Sol_140R3026R0004_Amd_0003.pdf

PDF 184 KB Posted

Attached to
BROCK RESERVOIR GATE REPLACEMENT/REPAIRS Federal contract opportunity
Solicitation number
140R3026R0004
Issued by
Department of the Interior Bureau of Reclamation

About this file

This is Amendment 0004 to Solicitation 140R3026R0004 issued by the Bureau of Reclamation, Lower Colorado Region. The amendment extends the proposal due date to February 23, 2026, by 10:00 a.m., Pacific Time. No new questions will be accepted; only questions or clarifications pertaining to this amendment are permitted and must be submitted via email to Diane Rodriguez at DLRodriguez@usbr.gov by no later than 12:00 p.m., February 17, 2026, Pacific Time.

The amendment revises multiple technical sections and documents including: SF 1442 form with updated award and mandatory boxes; Attachment 1 Specifications sections for Quality Procedures (01 46 00), Control of Water (31 03 10), and Slide Gates and Actuators (35 23 11); Marked-up Drawing 423-D-60247; Rodney Hunt shop drawings E70542, E70543, E70545, E70553, and E7055; site visit sign-in sheet; Attachment 8 Key Subcontractor Specialized Experience Form; and Solicitation Document Page L-12. Contractors must acknowledge receipt of this amendment by one of three methods: completing items 8 and 15 on the SF 30 form and returning it, acknowledging receipt on each copy of the offer submitted, or sending a separate letter or electronic communication referencing the solicitation and amendment numbers. Acknowledgement must be received at the designated location prior to the specified deadline.

View the file

Other files for this federal contract opportunity

Other files attached to BROCK RESERVOIR GATE REPLACEMENT/REPAIRS, newest first.
File Type Posted
Sol_140R3026R0004_Amd_0005.pdf PDF
Revised_Page_L-15_0004.pdf PDF
Sol_140R3026R0004_Amd_0004.pdf PDF
140R3026R0004_-_Questions_from_Site_Visit_0004.pdf PDF
140R3026R0004_-_Site_Visit_Sign-In_Sheet_0003.pdf PDF
SF_1442_0003.pdf PDF
Attachment_8_Key_Subcontractor_Specialized_Experience_0003.pdf PDF
Specifications_35_23_11_0003.pdf PDF
Revised_Page_L-12_0003.pdf PDF
Specifications_01_46_00_0003.pdf PDF
Specifications_31_01_10_0003.pdf PDF
423-D-60247-Cell_1_Option_0003.pdf PDF
Rodney_Hunt_Shop_Drawings_0003.pdf PDF
Attachment_1A_Statement_of_Work_0002.pdf PDF
Sol_140R3026R0004_Amd_0002.pdf PDF
Sol_140R3026R0004_Amd_0001.pdf PDF
Solicitation_No__140R3026R0004_0001.pdf PDF
Attachment_7_-_Past_Performanc_Questionnaire.pdf PDF
Attachment_4_Bid_Bond_SF24.pdf PDF
Sol_140R3026R0004.pdf PDF
Attachment_2__Drawings.pdf PDF
Attachment_3_Wage_Determination_CA20260002.pdf PDF
Attachment_1_Specifications.pdf PDF
Attachment_6_DI-137_Release_of_Claims.pdf PDF
Attachment_5_Payment_Bond_SF25A.pdf PDF
Attachment_8_Subcontracting_Plan_Template.docx DOCX document
Attachment_5_Performance_Bond_SF25.pdf PDF
Attachment_9_Subcontracting_Plan_Template.pdf PDF
Show all 28

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: is not is required copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7.ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

PAGESOF

Contractor

The hour and date specified for receipt of Offers to sign this document and return

Maribel Ruble

See continuation page

Bureau of Reclamation Lower Colorado Region Regional Office 500 Fir Street Boulder City NV 89005

R30

140R3026R0004

02/13/2026

01/12/2026

1 2

Purpose of Amendment: The purpose of this Amendment 0004 is to provide a copy of the sign-in sheet from the site visit, responses to questions submitted, update sections of the Specification attachment, provide original gate and thimble drawings, and extend the proposal due date.

No new questions will be accepted. Only questions/clarifications pertaining to this Amendment will be accepted. Your questions must be submitted via email to Diane Rodriguez at DLRodriguez@usbr.gov by no later than 12:00 pm, February 17, 2026, Pacific Time.

Receipt of Offers: The date for receipt of offers is extended to February 23, 2026, by 10:00 a.m., Pacific Time.

Acknowledgement: See block 11 of the SF 30 of this amendment regarding how to acknowledge this amendment. The acknowledgement must be received at the place designated for receipt of offers.

Offer/Bid Modification: See block 11 of the SF 30 of this amendment if you have submitted your offer/bid and now desire to modify it or withdraw it.

As a result of the above, this amendment revises the following and provides the appropriate revised pages:

1. The SF 1442 is being revised to reflect the changes made in Block 11. Box for "award" is being checked instead of box for "notice to proceed"; and box for mandatory" is being checked instead of the box for "negotiable".

2. Attachment 1, Specifications, Section 01 46 00, Quality Procedures is being replaced via this

Amendment.

3. Attachment 1, Specifications, Section 31 03 10, Control of Water is being replaced vis this

Amendment.

4. Attachment 1, Specifications, Section 35 23 11, Slide Gates and Actuators is being replaced via this Amendment.

5. Marked-up Drawing 423-D-60247.

6. Rodney Hunt shop drawings E70542, E70543, E70545, E70553 and E7055.

7. Sign-In Sheet from Site Visit.

8. Attachment 8, Key Subcontractor Specialized Experience Form

9. Solicitation Document, Page L-12 is being replaced via this Amendment.

mailto:DLRodriguez@usbr.gov

Amendment of solicitation/modification of contract
Contract ID code
Amendment/modification number
Effective date
Requisition/purchase requisition number
Project number
Issued by
Code
Administered by
Code
Name and address of contractor
Code
Facility code
Amendment of solicitation number
Dated
Modification of contract/order number
Dated
This item only applies to amendments of solicitations
Accounting and appropriation data
This item applies only to modifications of contracts/orders.
This change order is issued pursuant to:
The above numbered contract/order is modified to reflect the administrative changes
This supplemental agreement is entered into pursuant to authority of:
Other
Important:
Description of amendment/modification
Name and title of signer
Contractor/offeror
Date signed
Name and title of contracting officer
Signature of Contracting Officer
Date signed
Previous edition unusable
Standard form 30 (rev. 11/2016)

File details come from the government source that posted it. Updated .