Attachment_No__1_-_FKC_Pre-Proposal_Presentation_Slides_0002.pdf

PDF 15 MB Posted

Attached to
FKC Middle Reach Capacity Correction Project Phase Federal contract opportunity
Solicitation number
140R2020R0009
Issued by
Department of the Interior Bureau of Reclamation

About this file

This document provides details on a federal contract opportunity for the FKC Middle Reach Capacity Correction Project Phase 1. The solicitation number is 140R2020R0009 and is being issued by the Department of the Interior Bureau of Reclamation. The opportunity is for the FKC Middle Reach Capacity Correction Project Phase 1, which aims to increase the water carrying capacity of the Friant-Kern Canal in the central San Joaquin Valley of California. Interested parties can find additional information on project background and requirements in Attachment 1, which contains presentation slides from a pre-proposal meeting. The response due date and anticipated award date are not stated.

View the file

Other files for this federal contract opportunity

Other files attached to FKC Middle Reach Capacity Correction Project Phase, newest first.
File Type Posted
Attachment_8_Amendment_0008_0008.pdf PDF
Sol_140R2020R0009_Amd_0008.pdf PDF
Amendment_0007_for_Solicitation_140R2020R0009_0007.pdf PDF
Sol_140R2020R0009_Amd_0007.pdf PDF
Attachment_7_Amendment_0006_0006.pdf PDF
Sol_140R2020R0009_Amd_0006.pdf PDF
Attachment_B_1_Amendment_No_0005_0005.xlsx XLSX spreadsheet
Attachment_42_Amendment_0005_0005.pdf PDF
Attachment_37_Amendment_No__0005_0005.pdf PDF
Attachment_35_Amendment_No__0005_0005.pdf PDF
Attachment_33_Amendment_No__0005_0005.pdf PDF
Attachment_32_Amendment_No__0005_0005.pdf PDF
Attachment_26_Amendment_No__0005_0005.pdf PDF
Attachment_10_Amendment_No_0005_0005.pdf PDF
Attachment_4_Amendment_No_0005_0005.pdf PDF
Attachment_2_Amendment_No_0005_0005.pdf PDF
Attachment_25_Amendment_No__0004_0004.pdf PDF
Attachment_21_Amendment_No__0004_0004.pdf PDF
Attachment_19_Amendment_No__0004_0004.pdf PDF
Attachment_15_Amendment_No__0004_0004.pdf PDF
Attachment_7_Amendment_No_0004_0004.pdf PDF
Attachment_14_Amendment_No__0004_0004.pdf PDF
Attachment_29_Amendment_No_0004_0004.pdf PDF
Attachment_28_Amendment_No__0004_0004.pdf PDF
Attachment_23_Amendment_No__0004_0004.pdf PDF
Attachment_22_Amendment_No__0004_0004.pdf PDF
Attachment_20_Amendment_No__0004_0004.pdf PDF
Drawing_GC-17_Attachment_21_Amendment_No__0003_0003.pdf PDF
Drawing_G-03_Attachment_18_Amendment_No__0003_0003.pdf PDF
Drawing_C-703_Attachment_16_Amendment_No__0003_0003.pdf PDF
Drawing_C-304_Attachment_14_Amendment_No__0003_0003.pdf PDF
Drawing_C-203_Attachment_6_Amendment_No__0003_0003.pdf PDF
Amendment_No__0003_for_Solicitation_140R2020R0009_0003.pdf PDF
Attachment_1_Amendment_No_0003_0003.pdf PDF
Drawing_GC-15_Attachment_20_Amendment_No__0003_0003.pdf PDF
Drawing_G-13_Attachment_17__Amendment_No__0003_0003.pdf PDF
Drawing_C-506_Attachment_15_Amendment_No__0003_0003.pdf PDF
Drawing_C-215_Attachment_12_Amendment_No__0003_0003.pdf PDF
Drawing_C-214_Attachment_11_Amendment_No__0003_0003.pdf PDF
Drawing_C-204_Attachment_7_Amendment_No__0003_0003.pdf PDF
FKC_31_30_00-12_Att_7_Amendment_0002_0002.pdf PDF
FKC_01_14_00-12_Att_6__Amendment_0002_0002.pdf PDF
GC-10-REV-1_Att_5_Amendment_No__0002_0002.pdf PDF
Attachment_No__2_-_FKC_Pre-Proposal_Presentation_Sign_in_Sheet_0002.pdf PDF
Attachment 3 - Past Performance Questionnaire.pdf PDF
Solicitation 140R2020R0009.pdf PDF
Attachment 13 - Drawing Part 1 of 5.pdf PDF
Attachment 9 - Experience and Management.pdf PDF
Attachment 4 - Offeror Responsibility Information.pdf PDF
Attachment 2 - Subcontracting Plan.pdf PDF
Show all 50

FKC Middle Reach Capacity Correction Project Phase has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-Site Visit Conference Friant-Kern Canal Middle Reach Capacity Correction Project, Phase 1

Welcome

1. Please send us your name and the Company represented in the Chat/Question box

2. We will begin the presentation at 9:05 am to allow everyone to get logged

Amendment No 0002 Attachment No 1

Pre-Site Visit Conference Friant-Kern Canal Middle Reach Capacity Correction Project, Phase 1 Date: May 18, 2021

AGENDA

• Introductions Reclamation Field Engineer (FE)

• Project Formation/History Friant Water Authority

• Project Scope/Design Considerations Stantec PM & Lead Designer

• Construction Considerations Reclamation FE & Environmental Lead

• Safety and Health Reclamation Construction Manager (CM)

• Solicitation/Proposal Instructions Reclamation Contracting Officer (CO)

• Site Visit Date/Information Reclamation FE

• Closeout Reclamation FE

History of the Friant- Kern Canal

• Friant-Kern Canal (FKC): is a Federally constructed (1945-1951) and owned appurtenant works of Central Valley Project Act of 1937.

• Friant Water Authority (FWA): Non-Federal operating entity under contract with Reclamation to operate, maintain, repair or replace works of the FKC.

• Friant Division of Central Valley Project delivers water to over one million acres of irrigable farmland and water for over 250K residents along eastside of southern San Joaquin Valley.

BACKGROUND

• Designed conveyance capacity of FKC compromised by various factors since start of operation in 1951 o Subsidence of land negatively affected FKC’s ability to convey water; canal designed as gravity conveyance feature o Land subsidence in Corcoran/Tulare Basin area caused estimated 54% reduction in capacity oOriginal design and constructed capacity resulted in reduced capacity o Reclamation & FWA worked together in development of project to address reduced capacity in FKC and identified general objectives of FKC modifications-based canal reaches.

• Repair costs ~$ 4.1 M in 1979

• Mile Post 99.37 to 115.94

• 330,000 acres effected

• Liner Rehabilitation up to 5’

• 4 bridges raised

Recent FKC Subsidence Friant Dam

Fresno

Bakersfield

Mendota

• Centered around mile post 95 (of 152 length)

• Designed capacity of 4,000 cfs in that reach

• Estimated capacity in April 2017

1,600 cfs (60% below design capacity)

• ~330,000 acres Friant Districts lands below the pinch point

• 300,000-acre-foot reduction in 2017 deliveries

• Long-term Class 2 deliveries expected to be half of historical, with present canal condition

• Unlikely delivery of Section 215, RWA and URF

Water in future, without repair

PROJECT SCOPE / DESIGN CONSIDERATIONS

• Alignment overview

• Canal alignment

• Aerial topography

• Earthwork

• Geotechnical information

• Borrow sources

• Typical canal section

• Roadway crossing siphons

• Structural Backfill

• Roadway improvements for detours

• Deer Creek Check, Siphon & Wasteway

• Turnouts

• Canal Tie-ins

Alignment Overview Phase 1 Project:

• 10 miles new parallel canal, (MP98.4 to 108.4)

• 7 new roadway crossing siphons

• 1 check structure/siphon/wasteway at Deer

Creek

• 9 turnouts

Canal Alignment

• Drawing C-21 through C-43 Canal Plan and Profiles

• C-700 Series Drawings for Cross Sections

Aerial Topography

Section 01 10 00 – Request data files from the Contracting Officer

Earthwork (Drawing GC-8)

• Drawing GC-15 Existing Canal Bank Restoration

• Section 01 14 00 Sequencing

• Section 31 30 00 Earthwork

Geotechnical Information

• Geotechnical Investigations and Geotechnical Data Report (GDR) completed for entire Middle Reach Project

• Provided in Solicitation Attachment 11 on website

• Exploration maps, boring and CPT logs and laboratory test results provided in Appendices B,D,E, and F, respectively of GDR

• Boring and laboratory summary plots showing locations of material types provided in Appendix G of GDR

Borrow Sources

TBID 160 Acre borrow site, (Drawing GC-14)

Geotechnical Data Report in Appendices

• Appendix B – TBID Borrow Site

Borrow Sources

• TBID borrow site (Drawing GC-14 for grading criteria)

• Existing canal bank material (Drawing

GC-15 for restoration criteria)

• Contractor furnished off-site borrow sources approved by the Government Deer Creek Check

Typical Canal Section

• 3.5” thick concrete lining

• Side slopes at 1.5H to 1V

• 24-ft bottom width

• 23.37 to 26.37-ft lining height

• 2.5-ft earth freeboard

• Longitudinal and transverse joints at 14-ft w/waterstops

• Canal lining expansion joints

• All weather O&M road on canal right bank

• Safety Ladders

Drawings GC- 8 through 12

Roadway Crossing Siphons

Existing Bridge New Roadway Crossing Siphon

• C-200 Series Drawings, S-1 through S-8

• Road Section on Drawing GC-2

Structural backfill

• Native 2 (N2) material required in the structural backfill zones identified on

Detail S-904

• N2 - Coarse-grained (SW, SP, SM, SC) suitable materials obtained from on-

Site excavations

Drawing GS-5

Roadway Crossing Siphons - Utilities

Plan View

Profile View

Irrigation pipeline relocation Gas line relocation

Te rr a Be lla A ve

• Utility Relocation Work By Others (Section 01 14 00 Attachment)

• C-400 Series Drawings for irrigation pipeline replacement contract work.

Roadway Improvements for Detours

AC Overlays

Shoofly at Rd 192 (Drawings T2-T5)

Drawings T-2 through T-7

Deer Creek Check, Siphon, & Wasteway

Drawings C-100,C-508, S-10 through S-28, S-34, M-1 through M-3 D ee r C re ek

Existing Canal

New Parallel Canal

Turnouts

• 9 water delivery turnouts to FWA contractors

• 2 gravity, and 7 pumped turnouts

• Single bay to triple bay

• Manually and Electrically operated slide gates

• Embedded stop log guides with stop logs

• Trash racks

• Terra Bella ID turnout goes to weir box with connecting pipelines to existing pump station (C-403, S-37 and 38)

• C-400 Series Drawings for Turnouts to Pump Stations

• C-500 Series Drawings for Gravity Turnouts

Canal Tie-ins

Avenue 136 Avenue 64 Drawing C-302 Drawing C-304

Av en ue

Av en ue

Existing Canal

A FEW CONSTRUCTION CONSIDERATIONS

• Schedules

• Some Important Dates

• Constraints and Sequencing

• Canal Work Considerations

• Existing Utilities and Improvements

• Permits

• Environmental Commitments

Construction Schedules

• Proposal Construction Schedule and Narrative - Sections L

• Requirements and evaluation factors

• Section L- page 14: For the purpose of developing the schedule and in analyzing proposals during evaluation only, use the notice to proceed date of November 8, 2021.

• Contract Schedules – Section C 01 32 16 Construction Program

• Requirements for Baseline and Updated Schedules & Time Impact Analysis

Construction Schedules Important dates to note (This is not an all-inclusive list)

• Section C 01 14 00 CONSTRUCTION CONSTRAINTS AND SEQUENCING

• The acquisition of rights-of-way necessary for work obtained by November 30, 2021

(pg 19)

• Schedule dates for Utility Relocation Work by others (table on pg 79)

• Section H.1 Intermediate Milestones and Limitations (pg H-1)

• Completed pre-commissioning (and other listed items) in preparation for new parallel canal and turnout tie-ins by November 30, 2023

• Complete new parallel canal and turnout tie-ins for canal operation by January 26, 2024

• Section F Deliveries or Performance

• Complete entire work ready for use not later than September 1, 2024 (pg F-1)

Construction Constraints and Sequencing Section C 01 14 00 (This is not an all-inclusive list)

• The WORK shall be executed while the existing canal, including water deliveries to existing turnouts, is in operation (Subpart 1.2)

• Annual Canal Outages Periods

• Estimated dates Dec 12th – Jan 26th (Subpart 1.10 C. 4.)

• Items of work that conflict with existing FKC shall occur during canal outage periods (Subpart 1.10 C. 6.)

• Deer Creek Check, Siphon, and Wasteway

• Check and Siphon – specific permit requirements and annual work window (Subpart 1.10 C. 3.)

• Wasteway Pipeline under existing canal – Construct after new canal in operation (Subpart 1.10 C. 5.)

• Maintain water deliveries via Deer Creek annually from April to July

• Requirements for work within Tulare County Rights-of-Way (Subpart 1.9 B. 6.)

• Include requirements for Siphon sequencing, detour road improvements etc.

Canal Work Considerations

• Submittals – Section 01 33 00 and Subparts of most other sections

• Contract Document Management System required (01 31 30)

• Survey

• annual subsidence monitoring surveys required (01 71 20 3.6)

• Photo/video documentation pre/post construction (01 71 20 3.8 & 3.9)

• Staging Area locations & requirements (Dwg G-12 & 13, 01 14 10, 01 30 00)

• Access to the work and haul road requirements (Sections 01 14 00, 31 30 00)

• Quality Control – required for all aspects of work (01 45 00)

Existing Utilities and Improvements (Section 01 50 10 and 01 14 00)

• Utilities to be Relocated by Others

• Schedule of dates for Utility Relocation Work by others (table on pg 79)

• Sequence work and cooperate with utility owners

• Utilities to be Relocated by Contractor

• Includes temporary and permanent relocations

• Example – Irrigation districts’ delivery system piles in conflict with work

• Pothole plans and pothole reports required

• Temporary Connections

• Temporary facilities, piping, electrical, controls etc required to complete the work are the responsibility of the Contractor, as approved by the Gov’t

Permits

• Clean Water Act Permits (Section 01 14 00)

• 404 – Letter of Permission for Deer Creek – pending

• 401 – Water Quality Certification for Deer Creek – received

• Construction should be constrained to dry season (April to Nov)

• 402 – NPDES applicable permitting will need to be acquired by

Contractor

• Contractor to prepare SWPPP/ESCP (Section 01 40 40)

• San Joaquin Valley Air Pollution Control District

• Air quality requirements in Section 01 30 00, include submittal of clean construction equipment and monthly logs, dust control plan and daily records

• California Department of Fish and Wildlife

• Section 1600 – Lake or Streambed Alteration Agreement

• Construction should be constrained to dry season (April to Nov)

Environmental Commitments (Section 01 30 00)

• Record of Decision, Environmental Impact Statement/Environmental

Impact Report

• Government Environmental Coordinator & Designated Biologist

• Mitigation and Compliance Measures (Refer to Spec Table 1) include but are not limited to:

• Worker environmental awareness trainings for all construction personnel

• Pre-construction inventories and monitoring of special status species, requires close coordination with Designated Biologist

• Specific measures to avoid impacts to Buena Vista Lake Shrew at Deer Creek

SAFETY (Sections 01 35 20, 01 35 30)

• Safety Program-Reclamation Safety and Health

Standards, appendix B (https://www.usbr.gov/safety/rshs/index.html)

• Follow Cal/Federal OSHA standards as well (The most stringent!)

• Contractor responsible for all operations, including subcontractors

• Required to have a full-time safety representative and part-time safety professional

• Requirements for planning, inspections, reporting and meetings

Solicitation/Proposal Sections L and M of the RFP:

• Provides explicit instructions to offerors regarding proposal content, format, and limitations (L).

• Provides in detail, the evaluation factors, and the relative importance of those factors (L).

• Details how the Government will evaluate the proposals (M).

Electronic Submission of Proposals:

• Submit in accordance with the instructions provided at Section L.

• Review Section J, Attachment 10, regarding electronic submission of proposals via Kiteworks.

Pre-Proposal Site Visit

Date: May 20, 2021 Meeting Time: 9:00-14:00 Location: 2700 Teapot Dome Ave, Porterville, CA. 93257

Register to attend by contacting:

Scott Wolfert at swolfert@usbr.gov

Amendment No 0002 mailto:swolfert@usbr.gov

Questions ???

Page L-1 of solicitation:

FAR 52.215-1 Instructions to Offerors - Competitive Acquisition - Addendum Inquiries. All inquiries pertaining to this solicitation (except where noted for the onsite site visit) shall be submitted in writing to both Contract Specialist, Clinton Lowery at clowery@usbr.gov and Contracting Officer, Sarah Rall, srall@usbr.gov no later than 12:00 PM Pacific, May 27, 2021. Responses pertinent to all prospective offerors will be included in an amendment to the solicitation.

Amendment No 0002 Attachment No 1 mailto:clowery@usbr.gov mailto:srall@usbr.gov

Pre-Site Visit Conference�Friant-Kern Canal Middle Reach Capacity Correction Project, Phase 1
Slide Number 2
AGENDA
History of the Friant-Kern Canal
BACKGROUND
Recent FKC Subsidence
PROJECT SCOPE / DESIGN CONSIDERATIONS
Alignment Overview
Canal Alignment
Aerial Topography
Earthwork (Drawing GC-8)
Geotechnical Information
Borrow Sources
Typical Canal Section
Roadway Crossing Siphons
Structural backfill
Roadway Crossing Siphons - Utilities
Roadway Improvements for Detours
Deer Creek Check, Siphon, & Wasteway
Turnouts
Canal Tie-ins
A FEW CONSTRUCTION CONSIDERATIONS
Construction Schedules�
Construction Schedules� Important dates to note (This is not an all-inclusive list)
Construction Constraints and Sequencing� Section C 01 14 00 (This is not an all-inclusive list)
Canal Work Considerations
Existing Utilities and Improvements�(Section 01 50 10 and 01 14 00)
Permits
Environmental Commitments (Section 01 30 00)
SAFETY (Sections 01 35 20, 01 35 30)
Solicitation/Proposal
Pre-Proposal Site Visit
Questions ???