Compilation_Addendum_1.pdf
PDF 9 MB Posted
- Attached to
- Fort Yuma Health Care Center
- Solicitation number
- 15-102-SOL-00009
About this file
Compilation Addendum 1
View the file
Other files
Show 40 more
Latest 50 of 59 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INTENT: IF CERTAIN FEATURES ARE NOT FULLY SHOWN OR
CALLED FOR ON THE DRAWINGS OR SPECIFICATIONS, THEIR
CONSTRUCTION SHALL BE OF THE SAME CHARACTER AS
FOR SIMILAR CONDITIONS THAT ARE CALLED FOR.
FOR DETAILS, LOCATIONS AND NUMBER OF INSERTS,
EMBEDDED ITEMS, EQUIPMENT SUPPORT PADS, EQUIPMENT
ANCHOR BOLTS AND SIMILAR ITEMS, REFER TO
ARCHITECTURAL AND MECHANICAL DRAWINGS.
A. ASTM A992M GRADE 345 FOR ALL WIDE FLANGE STEEL
SHAPES.
B. ASTM A36M GR 250 FOR ALL STRUCTURAL AND
MISCELLANEOUS STEEL CHANNELS, ANGLES, BARS,
PLATES, AND CONNECTIONS UNLESS NOTED
OTHERWISE.
C. ASTM A500M GRADE B Fy = 320MPa FOR ALL
STRUCTURAL TUBING.
D. ASTM A53M, TYPE E OR S, GRADE B Fy = 240MPa FOR
ALL STRUCTURAL PIPE.
E. ASTM A325M TENSION CONTROL BOLTS, UNLESS
SPECIFICALLY NOTED OTHERWISE, WITH SIZES AS
SHOWN ON DRAWINGS. ALL BOLTS SHALL BE
TIGHTENED SO AS TO SHEAR THE SPLINE OFF THE
BOLT. WHERE CLEARANCES DO NOT PERMIT, USE
STANDARD A325M BOLTS, TIGHTENED AND INSPECTED
IN ACCORDANCE WITH THE AISC "SPECIFICATION FOR
STRUCTURAL JOINTS USING ASTM A325M OR A490M
BOLTS."
F. ASTM F1554 GRADE 250 FOR ALL ANCHOR RODS
EMBEDDED IN CONCRETE, UNLESS NOTED OTHERWISE
IN DRAWINGS. PROVIDE FLAT WASHERS BETWEEN ALL
NUTS AND BASE PLATES.
G. ALL WELDING SHALL COMPLY WITH THE LATEST
EDITION OF THE AWS STRUCTURAL WELDING CODE.
ALL REINFORCING STEEL SHALL BE FABRICATED AND
PLACED IN ACCORDANCE WITH THE BUILDING CODE
REQUIREMENTS FOR REINFORCED CONCRETE (ACI 318)
AND THE STANDARD MANUAL (ACI 315).
USE ASTM A615M GRADE 420 FOR ALL REINFORCING
STEEL. USE ASTM A185M GRADE 420 FOR ALL WELDED
WIRE FABRIC. PROVIDE IN FLAT SHEETS ONLY.
LAP WIRE FABRIC TWO FULL MESH PANELS AND TIE
SECURELY.
ALL REINFORCEMENT SHALL BE CONTINUOUS. STAGGER
SPLICES WHERE POSSIBLE. LAPS FOR SPLICES SHALL BE
AS INDICATED ON SHEET S501, UNLESS OTHERWISE
SHOWN OR NOTED.
F'c = 30 MPa (NORMAL WEIGHT, AIR ENTRAINED) ALL
EXPOSED CONCRETE FLATWORK AND RETAINING WALLS
F'c = 25 MPa (NORMAL WEIGHT, AIR ENTRAINED) ALL
FOUNDATION CONCRETE (FOOTINGS, TIE BEAMS, STEM
WALLS, GRADE BEAMS)
F'c = 35 MPa (NORMAL WEIGHT) ALL POLISHED SLABS
F'c = 40 MPa AT 28 DAYS FOR NON-SHRINK GROUT FOR
PLACEMENT UNDER COLUMN BASE PLATES. GROUT TO
COMPLY WITH ASTM C1107.
F'c = 35 MPa FOR ALL PRECAST CONCRETE
A SUBSURFACE GEOTECHNICAL INVESTIGATION HAS BEEN
PERFORMED BY NICKLAUS ENGINEERING, INC (NEI). A
REPORT OF THIS INVESTIGATION DATED JUNE 26, 2015
AND NUMBERED 015-0098 IS AVAILABLE.
IMPORTANT ADDITIONAL INFORMATION CONCERNING
SPECIFIC SOIL CONDITIONS IS CONTAINED IN THIS REPORT
AND SHALL BE REVIEWED PRIOR TO START OF
CONSTRUCTION.
THE GEOTECHNICAL INVESTIGATION REPORT CONTAINS
SPECIFIC REQUIREMENTS CONCERNING CLEARING AND
GRUBBING, SITE, SUBFLOOR AND BEARING SURFACE
PREPARATION, STRUCTURAL FILL REQUIREMENTS, AND
COMPACTION REQUIREMENTS NOT NECESSARILY SHOWN
ON THESE DRAWINGS. REFER ANY CONFLICTS BETWEEN
THESE DRAWINGS AND THE REPORT TO THE
ARCHITECT/CONTRACTING OFFICER'S REPRESENTATIVE
FOR DIRECTION PRIOR TO BEGINNING ANY WORK.
CONTRACTOR SHALL EMPLOY THE SERVICES OF A
REGISTERED, LICENSED GEOTECHNICAL ENGINEER TO
OBSERVE ALL CONTROLLED EARTHWORK. THE
GEOTECHNICAL ENGINEER SHALL PROVIDE CONTINUOUS
ON-SITE OBSERVATION BY EXPERIENCED PERSONNEL
DURING CONSTRUCTION OF CONTROLLED EARTHWORK
AND SOIL SPECIAL INSPECTION WORK NOTED ON S002.
NOTIFY THE GEOTECHNICAL ENGINEER AT LEAST TWO
WORKING DAYS IN ADVANCE OF ANY FIELD OPERATIONS
OF THE CONTROLLED EARTHWORK. A REPRESENTATIVE
OF THE GEOTECHNICAL ENGINEER SHALL BE PRESENT TO
CONFIRM THE COMPLETE EXCAVATION OF ANY
UNCONTROLLED FILL.
4.80
4.80
3.80
7.2
PER CODE
4.80
1.0
0.25
DEAD LOADS - BUILDING IS DESIGNED FOR THE ACTUAL
IN-PLACE WEIGHTS OF ALL MATERIALS SHOWN ON THE
CONSTRUCTION DOCUMENTS. DEAD LOADS IN ADDITION
TO STRUCTURE SELF WEIGHTS ARE NOTED BELOW.
ADDITIONAL DEAD LOADS INCLUDE ARCHITECTURAL
FINISHES, MECHANICAL & SUSPENDED EQUIPMENT.
DESIGN LOADS:
FIRST FLOOR CORRIDORS
STAIRS
STORAGE AREAS
MEDICAL FILE STORAGE, AREA D
CONCENTRATED FLOOR LOAD
REDUCTION FACTOR, R
MECHANICAL ROOMS
ROOF AREAS A,BC,D & E
ADDITIONAL SUPERIMPOSED LIVE LOADS:
SUSPENDED EQUIPMENT
THE FOLLOWING CRITERIA COVERS THE STRUCTURAL DESIGN
OF THIS BUILDING STRUCTURE.
CODES AND MANUALS - MOST STRINGENT OF:
INTERNATIONAL BUILDING CODE, 2015 EDITION.
AISC MANUAL OF STEEL CONSTRUCTION, 14th EDITION, LRFD.
STEEL JOIST INSTITUTE STANDARD SPECIFICATIONS,
LOAD TABLES AND WEIGHT TABLES FOR STEEL JOISTS
AND JOIST GIRDERS.
AISI COLD FORMED STEEL MANUAL.
ACI BUILDING CODE REQUIREMENTS FOR REINFORCED
CONCRETE. ACI 318 - 14.
BUILDING CODE REQUIREMENTS FOR MASONRY
STRUCTURES ACI 530/ASCE5 / TMS 402.
AISC SEISMIC DESIGN MANUAL, AISC 341-10.
1.50
1.05
SEE DRAWINGS OTHER THAN STRUCTURAL FOR KINDS
OF FLOOR FINISH AND THEIR LOCATION, DEPRESSIONS
IN FLOOR SLABS, OPENINGS IN WALLS AND FLOORS
REQUIRED BY ARCHITECTURAL FEATURES, WALKS,
RAMPS, STAIRS, CURBS, ETC.
HOLES AND OPENINGS THROUGH WALLS, BEAMS, AND
FLOORS FOR DUCTS, PIPING AND VENTILATION SHALL
BE CHECKED BY THE CONTRACTOR, WHO SHALL
VERIFY SIZES AND LOCATIONS OF SUCH HOLES OR
OPENINGS WITH THE PLUMBING, HVAC AND ELECTRICAL
DRAWINGS AND THESE SUB-CONTRACTORS.
SEE ARCHITECTURAL DRAWINGS FOR WALLS NOT
SHOWN ON STRUCTURAL DRAWINGS.
DISCREPANCIES: COORDINATE STRUCTURAL DRAWINGS
WITH OTHER DRAWINGS FOR INDIVIDUAL ITEMS.
DISCREPANCIES UNCOVERED, IF ANY, SHALL BE
REPORTED TO THE ARCHITECT/CONTRACTING
OFFICER'S REPRESENTATIVE BEFORE PROCEEDING
WITH THE WORK.
TYPICAL EDGE OF STRUCTURE / SLAB IS SHOWN ON THE
STRUCTURAL DRAWINGS. CONTRACTOR TO
COORDINATE LOCATIONS, DIMENSIONS AND
ELEVATIONS WITH ARCHITECTURAL EXTERIOR WALL
SECTIONS.
TYPICAL CURB DETAILS ARE SHOWN ON STRUCTURAL
DRAWINGS. CONTRACTOR TO COORDINATE
LOCATIONS WITH ARCHITECTURAL DETAILS.
DO NOT SCALE DRAWINGS FOR THE PURPOSE OF
DETERMINING DIMENSIONS.
ALL DIMENSIONS IN MILLIMETERS (mm) UNLESS NOTED
OTHERWISE.
COORDINATION WITH OTHER DRAWINGS:
EXISTING CONDITIONS:
GENERAL CRITERIA:
GENERAL NOTES:
REMOVE ALL MATERIAL THAT WILL INTERFERE WITH NEW
BUILDING FOUNDATIONS AND STRUCTURAL FILL AS PER
GEOTECHNICAL CONSULTANT'S RECOMMENDATIONS.
STRUCTURAL STABILITY:
A. THE STRUCTURE SHOWN ON THESE DRAWINGS HAS
BEEN DESIGNED FOR STABILITY UNDER FINAL, FULLY
CONSTRUCTED CONDITIONS.
B. PROVIDE SAFE AND ADEQUATE SHORING FOR ALL
PARTS OF THE STRUCTURE DURING CONSTRUCTION.
C. WHERE BACKFILL IS PLACED AGAINST WALLS, THE
WALLS SHALL BE BRACED OR OTHERWISE
ADEQUATELY SHORED UNTIL PERMANENT BRACING
ELEMENTS OR SLABS HAVE BEEN ERECTED AND HAVE
ATTAINED DESIGN STRENGTH.
MATERIAL CRITERIA
STRUCTURAL STEEL:
STEEL JOISTS:
NO CONSTRUCTION LOADS SHALL BE PLACED ON
UNBRIDGED JOISTS.
WHERE COLUMNS ARE NOT FRAMED IN AT LEAST TWO
DIRECTIONS WITH STRUCTURAL STEEL MEMBERS, JOISTS
AT OR CLOSEST TO COLUMN LINES SHALL BE FIELD
BOLTED TO PROVIDE LATERAL STABILITY DURING
CONSTRUCTION.
PROVIDE BRIDGING IN ACCORDANCE WITH THE LATEST
EDITION OF SJI STANDARD SPECIFICATIONS.
PLANS SEE DETAIL B3/S507.
PROVIDE 65mm MINIMUM BEARING ON STRUCTURAL STEEL
FOR K-SERIES JOISTS UNLESS GREATER LENGTHS ARE
SHOWN ON DRAWINGS.
IN THE INSTANCE WHERE A SUPPORT BEAM FLANGE IS
NOT WIDE ENOUGH TO ACCOMMODATE PROPER BEARING
FOR TWO JOIST SEATS, STAGGER JOISTS AS REQUIRED
TO ACHIEVE PROPER BEARING.
JOIST SIZES SHOWN ON DRAWINGS ARE BASED ON
UNINFORM GRAVITY LOADS. DESIGN JOISTS FOR UNIFORM
GRAVITY LOADS IN ADDITION TO OTHER LOADS (UPLIFT,
AXIAL LOADS, CONCENTRATED LOADS, MOMENTS, ETC.)
INDICATED ON DRAWINGS.
STEEL DECK:
ALL STEEL DECK SHALL BE FABRICATED AND ERECTED IN
ACCORDANCE WITH THE LATEST STEEL DECK INSTITUTE
SPECIFICATIONS.
SEE PLANS FOR STEEL DECK TYPE, GAGE, FINISH AND
CONNECTIONS.
PROVIDE 38mm MINIMUM BEARING AT ALL STEEL DECK
SUPPORT CONDITIONS.
ALL SPLICES AND LAPS SHALL BE A MINIMUM OF 50mm AND
SHALL BE CENTERED OVER SUPPORTS.
ALL STEEL DECK SHALL BE CONTINUOUS OVER THREE
SPANS WHEREVER FRAMING ALLOWS. SEE B2/S506 FOR
ADDITIONAL RESTRICITONS.
OPENINGS THROUGH STEEL DECK FLOORS AND ROOFS ON
FRAMING PLANS ARE NOT COMPLETE AS TO NUMBER, SIZE
AND LOCATION. FOR COMPLETE INFORMATION, REFER TO
DRAWINGS OTHER THAN STRUCTURAL.
PROVIDE STANDARD ACCESSORY MATERIALS, INCLUDING
BUT NOT LIMITED TO, CLOSURE STRIPS, POUR STOPS,
GIRDER FILLERS, ETC. ACCORDING TO SDI
RECOMMENDATIONS, TO PROVIDE TIGHT FITTING
CLOSURE AT OPEN ENDS AND SIDES OF DECKING.
AT ENDS OF DECKS OR WHERE CHANGES OF DECK
DIRECTION OCCUR FASTEN TO SUPPORTS AT EACH FLUTE.
PROVIDE ADEQUATE CLOSURES AND FASTENERS TO
SIDES AT 450mm ON CENTER, UNLESS STRICTER
REQUIREMENTS EXIST ON PLANS.
NOTHING WEIGHING MORE THAN 10 kg IS TO BE
SUPPORTED FROM THE METAL ROOF DECK UNLESS
SPECIFICALLY DETAILED IN THESE PLANS.
ITEMS WEIGHING MORE THAN 10 kg SHALL HAVE THEIR
OWN SUPPORT FRAMING OR THEY SHALL BE HUNG
DIRECTLY FROM THE MAIN FRAMING BEAMS. IT SHALL BE
THE RESPONSIBILITY OF EACH TRADE TO DESIGN A
SUPPORT SYSTEM FOR THEIR EQUIPMENT WHICH WILL
CONFORM TO THIS CRITERIA. DESIGN OF HANGERS AND
THEIR ANCHORAGES SHALL BE BY THE GENERAL
CONTRACTOR.
CONCRETE:
ALL CONCRETE WORK SHALL CONFORM TO THE LATEST
EDITION OF "SPECIFICATIONS FOR STRUCTURAL
CONCRETE," ACI 301.
ALL CONCRETE SHALL BE REINFORCED UNLESS
SPECIFICALLY NOTED "NOT REINFORCED."
STEM WALLS, GRADE BEAMS, AND RETAINING WALLS
SHALL NOT BE CAST AGAINST EXCAVATED VERTICAL
SIDE SURFACES.
CONTROL JOINTS IN SLABS ON GRADE SHALL BE
APPROVED WHERE NOTED ON PLANS, BUT SHALL NOT
EXCEED 36 TIMES THE MINIMUM SLAB THICKNESS OR 6
METERS.
LIMIT SITE AND RETAINING WALL POURS TO A MAXIMUM OF
12 m BETWEEN CONSTRUCTION JOINTS. CONTROL JOINT
SPACING IN WALLS SHALL NOT EXCEED HALF OF THE
SPACING BETWEEN CONSTRUCTION JOINTS OR 6 m. 13 mm
EXPANSION JOINTS IN RETAINING WALL SHALL BE PLACED
A SPACING NOT EXCEEDING 12 m. COORDINATE
LOCATIONS OF JOINTS WITH ARCHITECTURAL PLANS.
ALL ANCHOR RODS FOR STRUCTURAL COLUMNS MUST BE
SECURELY SUPPORTED IN POSITION PRIOR TO
PLACEMENT OF CONCRETE. INSERTING THESE BOLTS
INTO WET CONCRETE IS NOT ALLOWED UNLESS
SPECIFICALLY NOTED ON THE DRAWINGS OR APPROVED
IN WRITING.
PIPE AND CONDUIT WILL NOT BE PERMITTED TO BE INSTALLED
HORIZONTALLY IN SLABS WITHOUT PRIOR APPROVAL OF THE
ARCHITECT. ALL CONDUIT SHALL BE "SCRATCHED" INTO
GROUND BELOW VAPOR RETARDER.
AT INTERIOR SLABS-ON-GROUND OVER VAPOR RETARDER
USE CONCRETE THAT COMPLIES WITH THE FOLLOWING:
a. W/C=0.45 OR LESS. STRICT ADHERENCE TO THE
SPECIFIED WATER TO CEMENT RATIO IS REQUIRED.
WATER SHALL NOT BE ADDED TO THE MIX AT TIME OF
PLACEMENT.
b. DO NOT ADD EXTRA WATER. WATER-REDUCING
ADMIXTURES ARE PERMITTED TO ENHANCE
WORKABLILITY.
c. MOIST CURING OF SLABS ON GROUND IS REQUIRED.
SEE SPECIFICATIONS FOR MORE INFORMATION.
d. CARE SHALL BE TAKEN TO PREVENT WATER
INTRUSION INTO THE SUBGRADE BOTH PRIOR TO AND
AFTER SLAB POURS.
e. TIMING OF SLAB SAWCUT JOINTS IS CRITICAL TO SLAB
CURING PERFORMANCE. SAWCUT JOINTS FOR
CONTROL JOINTS SHALL BE MADE AT THE EARLIEST
POSSIBLE TIME THAT THE CONCRETE WILL SUPPORT
THE WEIGHT OF EQUIPMENT AND OPERATORS.
f. CONTROL JOINTS IN SLABS ON GRADE SHALL BE
PROVIDED WHERE NOTED ON PLANS, BUT SHALL NOT
EXCEED 36 TIMES THE MINIMUM SLAB THICKNESS OR
4 m MAXIMUM .
g. SEE SPECIFICATIONS FOR ADDITIONAL
REQUIREMENTS.
REINFORCING STEEL:
DESIGN CRITERIA:
DESIGN LOADS:
VERTICAL:
LIVE DEAD
kPa kPa kPa kPa kN kPa kPa kPa kPa kPa kPa kPa kN kPa kPa
HORIZONTAL:
WIND DESIGN DATA:
ANALYTIC PROCEDURE:
RISK CATEGORY
BASIC WIND SPEED (3 SEC. GUST)
WIND IMPORTANCE FACTOR, Iw
WIND EXPOSURE CATEGORY
INTERNAL PRESSURE COEFFICIENT
II
51 m/s
1.0
C
±0.18
EQUIVALENT LATERAL FORCE
PROCEDURE (ACSE 7-10)
EARTHQUAKE DESIGN DATA:
ANALYSIS PROCEDURE:
SOIL SITE CLASS
SPECTRAL RESPONSE ACCELERATIONS
SITE COEFFICIENTS
EARTHQUAKE SPECIAL RESPONSE
ACCELERATION PARAMETERS
SEISMIC IMPORTANCE FACTOR, I
SEISMIC DESIGN CATEGORY
SEISMIC FORCE-RESISTING SYSTEM:
RESPONSE MODIFICATION COEFFICIENT, R
Vmin.
V
Vmax.
= 0.044SDS IW ≥ 0.01W
= SDS W I/R
= SDI I W/(TR)
Ss =
S1 =
Fa =
Fv =
SMS =
SM1 =
SDS =
SD1 =
D
0.683
0.261
1.254
1.879
0.856
0.490
0.571
0.326
1.0
D
3.25
ORDINARY STEEL
CONCENTRICALLY
BRACED FRAMES
FOUNDATION NOTES:
GENERAL CRITERIA:
BASIS FOR DESIGN:
ALLOWABLE SOIL BEARING PRESSURE FOR FOUNDATIONS
SUPPORTING DEAD AND LIVE LOADS = 120 kPa
ALLOWABLE SOIL BEARING PRESSURE = 160 kPa. FOR
FOUNDATIONS SUPPORTING DEAD, LIVE, AND WIND OR
SEISMIC LOADS.
FIELD OBSERVATION AND TESTING REQUIREMENTS:
MATERIAL LARGER THAN 150mm SHALL NOT BE PLACED
NO BRUSH, SOD, FROZEN MATERIAL OR OTHER
UNSUITABLE MATERIAL SHALL BE PLACED IN THE
STRUCTURAL FILL. MATERIAL SHALL BE PLACED IN
SUCH A MANNER AS TO RESULT IN UNIFORMLY
COMPACTED FILL.
5. SELECT FILL SHALL CONSIST OF GRANULAR SOIL
THAT CONTAINS AT LEAST 40 PERCENT OF MATERIAL,
BY DRY WEIGHT, LESS THAN 1/4 INCH IN SIZE.
SELECT FILL SHALL NOT CONTAIN ROCK OR HARD
LUMPS GREATER THAN 75 MM IN MAXIMUM
DIMENSION. EXPANSION INDEX SHALL BE LESS THAN
20, LL LESS THAN 30, AND PI LESS THAN OR EQUAL TO
15.
COMPACTION REQUIREMENTS:
SUBGRADE SOILS AND STRUCTURAL FILL MATERIALS
SHALL BE COMPACTED TO THE FOLLOWING MINIMUM
PERCENTAGES OF THE ASTM D1557 MAXIMUM DRY
DENSITY AT +/- 2% OPTIMUM MOISTURE CONTENT.
MATERIAL PERCENT COMPACTION
STRUCTURAL FILL
SUBBASE FOR SLAB SUPPORT
MISCELLANEOUS BACKFILL
DESIGN BASE SHEAR: (IBC 2015)
LIGHTGAGE STEEL FRAMING SHALL MEET THE MINIMUM
PROPERTIES AS SHOWN IN THE STEEL STUD SCHEDULE.
ALL TRACK SHALL BE 32MM LEG, 1.088 mm THICK MINIMUM.
TRACK SHALL BE ANCHORED TO SLAB AND STEM WALLS
PER D5/S505, U.N.O. ON PLANS OR SECTION.
CONCRETE CAST AGAINST AND
PERMANENTLY EXPOSED TO EARTH:
CONCRETE EXPOSED TO EARTH
OR WEATHER:
COLUMNS AND BEAMS:
STRUCTURAL SLABS AND WALLS:
SLABS ON METAL DECK:
REINFORCING SHALL NOT BE TACK WELDED OR WELDED
IN ANY MANNER UNLESS SPECIFICALLY DETAILED ON THE
STRUCTURAL PLANS.
MINIMUM CONCRETE PROTECTION FOR REINFORCEMENT
(CLEAR DISTANCE):
75mm
50mm (#19 & LARGER)
40mm (#16 & SMALLER)
40mm
25mm
25mm
TYPICAL REINFORCEMENT UNLESS OTHERWISE SHOWN:
UP TO 200mm CONCRETE WALLS: #13 @ 200 mm O.C.
EACH WAY AT CENTER OF WALL.
OVER 200mm TO 300mm CONCRETE WALLS: #13 @ 300 mm O.C. EACH WAY, EACH FACE.
OVER 300 mm THICK: #16 @ 300mm O.C. EACH WAY, EACH FACE.
ALL HORIZONTAL REINFORCING IN FOOTINGS, WALLS AND
BEAMS SHALL BE CONTINUOUS AROUND CORNERS OR
HAVE CORNER BARS OF THE SAME SIZE AND SPACING AS
THE HORIZONTAL BARS AND LAP SPLICES PER SCHEDULE.
SIDE WALLS OF EXCAVATION SHALL BE BATTERED A
MINIMUM OF 25mm HORIZONTAL TO 300mm VERTICAL.
THIS CUT SHALL BE ABLE TO REMAIN VERTICAL
WITHOUT ANY SLOUGHAGE.
BOTTOM WIDTH OF EXCAVATIONS SHALL BE 25mm
WIDER AT EACH SIDE THAN IS SHOWN ON DRAWINGS.
IF ANY SANDY OR LOOSE SOIL MATERIALS ARE
ENCOUNTERED, FOOTINGS MAY NOT BE EARTH
FORMED.
ALL REINFORCING STEEL SHALL BE CORRECTLY
ALIGNED AND MAINTAINED, AND SHALL HAVE A MINIMUM
OF 75mm OF CONCRETE COVER WHERE CAST AGAINST
EARTH.
DURING CASTING, ANY SOIL SLOUGHAGE SHALL BE
REMOVED FROM THE WET CONCRETE.
FOOTINGS NOT MEETING THE ABOVE CONDITIONS
SHALL BE REMOVED AND RECAST.
KEEP OPEN EXCAVATIONS AND EXCAVATIONS FOR
FOOTINGS AROUND AND WITHIN BUILDING PERIMETER
DRY. BACKFILL AGAINST FOUNDATIONS AND GRADE
BEAMS AS SOON AS PRACTICAL. PUMP WATER OUT OF
OPEN EXCAVATIONS, IF FLOODED PRIOR TO
BACKFILLING.
STRUCTURAL FILL SHALL NOT BE PLACED WHEN THE
ATMOSPHERIC TEMPERATURE IS BELOW 2 DEGREES
CELSIUS. WHEN THE TEMPERATURE FALLS BELOW 2
DEGREES, ALL AREAS OF COMPLETED WORK SHALL BE
PROTECTED AGAINST DETRIMENTAL EFFECTS OF
GROUND FREEZING, AND ANY AREAS AFFECTED BY
FREEZING SHALL BE RECONDITIONED AND COMPACTED
IN CONFORMANCE WITH THE ABOVE REQUIREMENTS.
ANY SOILS DISTURBED DUE TO WETTING, DRYING OR
OTHER CAUSES SHALL ALSO BE RECONDITIONED PRIOR
TO PLACEMENT OF ADDITIONAL FILL OR CONSTRUCTION
OF FOUNDATIONS, FLOOR SLABS, OR OTHER
STRUCTURAL ELEMENTS. RECONDITIONING SHALL
INCLUDE SCARIFICATION, MOISTURE CONDITIONING,
AND RECOMPACTION IN ACCORDANCE WITH THE
REQUIREMENTS PRESENTED IN THESE NOTES.
CLAY SOILS ENCOUNTERED NEAR THE SURFACE
SHOULD BE REMOVED FROM BELOW THE FOUNDATION
PRIOR TO PLACEMENT OF ENGINEERED FILL.
FOOTINGS MAY BE CAST DIRECTLY AGAINST THE
VERTICAL SIDES OF THE EXCAVATIONS PROVIDED ALL OF
THE FOLLOWING CRITERIA ARE SATISFIED:
STRUCTURAL FILL REQUIREMENTS:
MATERIAL SHALL COMPLY WITH THE GEOTECHNICAL
RECOMMENDATIONS.
PLACE ALL STRUCTURAL FILL IN APPROXIMATELY
HORIZONTAL LAYERS NOT GREATER THAN 200mm IN
THICKNESS FOR HEAVY EQUIPMENT COMPACTION
MOISTEN TO OPTIMUM MOISTURE CONTENT +/- 3% AND
COMPACT TO DENSITY SPECIFIED IN THESE
REQUIREMENTS.
ALL EARTHWORK & OVER EXCAVATION FOR THE
BUILDING PAD SHALL EXTEND A MINIMUM OF 3 METERS
BEYOND THE PERIMETER FOOTINGS.
MAINTAIN SUBGRADE AND FILL MOISTURE CONTENT
UNTIL FOUNDATIONS ARE PLACED.
DO NOT PLACE FOOTINGS OR SLABS AGAINST
SUBGRADE CONTAINING FREE WATER, FROST, OR ICE.
MAINTAIN PROPER SITE DRAINAGE DURING
CONSTRUCTION TO ENSURE SURFACE RUNOFF AWAY
FROM STRUCTURES AND TO PREVENT PONDING OF
SURFACE RUNOFF NEAR THE STRUCTURES.
IF CONTRACTOR SUPPLIES PLATE BASED ON ENGLISH
THICKNESS THE FOLLOWING COVERSIONS SHALL BE
USED.
5mm = 3/16"
6mm = 1/4"
8mm = 5/16"
10mm = 3/8"
13mm = 1/2"
16mm = 5/8"
19mm = 3/4"
22mm = 7/8"
25mm = 1"
32mm = 1 1/4"
38mm = 1 1/2"
I. WHERE WELD ELECTRODES ARE SUPPLIED BASED ON
ENGLISH SYSTEM OF UNITS, EQUIVALENT SIZES SHALL
BE PER AISC 14TH EDITION TABLE J2.3.
J. ALL FIELD DRILLING SHALL BE DONE WITH A MAG DRILL.
FLAME CUTTING OF HOLES OR ENLARGING OF UNFAIR
HOLES WILL NOT BE PERMITTED.
TYPICAL CONSTRUCTION DETAILS AND STEEL STUD
SCHEDULE FOR LIGHTGAGE FRAMING ARE SHOWN ON
SHEET S505. REFER TO ARCHITECTURAL DRAWINGS FOR
SPECIFIC CONFIGURATION AND DIMENSIONS OF ALL
LIGHTGAGE STEEL FRAMING NOT SHOWN ON THE
STRUCTURAL DRAWINGS.
ALL LIGHTGAGE STEEL FRAMING SHALL CONFORM TO
LATEST EDITION OF AISI "NORTH AMERICAN
SPECIFICATION FOR THE DESIGN OF COLD-FORMED STEEL
STRUCTURAL MEMBERS."
WALLS SHALL BE PROVIDED WITH MANUFACTURER'S
STANDARD BRIDGING: (EITHER WELDED 64 X 1.088 mm
THICK STUD OR CLIPPED COLD-ROLLED CHANNEL 38 X
1.366 mm THICK). PROVIDE BRIDGING @ 1200 O.C.
MAXIMUM.
PROVIDE ALL MISCELLANEOUS ACCESSORIES AND
FOLLOW ERECTION PROCEDURES PER MANUFACTURER'S
SPECIFICATIONS AND RECOMMENDATIONS.
COLD FORMED STEEL FRAMING (0.835mm THICK AND
HEAVIER):
0.835
1.088
1.366
1.720
2.454
2.997
GAGE
THICKNESS, mm
BAR SUPPORTS AND SPACERS FOR REINFORCING SHALL
BE PROVIDED IN ACCORDANCE WITH ACI 315. CHAIRS
WITH 0.7mm. SAND PLATES OR PRECAST BLOCKS SHALL
BE PROVIDED FOR ALL REINFORCING OF CONCRETE IN
CONTACT WITH GRADE. DECK CHAIRS SHALL BE
PROVIDED FOR ALL WELDED WIRE FABRIC IN SLABS OVER
METAL DECK. REINFORCING SHALL BE SECURELY TIED TO
SUPPORTS.
REFER TO GEOTECHNICAL REPORT FOR SPECIFIC
RECOMMENDATIONS.
REMOVE ALL TOPSOIL FROM THE CONSTRUCTION AREA.
THIS MATERIAL SHALL NOT BE USED AS FILL MATERIAL,
SPECIFIC SOIL PREPARATION REQUIREMENTS:
CLEARING AND GRUBBING:
SITE AND SUBSURFACE PREPARATION:
OVEREXCAVATE ALL SOILS UNDERLYING FOOTINGS AND
FLOOR SLAB AS NOTED ON S002.
MOISTURE CONDITIONED AND PROOF-ROLL PRIOR TO
COMPACTING NEW FILL.
INSTALL SUITABLE ENGINEERED FILL AND TENSAR TRIAX
TX GOEGRID LAYERS PER GEOTECHNICAL
RECOMMENDATIONS. INSTALL SELECT STRUCTURAL FILL
AT THE TOP 1m OF SOIL PER THE GEOTECHNICAL
RECOMMENDATIONS.
A
BC
D
E
0.176
0.176
0.176
0.176
SEISMIC
RESPONSE
COEFFICENT C
s
DESIGN BASE
SHEAR, kN
SEISMIC COLLECTOR BEAMS ARE REQUIRED WHERE
NOTED ON PLAN. ROOF DECK SHALL BE WELDED TO
COLLECTOR BEAMS AS NOTED ON PLAN. MECHANICAL
PIN ATTACHMENT ANCHORS SHALL NOT BE USED FOR
ATTACHING ROOF DECK TO COLLECTOR BEAMS OR
FRAME BEAMS NEXT TO COLLECTOR BEAMS.
NOTE: BUILDING DESIGNATIONS ARE BETWEEN
EXPANSION JOINTS.
BUILDING
VERTICAL DEFLECTION AND RIGID CLIPS SHALL BE 1.727mm
THICK AND SIMILAR TO HILTI VERTICLIP SLB600 OR 140mm
DIETRICH FASTCLIP. EACH STUD SHALL BE ATTACHED TO
EDGE PLATE OR ANGLE WITH CLIP NOTED UNO. CLIPS
SHALL BE WELDED TO EDGE ANGLE OR BENT EDGE PLATE.
ALL SCREWS USED IN COLD FORMED STEEL CONNECTIONS
SHALL BE A MINIMUM #6 OR WELDED UNO ON PLANS.
ALL 1.366mm AND HEAVIER MEMBERS SHALL BE FORMED
FROM STEEL CORRESPONDING TO WHAT IS LISTED IN THE
AISI "SPECIFICATION FOR THE DESIGN OF COLD-FORMED
STEEL STRUCTURAL MEMBERS", WITH A MINIMUM YIELD
STRENGTH OF 345 MPA UNLESS SPECIFICALLY NOTED
OTHERWISE.
WHERE GAGE MATERIAL IS SUPPLIED FOR COLD FORMED
STEEL FRAMING THE FOLLOWING CONVERSIONS SHALL BE
USED.
ROOF SNOW LOAD:
GROUND SNOW LOAD, Pg
FLAT ROOF SNOW LOAD, Pf
SNOW EXPOSURE FACTOR, Ce
SNOW IMPORTANCE FACTOR, I
THERMAL FACTOR, Ct
ROOF SUPPORTED MECHANICAL EQUIPMENT:
AC-1
AC-2
AC-3
AC-4
AC-LN
AC-LS
WHP8
AC-5
DEAD, kN DEAD, kN
1.0
1.0
1.0 kPa kPa
ONE MOISTURE-DENSITY CURVE FOR EACH TYPE OF
MATERIAL USED, AS INDICATED BY SIEVE ANALYSIS AND
PLASTICITY INDEX.
THE GEOTECHNICAL ENGINEER SHALL SUBMIT THE
RESULTS OF ALL REQUIRED TESTS TO THE
ARCHITECT/CONTRACTING OFFICER'S REPRESENTATIVE
WITHIN 2 WORKING DAYS AFTER THE TEST.
ONE FIELD DENSITY TEST PER EACH 420 SQUARE METERS
OF STRUCTURAL FILL PLACED IN EACH HORIZONTAL
LAYER OF STRUCTURAL FILL, WITH A MINIMUM OF 3 TESTS.
GENERAL:
CONTRACTOR SHALL SUBMIT TECHNICAL LITERATURE
FOR PROPOSED ANCHORING SYSTEM TO ARCHITECT
FOR REVIEW PRIOR TO INSTALLATION.
ANCHORING SYSTEM SHALL BE INSTALLED IN STRICT
ACCORDANCE WITH MANUFACTURER'S GUIDELINES FOR
INSTALLATION AND CURRENT ICC-ES REPORT
REQUIREMENTS.
ALL POST-INSTALLED ANCHORS SHALL HAVE A MINIMUM
13 DIAMETER UNLESS NOTED OTHERWISE ON THE
PLANS.
INSTALLATION DEPTHS SHOWN IN THESE PLANS ARE
THE MINIMUM EMBEDMENT DEPTHS. CONTRACTOR
SHALL SUPPLY ANCHORS WITH ADDITIONAL LENGTH TO
ENSURE THAT PROPER INSTALLATION OF ATTACHING
EQUIPMENT CAN BE MADE.
POST-INSTALLED ANCHORS SHALL ONLY BE USED
WHERE SPECIFIED ON THE DRAWINGS.
CONTRACTOR SHALL OBTAIN APPROVAL FROM THE
ARCHITECT PRIOR TO USING POST-INSTALLED ANCHORS
FOR MISSING OR MISPLACED CAST-IN-PLACE ANCHORS.
CARE SHALL BE GIVEN TO AVOID CONFLICTS WITH
EXISTING REBAR. HOLES SHALL BE DRILLED AND
CLEANED PER THE MANUFACTURER'S INSTRUCTIONS.
ANCHORS SHALL BE INSTALLED PER THE
MANUFACTURER'S INSTALLATION INSTRUCTIONS AT NOT
LESS THAN MINIMUM EDGE DISTANCES, EMBEDMENT,
AND / OR SPACING INDICATED IN THE MANUFACTURER'S
LITERATURE AND ICC-ES REPORT.
ANCHORS SHALL BE EMBEDDED IN THE APPROPRIATE
SUBSTRATE WITH THE EMBEDMENT INDICATED ON THE
DRAWINGS.
SUBSTITUTION REQUESTS FOR PRODUCTS OTHER THAN
THOSE LISTED BELOW SHALL BE SUBMITTED TO THE
ARCHITECT WITH CALCULATIONS THAT ARE PREPARED
AND SEALED BY A PROFESSIONAL ENGINEER LICENSED
IN THE JURISDICTION SHOWING THAT THE SUBSTITUTED
PRODUCT WILL ACHIEVE AN EQUIVALENT CAPACITY
USING THE APPROPRIATE DESIGN PROCEDURE
REQUIRED BY THE BUILDING CODE AND SHALL BE
ACCOMPIANIED BY A CURRENT
ICC-ES REPORT
SUBSTANTIATING SUITABILITY.
POST INSTALLED ANCHORS:
CONCRETE:
ALL SCREW TYPE ANCHORS SHALL BE POWERS WEDGE
BOLT +, HILTI KWIK HUS-EZ OR SIMPSON TITEN-HD
INSTALLED INTO CURED CONCRETE.
ALL EXPANSION ANCHORS SHALL BE HILTI KWIK BOLT
TZ, SIMPSON STRONG BOLT 2 OR POWERS
POWER-STUDS+SD2 UNLESS NOTED OTHERWISE ON
PLANS. EXPANSION ANCHORS SHALL BE INSTALLED
INTO CURED CONCRETE.
ALL ADHESIVE OR EPOXY GROUTED ANCHORS SHALL BE
HILTI HIT RE-500-SD, POWERS PE1000+ OR SIMPSON
SET-XP.
MASONRY:
ALL SCREW TYPE ANCHORS SHALL BE POWERS WEDGE
BOLT +, HILTI KWIK HUS-EZ OR SIMPSON TITEN-HD
INSTALLED INTO SOLID GROUTED AND CURED CMU AND
NOT INTO MORTAR JOINTS.
ALL EXPANSION ANCHORS SHALL BE HILTI KWIK BOLT 3,
SIMPSON STRONG BOLT 2 OR POWERS
POWER-STUDS+SD1 UNLESS NOTED OTHERWISE ON
PLANS. EXPANSION ANCHORS SHALL BE INSTALLED
INTO SOLID GROUTED AND CURED CMU.
ALL ADHESIVE OR EPOXY GROUTED ANCHORS SHALL BE
HILTI HIT HY 70, POWERS PURE 110+ OR SIMPSON SET
INTO SOLID GROUTED AND CURED CMU. ANCHORS FOR
HOLLOW MASONRY SHALL BE HILTI HIT HY 70, POWERS
PURE 110+ OR SIMPSON SET WITH ADHESIVE
ANCHORING SCREEN.
ONE FIELD DENSITY TEST PER EACH 420 SQUARE
METERS OF COMPACTED SUBGRADE PRIOR TO PLACING
STRUCTURAL FILL OR FLOOR SLAB CONSTRUCTION
WITH A MINIMUM OF 3 TESTS.
TESTS OF MATERIALS SHALL BE MADE AT THE FOLLOWING
RATES, UNLESS DIRECTED OTHERWISE BY GEOTECHNICAL
EGINEER:
A. STEEL JOISTS AND JOIST GIRDERS SHALL BE
MANUFACTURED BY A MEMBER OF THE STEEL JOIST
INSTITUTE.
B. STEEL JOISTS AND JOIST GIRDERS SHALL BE DESIGNED,
FABRICATED AND ERECTED IN ACCORDANCE WITH THE
LATEST STEEL JOIST INSTITUTE SPECIFICATIONS AND
OSHA REGULATIONS.
1.5
CONCENTRATED ROOF LOAD
kN kN
REINFORCED CONCRETE MASONRY:
BASIS FOR DESIGN: ALL MASONRY UNITS SHALL BE TYPE I
WITH A MINIMUM COMPRESSIVE STRENGTH OF 15 MPa
(NET AREA). F'm = 10.3 MPa.
MORTAR SHALL BE TYPE S. GROUT - F'c = 13.8 MPa.
CELLS CONTAINING REBAR SHALL BE GROUTED SOLID
FROM THE BOTTOM TO THE TOP OF THE WALL IN
ACCORDANCE WITH THE INTERNATIONAL BUILDING CODE.
ALL VERTICAL REBAR SHALL BE IN PLACE AND SECURED
WITH REBAR POSITIONERS PRIOR TO GROUTING.
UNLESS OTHERWISE NOTED, MASONRY CELLS SHALL BE
GROUTED IN ACCORDANCE WITH THE LOW-LIFT METHOD
AS DESCRIBED IN THE INTERNATIONAL BUILDING CODE.
(MAXIMUM 1.2 METER LIFTS)
ALL CELLS BELOW GRADE SHALL BE GROUTED SOLID UP
TO GRADE.
LAP ALL REBAR 48 BAR DIAMETERS OR 600mm MINIMUM
UNLESS NOTED OTHERWISE.
LAP ALL JOINT REINFORCEMENT 75 WIRE DIAMETERS.
ALL HORIZONTAL REINFORCING IN BOND BEAMS SHALL BE
CONTINUOUS AROUND CORNERS OR HAVE CORNER BARS
OF THE SAME SIZE AND A LAP OF 48 BAR DIAMETER OR
600mm MINIMUM. VERTICAL REBAR SHALL CONTINUE
THROUGH BOND BEAMS. IF BOND BEAMS AT
INTERSECTING WALLS MEET AT DIFFERENT ELEVATIONS,
EXTEND BOND BEAMS AROUND INTERSECTING CORNER
TO FIRST INTERIOR REINFORCED CELL, BUT NOT LESS
THAN 1.2 METERS.
PROVIDE STANDARD TRUSS TYPE JOINT REINFORCING @
400 mm O.C. (ALTERNATE COURSES) UNLESS NOTED
OTHERWISE. USE PREFABRICATED CORNERS AND TEES
AT ALL WALL CORNERS AND INTERSECTIONS
RESPECTIVELY.
ALL CMU SHALL BE REINFORCED UNLESS SPECIFICALLY
NOTED "NOT REINFORCED."
TYPICAL REINFORCEMENT UNLESS OTHERWISE SHOWN:
150mm CMU WALLS: #13 @ 200mm O.C. VERTICAL
200mm CMU WALLS: #13 @ 400mm O.C. VERTICAL
300mm CMU WALLS: #16 @ 400mm O.C. VERTICAL
TYPICAL DETAIL SECTIONS AND SCHEDULES ARE SHOWN
ON SHEETS S501 THROUGH S508 AND APPLY TO ALL
CONSTRUCTION EXCEPT WHERE SHOWN DIFFERENTLY ON
THE PLANS AND DETAILS.
SUBMITTAL REQUIREMENTS:
A. SHOP DRAWINGS SHALL INCLUDE ITEMS REQUIRED BY
THE SPECIFICATION AND THE FOLLOWING, AS
APPLICABLE:
a. DESIGNATION OF THE MEMBERS AND
CONNECTIONS THAT ARE PART OF THE SEISMIC
LATERAL RESISTING SYSTEM (SLRS).
b. CONNECTION MATERIAL SPECIFICATIONS.
c. WELDING REQUIREMENTS AS SPECIFIED IN
APPENDIX W, SECTION W2.2.
B. ERECTION DRAWINGS SHALL INCLUDE ITEMS
REQUIRED BY THE SPECIFICATION AND THE
FOLLOWING, AS APPLICABLE:
a. DESIGNATION OF THE MEMBERS AND
CONNECTIONS THAT ARE PART OF THE SEISMIC
LATERAL RESISTING SYSTEM (SLRS).
b. FIELD CONNECTION MATERIAL SPECIFICATIONS
AND SIZES.
c. LOCATIONS OF PRETENSIONED BOLTS.
d. FIELD WELDING REQUIREMENTS AS SPECIFIED IN
APPENDIX W, SECTION W2.3.
FOR CONCENTRATED LOADS NOT SHOWN ON FRAMING
MILS
VAPOR RETARDER:
A. PLACE VAPOR RETARDER DIRECTLY BENEATH INTERIOR
SLABS-ON-GRADE, BETWEEN SLAB AND BASE.
B. LAP AND SEAL ALL EDGES, PUNCTURES, AND
PENETRATIONS.
C. MEET THE REQUIREMENTS OF ASTM E1745 WITH A
WATER VAPOR PERMEANCE LESS THAN 0.030 PERMS.
D. BASIS OF DESIGN: STEGO WRAP, 15 MIL MINIMUM.
E. SEE DETAIL A4/S502 FOR TYPICAL VAPOR RETARDER
SYSTEM.
F. SEE SPECIFICATIONS AND MANUFACTURER'S
INSTRUCTIONS FOR ADDITIONAL REQUIREMENTS.
BASIS FOR DESIGN, STRENGTH AT 28 DAYS:
K. STRUCTURAL STEEL TO BE FABRICATED AND ERECTED IN
ACCORDANCE WITH LATEST OSHA REGULATIONS.
L. SPLICING OF STRUCTURAL STEEL MEMBERS IS PROHIBITED
WITHOUT PRIOR APPROVAL OF THE ARCHITECT /
CONTRACTING OFFICER.
M. CONFORM TO THE AISC CODE OF STANDARD PRACTICE
FOR ERECTION TOLERANCES. FIELD MODIFICATION TO
STRUCTURAL STEEL IS PROHIBITED WITHOUT PRIOR
APPROVAL FROM THE ARCHITECT.
N. REFER TO SPECIFICATION 05 12 00 FOR LIMITS AND
REQUIREMENTS OF ARCHITECTURALLY EXPOSED
STRUCTURAL STEEL (AESS).
ALL 1.088mm AND LIGHTER MEMBERS SHALL BE FORMED
FROM STEEL CORRESPONDING TO WHAT IS LISTED IN THE
AISI "SPECIFICATION FOR THE DESIGN OF COLD-FORMED
STEEL STRUCTURAL MEMBERS", WITH A MINIMUM YIELD
STRENGTH OF 225 MPA UNLESS SPECIFICALLY NOTED
OTHERWISE.
ALL STUD SIZES SHOWN IN MILLIMETERS (MM).
F'c = 25 MPa (NORMAL WEIGHT) ALL OTHER CONCRETE
EXPANSION INDEX SHALL BE LESS THAN 50 FOR
STRUCTURAL FILL.
S001
GENERAL
STRUCTURAL
NOTES
11.13.15 ADDENDUM 001
REV
ISSUE: 10.15.15 - SUBMITTAL 3
PROJECT NO: 08-0110.001
CAD DWG FILE: 08-0110-S001.dwg
DRAWN BY:
CHECKED BY:
SHEET TITLE
DATE DESCRIPTION
CONSULTANTS
U. S. DEPARTMENT
OF HEALTH AND
HUMAN SERVICES
E
21 3 4 5 6
D
C
B
A
D
C
B
A
21 3 4 5 6
10/15/15
From: Antonio Alvarez <aalvarez@NEIAW.COM>
Sent: Thursday, November 12, 2015 5:03 PM
To: Chuck Hanson
Subject: Fort Yuma Health Care Center (NEI Job No. 015-0098)
Hello Mr. Hanson, I am sending you this e-mail in regards to the above referenced project. Please note, that our
Revised Geotechnical Report signed on 6/26/15, under section 8.4 Fills Materials, included a typo. The second paragraph under the aforementioned section currently reads "Engineered Fill should consist of native or import soil that has a plasticity index less than 50 and does not contain quantities of oversize material that could make compaction difficult." It should read
"Engineered Fill should consist of native or import soil that has an expansion index less than 50 and does not contain quantities of oversize material that could make compaction difficult."
Thanks, Antonio Alvarez, PE
Nicklaus Engineering, Inc.
June 2015
REVISED GEOTECHNICAL REPORT
Prepa red for:
DEKKER/PERICH/SABATINI
7601 JEFFERSON NE, SUITE 100
ALBUQUERQUE, NM 87109
Prepared by: .'
NICKLAUS ENGINEERING, INC.
1851 W. 24TH STREET, SUITE 101
YUMA, AZ 85364
Nicklaus Engineering, Inc. 1851 W. 24th Street, Yuma, AZ 85364 I Ph: 928.344.8374 I Fax: 928.726.6994
Fort Yuma Health Care Center Geotechnical Report (Draft) NEI Job No. 015‐0098
June 25, 2015
Dekker/Perich/Sabatini 7601 Jefferson NE, Suite 100 Albuquerque, NM 87109
Attention: Mr. Chuck Hanson, P.E.
Reference: Fort Yuma Health Care Center – Geotechnical Investigation NEI Job No. 015‐0098
Dear Mr. Hanson, Please accept this report as a revision to our report dated June 23, 2015 of the same title.
As discussed in our proposal dated May 11, 2015, we reviewed the original geotechnical investigation report titled, “Soils Investigation for Fort Yuma Health Care Center in Imperial County, California,” dated April 2008. Based on our review of the April 2008 report and our proposal, please accept the following report as an updated report to the aforementioned geotechnical investigation. The 2008 report is considered preliminary for purposes of this updated report, and its field and laboratory results are used as a reference.
In order to evaluate the proposed site layout and the revised building code, NEI performed additional field explorations and laboratory testing as part of the updated geotechnical investigation; which included mud rotary drilling within the proposed building limits and testing below the groundwater table. The engineering analyses in this report includes an evaluation of the site liquefaction potential and possible site improvement recommendations, including geotechnical engineering conclusions and recommendations for both design and construction.
It is our recommendation that a copy of this report be given to the Structural Engineer and Earthwork Contractor.
Sincerely, Nicklaus Engineering, Inc.
Antonio Alvarez, P.E.
Vice President
TABLE OF CONTENTS
1. INTRODUCTION
1.1. GENERAL
1.2. PROJECT LOCATION AND DESCRIPTION
2. FIELD INVESTIGATION
3. LABORATORY TESTING
4. GEOLOGIC CONDITIONS
4.1. GEOLOGIC SETTING
4.2. SEISMIC SETTING
5. SURFACE CONDITIONS
6. SUBSURFACE CONDTIONS
7. GEOLOGIC HAZARDS
7.1. FAULT GROUND RUPTURE
7.2. STRONG GROUND SHAKING
7.3. LIQUEFACTION POTENTIAL
7.3.1. EVALUATION METHODOLOGY
7.3.2. EVALUATION RESULTS
7.3.3. LIQUEFACTION IMPACTS
7.4. EXPANSIVE SOIL
7.5. FLOODING
7.6. HYDROCONSOLIDATION
7.7. OTHER GEOLOGIC HAZARDS
8. ENGINEERING RECOMMENDATIONS
8.1. EARTHWORK
8.2. SITE CLEARING AND DEMOLITION
8.3. REMEDIAL GRADING AND SITE PREPARATION
8.3.1. UNIFORM BUILDING/PAVEMENT SUPPORT
8.3.2. LIQUEFACTION EFFECTS
8.4. FILL MATERIALS
8.5. FILL PLACEMENT AND COMPACTION
8.6. SUBDRAINS
8.7. SURFACE DRAINAGE
8.8. CBC SEISMIC DESIGN PARAMETERS
8.9. SOIL LIQUEFACTION/GROUND IMPROVEMENT
8.9.1. REDUCTION OF SOIL LIQUEFACTION SURFACE EFFECTS
NEI Job No. 015-0098
+t
8.10. SHALLOW FOUNDATIONS
8.11. DEEP FOUNDATIONS
8.12. MAT FOUNDATIONS
8.13. ALLOWABLE LATERAL RESISTANCE
8.14. CONCRETE SLABS AND HARDSCAPE
8.15. UTILITY TRENCHES
8.16. PAVEMENTS
8.17. CORROSION POTENTIAL
8.18. CONSTRUCTION CONSIDERATIONS
9. RISK, LIMITATIONS AND OTHER CONSiDERATIONS
REFERENCES
ATIACHMENTS
BORING PLATES:
PLATE A - VICINITY MAP
PLATE B - LOCATION MAP
PLATE C - BORING LOCATION MAP
BORING LOGS
KEY TO SYMBOLS
LABORATORY REPORTS:
GRAIN SIZE DISTRIBUTION REPORTS
ATIERBERG LIMITS REPORTS
STANDARD PROCTOR / MOISTURE DENSITY RELATIONSHIP REPORT
R-VALUE REPORT
LAB SUMMARY
SITE PHOTOGRAPHS
------------------------------- Page 2 j;.
1. INTRODUCTION
1.1. GENERAL
Contained within this report are the results of our geotechnical study for the Fort Yuma Health Care
Center project in Winterhaven, California. The purpose of our study was to investigate the underlying soil conditions at the site and provide engineering recommendations for foundations, earthwork, asphaltic concrete pavement and other related activities. Our field efforts included exploratory borings at select locations within the proposed building footprint. The exploratory borings were conducted to acquire information on the subsurface conditions. Field data collected, along with laboratory test results, were analyzed to develop design recommendations for the project.
1.2. PROJECT LOCATION AND DESCRIPTION
The Fort Yuma Health Care Center will be located in Winterhaven, California on an approximately 13 acre site. The site is bordered to the north by Highway S24 (Picacho Road), to the south and west by
Agnes Road and to the east by Quechan Drive. Proposed construction will consist of an approximately 70,000 square foot, single story, steel frame building with additional improvements including an asphaltic concrete paved parking area along with associated utilities.
2. FIELD INVESTIGATION
A total of three (3) test borings were advanced across the proposed site for this update. Two (2) hollow stem auger borings were advanced to fifteen and a half (15½) feet below ground surface and one (1) mud rotary boring was advanced to fifty‐one and a half (51½) feet below ground surface. All boreholes were advanced utilizing a truck mounted Diedrich D‐50 drill rig. Standard penetration tests were made at selected intervals employing a Modified California Sampler which was driven by a free‐fall 140‐pound hammer with a fall distance of thirty (30) inches. The number of blows required to advance the sampler twelve (12) inches, after initial six (6) inch seating, was noted and was designated as the standard penetration value. The standard penetration value at each borehole location is shown on the attached detailed boring logs.
TABLE 1: SCHEDULE OF BOREHOLES
LOCATION
DESIGNATION
BOREHOLE
NUMBER
BOREHOLE
DEPTH (FT)
Fort Yuma Health Care Center
BH‐1 15½
BH‐2 15½
BH‐3 51½
3. LABORATORY TESTING
Samples were recovered from a Modified California Sampler for laboratory analysis as described in
Section 2 of this report. Dry preparation of soil samples were conducted in accordance with ASTM D421.
The laboratory testing program consisted of the following:
TABLE 2: SCHEDULE OF LABORATORY TESTS
TEST NUMBER OF TESTS ASTM STANDARD
Particle Size Analysis 19 ASTM D422
Atterberg Limits 19 ASTM D4318
Moisture Content of Soil 19 ASTM D2216
Standard Proctor 1 ASTM D698 pH 1 Caltrans Method 643
Soluble Sulfates & Chlorides 1 Caltrans Method 417 & 422
R‐Value 1 ASTM D2844 / CAL 301
Soil classification was conducted in accordance with ASTM D2487.
4. GEOLOGIC CONDITIONS
4.1. Geologic Setting
The project site is situated in the Lower Colorado River geographic sub‐region within the Sonoran
Desert of the Basin and Range geomorphic province. This province is characterized by broad desert alluvial basins separated by barren rugged mountains [Radtke, 1988]. Landforms within the southern portion of this subregion are dominated by the fluvial geomorphology of the Colorado River drainage.
The Project area is situated on a relatively flat, fluvial terraced surface at an approximate elevation of 130 feet, Mean Sea Level (MSL) underlain by several thousand feet of alluvial, fluvial, and sedimentary deposits [Eberley et al., 1978].
4.2. Seismic Setting
The tectonic setting of the Winterhaven, California area is influenced by the transition zone between the crustal spreading centers in the Gulf and the right‐lateral transform boundary between the North
American and Pacific Plates. Although the San Andreas Fault zone is the primary element in this transform boundary, the total plate motion is distributed across a broad zone of deformation that extends from the San Andreas Fault on the east to offshore faults to the west. Primary seismic sources in the vicinity are the right slip faults associated with the transform boundary that include the San Andreas, San Jacinto, and Elsinore fault systems. Within the Salton Trough to the west of the site, the Imperial, Cerro Prieto, and Brawley faults represent relatively short but active seismic components of the San Andreas Fault system. Other distant active faults include the San Miguel, and the Calabasas faults in northwestern Baja California, and the extensional faults of the Basin and
Range province to the northeast.
The closest active fault (exhibiting evidence of displacement in the last 11,000 years) to the site is the Imperial fault which exhibited surface rupture most recently during seismic events in 1940 (M
6.9) and 1979 (M 6.4) [SCEC, 2014]. The Imperial fault is mapped approximately 40 miles (64 km) west‐southwest of the site [Jennings, 1994]. The nearest potentially active fault (exhibiting evidence of displacement between 11,000 and 1.6 million years) is the Algodones fault zone, approximately
7.5 miles (12 km) southwest of the site [Scarborough et al., 1986]. The Algonones fault zone is comprised of a series of two northwest‐southeast trending Quaternary‐age faults that exhibit a northeast dip‐slip component. The fault zone is predominantly concealed by windblown sand and young alluvial deposits but exhibits displacement of alluvial material with the latest Pleistocene
(11,000 to 30,000 years).
5. SURFACE CONDITIONS
The site was most recently used as a tribal mobile home park and is currently vacant. The approximately
13‐acre site is relatively flat and is sparsely vegetated. See attached photos for general surface conditions at time of drilling operations.
6. SUBSURFACE CONDTIONS
The site is underlain by recent alluvium. These deposits, as encountered during part of the 2008 field investigation, as well as, the current field investigation, generally consist of interbedded silts, lean clays, silty sands, and poorly graded sands (Unified Soil Classification System [USCS] classification ML, CL, SM, and SP, respectively). Raw sampler blow counts for SPT and split‐spoon samplers ranged from 2 to 52 in the current and previous 2008 field investigations for the project. Groundwater was encountered between 13 and 15 feet below the existing ground surface during these field investigations.
7. GEOLOGIC HAZARDS
The conclusions and discussions below are based on the current and 2008 field explorations performed for this project, laboratory testing, and geologic interpretation of the site‐specific subsurface information.
7.1. Fault Ground Rupture
The potential for fault surface rupture is generally considered to be significant along “active” faults and to a lesser degree along “potentially active” faults. A review of published geologic maps indicates that there are no known (mapped) active or potentially active faults which project toward, across, or are located within the immediate vicinity of the project Site. Furthermore, the site is not within an Alquist‐Priolo Earthquake Fault Zone as delineated by the State of California. Therefore, it is our opinion that the potential for fault surface rupture at the project site is low.
7.2. Strong Ground Shaking
The project site is situated within a seismically‐active region and will likely experience moderate to severe ground shaking in response to a large magnitude earthquake occurring on a local or more distant active fault during the expected lifespan of the project. As a result, seismically‐induced ground shaking in response to an earthquake occurring on a nearby active fault, such as the Imperial
Fault, or a regional fault, such as the San Andreas fault zone, is considered to be the major geologic hazard affecting the project. Site‐specific seismic design recommendations are presented in later sections of this report.
7.3. Liquefaction Potential
Seismically‐induced liquefaction is a phenomenon in which saturated soils lose a significant portion of their strength and acquire some mobility from seismic shaking or other large cyclic loading. The material types considered most susceptible to liquefaction are granular and low‐plasticity fine grained soils which are saturated and loose to medium dense. A rapid increase in groundwater pressures (excess pore water pressures) causes the loss of soil strength.
Manifestations of soil liquefaction can include sand boils, surface settlements and tilting in level ground, lateral spreading, and global instability (flow slides) in areas of sloping ground. The impact of liquefaction on structures can include loss of bearing capacity, drag loads on deep foundations, liquefaction‐induced total and differential settlement, and increased lateral and uplift pressures on buried structures.
A summary of the liquefaction potential evaluation methodology, evaluation results, and potential impacts to the project are presented in the following subsections.
7.3.1. Evaluation Methodology
For the current study, a detailed evaluation of soil liquefaction potential was performed using the available SPT blow count data, considering the corrections for the split‐spoon sampler blow count data. Liquefaction potential was evaluated using the Idriss‐Boulanger methodology [Idriss‐
Boulanger, 2008].
The procedure for evaluating liquefaction potential is empirical and is based on data and observations at sites that have and have not liquefied during an earthquake. The capacity of the soil to resist liquefaction is expressed as the cyclic resistance ratio. The seismic demand is a function of the anticipated peak ground acceleration (PGA) at the site generated by the design earthquake and is termed the cyclic stress ratio. Materials are considered potentially liquefiable if the factor of safety against liquefaction, calculated as the cyclic resistance ratio divided by the cyclic stress ratio, is less than 1.0. Estimates of the liquefaction‐induced settlements were calculated using the Zhang methodology [Zhang et al., 2002].
The values of PGA (expressed as units of gravity [g]) and earthquake magnitude used in the liquefaction evaluation are 0.24g (from the California Building Code) and M6.9 (from the previous maximum magnitude event described above), respectively. The evaluation assumes a high groundwater level of 14 feet bgs.
7.3.2. Evaluation Results
The results of the liquefaction analyses indicate that the subsurface soils at a depth between approximately 30 to 40 feet below the existing ground surface have the potential for liquefaction based on analyses performed for the subsurface information from Boring #3. These analyses also indicate that the total liquefaction‐induced settlements could be as much as 3 inches. Differential settlements at the ground surface may be on the order of half that amount.
7.3.3. Liquefaction Impacts
Liquefaction potential will impact the site design, and may impact the site after development.
Liquefaction would most likely be manifested at this site as local ground subsidence, settlement, and localized reduction in shear strength at depth.
The potential for lateral spreading at the site is considered to be low as (i) the site is relatively level; (ii) the potentially liquefiable lenses are located at depth; and (iii) a free face and/or steep slopes are not present in the immediate site vicinity.
7.4. Expansive Soil
Soils with some expansion potential are suspected in the near surface of the site. Based on the plasticity characteristics of the near surface soils encountered (typically indicating low plasticity silt, lean clay, and silty sands), the near surface soils are considered to have a low to medium potential for expansion.
7.5. Flooding
The Federal Emergency Management Agency (FEMA) presents the flood hazard potential in the vicinity of the site as part of their Flood Insurance Rate Maps. FEMA Map No. 04027C1530F, dated
15 January 2014 [FEMA, 2015], indicates that the subject area is located in a flood hazard zone defined as “0.2% annual chance flood hazard”. Based on our review of the FEMA mapping, the geologic setting, the potential for flooding at the site during the design life of the structure is low.
7.6. Hydroconsolidation
Hydroconsolidation is the collapse and compaction of silty to sandy soil having a low bulk density that has been deposited under saturated conditions, but has remained unsaturated since deposition.
Given the location and subsurface conditions observed at the site, when combined with the engineering recommendation provided for site earthwork activities, the potential for hydroconsolidation is considered to be very low.
7.7. Other Geologic Hazards
Other potential geologic hazards evaluated which could possibly affect the site include slope instability, floods, seiches, and tsunamis. The site is relatively flat, and new slopes, if proposed at the site, will be engineered slopes designed at stable inclinations. Therefore, slope instability is not considered a hazard. Tsunamis are seismically‐induced waves generated by sudden movements of the ocean bottom during submarine earthquakes, landslides or volcanic activity. Seiches are similarly generated but are oscillating waves within bodies of water such as reservoirs, lakes or bays. The site is not located near the ocean. Based on the physiographic setting of this site, the distance to the ocean or other large water bodies, and the elevation of the site, it is our opinion that the potential for flooding from seismically‐induced seiches and tsunamis is very low.
8. ENGINEERING RECOMMENDATIONS
The conclusions and design recommendations presented herein for the design of the proposed Fort
Yuma Health Care Center are based on our current understanding of the proposed project, review of the
2008 investigation for the project, and results of the current field investigation, laboratory testing, engineering and geologic analyses, and professional judgment. In our opinion, the site is suitable for the construction of the project, provided the recommendations of this report are incorporated into design and construction.
8.1. Earthwork
Site earthwork will generally consist of demolition of existing site features, site grading and engineered fill placement to construct a relatively level building pad, foundation excavations, and backfill of utility trenches. Engineered fill is defined as fill meeting the material, placement, and compaction recommendations presented in this report. Earthwork should be performed in accordance with the recommendations of this report, the Standard Specifications for Public Works
Construction “Greenbook” [2015], and California Occupational Safety and Health Administration (Cal
OSHA) safety requirements. A preconstruction meeting should be held at the site with owner, the contractor, civil engineer, and geotechnical engineer in attendance.
8.2. Site Clearing and Demolition
Existing utilities should be properly terminated and removed completely from the proposed development area. General debris, construction debris, and vegetative matter in the project area should be cleared and properly disposed off‐site. Due to the previous site uses, this site may have septic tanks, leach lines, cesspools, and other unseen obstacles. All unsuitable material should be removed from the site and disposed of properly.
8.3. Remedial Grading and Site Preparation
Based on the explorations performed for this project, the site is underlain by loose sands and soft silts and clays with some loose sand layers. These materials are conventionally considered unsuitable soils as compacted for bearing and should be overexcavated and recompacted (if suitable fill material) prior to site development. Remedial site grading should be performed to provide uniform support of the proposed building structures. In addition, remedial site grading may be performed to reduce the effects of soil liquefaction at the ground surface. Remedial grading recommendations are provided below.
8.3.1. Uniform Building/Pavement Support
To provide uniform support for the new building structures supported on shallow foundations, we recommend that the upper three feet of soil (from the lowest of existing or final grade) be overexcavated and recompacted (if suitable for fill material) prior to building foundation excavation. The upper three feet of soil beneath the footprint of new building structures should be backfilled with non‐expansive select soil. On‐site soils may not be suitable for select soil, and import soils may be required. Foundation design parameters and estimated settlements for shallow foundations provided in subsequent sections of this report incorporate this remedial grading recommendation.
Areas to be overexcavated and recompacted should extend a minimum of ten feet beyond the footprint of the foundations laterally in each direction. If variable depths of remedial grading are needed, areas of deeper remedial grading should transition to areas of shallower remedial grading to reduce the potential contrast in stiffness between materials. Specific guidelines for such transitions should be determined in the field during grading operations by a representative of the geotechnical engineer.
We recommend that in areas to receive pavement and hardscaping, the upper 1 foot of soil should be overexcavated and recompacted (if suitable for select fill material). Similarly, if buildings are to be supported on deep foundations, we recommend that the upper 1 foot of soil beneath the building footprint be overexcavated and recompacted.
Loose or soft soil, or soil disturbed by demolition activities within the proposed grading area, as identified by the geotechnical engineer during grading and foundation excavation, should be excavated or scarified as required, moisture conditioned, and then recompacted before placing additional fill or preparing subgrade. Soil containing organic or other deleterious matter, if encountered, should be removed from the site and properly disposed. Areas to receive new fill, including areas of overexcavation and recompaction, should be proof rolled and moisture conditioned prior to compacting new fill.
8.3.2. Liquefaction Effects
To provide a reduction in the effects of liquefaction‐induced settlement at the ground…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .