This document contains responses from the FBI to inquiries regarding a solicitation for Regional Multiple Award Construction Contracts. The solicitation is for indefinite-delivery, indefinite-quantity construction contracts across multiple regions, with an initial seed project located at the FBI's Terrorist Explosive Device Analytical Center in Huntsville, Alabama. The seed project involves construction of an Explosive Technical Laboratory building and is fully designed.

The responses provide clarification on various requirements for the seed project, such as confirmation that approximately 22,000 cubic yards of structural fill material is stockpiled for use on site. Submission requirements are also clarified, including the need to submit six hard copies and one electronic copy of proposals to the FBI office in Huntsville by August 26, 2019.

15F06719R0000004 0009 Atch 8 RFI Region 1 Responses 23AUG19Final

View the file

Other files

File Type Posted
15F06719R0000004_0013_Atch_8_Responses_7OCT19.pdf PDF
SF_30,_15F06719R0000004_0013_7OCT19.pdf PDF
15F06719R0000004_0013,_Atch_1_SF_1442_7OCT19.pdf PDF
15F06719R0000004_0012,_Atch_1_SF_1442_20SEP19.pdf PDF
15F06719R0000004_0012_Atch_8_Responses_20SEP19.pdf PDF
SF_30,_15F06719R0000004_0012_20SEP19.pdf PDF
15F06719R0000004_Atch_19_Request_For_Const_Docs_Cert.pdf PDF
15F06719R0000004_0011_Atch_8_Responses_13SEP19.pdf PDF
15F06719R0000004_0011,_Atch_1_SF_1442_13SEP19.pdf PDF
SF_30,_15F06719R0000004_0011_17SEP19.pdf PDF
15F06719R0000004_0011_13SEP19.pdf PDF
SF_30,_15F06719R0000004_0010_30AUG19Final.pdf PDF
15F06719R0000004_0009,_Atch_1_SF_1442_23AUG19Final.pdf PDF
SF_30,_15F06719R0000004_0009_23AUG19Final.pdf PDF
15F06719R0000004_0009_23AUG19Final.pdf PDF
15F06719R0000004_0009,_Atch_19,_Request_For_Const_Docs_Cert.pdf PDF
SF_30,_15F06719R0000004_0008__16AUG19Final.pdf PDF
15F06719R0000004_0007,_Atch_24_FD_219_Visitor_Request_Form.xlsx XLSX spreadsheet
15F06719R0000004_0007,_Atch_20_Policy_Directive_0130D.pdf PDF
15F06719R0000004_0007,_Atch_23_Submitting_Candidates_for_Access_to_FBI_Facilities.pdf PDF
15F06719R0000004_0007,_Atch_19,_Request_For_Const_Docs_Cert.pdf PDF
15F06719R0000004_0007,_Atch_21_OCONUS_Gen_Reqmts&Prov_Div_1.pdf PDF
15F06719R0000004_0007,_Atch_12_Price_Model_Template.xlsx XLSX spreadsheet
15F06719R0000004_0007,_Atch_15_Resume_Template.docx DOCX document
15F06719R0000004_0007,_Atch_17_FBI_LAR_Guide_&_SF_85.pdf PDF
15F06719R0000004_0007,_Atch_18_FD-857a_Sensitive_Info_NDA.pdf PDF
15F06719R0000004_0007,_Atch_25_Request_For_Construction_Documents_Certification.pdf PDF
15F06719R0000004_0007,_Atch_8_Submission_of_Questions_Form.xlsx XLSX spreadsheet
15F06719R0000004_Amendment_0007_26JUL19Final.pdf PDF
15F067-19-R0000004_Amendment_0006,_Responses_FBO_Post_11JAN19Final.pdf PDF
SF_30,_15F067-19-R0000004_Amendment_0006_11JAN19Final.pdf PDF
15F067-19-R0000004_Amendment_0005,_Inquiries_and_Responses_FBO_Post_10JAN19Final.pdf PDF
SF_30,_15F067-19-R0000004_Amendment_0005_10JAN19Final.pdf PDF
15F067-19-R0000004_Rev_2,_Amendment_0005_FBO_Post_10JAN19Final.pdf PDF
Atch_1_SF_1442_Amendment_0004_02JAN19Final.pdf PDF
SF_30,_15F067-19-R0000004_Amendment_0004_02JAN19Final.pdf PDF
SF_30,_15F067-19-R0000004_Amendment_0003_21DEC18Final.pdf PDF
Atch_1_SF_1442_Amendment_0003_21DEC18Final.pdf PDF
15F067-19-R0000004_Revision_1,_Amendment_0002_20DEC19Final.pdf PDF
Atch_1_SF_1442_Amendment_0002_20DEC18Final.pdf PDF
SF_30,_15F067-19-R0000004_Amendment_0002_20DEC18Final.pdf PDF
Atch_11_List_of_Projects,_HSV_Only,_Amendment_0002_20DEC18Final.pdf PDF
15F067-19-R0000004_Amendment_0002,_Responses-FBO_Copy_20DEC18Final.pdf PDF
Atch_5_PPQ,_Amendment_0002_20DEC18Final.docx DOCX document
Atch_10_Corp_Perform_Ref_Info,_Amendment_0002_20DEC18Final.docx DOCX document
15F067-19-R0000004_Amendment_0001_14DEC18Final_1.pdf PDF
Sol__Cvr_Ltr_14NOV18Final-signed.pdf PDF
Atch_11_List_of_Projects,_HSV_Only_FINAL.xlsx XLSX spreadsheet
ATTACHMENT_1_SF_1442.pdf PDF
Atch_4_DOS_Security_Rqmts_for_Overseas_Work_FINAL.pdf PDF
Show 40 more

Latest 50 of 58 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Item # Government Response

1 The location of the Pre-Proposal Conference will be at the FBI North Campus site, 4940 Fowler Road, Redstone Arsenal, AL 35898. You may refer to the same location in Section L.10.7.2.

Yes, refer to e-mail transmission from Debra Keeling on 5 Aug 2019 @ 1:30 p.m. Attachment 7 FBI Nondisclosure Agreement for FBI Sensitive Data "shall be returned to us for authorization before sending documents to subcontractors and designers. The Prime Offeror shall complete the FBI NDA for FBI Sensitive Data form and have all subcontractor personnel complete the continuation signature page.

Return for the entire form to obtain the Contracting Officer’s authorization signature. Amendment 0008 is forthcoming to add this document to the Section J List of Attachments to the solicitation, 15F06719R0000004 RMACC."

Yes, refer to e-mail transmission from Debra Keeling on 5 Aug 2019 at 1:30 p.m.

Yes, an SF 1442 will be provided with Amendment 0009

The CLIN structure contained in the solicitation is the structure for the resultant IDIQ contract awards.

The CLIN structure at the TO level will be sequentially numbered CLINs that will link to the CLINs under the awarded IDIQ contracts as applicable.

The offeror is required to submit the items identified as written in the solicitation; see Amendment 0009.

7 Yes, an SF 30 will be provided via an upcoming amendment; See amendment 0009.

The Offeror shall provide one (1) original and five (5) copies of Volumes III and IV and one CD containing the entire proposal. Refer to paragraph L.20.1 Execution and Completeness of the Seed Project.

9 Section 313116 Termite Control was incorrectly omitted. Termite control specifications will be addressed in the next amendment to the R1 TORFP.

10 Yes. Attachment 1 "Request for Construction Documents Certification" was mistakenly labeled Attachment 20. However both of these documents are required for disclosure of FBI Sensitive of Unclassified information. See document correction in Amendment 0009.

11 In accordance with Section L.17.5.1.1, and the 15F067-19-R0000004 Regional Multiple Award Construction Contracts, Phase II Task Order Request for Proposal (TORFP) for Region 1, Seed Project letters, all inquiries/comments shall be received no later than August 09 2019 at 12:00 p.m. CST.

12 The requirement for the Lead Architect in the solicitation is for the resulting overarching IDIQ contracts that would provide oversight for the entire period of the IDIQ contract. The Region 1 Seed project is a fully designed project and the need for an Architect is at the discretion of the Contractor.

This is a Multiple Award Contract spanning multiple regions, and multiple project types. The language ins the solicitation is written to cover various projects spanning the life of the resultant IDIQ contract awards.

However, the TEDAC ETL Region 1 Seed project is fully designed and a Design Bid Build project delivery method is most applicable.

This is a Multiple Award Contract spanning multiple regions, and multiple project types. The language ins the solicitation is written to cover various projects spanning the life of the resultant IDIQ contract awards.

However, the TEDAC ETL Region 1 Seed project is fully designed and a Design Bid Build project delivery method is most applicable.

RFP 15F06719R0000004 AMENDMENT 0009 RMACC PHASE II REGION 1 RESPONSES ONLY

QuestionDrawing # Specification #

N/A

N/A

N/A

Section L

Paragraph L.17.5.1.1 states Region 1 pre-proposal inquiries are to be submitted no later than August 09, 2019 at 12:00 p.m. CST. Paragraph L.17.7.1 states Region 1 inquiries are to be submitted no later than August 16, 2019 at 12:00 p.m. CST.

Which date is correct?

Section L L.21.1.6.f Lead Architect: Please clarify the scope of services to be provided by the Lead Architect for the Region 1 Seed Project that is fully designed.

N/A Amendment #7 Please confirm that 1 original, 5 copies, and 1 CD of Volume IV are required.

N/A "Amendment #7 Table 3 Phase II Proposal Content and Organization"

The project documents do not include a specification section for termite treatment.

Please provide the specification or confirm that Termite Treatment is not required for this project.

N/A Amend 7, Phase 2 RFP, Attachment

Is the Attachment 20, 15F06719R0000004 0007 RMACC "Request For Construction Document Certification" required to be completed by each Subcontractor and Vendor, as well as the Non-Disclosure Agreement, prior to allowing them access to the Phase 2 Proposal Documents (i.e. - Specifications, Drawing, wage decision, Etc.)

N/A RFP Phase 2

During the proposal phase; are all Subcontractors and Vendors required to sign the Non-Disclosure Agreement (NDA) provided prior to receiving RFP Phase 2 documents (Plans and Specifications)?

N/A RFP Phase 2 Can Phase 2 documents (plans and specifications) be distributed to subcontractors and vendors via the internet for bid purposes?

N/A Amendment #7 Does the FBI intend to publish a SF 1442 for Phase Two, or should the Offeror use the SF 1442 from Phase One, and change the date?

N/A Amendment #7 Please clarify if the CLIN Schedule, found on pages 3 & 4 is correct. It doesn't appear to match the Task Order.

N/A

Please clarify the requirements for Tab D Contract Documentation. Is the Offeror required to submit the entire Sections A through K or just the items in the bullet list: SF 1442; Section B, Section I, and Section K?

N/A

"Amendment #7, L.22.5.1"

Please provide an SF 30 for Amendment #7.Amendment #7

Section L

L.21.1.7 Tab D Construction Schedule: Narrative paragraph states, "...Offeror will address the design, construction and closeout and warranty phases…" Please clarify or delete "design phase" as this Region 1 Seed Project is fully designed.

N/A Section L

L.21.1.7 Tab D Construction Schedule: Schedule Graphic paragraph states, "…identify key design, construction, commissioning, closeout and warranty activities." Please clarify or delete "design activities" as this Region 1 Seed Project is fully designed.

REGION 1

N/A Amendment 7

Paragraph L.17.6.1 states "The location of the Pre-Proposal Conference will be identified on the TORFP letter". Please Provide the TORFP letter or a address for the Pre-Proposal Conference.

This is a Multiple Award Contract spanning multiple regions, and multiple project types. The language ins the solicitation is written to cover various projects spanning the life of the resultant IDIQ contract awards.

However, the TEDAC ETL Region 1 Seed project is fully designed and a Design Bid Build project delivery method is most applicable.

16 The requirement for establishing a PLA and FAR clauses 52.222-33 and 52.222-34 are removed. See Amendment 0009.

See Amendment 0009 revising proposal data sheet to Attachment 12 Price Model.

18 If referring to Tab A of volume IV see revised paragraph L.22.2 Volume IV Tab A Cost/Price Information (Price Model) in Amendment 0009.

19 See revised solicitation language in under paragraph L.22 Cost/Price Information (Price Model), and Contract Line Item Number (CLIN) via Amendment 0009.

20 The requirement for establishing a PLA and FAR clauses 52.222-33 and 52.222-34 are removed. See Amendment 0009.

The deadline for submission of RFI remains as written in the solicitation.

1. Yes, antimicrobial coating will go on top on the G90 finish.

2. This section is in addition to the general sheet metal section. Antimicrobial coating shall be applied to all ductwork. During inspection, if any areas show fungal growth or contamination, apply additional coating. This may apply to ductwork and ductwork accessories.

3. Initial coating applies only to ductwork, not ductwork accessories. If inspection reveals suspected fungal growth at any ductwork accessories, coating shall be applied, so above.

4. No, if ductwork inspection reveals no areas requiring cleaning, system shall not be cleaned. This is mos often achieved by protecting ductwork opening throughout shipping, storage, construction, and start-up.

Confirmed; however product data sheets for or products shall be provided to the government COR/PM for approval.

All written inquiries/comments shall be received no later than August 09 2019 at 12:00 p.m. CST.

The TORFP letter(s) will be amended to add the Geotechnical Report

N/A

N/A Amendment #7, L.22 - Tab A Please clarify if Proposal Data Sheet is required. If so, please provide.

Amendment #7, L.22 - Tab A

Please clarify if Contract Line Item (CLIN) is required for Tab A. If so, please provide.

N/A Amendment #7, L.22 - Tab A & L.22.5 Tab D

Please clarify the difference between the CLIN schedule required in Tab A and Section B Supplies and Services required in Tab D. Are these two different price-related documents?

N/A RFP, Section I, Clause 52.222-33 Does the Project Labor Agreement apply only to the Seed Project Task Order or to all future Task Orders at Redstone Arsenal as well?

N/A RFP issued with Amend 7, section I

Page 45 of 100, Clause 52.222-33…… Please remove the requirement for the the successful offeror to negotiate a Project Labor Agreement (PLA). Using a PLA will severely limit the subcontractor pool and thus competition, especially in Huntsville, AL.

N/A Section L L.21.1.7.1 Design after Award: Please clarify requirements or delete as this Region 1 Seed Project is fully designed.

N/A

15F06719R0000004 RMACC -

Attachment 7 FBI NDA to the TORFP letter

We are in receipt of the added Attachment 7 NDA form. Given the process will require new separate forms for even those contractors/vendors currently under signature of NDA's of related projects, as well as the requirement to submit to the FBI for approval prior to providing access to the project documents, we respectfully request an extension to the scheduled bid date in order to ensure adequate bid coverage and proper time for bidders to review the project documents. We would also like to request an extension to the deadline for submission of RFI's. The current cutoff date for submissions is 08/09/2019 and many bidders may not have access to the documents by that time.

N/A 230130.51-5 & 233113-9

Specification Section 230130.51-5, HVAC AIR DISTRIBUTION SYSTEM CLEANING, Section O, 1., States, “Apply antimicrobial agents and coatings if active fungal growth is reasonably suspected or where unacceptable levels of fungal contamination have been verified.”

Specification Section 233113-9, AIR DISTRIBUTION SYSTEMS-METAL DUCTS, Section 2.2 G., Indicated to have a Factory-or Shop-Applied Antimicrobial Coating The table on Page 233113-49 calls for the supply and some other ductwork to made from G90 galvanized.

QUESTIONS:

1.) The sheet metal ductwork will have a G90 finish, does this need the antimicrobial coating as well?

2.) The cleaning specification indicates to only apply the coating if there is a suspect of fungal growth, does this mean the entire system does not need the coating initially?

3.) If the coating is required, is it required on all HVAC ductwork accessories as well, i.e., dampers, fire dampers, etc.?

4.) If the ductwork system is tested and found to be clean without mechanical cleaning, will the system be required to be cleaned anyway?

N/A 87100

Please confirm that alternate door hardware manufacturers/products other than those listed in specification 087100 will be acceptable as long as each type and variety of door hardware is obtained from a single source as stated in Paragraph 1.5.A. - 087100.

N/A TORFP Letter Item #3

The letter requesting a proposal for the seed project states that RFI's are due no later than 12:00 PM CST on August 9. The slideshow from the prebid conference states 10:00 AM CST. Please clarify which is correct.

N/A 3132 Can a copy of the referenced final soils report be provided for information?

26 Correct. The Offeror's Price Model shall include a summary sheet that rolls up all proposed pricing to a LS firm-fixed-price CLIN as shown Section B Supplies or Services and Prices/Costs. See upcoming Amendment 0009, paragraph L.22.5 TAB D Contract Documentation.

Yes, there is approximately 22,000 CYs of structural fill material stockpiled south of the ETL on site.

This specific specification section will be removed in a future amendment

Confirm that no unit price is required for Asphalt.

The TORFP letter(s) will be amended to add applicable liquidated damage amount(s).

Arriscraft is identified in the existing building base.

Yes, see Amendment 0009, paragraph L.17.8.1 Region 1. However, the delivery method chosen by the Offeror, the Offeror is responsible for ensuring that the proposal is received at the designated point of delivery by the proposal due date and time.

In accordance with paragraph L.14, The Offeror shall be responsible for ensuring that the proposal is sent either by registered or certified mail, post marked by a USPS via hand stamp clearly showing the date of receipt at the Government installation designated for receipt of proposal and was under the Government control prior to the time set for receipt of proposals.

34 The Offeror shall submit six (6) hardcopies of the proposal, one (1) original and five (5) copies, and one

(1) electronic CD or DVD with company proprietary, security, and other proposal markings as specified in the solicitation no later than 12:00 p.m. CST on August 26, 2019. Hand delivery is permitted for Region 1 only Phase II proposals only. See Amendment 0009; paragraph L.17.8.1. Region 1.

UFC is the controlling code for ATFP design for this project and does not require blast doors or windows on the exterior. However, the project does require internal blast doors for the internal hazards specific to this site (in the lab areas). This hazard is not a hazard specified in the UFC, but is still required for the safety of the occupants. Spec section 18326 reflects this and is in line with the project specific criteria.

Yes, only one of the found endorsements/certifications is required.

37 The Offeror shall submit six (6) hardcopies of the proposal, one (1) original and five (5) copies, and one

(1) electronic CD or DVD with company proprietary, security, and other proposal markings as specified in the solicitation no later than 12:00 p.m. CST on August 26, 2019. Hand delivery is permitted for Region 1 only Phase II proposals only. See Amendment 0009; paragraph L.17.8.1. Region 1.

All documentation is required as specified in the solicitation and TORFP letters. The resultant five-year option IDIQ contract will require various types of construction services presented in Section C Description/Specifications/Statement of Work, paragraph C.2 Scope. Documentation is required for evaluation for award of an IDIQ contract as well as for TOs for Seed Project(s).

Proposal Requirements

Please consider allowing proposals to be hand delivered to the FBI security office as done on past projects. Considering the amount of projects bidding in the area, allowing contractors to use the weekend would increase coverage and ensure more accurate and competitive pricing. Mandating delivery service will force contractors to ship proposals the week before in order to meet the deadline.

N/A

N/A 51200

N/A Attachment #3 Please confirm quantities for unit prices shall be 1 and the Contractor is not required to propose quantities.

N/A TORFP Letter

The Phase II RFP Letter provides a contract duration of 600 calendar days but does not stipulate any applicable liquidated damages. If damages are a condition of the contract performance, please provide.

N/A 044200-2.1

Arriscraft Stone has proprietary manufacturing and performance properties for which no known equal is commercially available in the domestic market. In addition, the product is considerably more expensive than similar standard masonry products. Please confirm no industry standard products from alternate manufacturers will be accepted and/or provide J&A for sole source limitation to ensure all bidders are including the correct product in their pricing.

N/A Proposal Requirements Will contractors be allowed to use delivery services other than Fed-Ex or UPS for the submission of proposals?

N/A Pre-bid

Please confirm the contractor will be allowed to use the onsite stockpile as discussed at the pre-bid conference for structural fill in lieu of importing at no additional cost.

N/A 230800-1.6

The Commissioning specification references unit price adjustments based on actual testing time. Please revise the supplemental bid form or remove this section to eliminate confusion.

N/A 321216-1.3 Please confirm no unit price is required for Asphalt.

Paragraph 1.7.C. states that the shop-paint applicator shall have AISC's Sophisticated Paint Endorsements P1, P2, P3 or an SSPC-QP 3 certification. Please confirm that the minimum requirement for the paint-shop applicator is only to have one of the four endorsements/certifications listed in this paragraph.

N/A 15F067-19-R0000004 0007

RMACC

Please further clarify what is required for submission of price. The CLIN schedule on pages 3 & 4 is generic and there is no information in Section C that identifies what work should be included in each line item. Should contractors forego the completion of the CLIN schedule and submit the excel spreadsheets provided which include a ful divisional breakdown for the base bid and a supplemental sheet for

N/A 15F067-19-R0000004 0007

RMACC

Several sections seem to only be applicable to Design Build delivery method. Please confirm no design or design resume info is required with the submission of proposals for this task order.

N/A Proposal Requirements

If the contractor is able to provide proof or tracking information that would indicate reasonable time to expect delivery prior to the deadline, yet the delivery service is late, will the proposal still be accepted?

N/A

18326

It was mentioned at the pre-bid that blast requirements for the project would adopt the standards of the UFC. This is not currently reflected in the documents. Please confirm the most recent version of UFC 04-010-01 will govern over requirements currently included in the documents as it pertains to ATFP.

The TORFP letter(s) will be amended to add applicable liquidated damage amount(s).

Correct. FAR 52.232-5 governs and the contractor will be allowed to bill for progress payments, including work performed by subcontractors, in the same payment period so long as certification of timely payment for all previously billed work is provided.

Propose per the written specifications. The Contractor is responsible for LEED Silver Certification with plaque on the wall.

Yes, the Government would evaluate an alternate performance period with justification.

42 G.3 should read "Customary progress payments at standard uniform percentages of total costs are authorized to be made hereunder in accordance Section I Contract Clauses, FAR clause 52.232-5 Payments under Fixed-Price Construction Contracts and 52.232-16 "Progress Payments". See Amendment 0009

The specified minimum amounts are aggregate amounts. See revised language in Amendment 0009.

Yes, the intent is to include all commissioning in accordance with the Specification.

45 The minimum amount is twenty-five percent (25%). See Amendment 0009, revised language under clause 52.236-1 Performance of Work by the Contractor.

46 Yes, GC is responsible for maintaining proper egress. As long as this is maintained and approved by the AHJ, work can begin on the loading dock.

Yes, the requirement for the Lead Architect in the solicitation is for the resulting overarching IDIQ contract that would provide oversight for the entire period of the IDIQ contract.

This is a Multiple Award Contract spanning multiple regions, and multiple project types. The language ins the solicitation is written to cover various projects spanning the life of the resultant IDIQ contract awards.

However, the TEDAC ETL Region 1 Seed project is fully designed and a Design Bid Build project delivery method is most applicable.

This is a Multiple Award Contract spanning multiple regions, and multiple project types. The language ins the solicitation is written to cover various projects spanning the life of the resultant IDIQ contract awards.

However, the TEDAC ETL Region 1 Seed project is fully designed and a Design Bid Build project delivery method is most applicable.

Yes. The offeror is to purchase and install the workstation furniture/furnishings as called for in 125000.I311-I314 125000

Please confirm it is intended for the GC to purchase & install workstation furniture/furnishings shown in the referenced drawings/specs.

N/A 15F067-19-R0000004 0007 RMACC - Section C.15

Please issue or advise where applicable liquidated damages for this task order are located.

N/A 15F067-19-R0000004 0007 RMACC - Section H.27

Please advise if the contractor is responsible for costs related to registering and obtaining certification for LEED Silver or if the contractor should only include associated construction costs and administrative overhead for compiling the required documentation.

N/A 15F067-19-R0000004 0007 RMACC - Section C.14

Please confirm contractors have the option to propose an alternate performance period. If so, will the maximum allowed period be 600 calendar days or does the contractor have the option to provide reasoning within the proposal schedule/narratives to justify a longer duration if (after extensive review and schedule analysis) it is determined that it is the most likely outcome.

N/A

N/A N/A

The TEDAC Phase 4 drawings and specifications appear to be a full design. Please confirm the Government will accomplish the 100% design for this project and contractor is not required to carry any design fees in our price proposal.

RFP L.21.1.7.1

This section notes schedule requirements for Design After Award. Please confirm the information in this section does not apply to the TEDAC Phase 4 seed project.

N/A

15F067-19-R0000004 0007 RMACC - Clauses Incorporated by Reference

FAR 52.236-1 states "Twenty Percent (25%)". Please clarify the minimum amount of work to be self performed by the contractor.

N/A N/A Are we allowed to begin work at the loading dock area (Phase 2) before the new egress door is installed at the existing building (Phase 1)?

N/A

15F067-19-R0000004 0007 RMACC - Section L21.1.6

In document 15F06719R0000004_Amendment_0007_26JUL19Final Section L.21.1.6 VOLUME III - TAB C WORKFORCE/PROJECT TEAM, Lead Architect is listed. Is a resume for the Lead Architect required for the Region 1 proposals since the seed project is DBB?

N/A 15F067-19-R0000004 0007 RMACC - Section G.3

Please confirm the statement reading "Customary progress payments at standard uniform percentages of total costs are authorized to be made in accordance with Section I Contract Clauses, FAR 52.232-5 hereunder in accordance Section I Contract Clauses, FAR clause 52.232-17 Progress Payments" should reference FAR clause 52.232-5 as 52.232-17 references interest due associated with contractor payments to the Government and not progress payments.

N/A 15F067-19-R0000004 0007 RMACC - Section H20.2

Please confirm the minimum amounts listed for the Project Executive and Lead Project Manager of $75 million are aggregate and not single project amounts.

15F067-19-R0000004 0007 RMACC - Section H35 & 01 80 00

Please clarify if the contractor is to include all commissioning in accordance with Section 01 80 00 in the base bid or if commissioning shall be an option as referenced in RFP H.35

N/A 15F067-19-R0000004 0007 RMACC - Section G.3

9. Section G.3 notes that ‘Contractors are not permitted to invoice for Subcontractor costs until the Subcontractor(s) cost have been paid by the prime contractor.’. FAR 52.232-5 included in the solicitation requires the contractor to certify that ‘All payments due to Subcontractors from previous payments received under the contract have been made, and timely payments will be made from the proceeds of the payment covered by this certification,…’. Please confirm FAR 52.232-5 should govern and the contractor will be allowed to bill for progress payments including work performed by subcontractors in the same payment period so long as certification of timely payment for all previously billed work is provided.

51 Noted. Please identify any specific conflicts that need resolution in order to effectively complete your proposal. See Amendment 0009

The Offeror shall submit six (6) hardcopies of the proposal, one (1) original and five (5) copies, and one

(1) electronic CD or DVD with company proprietary, security, and other proposal markings as specified in the solicitation no later than 10:00 a.m. CST on August 26, 2019. Hand delivery is permitted for Region 1 only Phase II proposals only. See Amendment 0009; paragraph L.17.8.1. Region 1.

The Offeror shall submit six (6) hardcopies of the proposal, one (1) original and five (5) copies, and one

(1) electronic CD or DVD with company proprietary, security, and other proposal markings as specified in the solicitation no later than 10:00 a.m. CST on August 26, 2019. Hand delivery is permitted for Region 1 only Phase II proposals only. See Amendment 0009; paragraph L.17.8.1. Region 1.

This will be addressed in a forthcoming amendment to the Region 1 TORFP.

Barbwire is not required for construction temp fencing.

56 The Security and FBI Construction Trailers mentioned in the CSP are not applicable. These trailer leases are by others.

The Security and FBI Construction Trailers mentioned in the CSP are not applicable. These trailer leases are by others.

58 Key personnel can get approval from FBI Security to carry devices. PED approved devices can be on the job site. Unapproved PED's are not allowed on the job site.

Any CCTV will be installed by the FBI.

Security Personnel are provided by the FBI.

Paragraph L.21.1.6 addresses key personnel required at the overarching IDIQ contract level. Additional on-site personnel will be identified at the TORFP level as required.

Offerors shall use the Pricing models attached to the TORFP letters.

Other equal manufacturers will be allowed.

See specification 123553 (Metal Laboratory Casework), ceiling service panels are described under 2.11

65 Provide black epoxy pegboards matching those in the existing building, except for trace exam labs.

Provide SS pegboards for trace exam.

Other equal manufacturers will be allowed

N/A RFP

The RFP contains conflicting information and incorrect cross-references too numerous to list. Please ensure accuracy of all attachments and related cross-references and consider re-issue of the RFP as necessary.

N/A N/A RFP Document page 26 lists out key personnel required for the project. Of the six

(6) named personnel, please confirm which are required to be onsite full time.

N/A N/A

There are multiple references to Attachment 9 Pricing Model to be submitted in Volume IV of proposal. In the provided documents, the Pricing Model is found in Attachment 12. Please confirm attachment 12 price model is the correct form to use.

N/A N/A Please consider permitting submission of the electronic proposal (CD) within 24 hours of the proposal due date.

N/A 28 31 11

28 31 11 lists Simplex as the only Fire Alarm provider. Please clarify that the intent is to sole source the fire alarm system to Simplex or if alternate manufacturers will be allowed.

N/A N/A

Please consider permitting email submission of Attachment 12 Price Model Template. This would better enable offerors to ensure timely submission of the balance of the proposal via delivery service or hand delivery.

N/A 115313

115313 lists Labconco Corporation as the only fume hood provider. Please clarify that the intent is to sole source the fume hoods to Labconco or if Mott Manufacturing or other sources will be allowed.

N/A Exhibit 3

Reference Exhibit 3 Construction Security Plan - Document references to have barbwire on temporary fence if in an area that allows barbwire. Please clarify if our temporary construction fence is to include strands of barbwire.

N/A Exhibit 3

Reference Exhibit 3 Construction Security Plan - Document references the Access Control Facility trailer. Please confirm the ACF trailer is to be provided by the GC for this project.

N/A Exhibit 3 Reference Exhibit 3 Construction Security Plan - If ACF trailer is confirmed to be included in our scope - please provide data/comm requirements for the trailer.

N/A Exhibit 3

Reference Exhibit 3 Construction Security Plan - Document notes that no phones, iPads, or laptops are allowed on the construction site. Please consider waiving this requirement for approved key personnel on the project.

N/A Exhibit 3 Reference Exhibit 3 Construction Security Plan - Please confirm CCTV for site during construction will be furnished, installed, and maintained by FBI.

N/A Exhibit 3 Reference Exhibit 3 Construction Security Plan - Confirm all security personnel (permanent and temporary) are provided by FBI.

N/A N/A Please clarify if the ceiling service panels are to be supplied with cutouts only or with service valve disconnects and hoses

N/A

N/A

N/A Please clarify if the pegboards/drying racks are to be stainless steel or epoxy

125000a

125000a lists Teknion and Herman Miller as furniture manufacturers. Please clarify that the intent is to sole source these items to Teknion and Herman Miller or if Steelcase and other equal manufacturers will be allowed.

CMU wall to be minimum 10" thick.

Schedule sheet P700 covers laboratory trim fittings on the Laboratory Trim Fittings Schedule (designations T-1 to T-4)

69 The sinks are specified under lab casework however lab faucet is called out on plumbing schedule, see sheet P700.

This is confirmed. All units shown on the plumbing plans shall be provided.

No. Power reel is only required where shown on the Reflected Ceiling Plans.

Provide black epoxy countertop matching that in the existing building, unless otherwise noted. FBI to confirm.

If referring to Attachment 21OCONUS General Requirements and Provisions Division 00 01 00, that attachment is for OCONUS requirements and is not applicable to the Region 1 requirement. Please review the Specifications attached to the TORFP letter.

Yes, the complete design provided for the seed project is considered to be in compliance with all the requirements.

Attachments applicable to the Seed Project are identified in the TORFP letter. You should follow the Specifications attached to the Region 1 TORFP letter.

The TORFP letter(s) will be amended to add applicable liquidated damage amount(s).

Refer to paragraph L.20 Proposal Content and Organization and subsequent paragraphs thereafter. See revised language in Amendment 0009.

N/A 123553.13-2.14

123553.13-2.14 refers to Division 22 for the water and laboratory gas service fittings. Spec 226113 shows gas fittings and piping as an assembly by the plumbing contractor. Please clarify that this is correct. If not, please provide the the gas fixture specification, model numbers and options

N/A 123553.13-2.14

123553.13-2.14 Please clarify who is to supply the lab faucets. If the lab casework contractor is to supply, please provide laboratory faucet specification, model numbers and options to supply correctly.

N/A 224500 Please confirm that all of the emergency showers and eyewashes are to be included in the plumbing scope of work.

A214; A701 & A918 N/A

The floor plan on A214 shows all CMU walls to be 8" thick. The cut section of this area shown on 1/A701 shows some of these CMU walls to be +/- 30 ft tall. The table shown on 10/A918 "Typical Min. wall reinforcing for non-load bearing walls" gives the max vertical span of an 8" CMU wall to be 25'. Please adivse if CMU wal dimensions should be changed in areas that exceed 25' high.

N/A General Requirements & Provisions for RMACC 01 81 13.01

Paragraph 1.1 states "This project is required to meet all FBI sustainable design and construction requirements included in this section…." Please confirm the complete design for the Seed project is in compliance with all requirements of this section.

N/A RFP Attachments

Please provide a complete listing of RFP attachments to assist with confusion in the provided documents. For instance, The file named "15F06719R0000004_007 Atch_21_OCONUS_Gen_Reqmts&Prov_Div1" is labeled in the document as Attachment 7 and appears to apply to CONUS in lieu of OCONUS. Additionally, Section C.9 of Amendment 7 indicates that CONUS General Requirements and Provisions should be Attachment 22 and is to be provided on a task order basis.

Please provide attachment 22 to be used for the Seed project.

N/A N/A

Reference C.15 LIQUIDATED DAMAGES of the agreement within Amendment

7. "Liquidated damages, when applicable, will be identified at the TO level." As there are no liquidated damages provided for the seed project, please confirm they are not applicable or provide the amount.

B902 N/A B902 Detail 4 shows a double ceiling service panel/hose reel assembly. Please clarify that every CSP as shown on the RCPs receives both panels (with reel).

N/A 123553.13-2.6-B-4

123553.13-2.6-B-4 states epoxy color shall be selected by the Government. Sheet B001 states all tops to be black u.n.o. black is standard. All of the other approximately 15 colors carry varying degrees of upcharge in price. Please clarify if a specific color has been selected.

N/A General Requirements & Provisions for RMACC 01 45 00.00

Section 01 45 00.00 of the General RMACC document states in paragraph 3.4.4 state that QC Specialists with no other duties are required for the following disciplines: Civil, Mechanical, Electrical, Structural, Architectural, Test and Balance, As Built Documents, and Commissioning. Please confirm that all of these positions do not apply to EVERY task order and that task order personnel requirements are determined on a task order basis.

N/A N/A

The solicitation requires offerors to provide a copy of "the contract" to the Government as part of the proposal response. The solicitation documents have many components and associated addendum(a). Please consider providing a table of contents, summary outline or other comprehensive listing identifying the solicitation, construction documents and all elements that make up "the contract".

This summary can provide certainty to the Government that the offerors understand the wholeness of the scope and requirements.

The Offeror shall submit six (6) hardcopies of the proposal, one (1) original and five (5) copies, and one

(1) electronic CD or DVD with company proprietary, security, and other proposal markings as specified in the solicitation no later than 12:00 p.m. CST on August 26, 2019. Hand delivery is permitted for Region 1 only Phase II proposals only. See Amendment 0009; paragraph L.17.8.1. Region 1.

Per FBI direction, the accessories in question are to be Government Furnished Contractor Installed (GFCI). The basis of design was supplied by the FBI.

TA accessory to be added to drawings in a future amendment.

Display cases are to be millwork as detailed.

Toilet partitions are to be ceiling-hung .

Per typical corridor elevation 1/A604 and detail 8/A920, wall guards and abuse-resistant are wall coverings are depicted within the lab corridors. Finish plans starting at I211

84 No, refer to sheets, A111, A211, A212, A213 and A214 for fire extinguisher information. Refer also to the specifications for fire extinguisher requirement. While not located in the plans, fire extinguishers are required for back of house spaces and shall be provided in compliance with requirement of AHJ.

85 Manually operated spacesaver system to be provided in HD STORAGE (FILE) 3122, note added and sheet I313 will be issued with a future amendment. Locations for shelving units are noted in the B210's plans.

Laptop lockers are only located in the Entry Vestibule as called for in detail 3/A401.

Paragraph G.3 is revised. See Amendment 0009

See Amendment 0009 revised paragraph H.45 Non-local/Foreign Travel, Region 3 only.

No casework specialties in 3800, 3801 and 3802.

30-Aug-19

N/A

B214.4a, B606

Amendment 7, H.45

Amendment 7, Paragraph H.45 lists requirements for detailed billing and substantiation of travel costs. Please confirm this paragraph does not apply to firm fixed task price task orders.

N/A Please specify what casework/specialties are to be included in 3710, 3711, 3712, 3800, 3801, and 3802 as no details or tags are provided for these rooms.

N/A

B11-1a, B212-2a, B213-3a and B214-4a show locations for Bracket Mounted Fire Extinguishers. Please clarify that these are the only fire extinguishers to be provided.

105626

Regarding spec 105626 Mobile Storage Shelving: There are no shelving units or manually operate spacesaver systems labeled on plans. Please clarify that this is correct.

N/A Please Clarify that there are no other laptop lockers other than those that are shown on A401 detail 3

Amendment 7, G.3

Amendment 7, Paragraph G.3 states that subcontractor costs can not be included in the prime contractor’s invoice until the subcontractor costs have been paid by the prime. This is an extreme variance from construction industry standard practice and is in conflict with the Prompt Payment Act which allows prime contractors 7 days from the receipt of payment by the government to pay subcontractor billings. Please confirm that the FBI intends to follow the provisions of the Prompt Payment Act for this MACC.

N/A RFP

A submission deadline of 10:00 AM on a Monday, with a requirement to utilize a delivery service (FedEx, UPS), puts an undue burden on offerors as packages would need to be send the previous Friday for first AM delivery the following Monday and late delivery - which we have no control over - renders an offeror ineligible for award. Please consider pushing the due date to 4:00 PM on Tuesday, August 27. If this is not possible please consider pushing due time offers are due to 4:00 PM on August 26. If these options are not possible please consider accepting hand-delivered offers at the Redstone Arsenal Gate 9 Visitors Center at the currently scheduled due date and time.

A451

A451

A601

A602

A920

B211-1a, B212-2a, B213-3a, B214-4a

N/A

A401

N/A

N/A Please indicate the anticipated date that the FBI will receive final, stamped IFC (Issued for Construction) documents from the designer of record.

102800

102800 states that TA-1A, TA-3, TA-5, and TA-6 are not in contract and to be supplied by the owner; however drawing A451 specifies a vendor. Please clarify who is to supply these items. Please clarify the basis of design for TA-5, as there is no 3500 series for napkin vendors.

102800 A451 does not show any TA-6B Toilet Seat Cover Dispensers. Please clarify this is correct.

101200

101200 calls for pre-manufactured display cases. Please clarify if these are for display cases in lobby 3007. Drawing A609, detail 9 calls for these cases to be custom millwork. Please clarify which method is to be used.

102113

Spec 102113 3.2B calls for Ceiling-Hung Partitions. However the interior elevations on A602 do not depict this. Please verify that they are to be ceiling hung.

With 10' ceilings, some floor to ceiling pilasters or crossbracing may be required.

102600

Spec 102600 lists wall guards, corner gauds and abuse-resistant wall coverings.

Drawing A920 only shows W-3 as wall coverings. Corner Guards and Wall Guards are not on finish schedule or finish plans. Please clarify that this is correct.

N/A

Disclosure of other shortlisted firms and site visit attendees is not intended.

The Price Model Attachment is revised to read Attachment 19. However, see all applicable revised language in Amendment 0009.

93 Refer to Section L.22 of Amendment 0009. This information is requested to support the unbalanced line item costs/prices and to conduct negotiations, if necessary.

This Multiple Award Contract spans multiple regions, and includes multiple project delivery methods;

therefore some of the language in the solicitation is broadly addressed. However, the TEDAC ETL Region 1 Seed project is fully designed and a Design Bid Build project delivery method is most applicable.

The requirement for establishing a PLA and FAR clauses 52.222-33 and 52.222-34 are removed. See Amendment 0009.

The self perform requirement is twenty-five (25%). See Amendment 0009.

97 The Offeror shall submit six (6) hardcopies of the proposal, one (1) original and five (5) copies, and one

(1) electronic CD or DVD with company proprietary, security, and other proposal markings as specified in the solicitation no later than 12:00 p.m. CST on August 26, 2019. Hand delivery is permitted for Region 1 only Phase II proposals only. See Amendment 0009; paragraph L.17.8.1. Region 1.

No. Disclosure of other shortlisted firms is not intended.

The Offeror shall submit six (6) hardcopies of the proposal, one (1) original and five (5) copies, and one

(1) electronic CD or DVD with company proprietary, security, and other proposal markings as specified in the solicitation no later than 12:00 p.m. CST on August 26, 2019. Hand delivery is permitted for Region 1 only Phase II proposals only. See Amendment 0009; paragraph L.17.8.1. Region 1.

Offerors that are awarded RMACC IDIQ contracts shall compete amongst other Offerors within their specific Regions for award of TO contracts.

Yes, there is approximately 22,000 CYs of structural fill material stockpiled south of the ETL on site.

N/A N/A

The Phase II Task Order Request for Proposal (TORFP) for Region 1 states this project is a Firm-Fixed Price and requests that the pricing be provided on Attachment 3 Supplemental Bid Request however Phase II evaluation factors state Factor 3 should be provided with Attachment 9 Pricing Model. Please confirm what documentation is required for Factor 3 Volume IV Price and Pro Forma Information. If Attachment 9 is required please confirm this is the same as 15F06719R0000004_0007,_Atch_12_Price_Model_Template.xlsx provided in Amendment #7.

N/A

N/A

N/A

The Phase II Task Order Request for Proposal (TORFP) for Region 1 states this project is a Firm-Fixed Price. If the project is Firm-Fixed Price what is the intent of the Pricing Model cost breakdown?

The Phase II Task Order Request for Proposal (TORFP) for Region 1 states this project is a Firm-Fixed Price Design Build (DB) Construction Scope however the drawings and specifications appear to be fully designed. Is the Explosive Technical Laboratory (ETL) – Terrorist Explosive Device Analytical Center (TEDAC) Phase IV design build? If so, what is the design build responsibility for this project?

52.222-33 Notice of Requirement for Project Labor Agreement (PLA) was added to the RFP requirements which states "The apparent successful offeror shall negotiate a project labor agreement with one or more labor organizations for the term of the resulting construction contract." Is a PLA is required for (TEDAC) Phase 4 – Explosives Technical Laboratory (ETL) project? If so, can you explain what you are looking for regarding the PLA on this project and if the pricing proposal shall be provide with a PLA and Non PLA price.

52.236-1 Performance of Work by the Contractor states two self-performed percentage goals. In words 52.236-1 states "Twenty Percent" however the percentage listed is "25%". Is the self-perform requirement 20% or 25%?

Since our submission will need to be delivered on a secure site at 10:00 am CST, can we email our submission on August 26th by 10:00 am CST and mail the hard copies out the next business day?

N/A

N/A

Can you let us know who the other shortlisted firms are?

Due to the security processes, there will be a substantial amount of time that the subcontractors do not have access the contract documents. As a result, we request that the RFI deadline be extended two additional weeks to allow time for subcontractor review. Please advise if the RFI can be extended an additional two weeks.

N/A

N/A

N/A

N/A

N/A

N/A

N/A

Amendment #7 Page 45 of 100 & Page 46 of 100

Amendment #7 Page 47 of 100 / Page 43 of 100

N/A

During the Pre-Proposal Conference, all participants were told to provide a Best Value Acquisition firm fixed price (would be in Volume IV). Will the team that is awarded the Task Order be the prime team for the RMCC on the other projects that comprise the Region 1 IDIQ?

Please confirm that the structural fill stockpiled south of the site (about 1000 yards), which was described as for this project in the pre-proposal conference, is enough for the needs of this project as was stated in the preproposal conference.

20,000 cubic yards was the volume stated as stockpiled.N/A

N/A

N/A

N/A N/A Please provide a roster of attendees from the site visit.

3 months after NTP. Estimated 31 Jan 2020.

103 Refer to the North Site Infrastructure drawings, that show the location of the water distribution. GC to work this temp utilities plan per spec 015000 - 3 TEMPORARY FACILITIES AND CONTROLS.

FBI will provide modifications necessary for the security systems

FL-231 is similar to FL-230 but 6'-0" w.

The Government will provide an authorization letter

Provide workstation with ML72a2. Refer to plumbing documents for the utility sink in room 3710.

They are Owner Furnished and Installed

109 F-1 to F-6 at the bottom of the Interior Finish Legend on I001 is upholstery only for furnishings in respective spaces as designated under the "Notes" portion of the legend.

The system assembly is as specified by Novawall, however the fabric attached to the fabric wall panel assembly is by Carnegie.

A detail for the niche will be supplied in a future amendment, TA-19 to be eliminated.

A deluge sprinkler system is not required for the project.

Yes, The 15F067-19-R0000004 Regional Multiple Award Construction Contracts, Phase II Task Order Request for Proposal (TORFP) for Region 1, Seed Project letter will be revised to include a Justice Enterprise File Sharing (JEFS) request form, which uses the Box application.

Details 15 & 16 updated in Amendment 8, and yes they are identical to those in 2/A602.

Provide ETL-3f.

Benches in restrooms are to be 42".

Please refer to A600 series.

Sheets to be issued in Amendment 0009 with updated callouts in a future amendment.

Reference to be removed from B221.1a and B222.2a. Refer to A600's for lab elevations

H01F728 with BVA26/363622 and BFL26/363622.

Provide TA 4230b.

When will the “POV” parking lot be available for construction parking use relative to the issuance of Notice to Proceed? (x Months after NTP)

97713

102800

Division 21

N/A

N/A

N/A

N/A

N/A

Please provide a Furniture Specification sheet for item FL-231.

Where is the water connection for construction activities located?q g g ( areas), will the FBI be disconnecting the security systems for these rooms when tie in with new security is required or is this expected of the contractor?

Please advise if GSA Schedule pricing can be used for the Furniture.

Drawing B214.4a shows four locations of benches/casework in the Large Case rooms, but there are no elevations or details. Please provide additional information about these locations.

Please confirm that the Single and Double Door Refrigerators / Freezers shown under Misc Equipment on sheet B001 are Owner Furnished and Installed.

N/A

12500

12500

N/A

N/A The interior finish schedule calls out Fabric panels F-1 to F-4 manufactured by Carnegie however it also lists fabrics F-1 to F-6 by a variety of manufacturers.

Please clarify the extent of Fabric Panels vs Fabric as they use the same material tags.

Drawing 15,16/A602 calls out scheduled lockers but there are no lockers shown.

Please confirm that the scheduled lockers on 6/A602 are identical to drawing 2/A602.

The detail callouts on drawing A401 do not match the details on A601. Please clarify.

I001

A451

N/A

N/A

B211.1a B602

A111 A602

A211

Drawing I001 calls out stretched fabric wall panel F-1 to F-4 and states that the manufacturer is Carnegie. However, in spec 097713, it calls out the Novawall system. Please clarify which manufacturer shall be used for the fabric wall panels in Specification 097713.

The toilet accessory schedule calls out TA-19. However, there is no information provided in spec 102800. Please provide.

Please confirm the fire suppression sprinkler system does not include a deluge system.

Item 5) of the Non-Disclosure Agreement states that "These documents may not be transmitted over the internet in any form nor be installed on a system connected to a wide area network." Distributing the documents through hand delivery or mail delivery of USBs and/or CDs will require a large amount of time, therefore limiting the exposure the subcontractors have to the documents for review and pricing. As a result, we suggest using Box, which is a secure platform, to distribute the documents. In addition to password protecting the contract documents, the Box folder will be configured so that only named individuals who have been authorized, and have submitted a signed the NDA can access and download the documents.

Please advise if Box can be used for document distribution as described.

Please identify the table in the center of Room 3209 Office.

The locker room benches shown on drawing A111 are 3'-6" long and the benches shown on detail 2/A602 are 3' long. Please confirm that the benches in detail 2/A602 are to be used. g phone and laptop lockers however an elevation of these is not provided. Please provide an elevation or quantity of cell phone and laptop lockers to be provided.

I001

A602

A401 A601

N/A

N/A

N/A

A401

N/A

N/A

N/A

N/A

N/A

N/A

B214.4a B606

B001

B611 was not issued. Please issue drawing B611 or confirm these elevation references should be removed.

not labeled. Please confirm if these should be H01F72B, BFL26 / 363622, and

BVA26 / 363622.

Please identify the table in the center of Room 3704 ALS/RUVIS.

B211.2a B611 B212.2a B604

B212.3a

N/A

Provide EB-2b, as shown in similar elevation 11/B602 for island bench.

Gas meter will be located on the exterior of the building. Plumber to pick up gas service 5' outside of the building and provide the meter and PRV assembly on the exterior of the building. Gas meter shall communicate with the BAS system.

Laboratory equipment includes, fumehoods, point of use polishers and dishwashers

Per B212.2a Microcontroller/Memory 3403 is to have RF shielded walls, door, floor and ceiling lid. The MEP penetrations into the room do not require filtering per FBI request, that is why Room 3403 is not included in the Radio Frequency (RF) Shielded Room Accessories tables.

While 28 ga. galvanized shielding would provide much higher attenuation levels, those levels are not necessary…