15-NAT-8814 - Supplier Scheduling and Reporting Requirements Rev. 1.pdf
PDF 664 KB Posted
- Attached to
- RFP-2025-9827 RAC Pressure Drop Testing
- Solicitation number
- RFP-2025-9827
- Issued by
- Washington
About this file
This document is a Supplier Scheduling and Reporting Requirements document from TerraPower, LLC, related to a project under the Department of Energy (DOE) Cooperative Agreement No. DE-NE0009054. The document outlines comprehensive scheduling and reporting expectations for suppliers, detailing five levels of project scheduling from high-level overviews (Level 1) to daily task assignments (Level 5). Suppliers are required to develop and maintain a Level 3 detailed schedule that shows critical path activities, includes cost loading, incorporates third-party activities, and is updated at least monthly. The schedule must be baselined and approved by the company prior to beginning work, with preferred scheduling software being Primavera Project Management or Microsoft Project.
The reporting requirements mandate that suppliers submit schedule updates typically every week or every other week, but no less than once per month, with a Supplier Project Status Report required within 5 business days of the month-end close. The reporting format varies depending on the contract type: cost-type contracts must submit a Cost-Plus Monthly Report with a CP-Time Phased Forecast, while fixed-price contracts must submit the Firm Fixed Price Report portion of NAT-12844. The document emphasizes the importance of aligning planned and earned values with cost report data, and requires suppliers to demonstrate sound methodologies for tracking performance that must be reviewed and approved by the company's Program Management Office.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAT-8814 Rev 0
Supplier Scheduling and Reporting Requirements Page 1 of 8
Controlled Document - Verify Current Revision
SUBJECT TO DOE COOPERATIVE AGREEMENT NO. DE-NE0009054
TERRAPOWER PROPRIETARY AND CONFIDENTIAL – SUBJECT TO CONFIDENTIALITY AGREEMENT
NAT-5629 Rev. 1
Verify Current Revision
REVISION HISTORY
Revision No.
Effective Date Affected
Section(s) Description of Change(s)
0 All Rev New
Document Title:
Supplier Scheduling & Reporting Requirements
Natrium Document No.:
NAT-8814
Rev. No.:
Page:
Doc Type:
Administrative Document
Target Quality Level:
N/A
Alternate Document No.:
N/A
Alt. Rev.:
N/A
Originating Organization:
TerraPower, LLC
Quality Level:
N/A
Natrium MSL ID:
Procurement
Status:
Controlled
Open Items?
No
Approval
Approval signatures are captured and maintained electronically; see Electronic Approval Records in EDMS.
Signatures or Facsimile of Electronic Approval Record attached to document.
NAT-8814 Rev 0 Supplier Scheduling and Reporting Requirements Page 2 of 8
SUBJECT TO DOE COOPERATIVE AGREEMENT NO. DE-NE0009054
1 All Restructured document and cleaned information to be more specific
NAT-8814 Rev 0 Supplier Scheduling and Reporting Requirements Page 3 of 8
TABLE OF CONTENTS
1 INTRODUCTION
2 SUPPLIER TECHNICAL PROPOSAL
3 CONTRACT AWARD & KICKOFF
4 SCHEDULE REQUIREMENTS
4.1 Level 1: Project Summary Schedule (Master Schedule)
4.2 Level 2: Control Schedule
4.3 Level 3: Detailed Schedule (expected supplier reporting level)
4.4 Level 4: Work Package Schedule
4.5 Level 5: Daily Schedule
4.6 Summary of Differences:
4.7 Minimum Level 3 Schedule Requirements
5 REPORTING CYCLE
5.1 SCHEDULE
5.2 COST
LIST OF FIGURES
No table of figures entries found.
NAT-8814 Rev 0 Supplier Scheduling and Reporting Requirements Page 4 of 8
1 INTRODUCTION
The intent of the scheduling and reporting requirements is to reduce risk, to provide an accurate accounting of project status, and to be predictive. The Supplier is responsible for establishing project controls, scheduling work, monitoring progress, keeping the Company fully updated as it pertains to the contractual scope. Key objectives of this document are to explain the following:
Establish the minimum scheduling and reporting requirements
Expectations and responsibilities (Supplier and Company)
Reporting tools and methods
Timing of deliverables & reporting cadence
Ensure supplier cost and tracking tools align monthly performance report and IMCS
Best practices in Project Controls to reduce risk, improve communications, and provide guidance for resource and cost management to ensure project delivery
2 SUPPLIER TECHNICAL PROPOSAL
A Level 2 schedule (Work scope by Phase or Discipline) design, fabrication, and delivery with appropriate schedule milestones (see Schedule Level Definition in Section 4 below) and detail to reflect the work. Level 2 detail is the minimum level of detail required with a proposal although, more detail is encouraged.
Before the contract is awarded the supplier must provide examples the Level 3 schedule methodology, ability to align to the Company cost reporting requirements (if applicable) and any other Supplier specific tracking tools wanting to be utilized for the duration of the purchase order.
3 CONTRACT AWARD & KICKOFF
A Level 3 schedule shall be developed by the Supplier following award by the Company.
The Level 3 schedule lags the Technical Proposal depending on scope size and complexity. The schedule due date will be listed in the Statement of Work but shall be received no later than 60 calendar days post contract award.
NAT-8814 Rev 0 Supplier Scheduling and Reporting Requirements Page 5 of 8
4 SCHEDULE REQUIREMENTS
This section is meant to explain the differences between schedule levels and explain the level of detail required at each reporting level for the Suppler. The schedule is expected to provide accurate progress, tracking, impacts, cost payments, and forecasting.
4.1 Level 1: Project Summary Schedule (Master Schedule)
Scope: Entire project
Detail: Very high-level overview
Purpose: Provides an overall timeline and major deliverables or phases.
Components: Key project phases and major milestones (e.g., project initiation, design phase completion, major approvals, project completion).
Audience: Senior management, stakeholders, and executives.
Example: Project start, major design completion, testing start, project end.
4.2 Level 2: Control Schedule
Scope: Major project deliverables and phases
Detail: High-level, but more detailed than Level 1
Purpose: Guides the project management team by outlining key phases and critical paths.
Components: Major work packages, phase gates, and intermediate milestones.
Audience: Project managers and senior team members.
Example: Detailed design completion, procurement start, major subsystem installations.
4.3 Level 3: Detailed Schedule (expected supplier reporting level)
NAT-8814 Rev 0 Supplier Scheduling and Reporting Requirements Page 6 of 8
Scope: Work packages and specific deliverables
Detail: More granular, showing tasks and activities within each major deliverable.
Purpose: Provides a detailed plan for the project execution.
Components: Task breakdowns, dependencies, resource assignments, and more granular milestones.
Audience: Project team members and functional managers.
Example: Detailed tasks for each subsystem, integration testing phases, procurement milestones.
4.4 Level 4: Work Package Schedule
Scope: Individual work packages and activities
Detail: Very detailed, including individual tasks, durations, and resources.
Purpose: Facilitates day-to-day management and tracking of project tasks.
Components: Specific tasks, assigned resources, durations, start and finish dates, and detailed dependencies.
Audience: Team leads, project coordinators, and individual contributors.
Example: Specific engineering tasks, testing protocols, procurement of specific items, individual installation tasks.
4.5 Level 5: Daily Schedule
Scope: Individual tasks and activities
Detail: Most detailed level, down to daily tasks and assignments.
Purpose: Manages daily operations and ensures individual tasks are completed on time.
Components: Daily work activities, specific task assignments, timesheets, and daily check-ins.
Audience: Individual team members and supervisors.
Example: Daily work assignments, task checklists, daily progress updates.
NAT-8814 Rev 0 Supplier Scheduling and Reporting Requirements Page 7 of 8
4.6 Summary of Differences:
Level 1: Entire project, broad phases, senior management focus.
Level 2: Major deliverables, high-level tasks, project management focus.
Level 3: Detailed tasks, work packages, project team focus.
Level 4: Individual work package details, specific activities, team lead focus.
Level 5: Daily tasks, individual assignments, day-to-day operations focus.
4.7 Minimum Level 3 Schedule Requirements
A. Ability to show critical path and associated driving activity details.
B. Baselined and approved by the Company prior to beginning work.
a. Schedule has been approved through the Company specified deliverables management system.
C. Be available in electronic format when requested by the Company. Preferred software is Primavera Project Management or Microsoft Project, but other scheduling tools are acceptable if it fulfills the Level 3 Schedule Requirements. Schedules must be delivered on the required cadence in the native file and a PDF version.
D. Start and Finish Constraints should only be used in rare situations and are discouraged.
E. Should be baselined after the initial schedule approval has been received. The baseline dates must be in alignment with any contractual deliverable dates that specified in the SOW.
F. Include approved changes and show schedule impacts when applicable.
G. Schedule status must be taken as specified in the statement of work, but not less than once per month.
H. Schedule shall be cost-loaded (activities and/or Milestones) and equal contract value (to include any approved changes). If the schedule cannot be cost loaded, the Supplier must demonstrate to the Company Program Management Office sound methodology for tracking performance. The company must review and approve of the methodology.
I. Include third-party activities when applicable (deliveries, inspections, coatings, etc.).
J. Planned and Earned values from the schedule must correspond to the Cost Report data.
5 REPORTING CYCLE
5.1 SCHEDULE
NAT-8814 Rev 0 Supplier Scheduling and Reporting Requirements Page 8 of 8
Schedule updates will typically be received every week or every other week, but no less than one per month. The exact reporting cadence is found in the supplier SOW.
5.2 COST
Supplier Project Status Report is required within 5 business days of month end close of the supplier.
Note: All supplier cost types are required to submit a monthly performance report. The format of the monthly performance report will differ depending on the type of contract. Cost type contracts must submit the Cost-Plus Monthly Report, and the CP-Time Phased Forecast portion of NAT- 12844. Fixed Price contracts must submit the Firm Fixed Price Report portion of NAT-12844
END OF DOCUMENT