DRAFT_Specs_Hyrum_Dam_Spillway_Replacement_4.pdf
PDF 11 MB Posted
- Solicitation number
- 140R4024R0020
About this file
This document appears to be a draft set of specifications for the Hyrum Dam Spillway Replacement project, which is the subject of a federal contract opportunity issued by the Department of the Interior Bureau of Reclamation.
The key details are:
- The federal contract opportunity is a Special Notice for an Industry Day related to the Hyrum Dam Spillway Replacement project.
- The solicitation number is 140R4024R0020.
- The draft specifications provided cover technical details and requirements for the spillway replacement work.
- The contracting agency is the Department of the Interior Bureau of Reclamation, a civilian federal agency.
- No other details are provided about the contract requirements, pricing, set asides, award dates, or incumbents.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
U.S. Department of the Interior SPECIFICATIONS Bureau of Reclamation Technical Service Center Denver, Colorado July 2024
Hyrum Dam Spillway Replacement Hyrum, Utah
DRAFT
U.S. Department of the Interior SPECIFICATIONS Bureau of Reclamation Technical Service Center Denver, Colorado June 2024
This page intentionally left blank.
HYRUM DAM SPILLWAY REPLACEMENT
HYRUM PROJECT
UPPER COLORADO REGION, UTAH
FOREWORD
Work is for constructing a new spillway at Hyrum Dam. Work is located on Little Bear River just south of Hyrum City, Utah.
Principle features of work include: construction of a new spillway and radial gates, a new stilling basin, two new siphons, and a new precast concrete beam bridge.
Hyrum Dam Spillway Replacement Hyrum Project, Utah
Price Schedule
B - 1
CONTINUATION OF
SECTION B – SUPPLIES OR SERVICES AND PRICES
HYRUM DAM SPILLWAY REPLACEMENT
HYRUM PROJECT, UTAH
B.1 PRICE SCHEDULE
(a) Offers will be considered for award on the following Price Schedule, but no offer will be considered for award on only a part of the Price Schedules.
(b) Offers are subject to the terms and conditions of this solicitation.
(c) The Government will award Price Schedule A. Price Schedules B thru I are optional price schedules that the Government is not required to exercise.
(d) Quantities in the Price Schedule are estimated quantities for comparison of offers only.
Except as provided in the contract clause at FAR 52.211-18, Variation in Estimated Quantity, no claim shall be made against the Government for overruns or underruns. The contract clause at FAR 52.211-18, Variation in Estimated Quantity does not apply to lump sum items.
(e) See the contract clause at WBR 1452.232-81, Payment for Mobilization and Preparatory Work, for CLIN 1.
(f) Definitions:
(1) CLIN – Contract Line Item Number
PRICE SCHEDULE A
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
A-1. WBR
1452.23 2-81
Mobilization and preparatory work
For the lump sum of
A-2. 01 31 30 Contract Document Management System
For the lump sum of $
A-3. 02 41 07 Removal and Disposal of Existing Features
For the lump sum of $
B - 2
PRICE SCHEDULE A
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
A-4. 02 83 33 Removal and Disposal of Equipment with Coatings Containing Regulated Metals
For the lump sum of $
A-5. 03 11 10 Concrete Forming 110,000 ft2 $ $
A-6. 03 15 12 6-inch PVC Waterstops 5,900 lin ft $ $
A-7. 03 20 00 Concrete Reinforcing 6,000,000 lbs $ $
A-8. 03 20 00 Weldable Concrete Reinforcing
2,200 lbs $ $
A-9. 03 30 00 Cast-In-Place Concrete 3,100 yd3 $ $
A-10. 03 30 00 Reinforced Structural Mass Concrete (RSMC)
16,000 yd3 $ $
A-11. 03 30 00 Spillway Test Section For the lump sum of $
A-12. 03 30 39 Precast Concrete Deck Panels
For the lump sum of $
A-13. 03 41 33 Pretensioned Concrete Bridge Beams
For the lump sum of $
A-14. 03 81 10 Saw/Wire Cut Existing Concrete
750 lin ft $ $
A-15. 03 81 10 Concrete Removal 3,280 yd3 $ $
A-16. 03 81 10 Existing Bridge Removal For the lump sum of
A-17. 05 50 00 Miscellaneous Metalwork For the lump sum of
A-18. 07 21 20 Extruded Polystyrene Rigid Foam Insulation
6,500 ft2 $ $
A-19. 07 92 00 Joint Sealants For the lump sum of $
B - 3
PRICE SCHEDULE A
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
A-20. 13 34 20 Metal Building System For the lump sum of $
A-21. 26 05 02 Complete Electrical System
For the lump sum of $
A-22. 26 32 10 Diesel Engine-Generator Set
For the lump sum of $
A-23. 26 42 13 Galvanic Anode Cathodic Protection System
For the lump sum of $
A-24. 31 02 10 Water for Dust Abatement
For the lump sum of $
A-25. 31 03 23 New Spillway Cofferdam For the lump sum of $
A-26. 31 03 33 Stilling Basin Unwatering
For the lump sum of $
A-27. 31 03 33 Crest Structure Unwatering
For the lump sum of $
A-28. 31 03 33 Upper Chute Unwatering For the lump sum of $
A-29. 31 03 33 Deep Wells 3,400 Lin ft $ $
A-30. 31 03 33 Deep Wells Operation and Power
For the lump sum of $
A-31. 31 03 33 Well Points 1,000 Lin ft $ $
A-32. 31 03 33 Well Points Operation and Power
For the lump sum of $
A-33. 31 03 33 Passive Wells 2,300 Lin ft $ $
A-34. 31 03 33 Temporary Observation Wells
1,350 Lin ft $ $
A-35. 31 09 10 Abandoning Existing Piezometers
For the lump sum of
A-36. 31 09 26 Temporary Measurement Points (TMP)
26 Each $ $
Price Schedule B - 4
PRICE SCHEDULE A
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
A-37. 31 09 26 Spillway Measurement Points (SMP)
110 Each $ $
A-38. 31 09 26 Monitoring During Construction
For the lump sum of $
A-39. 31 14 10 Stripping 46 acres $ $
A-40. 31 23 30 Excavation 300,000 yd3 $ $
A-41. 31 23 51 Sand Filter 18,000 yd3 $ $
A-42. 31 23 52 Gravel Drain Material 3,800 yd3 $ $
A-43. 31 23 54 Miscellaneous Fill 82,000 yd3 $ $
A-44. 31 23 56 Structural Fill 2,500 yd3 $ $
A-45. 31 24 10 Impervious Fill 35,000 yd3 $ $
A-46. 31 24 20 Additional Embankment Materials
500 yd3 $ $
A-47. 31 32 26 Single Pier Modulus Tests
For the lump sum of $
A-48. 31 32 26 Multiple Pier Modulus Test
For the lump sum of $
A-49. 31 32 26 Installed Piers 18,500 lin ft $ $
A-50. 31 32 52 Inspection Well at the Existing Spillway
For the lump sum of $
A-51. 31 37 00 Type 1 Riprap 2,900 yd3 $ $
A-52. 31 37 00 Type 2 Riprap 3,900 yd3 $ $
A-53. 31 37 00 Type 3 Riprap 15,500 yd3 $ $
Price Schedule B - 5
PRICE SCHEDULE A
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
A-54. 31 37 10 Type 1 Riprap Bedding 3,400 yd3 $ $
A-55. 31 37 10 Type 2 Riprap Bedding 1,400 yd3 $
A-56. 31 37 10 Type 3 Riprap Bedding 6,900 yd3 $ $
A-57. 31 41 16 Steel Sheet Piles 18,000 ft2 $ $
A-58. 31 56 20 Cutoff 37,000 ft2 $ $
A-59. 32 12 00 County Road 2,800 yd2 $ $
A-60. 32 12 00 Access Roads 2,200 yd2 $ $
A-61. 32 12 00 Demolition of Existing County Road
2,800 yd2 $ $
A-62. 32 15 10 Gravel Surfacing 2,200 yd2 $ $
A-63. 32 31 10 Chain Link Fence For the lump sum of $
A-64. 32 31 30 Barbed Wire Fence 1,600 lin ft $ $
A-65. 32 91 19 Placing Topsoil 6 acres $ $
A-66. 32 91 60 Topsoil Erosion Control Matting
15,700 yd2 $ $
A-67. 32 92 20 Seeding 7.5 acres $ $
A-68. 33 05 33 Spillway Stilling Well For the lump sum of $
A-69. 33 11 14 East Field Inverted Siphon
For the lump sum of $
A-70. 33 11 14 Hyrum Feeder Ditch Pipeline Inverted Siphon
Price Schedule B - 6
PRICE SCHEDULE A
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
A-71. 33 11 16 Line Pipe – PVC 4,200 lin ft $ $
A-72. 33 11 16 Filling, Testing, and Draining Pipe
For the lump sum of $
A-73. 33 11 16 Repair Kits For the lump sum of $
A-74. 33 46 36 4-inch-Diameter Non-perforated HDPE Air Vent Pipe
93 lin ft $ $
A-75. 33 46 36 8-inch-Diameter Perforated HDPE Pipe
1,500 lin ft $ $
A-76. 33 46 36 10-inch-Diameter Perforated HDPE Pipe
5,200 lin ft $ $
A-77. 33 46 36 10-inch-Diameter Non-perforated HDPE Pipe
2,000 lin ft $ $
A-78. 33 46 36 12-inch-Diameter Perforated HDPE Pipe
790 lin ft $ $
A-79. 33 46 36 12-inch-Diameter Non-perforated HDPE Pipe
220 lin ft $ $
A-80. 33 46 36 18-inch-Diameter Non-perforated HDPE Pipe
32 lin ft $ $
A-81. 33 46 36 Cleanouts 39 each $ $
A-82. 33 46 36 Air Vents 7 each $ $
A-83. 33 46 42 Perimeter Drain Weir Boxes
For the lump sum of $
A-84. 34 71 10 Guardrail 2,900 lin ft $ $
A-85. 35 21 20 Stoplog Guides For the lump sum of $
A-86. 35 23 50 Radial Gates For the lump sum of $
B - 7
PRICE SCHEDULE A
CLIN Section Supplies or Services Quantity and Unit
Unit Price
Amount
A-87. 41 22 32 Radial Gate Hoists For the lump sum of $
TOTAL FOR PRICE SCHEDULE A: $_________________
PRICE SCHEDULE B
CLIN Section Supplies or
Services Quantity and Unit
Unit Price
Amount
B-1. 03 81 10 Existing Bridge Removal
TOTAL FOR PRICE SCHEDULE B: $________________
PRICE SCHEDULE C
CLIN Section Supplies or Services Quantity and Unit Unit Price Amount
C-1. 31 03 23 New Spillway Cofferdam Emergency Ice Berm
TOTAL FOR PRICE SCHEDULE C: $_________________
PRICE SCHEDULE D
and Unit
Unit Price Amount
D-1. 31 03 33 Supplementary Deep Wells Installation/Removal
900 LF $ $
D-2. 31 03 33 Supplementary Deep Wells Materials
900 LF $ $
TOTAL FOR PRICE SCHEDULE D: $_________________
PRICE SCHEDULE E
Price Schedule B - 8
CLIN Section Supplies or Services Quantity and Unit
Unit Price Amount
E-1.
31 03 33 Supplementary
Deep Wells Operation and Power
For the lump sum of $
TOTAL FOR PRICE SCHEDULE E: $_________________
PRICE SCHEDULE F
CLIN Section Supplies or Services Quantity and Unit Unit Price Amount
F-1.
31 03 33 Supplementary Well Points
Installation/Removal
510 LF $ $
F-2.
31 03 33 Supplementary Well Points
Materials
510 LF $ $
TOTAL FOR PRICE SCHEDULE F: $________________
PRICE SCHEDULE G
CLIN Section Supplies or Services Quantity and Unit Unit Price Amount
G-1.
31 03 33 Supplementary
Wells Point Operation and Power
For the lump sum of $
TOTAL FOR PRICE SCHEDULE G: $________________
B - 9
PRICE SCHEDULE H
and Unit
Unit Price Amount
H-1.
31 03 33 Supplementary
Passive Wells Installation/Removal
1,150 LF $ $
H-1.
31 03 33 Supplementary
Passive Wells
1,150 LF $ $
TOTAL FOR PRICE SCHEDULE H: $_________________
PRICE SCHEDULE I
and Unit Unit Price Amount
I-1.
31 03 33 Supplementary
Temporary Observation Wells Installation/Removal
690 LF $ $
I-1.
31 03 33 Supplementary
Temporary Observation Wells
690 LF $ $
TOTAL FOR PRICE SCHEDULE I: $_________________
TOTAL FOR PRICE SCHEDULES A, and B thru I: $_________________
END OF SUPPLIES OR SERVICES AND PRICES
B - 10
Table of Contents
00 01 10 - 1
SECTION C - DESCRIPTION / SPECIFICATIONS
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 14 10 Use of Site 01 14 12 Work Restrictions and Limitations 01 31 19 Project Management and Coordination 01 31 30 Contract Document Management System 01 32 10 Construction Program 01 33 00 Submittals 01 33 26 Electrical Drawings and Data 01 35 10 Safety Data Sheets 01 35 20 Safety and Health 01 35 30 Contractor’s Onsite Safety Personnel 01 42 10 Reference Standards 01 46 00 Quality Procedures 01 46 20 Testing Agency Services 01 51 00 Temporary Utilities 01 52 10 Field Office 01 55 00 Vehicular Access and Parking 01 55 20 Traffic Control 01 56 10 Protection of Existing Installations 01 56 15 Protection of Existing Utilities 01 56 32 Temporary Safety Fence 01 57 20 Environmental Controls 01 57 30 Water Pollution Control 01 57 50 Tree and Plant Protection 01 57 60 Protected Species 01 57 90 Preservation of Historical and Archeological Data 01 60 00 Product Requirements 01 71 20 Surveying 01 74 00 Cleaning and Waste Management 01 78 30 Project Record Documents
DIVISION 02 - EXISTING CONDITIONS
02 41 07 Removal and Disposal of Existing Features 02 83 33 Removal and Disposal of Equipment with Coatings Containing Regulated Metals
DIVISION 03 - CONCRETE
03 11 10 Concrete Forming
00 01 10 - 2
03 15 12 PVC Waterstops 03 20 00 Concrete Reinforcing 03 30 00 Cast-In-Place Concrete 03 30 39 Full-Depth Precast Concrete Deck Panels 03 41 33 Precast Pretensioned Bridge Beams 03 62 20 Nonshrink Grout for Equipment and Metalwork 03 81 10 Concrete Removal
DIVISION 05 - METALS
05 50 00 Metal Fabrications
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 21 20 Extruded Polystyrene Rigid Foam Insulation 07 41 13 Insulated Metal Roof Panels 07 42 13 Pre-Insulated Metal Wall Panels 07 92 00 Joint Sealants
DIVISION 08 - OPENINGS
08 11 10 Steel Doors and Frames 08 31 20 Floor Access Hatches 08 51 10 Aluminum Windows 08 71 00 Door Hardware
DIVISION 09 - FINISHES
09 96 20 Coatings
DIVISION 10 – SPECIALTIES
10 44 20 Fire Extinguishers
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 20 Metal Building System
DIVISION 26 - ELECTRICAL
26 05 02 Basic Electrical Materials and Methods 26 05 10 Conductors and Cables 26 05 20 Grounding and Bonding 26 05 33 Conduit 26 05 90 Wiring Checkout and Tests 26 22 16 Transformer Load Center
00 01 10 - 3
26 24 20 Panelboards 26 27 30 Wiring Devices 26 28 20 Service Disconnect Switch 26 32 10 Diesel Engine-Generator Set 26 36 22 Manual Transfer Switch 26 42 13 Submerged Galvanic Anode Cathodic Protection 26 51 00 Interior Lighting 26 56 00 Exterior Lighting
DIVISION 31 - EARTHWORK
31 02 10 Water for Dust Abatement 31 03 23 Cofferdam Construction 31 03 33 Removal and Control of Water 31 09 10 Abandoning Existing Piezometers 31 09 26 Measurement Points 31 11 00 Clearing and Grubbing 31 14 10 Stripping 31 23 00 Compacting Earth Materials 31 23 22 Pipe Trench Earthwork 31 23 30 Excavation 31 23 51 Sand Filter 31 23 52 Gravel Drain 31 23 54 Miscellaneous Fill 31 23 56 Structural Fill 31 23 70 Controlled Low Strength material 31 24 10 Impervious Fill 31 24 20 Embankment Construction 31 32 26 Aggregate Piers 31 32 32 Geotextile 31 32 52 Inspection Wells 31 37 00 Riprap 31 37 10 Riprap Bedding 31 41 16 Steel Sheet Piles 31 56 20 Cutoff
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 12 00 Roads 32 15 10 Gravel Surfacing 32 31 10 Chain Link Fence 32 31 30 Wire Fence 32 91 19 Placing Topsoil 32 91 60 Topsoil Erosion Control Matting 32 92 20 Seeding
DIVISION 33 - UTILITIES
00 01 10 - 4
33 05 31 Precast Concrete Pressure Manholes 33 05 33 Spillway Stilling Well 33 11 10 Pipeline General Requirements 33 11 14 Reinforced Concrete Pressure Pipe 33 11 16 PVC Pressure Pipe Hyrum Feeder Pipeline 33 46 36 Drain Pipes 33 46 42 Perimeter Drain Weir Boxes
DIVISION 34 – TRANSPORTATION
34 71 10 W-Beam Guardrails
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 21 20 Stoplog Guides 35 23 50 Spillway Radial Gates 35 69 20 Safety Cable with Floats
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 32 Radial Gate Hoists
DIVISION 51 - INFORMATION AVAILABLE TO OFFERORS
51 00 00 Information Available to Offerors 51 02 82 Hazardous Materials Survey and Analytical Results
DIVISION 52 - DRAWINGS
52 00 00 Drawings
DIVISION 53 - GEOLOGIC INVESTIGATIONS AND RECORDS
53 20 00 Geologic Investigations 53 30 00 Records of Geologic and Subsurface Investigations
END OF CONTENTS
Summary of Work
01 11 00 - 1
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.01 LOCATION
A. Work is located on the Little Bear River immediately south-west of Hyrum City, Utah.
1.02 PRINCIPAL COMPONENTS OF WORK
A. Construction includes:
1. Re-grade reservoir rim between the spillway and the dam
2. Excavation for a new spillway
3. Construction of a cofferdam for the new spillway
4. Constructing a new spillway
5. New gates and hoists
6. New hoist enclosure
7. New spillway chute and stilling basin
8. Embankment dike
9. Dewatering system
10. Aggregate pier foundation treatment
11. Two new siphons
12. New precast concrete beam bridge
13. County road realignment construction
14. Rerouting two access roads
15. Mechanical and electrical equipment
16. Construction of a cofferdam for existing spillway removal
17. Excavation and removal of existing spillway
Summary of Work 01 11 00 - 2
1.03 SPECIFICATIONS REQUIREMENTS
A. Requirements in Division 1, General Requirements, apply to Divisions 2 through 53.
B. Imperative statements in these specifications are Contractor requirements, unless otherwise stated.
C. Where specifications are written in streamlined form, words “shall be” are included by inference where a colon (:) is used within sentence or phrase.
1.04 DEFINITIONS
A. When specifications use a word or term defined in Federal Acquisition Regulations (FAR), definition of the word or term shall be in accordance with FAR sections in effect at the time solicitation was issued.
1.05 ACRONYMS
A. The following acronyms apply to specifications Divisions 1 through 53:
1. CO: Contracting Officer.
2. COR: Contracting Officer’s Representative.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
END OF SECTION
Use of Site 01 14 10 - 1
SECTION 01 14 10
USE OF SITE
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 REFERENCE STANDARDS
A. Bureau of Reclamation (USBR)
1. Cleaning Manual-2012 Inspection and Cleaning Manual for
Equipment and Vehicles to Prevent the Spread of Invasive Species (Technical memorandum No. 86-68220-07-05) 2012 Edition Available online at:
http://www.usbr.gov/mussels/prevention
1.03 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
B. RSN 01 14 10-1, Land Use and Landscape Rehabilitation Plan:
1. For each Contractor use site on Government land.
a. Show use location and extent of impact. Uses include but are not limited to the following:
1) Buildings and service areas including offices, shops, warehouses, storage areas, fuel and oil storage areas, and fabrication yards.
2) Parking areas, temporary roads, and haul routes.
3) Utilities including air, power, and water lines; fire hydrants; and compressor station.
4) First-aid and medical facilities.
5) Concrete and aggregate plants. Show sizes, rated capacities, and general features of aggregate processing plant including transporting, storing, screening, and washing facilities; concrete batching and mixing plant; and concrete conveying, placing, and cooling plants.
http://www.usbr.gov/mussels/prevention
01 14 10 - 2
6) Areas for processing, storing, and disposing of waste materials from construction operations.
7) Temporary fences.
b. Describe methods to preserve, protect, and repair, vegetation (such as trees, shrubs, and grass) and other landscape features on or adjacent to jobsite, which are not to be removed and which do not interfere with work required under this contract. Include methods to mark work area limits, protect disturbed areas, and prevent erosion.
c. Describe methods to protect, and repair if damaged, existing improvements and utilities at or near jobsite.
d. Describe methods for removing temporary structures and facilities, cleanup, and rehabilitating site after completion of construction activities.
2. Submit revised drawings of changes in use of Government land made during design and erection stages or after use of Government land is in operation.
1.04 PROJECT CONDITIONS
A. Government land as shown on drawings may be used for required construction facilities, as approved by the COR.
B. When private land is used for construction facilities, or other construction purposes, make necessary arrangements associated with use of private land.
C. Location, construction, operation, maintenance, and removal of construction facilities on Government land will be subject to approval of COR.
D. Do not interfere with work of other contractors or the Government in vicinity, or with reservations made by the Government for use of such land.
E. Areas on Government land which will be obliterated by permanent construction or inundated by reservoir may be used where use of such land will be discontinued and construction facilities, materials, equipment, and rubbish and waste materials will be removed to avoid interference with work in such areas or with filling of reservoir.
F. Housing for construction personnel will not be permitted on Government land, except housing for guards or watchmen as may be approved by COR.
PART 2 PRODUCTS
Not Used
01 14 10 - 3
PART 3 EXECUTION
3.01 CLEANING
A. Construction equipment:
1. Before bringing on site, clean construction equipment to remove dirt, vegetation, and other organic material to prevent introduction of noxious weeds, and invasive plant and animal species.
2. Contractor cleaning procedures shall result in equipment being cleaned as well or better than the procedures described in Cleaning Manual.
3. COR will inspect construction equipment following procedures described in Cleaning Manual before allowing equipment onsite.
3.02 RESTORATION
A. Restore Contractor use areas to pre-construction condition or as approved by COR.
B. After completion of work, regrade and scarify Government land used for construction purposes and not required for completed installation so that surfaces blend with natural terrain and are in a condition that will facilitate revegetation, provide proper drainage, and prevent erosion.
Use of Site 01 14 10 - 4
Work Restrictions and Limitations
01 14 12 - 1
SECTION 01 14 12
WORK RESTRICTIONS AND LIMITATIONS
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in Price Schedules for other items of work.
1.02 WORK RESTRICTIONS AND LIMITATIONS
A. Construction Requirements:
1. Reservoir rim excavation with 3:1 slope shall occur when the reservoir is below the lowest point of the excavation.
2. New Spillway Cofferdam sheet piles shall be in place to the lines and grades shown on drawings and sand drains shall be installed to the lowest elevation shown on drawings prior to excavating spillway foundation soils below elevation 4675 feet between new spillway station 5+00 and cofferdam alignment.
a. Slope protection riprap and cofferdam berm shall be in place prior to
January 1 of the calendar year following sheet pile installation.
3. The outlet channel downstream of the existing stilling basin Station 12+60 shall not be constructed until the new spillway stilling basin is complete and approved by COR.
4. New siphon for the East Field Canal must be connected during the non-irrigation season unless otherwise approved by COR.
5. New siphon for the Hyrum Feeder Canal must be connected during the non-irrigation season unless otherwise approved by COR.
6. Existing Spillway Demolition and Dike Construction:
a) Existing spillway shall remain operational during entire duration of construction of the new spillway. Do not begin demolition without approval by CO.
b) The new spillway and channel shall be fully operational before any work on the existing spillway excavation, modifications and embankment dike construction can begin.
c) A Contractor designed cofferdam to remove the existing spillway in accordance with Section 31 03 23 – Cofferdam Construction may be required depending on the Contractors means and methods.
01 14 12 - 2
d) Removal of the existing spillway and dike construction from station 2+77 to the Existing Stilling Basin shall be completed prior to any demolition of the existing spillway crest structure or gates.
e) Protect dike construction from reservoir water and wave action until dike completion to the lines and grades shown on drawings.
2) Contractor may attempt to sequence items of the work specified below Top of Active Conservation when the reservoir is low but Government makes no guarantee of reservoir levels outside of restrictions stated in Section 01 14 20 – Reservoir Operations for additional requirements and limitations.
7. Concrete placements from station 3+73 to 11+25 shall progress from downstream to upstream.
a) This does not apply to localized concrete panel sequencing.
8. Installation of drainage and mudmat within each panel shall be completed prior to concrete placement.
9. Contractor shall provide access to the existing stilling basin and downstream property for Reclamation employees and downstream landowner during the entirety of construction.
10. If reservoir ice loading occurs on the New Spillway Cofferdam above elevation 4669 feet an emergency berm shall be constructed abutting the sheet piles as shown on the drawings before any portion of ice abutting the sheet piles reaches 12-inches in thickness.
B. Allowable Work Hours: 7 am to 10 pm, 7 days a week unless otherwise approved by the
COR.
C. Prior to closing the road on the crest of Hyrum Dam and Dike, install the detour signs in accordance with Section 01 55 20 – Traffic Control.
D. Access to and from the Disposal site is restricted to routes shown on the Drawings.
E. Reservoir operations are limited and will not be adjusted to lower reservoir elevations to accommodate construction activities.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Work Restrictions and Limitations 01 14 12 - 3
01 14 12 - 4
Project Management and Coordination
01 31 19 - 1
SECTION 01 31 19
PROJECT MANAGEMENT AND COORDINATION
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Cost:
1. Include in prices offered in the Price Schedules for other items of work.
1.02 OTHER CONTRACTS
A. The Government anticipates other contractors working in the same general site location.
1. Includes removal of existing overhead power lines and replacement with new underground electrical conductor, as shown on drawings and described in Section 26 05 06 – Electrical Project Coordination.
B. The Contractor shall coordinate work with the Government, other contractors, and other agencies in the vicinity in accordance with WBR 1452.236-8 Other Contracts.
1.03 SUBMITTALS
A. Submit in accordance with Section 01 33 00 – Submittals.
B. RSN 01 31 19-1, Weekly Coordination Meeting Documentation:
1. Provide meeting agenda.
2. 3-week look-ahead schedule covering construction review items and tasks.
3. Work completed to date.
4. Meeting minutes from the previous weekly coordination meeting to include:
a. Date, time, and list of attendees.
b. Summary of topics discussed.
c. List of action items including:
1) Description of action item.
2) Responsible party.
3) Date to be completed.
1.04 SPECIFICATION DRAWINGS
A. AutoCAD files of specification drawings are available to the Contractor.
1. Contractor shall provide a written request with the requested drawing numbers.
Project Management and Coordination 01 31 19 - 2
2. Government will make these files available to Contractor within 21 days after the request is received.
1.05 PROJECT COORDINATION
A. The following meetings are considered significant, but do not relieve the Contractor from the responsibility of other meetings required by the specifications.
1. Pre-Construction Readiness Review Meeting:
a. Six weeks after Award, an in-person Readiness Review Meeting will be held in Cle Elum, Washington to review the contract requirements and associated pre-mobilization tasks.
b. The meeting is expected to begin at 8:00 A.M. local time, include a site visit, and last the entire day.
c. An agenda, including proposed dates, will be provided by the Government within 2 weeks of Award.
d. Environmental awareness training will be provided to all in attendance.
e. At a minimum, the following personnel will attend:
1) Contractor’s personnel:
a) Owner or Owner’s Representative.
b) Project Manager.
c) Project Engineer or responsible engineering representative who understands these specifications with respect to technical requirements, equipment to be furnished, and coordination necessary to complete work.
d) On-site Superintendent(s).
e) Key Subcontractor personnel.
f) Additional personnel that Contractor considers necessary.
2) Government personnel:
a) Contracting Officer.
b) Contracting Officer’s Representative.
c) Design Engineer(s).
d) Project Manager.
e) Environmental, Biological, and/or Cultural Specialists.
f. The meeting will be recorded for contractual purposes and meeting minutes published for review.
2. Weekly Construction Coordination Meetings:
01 31 19 - 3
a. Meeting shall be held weekly at the work site project office. Prepare agenda and distribute 24 hours before the meeting.
b. Prepare and distribute a meeting agenda
c. Prepare and distribute meeting minutes.
d. Attendees: Responsible representatives who have been fully informed of specifications with respect to technical requirements, and coordination necessary to complete construction. Representatives shall be determined on an as needed basis and typically should include:
1) Project Manager from Contractor.
2) Field Superintendent from Contractor.
3) COR and other Representatives from Bureau of Reclamation.
e. Representatives may attend by telephone and / or video conference.
f. Purpose: Review, schedule, construction progress, and coordination
1) Review submittals register, submittals currently in review and approval, and meeting submittals due dates or delivery time frames.
2) Review safety, security, environmental, schedule, project issues and concerns, submittals, contractor Requests for Information (RFI), Requests for Proposals (RFP), pending Contract Modifications, and other project related items.
3) Provide 3 week look-ahead schedule at least 2 hours before start of meeting.
4) Review as-built drawings.
5) Provide meeting minutes from the previous weekly meeting.
6) Review data that activities were started and completed, remaining duration, and percent complete.
3. Environmental Awareness Meetings and Training:
a. Environmental awareness training is required for all employees, contractors, and site visitors to educate on-site personnel about sensitive resources.
1) Reclamation’s qualified professional along with the Contractor will conduct training.
2) Contractor must provide a one week notice to Reclamation in advance of holding training.
3) Training shall be held on site unless Reclamation makes other arrangements.
b. This program will include, but not be limited to, special status species information and conservation; worker compliance responsibilities;
01 31 19 - 4 noncompliance penalties or significant risks of litigation; and best management practices (BMPs) and conservation measures described in this section, such as project speed limits, weed control, avoidance of wildlife buffers, species reporting, debris control, hazardous waste management, wetland protection, hazardous waste and spill containment, and permit stipulations; cultural resource protocols and protection, and historic built environment requirements.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
A. Cooperate and coordinate use of access routes, water supplies, staging areas; maintaining roads, dust-free operations; complying with environmental requirements; complying with permit requirements and abiding by applicable safety regulations.
Contract Document Management System
01 31 30 - 1
SECTION 01 31 30
CONTRACT DOCUMENT MANAGEMENT SYSTEM
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Contract Document Management System:
1. Payment: Lump sum price offered in Price Schedule A.
1.02 DEFINITIONS
A. Accepted RSNs: A copy of the Contractor’s transmittal sheet marked “Accepted” is enclosed and returned to the Contractor. Accepted comments and conditions are not intended to direct the Contractor’s work and shall not relieve the Contractor of the Contractor’s responsibility for the accuracy, completeness and correctness of details, nor of complying with the contract requirements. Acceptance shall not relieve the Contractor of the Contractor’s responsibility for compliance with Federal Acquisition Regulation 52.236-21, Specifications and Drawings for Construction. This completes all of the requirements under this Submittal. Proposed changes to accepted submittals shall be submitted and accepted before being implemented.
B. Approved RSNs “A”: A copy of the Contractor’s transmittal sheet marked “Approved” is enclosed and returned to the Contractor. Approval comments and conditions are not intended to direct the Contractor’s work and shall not relieve the Contractor of their responsibility for the accuracy, completeness, and correctness of details, nor of complying with the contract requirements. Approval shall not relieve the Contractor of their responsibility for compliance with Federal Acquisition Regulation 52.236-21, Specifications and Drawings for Construction.
1. Rarely an RSN will be returned with comments. The comments are intended to clarify specific interpretations or RSN language and shall not direct the Contractor’s work and shall not relieve the Contractor of their responsibility for the accuracy, completeness, and correctness of details, nor of complying with the contract requirements. Approval with comments shall not relieve the Contractor of their responsibility for compliance with Federal Acquisition Regulation 52.236-21, Specifications and Drawings for Construction.
C. Conditionally Accepted RSNs: A copy of the Contractor’s transmittal sheet marked “Conditionally Accepted” is enclosed and returned to the Contractor with comments.
Conditionally accepted comments and conditions are not intended to direct the Contractor’s work and shall not relieve the Contractor of the Contractor’s responsibility for the accuracy, completeness and correctness of details, nor of complying with the contract requirements. Conditional acceptance shall not relieve the Contractor of responsibility for compliance with Federal Acquisition Regulation 52.236-21, Specifications and Drawings for Construction.
01 31 30 - 2
D. Conditionally Approved RSNs: A copy of the Contractor’s transmittal sheet marked “Conditionally Approved” is enclosed and returned to the Contractor with comments.
Conditionally approved comments and conditions are not intended to direct the Contractor’s work and shall not relieve the Contractor of the Contractor’s responsibility for the accuracy, completeness and correctness of details, nor of complying with the contract requirements. Conditional approval shall not relieve the Contractor of responsibility for compliance with Federal Acquisition Regulation 52.236-21, Specifications and Drawings for Construction.
E. CDMS: Contract Document Management System.
1. Contract Documents include, but are not limited to:
a. Specifications.
b. Contract Drawings.
c. Submittals.
d. RFCs: Request for Change (Contractor generated document).
e. RFIs: Request for Information (Contractor generated document).
f. RFPs: Request for Proposal (Government generated document).
g. CMs: Contract Modifications.
h. Contractor Proposals.
i. Value Engineering Change Proposals.
j. Government Inspection Reports.
k. Invoices and Progress Payments.
l. Contract Schedules.
m. Meeting Agendas and Meeting Minutes.
n. Letters and Memos.
F. Not Accepted RSNs: A copy/Copies of the Contractor’s transmittal sheet/sheets marked “Not Accepted” is/are enclosed. Comments and conditions are not intended to direct the Contractor’s work and shall not relieve the Contractor of the Contractor’s responsibility for the accuracy, completeness, and correctness of details, nor of complying with the contract requirements.
G. Not Approved RSNs: A copy/Copies of the Contractor’s transmittal sheet/sheets marked “Not Approved” is/are enclosed. Comments and conditions are not intended to direct the Contractor’s work and shall not relieve the Contractor of the Contractor’s responsibility for the accuracy, completeness and correctness of details, nor of complying with the contract requirements.
1.03 SUBMITTALS
A. Submit in accordance with Section 01 33 00 - Submittals.
01 31 30 - 3
B. RSN 01 31 30-1, Approval Data:
1. System provider experience, number of systems operating, references.
2. Documentation of system capabilities.
3. Instructions for system use.
C. RSN 01 31 30-2, Final Data:
1. DVD or CD of documents uploaded to CDMS.
1.04 QUALIFICATIONS
A. System provider: At least 5 years successful performance in providing required services.
1.05 CDMS REQUIREMENTS
A. CDMS shall be capable of generating, storing, tracking, categorizing, and managing Contract Documents.
B. Access:
1. Web-based:
a. Contract Documents are stored and accessed by authorized individuals via an internet site.
b. Compatible with web browsers MS Internet Explorer, Apple Safari, Mozilla Firefox and Google Chrome.
2. Ability to upload Contract Documents and make available for user download in supported file formats, minimum:
a. Adobe Acrobat.
b. MS Word.
c. MS Excel.
d. MS Project or Oracle Primavera P6 Project Manager.
e. Autodesk AutoCAD Civil 3D.
3. Allow Contract Documents to be prepared by the Contractor or by Government.
a. Preparing organization will control access of documents. See Document
Security and Backup paragraph below.
4. Contractor and Government shall each have a project manager for CDMS.
a. Each project manager shall have capabilities to assign users within their organization and to assign user rights which control access to documents based on user class and document type.
b. Each organization shall be capable of defining its access hierarchy.
c. Inclusion of users will be prerogative of organizational project manager.
01 31 30 - 4
d. Government shall be able to create and modify project properties (i.e.
Contractor, project location, description, bid amount, project directory, etc).
5. Email notifications shall be automatically sent to selectable users when new documents are submitted and available for viewing, or alerts are generated.
Examples:
a. Updates to project information (e.g. entry of a new submittal);
b. Changes to project information (e.g. approval of a submittal);
c. Alerts (e.g. submittal under review for greater than 15 calendar days without action).
6. Ability to link files; examples:
a. RFP linked to a CM.
b. Submittal linked to a Specification Section or Drawing.
C. Reports:
1. Generate reports that list and sort documents by status, examples include:
a. Submittals that have been approved.
b. Invoices paid to date.
c. RFIs under review.
2. Generate alerts when documents requiring action approach or exceed allowable time.
3. Generate customizable summary reports, examples include:
a. Submittal Turn-around.
b. RFI Turn-Around.
c. CM Processing Turn-Around.
d. Total CM costs.
e. Total CM Request Exposure.
4. Reports shall be printable, exportable as searchable pdf or printer friendly HTML, and exportable to Excel, XML, or CSV.
5. Ability to link from an item in a report directly to item by clicking on it.
a. For example: in a submittal report, clicking on a submittal that is 15 days old takes you directly to information on that submittal.
6. Capable of producing a complete and logically organized set of documents within
CDMS in both pdf and xml format.
D. Document Security and Backup:
01 31 30 - 5
1. SSL encryption for secured data exchange between browser and server (Secure access to documents and information).
2. Allow document access security until authoring party chooses to share it with others.
a. Show parties that have access to a document.
b. Extent of document sharing shall be determined by authoring party.
c. Once documents are shared, track documents so that changes cannot occur without a record of changes.
3. Backup/Archiving to FTP site of documents to which an organization has access on a regular (minimum monthly) basis.
a. Backups shall be in pdf format.
4. Documents shall be downloadable to FTP sites where Government and other organizations can each access their own data confidentially.
E. General Tracking and Control:
1. Documents shall be grouped into categories (Submittals, RFC, RFI, RFP, CM, Payments, Daily Inspection Reports, Meeting Minutes).
2. CDMS shall track:
a. When documents were received or returned, as well as status of documents (e.g. Under Review; or Returned, Approved or Rejected, etc.).
b. Document changes including who entered or changed document and date change was made.
c. When a reviewer has opened an item.
F. Submittal Tracking and Control:
1. Ability to create master list of submittals (“Schedule of Submittals”).
2. Supply standard submittal form for entering information. CDMS shall allow customizing of standard submittal form. Contractor shall be able to enter submittal summary information (required submittal number, title, description, due date, and specification section shall be required fields) and then upload submittal data in electronic format.
3. Track date received, date response due, date returned, and approval status.
a. Status designations may be modified to fit Government standard designations - A/CAR/NA/Acc/CAcc/NAcc (Approved/Conditionally Approved, Resubmit/Not Approved, Accepted, Conditionally Accepted, Not Accepted).
4. Supply Submittal Tracking form for Government to enter review comments and action taken. CDMS shall allow customizing of submittal tracking form.
01 31 30 - 6
a. Allow for Government to route submittal to third parties by generating design-review transmittals with each submittal package item, to track status of individual sub-items within submittal package, and to route each sub-item to appropriate reviewers.
5. Ability to generate automatic notification after specified days without response.
G. RFI Tracking and Control:
1. Supply standard RFI form to enter information.
2. Ability to create or attach documents to the RFI form or links to other documents within CDMS.
3. Ability for Government to route RFI to appropriate reviewers and for reviewers to enter comments into standard response form.
H. Inspection Reports Tracking and Control:
1. Ability to attach Government standard inspection and report forms into CDMS and ability to create customizable inspection forms in CDMS. Typical forms:
a. Daily Inspection Report (DIR).
b. Survey requests.
c. Plant inspection reports.
d. Testing reports.
2. Ability to link or attach photos to forms and link forms to other documents within
CDMS.
I. Contract Modifications:
1. Supply standard Contractor Proposal form with ability to attach documents and link to other documents within CDMS.
2. Supply ability to upload Government’s standard CM form and RFP forms, or create an acceptable alternative, to enter information.
a. Submittals: Specification Section, Days Out, Status
(A/CAR/NA/Acc/CAcc/NAcc).
3. Ability to attach documents to these forms, and link to other documents within
CDMS.
4. Ability for Contractor to respond to RFP and CM form with Cost & Time impacts.
5. Ability to track date CM issued and date responded, with automatic notification after specified days without response.
J. Cost Tracking and Payment Request Management:
1. Ability to import payment bid items cost from a MS Excel spreadsheet.
01 31 30 - 7
2. Ability to edit percent complete and payment amount each month. Format to be spreadsheet, e.g. items available for editing at once, rather than needing to edit one item at a time, save, open next item and edit that, etc.
K. Correspondence:
1. Ability to generate letters and memos.
a. Ability to attach documents to letters and memos, and to reference other documents within CDMS.
b. CDMS shall ability automatically assign sequential numbers to letters and memos.
2. Ability to generate responses to letters and memos.
a. System automatically generates memo suffixes, e.g. 1st response to Memo
32 to be 32.1, 2nd response to be 32.2, etc.
3. Official correspondence from Government to Contractor shall contain
Government’s official letterhead and corresponding logos.
4. Ability to generate meeting agendas and meeting minutes and to attach documents to minutes.
a. CDMS shall automatically assign sequential meeting numbers.
L. Miscellaneous Tracking and Controls. Ability to:
1. Generate reports tracking RFCs, RFIs, RFPs, CMs, Submittals, Payments, Memos, DIR’s, survey requests, plant inspection reports and testing reports.
2. Filter logs based on criteria:
a. Submittals: Specification Section, Days Out, Status (A/AAN/R&R/
ACK/RWR).
b. RFI’s: Days out, Status (Open/Closed), Specification Section/Dwg No., Responsibility/Ball-In-Court.
3. Sort Logs based on a criteria, e.g. for Submittal, Specification Section, Days Out, Status, or other criteria determined by the COR.
4. Supply forms to match Government’s CM Form and Progress Payment Form or other forms when needed.
5. Track Cost Exposure with links to RFI and CM requests.
6. Measure productivity benchmarks on a project such as computing average review days for RFIs and submittals, categorize CMs, and track total CM percentages by category.
7. Keyword search of documents in database.
8. Allow online Payment Requests by Contractor.
M. Budget and Funding Source Tracking:
01 31 30 - 8
1. Ability to enter funding sources and assign contract line items to multiple funding sources.
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
3.01 IMPLEMENTATION
A. CDMS shall be in place and operating before Contractor transmits Contract Documents to Government, except RSN 01 31 30-1, Approval Data.
1. CDMS operation includes COR, or other authorized Government representative, having program control to assign users and user rights to Government personnel to access appropriate areas of system.
B. Contractor shall input Schedule of Submittals before making submittals. Include:
1. RSNs listed in Table 01 33 00A - List of Submittals.
2. Scheduled submittal date.
C. Contractor shall provide a report of submittal status monthly or as requested by COR.
Submittal status report shall be in a table format and include:
1. Required Submittal Number (RSN).
2. Section Title.
3. Submittal Title.
4. Date Submitted.
5. Date of Response.
6. Approval Status (Approved/Conditionally Approved, Resubmit/Not Approved, Accepted, Conditionally Accepted, Not Accepted).
7. Days in Review.
8. Due Date.
D. CDMS shall be operational until final project closeout.
Construction Program
01 32 10 - 1
SECTION 01 32 10
CONSTRUCTION PROGRAM
PART 1 GENERAL
1.01 MEASUREMENT AND PAYMENT
A. Costs:
1. Developing Baseline Schedule: Include in lump sum price offered in Price
Schedule A for Mobilization and Preparatory Work.
2. Updating and Using Construction Program: Include as part of Contractor’s overhead.
1.02 DEFINITIONS
A. Schedule: The Critical Path Method (CPM) of planning and scheduling a construction project where activities are arranged based on activity relationships and network calculations determine when activities can be performed and the critical path of the project.
B. Project Calendar(s): Cross reference of numerical work days with calendar days. Project calendars serve as the basis for day/date conversion and assign work days and non-workdays.
C. Resources: Equipment, labor or crews, materials, subcontractors, fabricators, manufacturers, and consultants.
D. Out of Sequence Work: An activity that starts before its predecessor activities are completed.
1.03 REFERENCE STANDARDS
A. Associated General Contractors of America (AGC)
1. AGC Manual Construction Planning and Scheduling
Manual, 2004
1.04 SUBMITTALS
A. Submit the following in accordance with Section 01 33 00 - Submittals.
1. Furnish database files in format compatible with Oracle Primavera P6
Professional Project Management.
2. Upon request, provide information and data used to develop and maintain the
Construction Program to the CO.
01 32 10 - 2
B. RSN 01 32 10-1, Representative Information:
1. Designation of authorized representative to develop and maintain Construction
Program. Include resume with training and experience.
C. RSN 01 32 10-2, Baseline Schedule:
1. Include:
a. Construction Program/Schedule database.
b. Definition of project calendars.
c. Primavera P6 layout file (.plf).
d. Gantt chart (Bar chart) for project on 11 by 17-inch print(s) and in portable document format (.pdf).
e. Activity report including logic constraints consisting of predecessors, successors, and constraint dates.
f. Tabular listings of resources and resource limitations used to produce baseline schedule. Correlate resources with schedule assumptions and offered price. Resource listings may be independent of schedule database.
g. Narrative explanation of project schedule development. Include impacts of resource limitations and weather conditions on project schedule development. Include planned number of work hours per day and hours per day for subcontractors.
D. RSN 01 32 10-3, Updated Schedule Reports:
1. This submittal is required for a proper invoice for progress payments in accordance with the clauses at FAR 52.232-27 - Prompt Payment for Construction Contracts and WBR 1452.232-82 - Other Invoice Requirements. In accordance with subparagraph (a)(i)(A) of the clause at FAR 52.232-27 - Prompt Payment for Construction Contracts, Government disapproval of this submittal will be considered failure of the Contractor to comply with contract requirements and payment due date may be delayed until 14 days after submittal contents are approved.
2. Include:
a. Construction Program database with updated activity and milestone data.
b. Definition of project calendars if revised from baseline calendars.
c. Primavera P6 layout file (.plf).
d. Gantt chart for project on 11 by 17-inch print(s) and in portable document format (.pdf).
e. Narrative report specifically stating status of project.
1) When negative float exists, cite specific actions and conditions which caused "behind schedule" condition and provide proposed course of action to complete the project within the specified
01 32 10 - 3 delivery time. When float changed from previous month’s updated schedule, explain reason for change.
2) List of Contractor-initiated changes to current schedule stating reason for action taken and unresolved issues relating to the Construction Program. Government reserves the right to reject Contractor-initiated changes to current schedule which negatively impact Government action which was initiated on the basis of current schedule.
3) Discuss contract milestones and significant activities that were started, continued, or completed during the update period or scheduled during the next update period.
f. Submittal Register:
1) List submittals as listed in Table 01 33 00A.
2) Update Submittal Register monthly to include submittals and revised submittals. Register fields shall include RSN name and number, date submitted, date of response, status (e.g., approved, not approved, resubmittal required).
3) This register document is separate from scheduling database.
E. RSN 01 32 10-4, Time Impact Analysis:
1. Include:
a. Construction Program database with proposed revised activity and milestone data.
b. Proposed revised schedule due to change or delay. Highlight or list added, changed, or deleted activities.
c. Primavera P6 layout file (.plf).
d. Gantt chart for project on 11 by 17-inch print(s) and in portable document format (.pdf).
e. Narrative report explaining results and conclusions.
1.05 QUALIFICATIONS
A. Representative: Experienced in developing and maintaining construction schedules and knowledgeable of activities and progress on-site to develop and maintain accurate and reliable schedules.
1.06 GENERAL
A. Develop, maintain, and use Construction Program to plan, monitor, evaluate, and report accomplishment of work.
01 32 10 - 4
1.07 SCHEDULES
A. Prepare construction schedules using Critical Path Method outlined in AGC Manual. Use a computer software program to perform mathematical analysis of scheduling data.
1. Prepare schedule based on required sequence and interdependence of activities.
Logically sequence activities.
2. Prepare detailed activity network for accomplishing required work organized by
Work Breakdown Structure (WBS). Utilize WBS in lieu of activity codes for organization of schedule. If activity codes are utilized in addition to WBS, use unique activity code names assigned as project codes rather than global codes.
3. Activities except “Award” shall have predecessor activities and activities except “Contract Complete” shall have successor activities.
4. Meet contract requirements; milestone(s) in accordance with the clause at FAR 52.211-10, Commencement, Prosecution, and Completion of Work;…