Att_2_Industry_Day_Presentation_1_Provo_Area_Office_5.pdf

PDF 4 MB Posted

Attached to
Post Industry Day - Hyrum Dam Spillway Replacement
Solicitation number
140R4024R0020
Issued by

About this file

This document appears to be an Industry Day presentation for the Hyrum Dam Spillway Replacement project. The presentation provides an overview of the existing Hyrum Dam, including its key features, deficiencies in the current spillway, and the need for corrective action. The proposed solution is to construct a new spillway on a new alignment, with 100% design completion targeted for December 2024 and construction beginning in Spring 2025. The presentation also discusses construction constraints, such as impacts to the Hyrum Feeder and East Field Canal, as well as construction considerations, including the need for a robust foundation treatment due to the poor erosive soils. The goals of the project are to commission the new spillway as soon as possible, continue irrigation deliveries during construction, and achieve a fair price. The related federal contract opportunity is a Special Notice for an Industry Day, with the solicitation number 140R4024R0020, issued by the Department of the Interior Bureau of Reclamation.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Hyrum Dam (UT)

Hyrum Dam

Located on Little Bear River near Logan, Utah

Provides Irrigation Water and Recreation

Completed 1935

Hyrum Dam Site Overview

Hyrum Dam

Existing Spillway

Key Features:

Trapezoidal Chute (~1,100 feet)

(3) 16 x 12.5-foot Radial Gates

Crest Elevation – 4660 feet

TOA Elevation – 4672.5 feet

Discharge Capacity ~9,000 cfs

Existing Spillway Deficiencies

Foundation

Spillway Chute

Stilling Basin

Crest Structure

Foundation Deficiencies Material

Low Strength

Erosive

Voids Under/Behind Spillway

Voids have been mapped with GPR

Spillway Chute Deficiencies

No Defensive Measures

No Waterstop Between Joints

No Drainage Behind Walls

Drainage Under Slab that is unfiltered

Poor Concrete Condition

Stilling Basin Deficiencies

Erosion in Downstream Channel

High Exit Velocities

Crest Structure Deficiencies

Lightly Reinforced

Not Designed for High Seismic Loads

Need for Corrective Action

Plan

Existing Spillway

Proposed New Spillway

• New spillway on a new alignment

• 100% Design – December 2024

• Construction Begin – Spring 2025

Outlet Works 24-inch pipe will only release 50 cfs

Outlet Works Improvements In the process to increase the outlet works size to a 36-inch pipe with a capacity of 200 cfs

Construction likely to start in September 2024

Construction Constraints

Features that will be impacted:

Hyrum Feeder

East Field Canal

Adjacent Landowner

East Field Canal Hyrum Feeder

Pipeline

Existing Spillway

Proposed New Spillway

Adjacent Landowner

Construction Considerations

Existing spillway is in poor condition Current outlet works are too small to impact reservoir operations Enlarged outlet works still too small to control reservoir during high runoff years East Field and Hyrum Feeder canals may be impacted by construction Downstream landowner access during construction Due to poor erosive soils, the foundation treatment (included in the design) will be a key consideration

Needs

Safe and reliable new spillway Continued operation of reservoir and existing spillway until new spillway is operational Open communication regarding impacts to East Field and Hyrum Feeder Canal

Goals

Commission new spillway as soon as possible Continue irrigation deliveries during construction Fair price

Questions

File details come from the government source that posted it. Updated .