania. If bidder operates under an assumed or fictitious name, they will state whether such name has been registered in Pennsylvania.

No contract will be awarded to a bidder who is a foreign corporation or operating under a fictitious or assumed name unless they have complied or agreed to comply with the proper registration under the laws of this Commonwealth.

6. PROOF OF BIDDER'S RESPONSIBILITY

To demonstrate Bidder’s qualifications to perform the Work, each bidder must complete with their bid, a Contractor’s Qualification Statement. Each Proposal must contain evidence of bidder’s qualifications to do business in the state where the Project is located or covenant to obtain such qualification prior to award of the contract.

The Qualification Statement will be certified to be true and correct by an affidavit sworn to or affirmed before a notary public, or other officer empowered to administer oaths or affirmations.

The bidder shall submit with their bid, a Financial Balance Statement listing assets and liabilities and an operating statement for the most recent fiscal year, but no earlier than the fiscal year ending 2023.

The bidder may be required to prove to the satisfaction of the Township that they have successfully completed a Contract for similar Work in an amount of not less than seventy-five percentum (75%) of the amount of the proposed Contract.

Additional information may be requested by the Township whenever in its judgment such information is necessary to determine the responsibility of the bidder.

Failure to provide an adequate Contractor’s Qualification Statement and a Financial Balance Statement shall result in the bidder’s disqualification.

Each Bidder shall complete the Responsible Contractor Certification Form provided, and shall submit the Form to the Township, to the attention of Eric Traub, Manager, via E-mail to

B-3 etraub@whitpaintownship.org, no later than Thursday, January 22, 2026 at 11:00 AM, fourteen

(14) days prior to the bid opening. Failure to submit the required Certification Form and supporting documentation, as required for pre-qualification, will automatically disqualify any bidder from submitting a bid.

7. CHANGES WHILE BIDDING

During the bidding period, bidders may be issued furnished addenda or bulletins for additions to or alterations of the plans or specifications, if any, which shall be included in the Work covered by the Proposal and become a part of the Contract Documents.

If any prospective bidder on the proposed contract is in doubt as to the true meaning of any part of the plans, specifications or other proposed contract documents, they may submit to the Engineer, a written request via PennBid’s “Clarifications” tab for an interpretation thereof. Any interpretation of the proposed documents shall be made only by an official answer posted to Pennbid and each prospective bidder shall be notified via email. The Engineer and/or Township shall not be responsible for any other explanations or interpretations of the proposed documents.

8. BID OPENING PROCEDURE

Sealed proposals on projects, shall be received by the Township and Engineer via Pennbid until Thursday, February 5, 2026 at 11:00 AM at which time all proposals shall be opened and posted on PennBid. The Township reserves the right to reject any or all bids, or parts thereof, as it may deem best for the interest of the Township.

9. COLLUSIVE BIDS

The proposal of any bidder or bidders who engage in collusive bidding shall be rejected, including but not limited to, any bidder who submits more than one proposal in such a manner as to make it appear that the proposals submitted are on a competitive basis from different parties shall be considered a collusive bidder. The Township may reject the bid proposals of any collusive bidder upon bid opening.

However, nothing in this section shall prevent a bidder from superseding a bid proposal by a subsequent proposal delivered prior to bid opening, which expressly revokes the previous bid.

10. WITHDRAWAL OF BIDS

A bidder may withdraw their bid anytime up to bid due date and time by simply clicking on Withdraw Bid, located at the bottom of the “Bid” tab. Once the bid closing time is complete, the PennBid system shall automatically submit the bids and no changes shall be able to be made after that time. Requests for withdrawal of bids after bid opening due to clerical error will be made in accordance with Commonwealth of Pennsylvania Act. No. 4 (S.B. 793), the Public Contract bid Withdrawal Law.

11. AWARD OF CONTRACT

The Township shall have the right to reject any or all proposals or any parts thereof or items therein.

The Township shall have the right to waive informalities for the best interests of the Township. The Township reserves the right to reject any submission that is not complete and does not conform to the format contained or requested herein. If an award of contract is made, it shall be made to the lowest responsible bidder, based on the tabulated Base Bid and any selected Add Alternates.

Thirty (30) day extensions of time may be made by the mutual written consent of the Township and the lowest responsible bidder. If the lowest responsible bidder withdraws their bid or refuses award of contract, the Township shall have the right to award the contract to the next lowest responsible bidder

B-4 or to reject all bids and re-bid the Project or cancel the Contract or the Project in their entirety. The Township reserves the right to reject any submission that is not complete and does not conform to the format contained or requested herein.

The Township reserves the right to reject all bids and re-bid the Project or cancel the Project in its sole discretion.

12. EXECUTION OF CONTRACT

The individual, firm or corporation to whom or to which the Contract has been awarded within fifteen

(15) days after receipt of said Documents shall sign and return to the Township, the Contract Documents and substitute for the certified check, or bid bond, which accompanied the proposal, a Contract bond or bonds in the penal sum at least equal to the amount of such Contract, for the faithful performance of the Contract, and also an additional bond for labor and materials, in the penal sum at least equal to the amount of such Contract, to cover the prompt payment in full for all materials furnished and labor supplied or performed, executed by a surety company or companies qualified to do business in the state where bid and a maintenance bond in the amount stipulated herein under "SPECIAL CONDITIONS". Each such bond shall be on the form approved by the Township.

The Contract shall be executed by the Township and the successful bidder within thirty (30) days of the date the Contract is awarded unless the time shall be extended by the mutual written consent of the Township and the successful bidder.

No proposals or awards shall be considered binding upon the Township unless and until the Contract Documents are properly executed by both parties.

13. FAILURE TO EXECUTE CONTRACT

If the lowest responsible bidder to whom the Contract is awarded fails to submit bonds or execute the Contract within the time specified, the amount of the proposal guaranty shall be paid to the Township as liquidated damages. In such case, the Township, at its discretion, may award the Contract to the next lowest responsible bidder, or reject all bids, cancel, delay or modify the Project in its sole discretion.

14. SUBLETTING OR ASSIGNING OF CONTRACT

The Contractor shall not sublet, sell, transfer, assign or otherwise dispose of the Contract or any portion thereof, of his right, title or interest therein, without the written consent of the Township.

15. REJECTION OF PROPOSALS

The right is reserved by the Township at its discretion to reject any or all bids or parts thereof.

Proposals may be rejected if they show any omission, alterations of form, addition or deductions not called for, conditional or uninvited alternate bids, or irregularities of any kind, or any other reason as the Township shall determine. However, the Township reserves the right to waive any defects or irregularities on proposals.

16. SUB-SURFACE INFORMATION

If a prospective bidder desires to make foundations, borings, or soundings or to dig test pits at or near the site of the work they shall do so at their own expense. Before making any excavations, borings or sounding or digging test pits the bidder will check the records for any municipal, public utility, or privately-owned structures that may be disturbed and notify the Township in accordance with Act 287

B-5 of 1974 as amended of such structures seventy-two (72) hours in advance of starting work. Bidders must obtain Township permission before making any borings and shall close bore holes and test pits.

C-1

C. FORM OF PROPOSAL

FOR: SR 73, SEC. MT2 (MPMS # 81892):

SCHOOL ROAD AND SKIPPACK PIKE (SR 0073) INTERSECTION

IMPROVEMENT PROJECT

Along

Skippack Pike (SR 0073) and School Road (SR 2016)

Within

Whitpain Township, Montgomery County, PA

TO: Whitpain Township, 960 Wentz Road, Blue Bell, PA 19422 Attn: Mr. Eric Traub

This proposal is submitted in accordance with your advertisement inviting proposals to be received by 11:00 AM, Thursday, February 5, 2026.

The undersigned hereby declare(s) that ______________________________ carefully examined the

Advertisement, Plans, Specifications, Form of Agreement and Contract Bond for the project named above;

that ______________________________ carefully examined the site of the project; and that ______________________________ will contract to carry out and complete the project as specified and delineated at the price per unit of measure for each scheduled item of work stated in the Schedule of Prices following.

It is understood that TOTAL BASE BID PRICE $______________________________stated by the undersigned in the Schedule of Prices is based on the estimated quantities and will control in the award of the Contract. It is further understood that the quantities may be increased or decreased as provided in the Specifications. The undersigned agrees, if awarded the Contract, to complete the Work within two hundred seventy (270) calendar days from Notice to Proceed, including the 30-day traffic signal testing period.

Whitpain Township reserves the right to reject any and all bids. It, likewise, reserves the right to waive any nonconformity with respect to any bid or any error with respect to the same, which does not constitute a substantial departure from the requirements herein set forth. The determination of whether an error or departure is of substance rests within the sole domain of the Township.

Whitpain Township also reserves the right to reduce, increase, delete or supplement items or quantities from the low Bidder when making the award, without negotiating the total lump sum, unit price or item with the low Bidder.

SIGN

TITLE

FIRM NAME

ADDRESS

C-2

1. SCHEDULE OF PRICES – For Reference ONLY

All Pricing shall be submitted via PennBid (https://pennbid.bonfirehub.com/)

Item

Number

Quantity

U/M Description

Unit

Price

Total

Price

4201-0001 1 LS Clearing and Grubbing, Including Tree Restrictions $_______ $_______

0203-0001 964 CY Class 1 Excavation $_______ $_______

0203-0006 900 LF Saw Cutting $_______ $_______

0204-0001 115 CY Class 2 Excavation $_______ $_______

0205-0100 10 CY Foreign Borrow Excavation $_______ $_______

0212-0014 881 SY Geotextile, Class 4, Type A $_______ $_______

0313-0322 293 SY Superpave Asphalt Mixture Design, Base Course, Pg 64S-22, < 0.3 Million ESALs, 25.0 Mm Mix, 4" Depth $_______ $_______

0313-0426 881 SY Superpave Asphalt Mixture Design, Base Course, Pg 64S-22, 0.3 To < 3 Million ESALs,, 25.0 Mm Mix, 6" Depth $_______ $_______

0350-0105 104 SY Subbase 5" Depth (No. 2A) $_______ $_______

0350-0106 881 SY Subbase 6" Depth (No. 2A) $_______ $_______

0413-0192 397 SY Superpave Asphalt Mixture Design, Wearing Course, Pg 64S-22, <

0.3 Million ESALs, 9.5 Mm Mix, 1 1/2" Depth, SRL-H $_______ $_______

0413-0245 2,581 SY Superpave Asphalt Mixture Design, Wearing Course, Pg 64S-22, 0.3 To < 3 Million ESALs, 9.5 Mm Mix, 1 1/2" Depth, SRL-H $_______ $_______

0413-2071 25 TON Superpave Asphalt Mixture Design, Wearing Course (Leveling), Pg 64S-22, 0.3 To < 3 Million ESALs, 9.5 Mm Mix, SRL-H $_______ $_______

0413-6045 881 SY Superpave Asphalt Mixture Design, Binder Course, Pg 64S-22, 0.3 To < 3 Million ESALs, 19.0 Mm Mix, 2 1/2" Depth $_______ $_______

0413-7009 25 TON Superpave Asphalt Mixture Design, Binder Course (Leveling), Pg 64S-22, 0.3 To < 3 Million ESALs, 19.0 Mm Mix $_______ $_______

0460-0001 3,462 SY Asphalt Tack Coat $_______ $_______

0491-0019 1,700 SY Milling of Bituminous Pavement Surface, Variable Depth, Milled Materials Retained By Contractor $_______ $_______

0601-7509 315 LF 18" Reinforced Concrete Pipe, Type A, 7' - 3' Fill, Shore/Trench Box, 100 Year Design Life $_______ $_______

0601-7517 30 LF 24" Reinforced Concrete Pipe, Type A, 7' - 3' Fill, Shore/Trench Box, 100 Year Design Life $_______ $_______

0604-7509 253 LF 18" Reinforced Concrete Pipe, Type A, (Open Joint), 7' - 3' Fill, Shore/Trench Box, 100 Year Design Life $_______ $_______

0604-7517 235 LF 24" Reinforced Concrete Pipe, Type A, (Open Joint), 7' - 3' Fill, Shore/Trench Box, 100 Year Design Life $_______ $_______

0605-2401 4 EACH Manhole Frame And Cover $_______ $_______

C-3

Unit

Price

Total

Price

0605-2780 3 EACH Type M Frame and Grate $_______ $_______

0605-2781 1 EACH Type M Frame And Bicycle Safe Grate $_______ $_______

0605-2850 9 EACH Standard Inlet Box, Height </= 10' $_______ $_______

0605-2854 8 EACH Type 4 Inlet Box, Height </= 10' $_______ $_______

4605-2858 1 EACH Doghouse Type 5 Inlet Box, Height </= 10' $_______ $_______

0605-3021 1 EACH Type 5 Manhole, Storm Water, Height >5' And < /= 10' $_______ $_______

0605-5721 11 EACH Type C Concrete Top Unit, 8" Curb Height And Bicycle Safe Grate $_______ $_______

0606-0150 1 EACH Grade Adjustment Of Existing Manhole $_______ $_______

0608-0001 1 LS Mobilization $_______ $_______

0630-0041 520 LF Plain Cement Concrete Curb, 8" Height $_______ $_______

0630-0045 13 LF Plain Cement Concrete Curb, 8" Height, Including Removal Of Existing Curb $_______ $_______

4664-0100 50 SF Modular Architectural Block Systems (With Cap Units) $_______ $_______

0676-0001 34 SY Cement Concrete Sidewalk $_______ $_______

4686-0020 1 LS Construction Surveying, Type B, Including As-Built $_______ $_______

0689-0001 1 LS Narrative Schedule $_______ $_______

0695-0004 20 SF Detectable Warning Surface, Polymer Composite $_______ $_______

0802-0001 100 CY Topsoil Furnished And Placed $_______ $_______

0804-0025 35 LB Seeding And Soil Supplements - Formula B Residential Mix, Including Mulch $_______ $_______

4804-0032 5 LB Seeding - Formula T Temporary Grass Mix, Including Mulch, As Directed $_______ $_______

0806-0113 350 SY Temporary Short-Term, Rolled Erosion Control Product, Type 2D $_______ $_______

4810-0026 90 LF Tree Trimming to a Max Height of 20' $_______ $_______

4810-0052 17 EACH Selective Tree Removal $_______ $_______

0845-0001 1 DOLLAR Unforeseen Water Pollution Control $_______ $_______

0860-0000 6 EACH Inlet Filter Bag for Type M Inlet $_______ $_______

C-4

Unit

Price

Total

Price

0860-0002 11 EACH Inlet Filter Bag for Type C Inlet $_______ $_______

0867-0012 570 LF Compost Filter Sock, 12" Diameter $_______ $_______

0901-0001 1 LS Maintenance and Protection of Traffic During Construction $_______ $_______

4910-2828 1 EA 250-Watt High Pressure Sodium Luminaire, Arm Mount, LED Lamp $_______ $_______

0910-4116 300 LF AWG 8 Underground Cable, Copper, 1 Conductor $_______ $_______

0931-0001 29 SF Post Mounted Signs, Type B, Steel Square Post $_______ $_______

0935-0001 15 SF Post Mounted Signs, Type F $_______ $_______

0936-0200 26 SF Structure Mounted Flat Sheet Aluminum Signs $_______ $_______

0941-0001 7 EACH Reset Post Mounted Signs, Type B $_______ $_______

0945-0001 1 EACH Reset Post Mounted Signs, Type F $_______ $_______

0950-0002 8000 DOLLAR Unforeseen Traffic Signal Work $1.00 $8,000.00

0951-0235 1 EA Traffic Signal Support, 35' Mast Arm, Powder Coated $_______ $_______

0951-2235 1 EA Traffic Signal Support, 35' Mast Arm with Luminaire Arm (30' Mounting Height), Powder Coated $_______ $_______

0951-4106 4 EA Traffic Signal Support, 14' Pedestal, Powder Coated $_______ $_______

0951-4112 1 EA Pedestrian Stub Pole, Type B, Powder Coated $_______ $_______

4952-1030 1 EA NEMA TS-2; Type 1 Controller Assembly, Type 1 Mounting, with ATC Timer Unit, Powder Coated Black $_______ $_______

0953-0601 1 EA Managed Network Switch, Field Switch, Type B $_______ $_______

0953-0802 1 LS Unified Command and Control Integration $_______ $_______

4954-0012 280 LF 2 Inch Conduit, PVC $_______ $_______

4954-0013 390 LF 3 Inch Conduit, PVC $_______ $_______

0954-0151 170 LF Trench and Backfill, Type I $_______ $_______

0954-0152 55 LF Trench and Backfill, Type II $_______ $_______

0954-0153 95 LF Trench and Backfill, Type III $_______ $_______

0954-0201 150 LF Signal Cable, 14 AWG, 3 Conductor $_______ $_______

C-5

Unit

Price

Total

Price

0954-0202 980 LF Signal Cable, 14 AWG, 5 Conductor $_______ $_______

0954-0203 430 LF Signal Cable, 14 AWG, 7 Conductor $_______ $_______

0954-0302 1 EA Junction Box, JB-27 $_______ $_______

0954-0305 2 EA Junction Box, JB-30 $_______ $_______

0954-0403 1 EA Electrical Service, Type C $_______ $_______

0954-0600 1 EA Uninterruptible Power Supply (UPS) $_______ $_______

0955-3208 6 EA Vehicular Signal Head, Three 12" Sections $_______ $_______

0955-3209 2 EA Vehicular Signal Head, Four 12" Sections $_______ $_______

0955-3210 1 EA Vehicular Signal Head, Five 12" Sections $_______ $_______

0955-3722 2 EA LED Countdown Pedestrian Signal Head, Type A $_______ $_______

0956-0709 1 EA Video Detection System $_______ $_______

4956-0771 1 EA Radar Detection System, Advance Detection $_______ $_______

0956-0790 2 EA Accessible Pedestrian Signals $_______ $_______

0956-0801 1 EA Optical Preemption System $_______ $_______

0960-0001 1,482 LF 4" White Hot Thermoplastic Pavement Markings $_______ $_______

0960-0002 2,068 LF 4" Yellow Hot Thermoplastic Pavement Markings $_______ $_______

0960-0005 244 LF 6" White Hot Thermoplastic Pavement Markings $_______ $_______

0960-0021 62 LF 24" White Hot Thermoplastic Pavement Markings $_______ $_______

0960-0022 127 LF 24" Yellow Hot Thermoplastic Pavement Markings $_______ $_______

0960-0101 1 EA White Hot Thermoplastic Legend, "Only", 8' - 0" $_______ $_______

0960-0224 1 EA White Hot Thermoplastic Legend, "Left Arrow", 12' - 0" X 3' - 0" $_______ $_______

0963-0001 50 SF Pavement Marking Removal $_______ $_______

0971-0001 2 EA Remove Post Mounted Signs, Type B $_______ $_______

9000-0001 1 LS Dismantle and Reconstruct Stone Wall And Steps $_______ $_______

C-6

Unit

Price

Total

Price

9000-0002 1 LS Relocate Sign and Ground Lighting $_______ $_______

9000-0003 2 EA Adjust Roof Drain $_______ $_______

9000-0004 1 LS Relocate Gas Service Line $_______ $_______

9000-0005 1 LS Relocate Water Service Line $_______ $_______

9000-0006 1 LS Dismantle Stone Wall $_______ $_______

9000-0007 2 EA Special Funding Sign $_______ $_______

9000-0008 222 LF Relocate Existing Stockade Fence $_______ $_______

9000-0009 4 EA Relocate Mailbox $_______ $_______

9000-0010 1 EA Utility Location Soft Digs $_______ $_______

9000-0011 50 CY Over Excavation and Backfill of Subgrade Areas $_______ $_______

9000-0012 1 LS Exploratory Excavation/Camera to Determine Existing Pipe Connection $_______ $_______

9000-0020 1 EA Fiber Optic Patch Panel $_______ $_______

9000-0021 1 EA Connection of Communication Cable to Traffic Signal Controller $_______ $_______

9000-0022 650 LF Single Mode Fiber Optic Cable, 12 Strand, with One 20-Foot Metal Guard $_______ $_______

TOTAL BASE BID PRICE $____________________

Alternate Bid*

Unit

Price

Total

Price

0956-0712 1 EA Omni-View Detection System $_______ $_______

*This item is included within this bid as an alternate to ITEM 0956-0709 VIDEO DETECTION SYSTEM.

TOTAL ALTERNATE BID PRICE $____________________

C-7

The Bidder must submit a bid for the Total Base Bid Price.

Whitpain Township reserves the right to reject any and all bids. It, likewise, reserves the right to waive any nonconformity with respect to any bid or any error with respect to the same, which does not constitute a substantial departure from the requirements herein set forth. The determination of whether an error or departure is of substance rests within the sole domain of the Township.

Whitpain Township also reserves the right to reduce, increase, delete, or supplement items or quantities from the low Bidder when making the award, without negotiating the Total Bid Price, unit price or item with the low Bidder.

SIGN

TITLE

FIRM NAME

ADDRESS

C-8

2. NON-COLLUSION AFFIDAVIT OF PRIME BIDDER

State of ) County of ) ) ss:

being duly sworn, deposes and says that:

(Name of Bidder’s Representative)

1) They are (Capacity of Bidder’s Representative – i.e., Owner, partner, officer, agent, etc.)

of (Name of Bidder)

2) They are fully informed respecting the preparation and contents of the attached Bid and of all pertinent circumstances respecting such Bid;

3) Such Bid is genuine and is not a collusive or sham bid;

4) Neither the said Bidder nor any of its officers, partners, Owners, agents, representatives, employees or parties in interest, including this affiant, has in any way colluded, conspired, connived or agreed, directly or indirectly, with any other Bidder, firm or person to submit a collusive or sham Bid in connection with the Contract for which the attached Bid has been submitted to refrain from bidding in connection with such Contract, or has in any manner, directly or indirectly, sought by agreement or collusion or communication or conference with any other Bidder, firm or person to fix the price or prices in the agreement or collusion or communication or conference with any other Bidder, firm or person to fix the price or prices in the attached Bid or of any other Bidder, or, to fix any overhead, profit or cost element of the bid price or the bid price of any other Bidder, or to secure through any collusion, conspiracy, connivance or unlawful agreement any advantage against the Owner to which the attached Bid is being submitted or any person interested in the proposed Contract; and

5) The price or prices quoted in the attached Bid are fair and proper and are not tainted by any collusion, conspiracy, connivance or unlawful agreement on the part of the Bidder or any of its agents, representatives, Owners, employees, or parties in interest, including this affiant.

(Name of Bidder)

(Signature of Bidder’s Representative)

(Title of Bidder’s Representative)

Sworn to and subscribed before me this day of , A.D. 20 .

(Signature of Notary)

My Commission Expires: .

(Title) (Date)

D-1

D. FORM OF GUARANTY:

ADDENDUMS:

The bidder acknowledges receipt of the hereinafter enumerated addendums that have been issued during period of bidding and agrees that said addendums will become a part of this contract. The bidder will list below the numbers and issuing dates of the addendums.

Addendum No. Issuing Date

The undersigned hereby certifies that this Proposal is genuine, and not sham or collusive, or submitted in the interest or on behalf of any person, firm or corporation not herein named, and has not induced any other persons to refrain from biddings, and has not in any way sought by collusion to secure for themself an advantage over any other bidder.

Accompanying this Proposal is a Certified Check or Bid Bond, payable to the Township in the sum of $__________, which the undersigned agree(s) is to be forfeited as liquidated damages, and not as a penalty, if the Contract is awarded to the undersigned and the undersigned shall fail to execute the Contract in conformity with the agreement incorporated in the contract documents, and furnish bonds as specified, within ten (10) days after receipt of notice to proceed. Otherwise, the Certified Check or Bid Bond will be returned to the undersigned.

(an Individual) The undersigned is: (a Partnership) under the laws of the State of _____________________ (a Corporation) having principal offices at:

Signed: ____________________________________________ Date: _____________

Address: ____________________________________________

D-2

1. LIST OF SUBCONTRACTORS

The Bidder further certifies that the following firms or businesses will be awarded subcontracts for the stated portions of the work in the event the Bidder is awarded the Contract. (Add additional pages as required)

Subcontractor Name & Address Specialty Area

1.

2.

3.

4.

E-1

E. GENERAL CONDITIONS

1. DEFINITIONS

The OWNER is the party referred to in the Advertisement and whenever the word Owner is used herein it will refer to Whitpain Township and designate the party of the first part of the Contract contained herein.

The CONTRACTOR is the individual, group, partnership or corporation undertaking to do the Work herein specified (including their heirs, legal representatives, successors or assigns) and is the party of second part of the Contract contained herein.

The ENGINEER, the person, firm or corporation who represents the Owner on the Contract contained herein.

The CONTRACT DOCUMENTS consist of the Advertisement, Instructions to Bidders, Form of Proposal, Form of Guaranty, General and Special Conditions, Construction Specifications, Form of Agreement, Contract Bond, List of Contract Documents, the Drawings, and Addenda.

A SUB-CONTRACTOR is an individual group, partnership or corporation, having a direct Contract with the Contractor to furnish a special service, labor or material towards the Completion for the Contractor’s Contract.

An INSPECTOR is an authorized representative of the Engineers and/or Owner, assigned to inspect the Work performed and the materials supplied by the Contractor as to compliance with the Contract Documents.

The term WORK, used herein, includes all labor and/or materials, equipment and any other facilities necessary for the Contractor to complete the Contract.

The CONTRACT is the agreement between the Owner and Contractor for the Contractor to complete the Work in accordance with the Contract Documents, subject to the terms and conditions therein.

The term APPROVED, used herein, will be held to mean as Approved by the Engineer.

The term SUBSTANTIAL COMPLETION used herein will be held to mean construction that is sufficiently completed in accordance with the Contract Documents and certified by the Engineer of the Owner, as modified by change orders agreed to by the parties, so that a project can be used, occupied or operated for its intended use. In no event will a project be certified as Substantially complete until at least 90% of the Work on the project is completed.

NOTICE will be deemed to have been duly served if written and delivered in person to the individual, or to a member of the firm, or to an officer of the Corporation for whom it is intended, or if delivered at or sent by registered mail to the last business address known to the party who gives Notice.

2. OTHER CONTRACTS

The Owner may award, or may have awarded other Contracts for additional Work, and the Contractor shall cooperate fully with such other Contractors, by scheduling Contractor’s Work with

E-2 that to be performed under other Contractors as may be directed by the Owner. The Contractor will not commit or permit any act which will interfere with the performance of Work by any other Contractor as scheduled.

3. SUB-CONTRACTS

No part of the Contract will be sublet without the prior written approval of the Owner, or their representatives, and setting forth requirements to be met. Each subcontractor must have written pre-approval prior to the start of work on the project.

4. MUTUAL RESPONSIBILITY OF CONTRACTORS

If, through acts or neglect on the part of the Contractor, any other Contractors, or any Subcontractor, will suffer loss or damage on the Work, the Contractor will settle with such other Contractor or Subcontractor by agreement or arbitration, if such other Contractor or Subcontractor will so settle. If such other Contractor, or Subcontractor will assert any claim against the Owner on account of any damage alleged to have been so sustained, the Owner will notify this Contractor, who will defend at its own expense any suit based upon such claim and, if any judgment or claims against the Owner will be allowed, the Contractor will pay or satisfy such judgment or claim and pay all costs and expenses in connection therewith. If the Owner incurs attorney’s fees as a result of any claim against the Owner by the Contractor or any Subcontractor, such attorney’s fees will be paid by the Contractor or Subcontractor as the case may be.

5. FITTING AND COORDINATION OF WORK

The Contractor will be responsible for the proper fitting of all Work and for the coordination of the operations of all trades, Subcontractors, or materialmen engaged upon this Contract. They will be prepared to guarantee to each of the Subcontractors the locations and measurements that they may require for the fitting of their Work to all surrounding Work.

6. SUPERINTENDENCE BY CONTRACTOR

At all times during which Work is being performed under or affecting this Contract, the Contractor will keep a competent superintendent acceptable to the Engineer constantly on the site from the commencement of Work under this Contract until the Completion thereof, who will be constantly in touch with Work and in all interlocking Contracts affected thereby. The superintendent will, in the absence of the Contractor, see that the instructions of the Engineer are carried out and all directions given such superintendent will be as binding as if given to the Contractor.

7. PERMITS, LICENSES AND TAXES

The Contractor will give all Notice required by and comply with all applicable laws, ordinances, and codes of the Local Government, all construction Work and/or utility installations will comply with all applicable ordinances, and codes including all written waivers. Before installing any Work, the Contractor will examine the Drawing and Construction Specifications for compliance with applicable ordinances and codes and will immediately report any discrepancy to the Owner. Where the requirements of the Drawings and Detail Specifications fail to comply with such applicable ordinances or codes, the Owner will adjust the Contract by Change Order to conform to such ordinances or codes (unless waivers in writing covering the difference have been granted by the governing body or department) and make appropriate adjustment in the Contract Price or stipulated unit prices.

E-3

The Contractor will at their own expense, secure and pay to the appropriate department of the Local Government the fees, or charges for all permits required by the local regulatory body or any of its agencies.

Permits for the opening and/or occupation of Township roads will be obtained by the Contractor and State and County Highway permits will be obtained by the Owner. However, all inspection fees and/or any other charges will be borne by the Contractor, whether same is billed directly to them or to the Owner. Should any such bill be left unpaid by the Contractor, the Owner will be empowered to pay such bills and the cost thereof deducted from any monies due or to become due the Contractor.

Whenever the proposed construction requires a sales, consumers use, or other similar tax, the contractor will pay for same.

8. PROVISIONS REQUIRED BY LAW

Each and every provision of law and clause required by law to be inserted in this Contract will be deemed to be inserted herein and the Contract will be read and enforced as though it were included herein; and, if through mistake or otherwise, any such provision is not inserted or is not correctly inserted, then upon the application of either party the Contract will forthwith be physically amended to make such insertion.

9. PROTECTION OF WORK AND PROPERTY

The Contractor will provide adequate protection against injury or loss arising in connection with this Contract for all their Work and the property of the Owner. They will make good any such damage, injury or loss, except such as may be due directly to errors in the drawings or specifications or caused by agents or employees of the Owner. They will adequately protect adjacent property as provided by law and the specifications and drawings. They will provide facilities for protection required by public authority or local conditions as passageways, guard fences, lights, etc.

The Contractor will preserve and protect all trees, shrubs and grass on or adjacent to the site which do not reasonably interfere with the construction as may be determined by the Engineer and the Contractor will be responsible for all unauthorized cutting or damaging or trees and shrubs, including damage due to careless operation of equipment, stockpiling of materials or tracking of grass areas by equipment. The Contractor will remove only those trees shown on the Drawings or as directed by the Engineer to be removed.

10. TEMPORARY PROVISION FOR PUBLIC TRAVEL

The Contractor will perform their Work in such a manner as to interfere as little as possible with the use of intersecting roads or adjoining property. No excavation will be left open or other obstruction allowed to remain longer than is absolutely necessary; and the Contractor will provide all safeguards and temporary passageways that may be necessary for the convenience and protection of all persons using said property either day or night.

11. SHOP DRAWINGS

The Contractor will check and verify all field measurements and will submit with such promptness as to cause no delay in their own Work or in that of any other Contractor, three copies, checked and approved by them, of all shop or setting drawings and schedules required for the Work of the various trades. The Engineers will check and approve, with reasonable promptness, such schedules and drawings only for conformance with the design concept of the Project and compliance with the

E-4 information given in the Contract Documents. The Contractor will make any corrections required by the Engineers, file with them two copies and furnish such other copies as may be needed. The Engineers' approval of such drawings or schedules will not relieve the Contractor from responsibility for deviations from Drawings or Specifications, unless they have, in writing, called the Engineers' attention to such deviations at the time of submission, and secured their written approval, nor will it relieve them from responsibility for errors in shop drawings or schedules.

12. TERMINATION; DELAYS; LIQUIDATED DAMAGES

If the Contractor refuses or fails to prosecute the Work with such diligence as will ensure its Completion within the time specified in these Contract Documents, or as modified as provided in these Contract Documents, the Owner, by written Notice to the Contractor, may terminate the Contractor's right to proceed with the Work. Upon such termination, the Owner may take over the Work and prosecute the same to Completion by Contract or otherwise, and the Contractor and their sureties will be liable to the Owner for additional cost incurred by the Owner for liquidated damages for any delay in the Completion of the Work as provided below. If the Contractor's right to proceed is so terminated, the Owner may take possession of and utilize, to complete the Work, any materials, tools, equipment and plants as may be on the site of the Work.

If the Work is not completed within the time stipulated, including any extensions of time for excusable delays as herein provided, the Contractor will pay to the Owner Liquidated Damages in the amount of $2,700.00 for each calendar day of delay, as set forth in the form of Agreement, and the Contractor and their sureties will be liable to the Owner for the amount thereof.

The right of the Contractor to proceed will not be terminated nor will the Contractor be charged with Liquidated Damages for any delays in the Completion of the Work due:

a) To any acts of the Government, including controls or restriction upon or requisitioning of materials, equipment, tools, or labor by reason of war, national defense, or any other national emergency;

b) To any acts of the Owner;

c) To causes not reasonably foreseeable by the parties to this Contract at the time of the execution of the contract which are beyond the control and without the fault of negligence of the Contractor, including, but not restricted to, acts of God or of the public enemy, acts of another Contractor in the performance of some other contract with the Owner, fires, floods, epidemics, quarantine, restrictions, strikes, freight embargoes, and weather of unusual severity such as hurricanes, tornadoes, cyclones and other extreme weather conditions; and

d) To any delay of any subcontractor occasioned by any of the causes specified in sub-paragraphs above.

Provided, however, that the Contractor promptly notified the Owner within ten (10) days in writing of the cause of the delay. Upon receipt of such notification, the Owner will ascertain the facts and the cause and extent of delay. If, upon the basis of the facts and the terms of this Contract, the delay is properly excusable, the Owner will extend the time of completing the Work for a period of time commensurate with the period of excusable delay; however, the Contractor shall not be entitled to any additional pay during or caused by the delay.

Should the Completion of the Work be delayed beyond the time herein specified for Completion for any reason…